02371 - Alberta Ministry of Transportation

advertisement
Section Cover Sheet
Section 02371
Gravel Armour Placement
2006-10-31
Use this section to specify requirements for gravel armour placement. This section is primarily
applicable to canal rehabilitation projects undertaken during the non-irrigation (winter) season.
Edit this section to suit the Contract requirements.
Heading of Specification Text
Part 1
General
1.1
Quality Control
1.2
Quality Assurance
.4
Part 2
Products
2.1
Materials
Part 3
Execution
3.1
Stockpiles
3.2
Placement
[.5]
3.3
Specification Note
Confirm the frequency of gradation testing.
Generally at least 1 test per 1000 m3 has been used
on contracts where large quantities of gravel armour
are required.
Include if required.
Placement Tolerances
[.1 & .2]
Include the appropriate clauses to suit the subgrade
material and the Contract requirements. Clause
3.3.1 is based on a 200 mm design thickness of
gravel armour, and clause 3.3.2 on a 300 mm
design thickness normally used on PVC membrane
liners.
.3
Clearly specify the top of armour elevations on the
Drawings. Edit as required.
END OF COVER SHEET
CWMS Civil Works Master Specification
Alberta Transportation
Master Specification System
Page 1
Tender No.: [
Section 02371
Gravel Armour Placement
Page 1
]
PART 1
GENERAL
1.1
QUALITY CONTROL
.1
Perform quality control tests of gravel armour as specified in Section 02330 –
Earthwork Materials.
.2
Transport only suitable materials meeting the specifications to the Site.
1.2
QUALITY ASSURANCE
.1
The Minister will perform any testing to assure conformance to the specified
requirements after the materials have been placed.
.2
The Minister may reject gravel armour at the source, in the transport vehicle, in
the stockpile, or in place.
.3
The Minister may take samples of gravel armour for quality assurance testing.
Co-operate with Minister during sampling and testing. Load and dispose of
sampled materials when no longer required by the Minister.
.4
The Minister may perform 1 gradation test for every [1,000] m 3 of placed material.
The frequency of gradation testing may be increased as deemed necessary by
the Minister until the Contractor consistently meets the specified requirements.
PART 2
PRODUCTS
2.1
MATERIALS
.1
Provide materials in accordance with the following.
.2
Gravel Armour Zone 5C:
material specifications.
PART 3
EXECUTION
3.1
STOCKPILES
Refer to Section 02330 – Earthwork Materials for
.1
Obtain prior authorization from the Minister for temporary stockpile locations on
Site. Do not stockpile gravel armour in areas where contamination with the
underlying soils can occur.
.2
Use stockpiling methods that do not cause loss of materials, segregation or particle
damage.
Tender No.: [
3.2
]
Section 02371
Gravel Armour Placement
Page 2
PLACEMENT
.1
Place gravel armour at the locations, and to the lines, grades, slopes, and
elevations specified in the Contract Documents.
.2
Surfaces to receive gravel armour may be frozen, but remove water, snow, ice,
frozen lumps, or deleterious materials from receiving surfaces.
.3
Do not place gravel armour until the receiving surfaces have been inspected by
the Minister. Rectify defects, including any identified by the Minister, until the
receiving surfaces meet the requirements of the Contract Documents.
.4
Place gravel armour to its full thickness in one operation to provide a uniform
thickness without any large unfilled voids.
[.5]
Place gravel armour on PVC membrane liner using overhead equipment such as
conveyors, clamshells, draglines, backhoes, gradealls, or other means that do
not result in direct or indirect equipment loading on the liner. Do not drop gravel
armour more than 1000 mm vertically onto the liner.
.6
Obtain the specified distribution of the various sizes of particles throughout the
mass by using selective loading at the source or stockpiles, by controlled
dumping of successive loads during placing, or by other methods of placement.
.7
During placement, regularly check the thickness of the placed material to enable
prompt adjustments to be made to the placement methodology.
If
measurements indicate that the specified thickness are not being attained,
temporarily terminate placement and implement corrective measures, as
authorized by the Minister, to provide the specified thickness.
.8
Do not cause segregation, particle damage, breakdown, or displacement of
adjacent previously placed gravel armour. Replace or repair damaged or
displaced material.
.9
Commence placement from the toe of the slope and proceed up the slope.
Dozing or pushing of gravel armour downslope from the top of the slope is not
permitted.
.10
Compaction of gravel armour is not required.
.11
Provide a completed gravel armour surface that is smooth, regular, and uniform.
Tender No.: [
3.3
]
Section 02371
Gravel Armour Placement
Page 3
PLACEMENT TOLERANCES
[.1]
Place gravel armour on the soil subgrade to a minimum thickness of 190 mm and
a maximum thickness of 230 mm at any location, and to an average thickness of
between 200 mm and 210 mm over any 1 km length of canal.
[.2]
Place gravel armour on PVC membrane liner to a minimum thickness of 290 mm
and a maximum thickness of 330 mm at any location and to an average
thickness of between 300 mm and 315 mm over any 1 km length of canal.
.3
Place gravel armour within a tolerance of +100 mm of the specified top of armour
elevation. Limit the maximum rate of change in deviation from the specified top of
armour elevation to a ratio 1V:50H. [Where the specified top of armour elevation
corresponds to the specified top of canal bank elevation, place gravel armour
level with, and to the same elevation as, the top of canal bank.]
END OF SECTION
Download