Mahony Bar – Floodplain Report Marion County, Oregon Prepared for: Marion County Zoning and Planning Department Courthouse Square 555 Court Street NE Room 2130 Salem OR 97301 Prepared By: Glen C. Krogman Lidstone and Associates, Inc. 4025 Automation Way Bldg. E Fort Collins CO 80525-3448 May 2004 Table of Contents 1.0 INTRODUCTION ........................................................................................................ 2 2.0 BACKGROUND INFORMATION ............................................................................. 2 3.0 3.1 3.2 HYDRAULIC ANALYSIS .......................................................................................... 7 EXISTING CONDITIONS .................................................................................. 7 PROPOSED CONDITION ................................................................................. 9 4.0 RESTORATION PLAN ............................................................................................... 9 5.0 SUMMARY – HYDRAULIC ANALYSIS ............................................................... 11 6.0 PROJECT SCHEDULE ............................................................................................. 11 FIGURES Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 ...................................................................................................................................... 3 ...................................................................................................................................... 6 ...................................................................................................................................... 8 ...................................................................................................................................... 9 .................................................................................................................................... 10 TABLES Table 1 Table 2 ...................................................................................................................................... 4 ...................................................................................................................................... 7 Mahony Bar – Floodplain Report 1 1.0 INTRODUCTION The purpose of this study is to evaluate the impacts of the Mahony Bar Enhancement Project. Hydraulic analyses were conducted to ensure that the proposed enhancement plan for the Mahony Bar would not increase the base flood level and/or adversely affect the stability of this reach of the river. This investigation determined that the proposed fish ingress/egress channels and other construction, including the anchoring of large woody debris (LWD) in the floodway, would result in “no net rise” in the 100-year water surface elevation (base flood level). The project is located on the Willamette River approximately five miles south of St. Paul, Oregon. It is situated above Lower Lambert Bend at River Mile 65.8 on the right channel bank in SW ¼ Section 11, Township 5S, Range 3W, Marion County. Multiple landowners are involved. The project location is known as Mahony Bar. Mahony Bar is situated on the right (east) channel bank of the Willamette River and comprises 17 acres within the floodway of the Willamette River (Figure 1). Natural elevations across the bar range from 86 to 95 feet. The elevations are based on a 2002 aerial of the site. Hydrologic modeling indicates the two-year flood elevation at Mahony Bar is ~89 feet. Historic extraction of sand and gravel has created seasonal ponds through the cumulative removal of ~150,000 yards and the creation of linear berms of soil removed from the extraction areas. These artificial features are generally located parallel to the channel and flood patterns. A small berm perpendicular to the flow pattern is proposed for removal. 2.0 BACKGROUND INFORMATION The project proposes to extend an alcove and connect it to floodplain gravel ponds dug in the 196070s. The purpose is to provide a fish ingress/egress channel via a low-water connection designed to prevent stranding of native fish and potentially to improve fish access to the floodplain. Mahony Bar floods on a frequent basis. Flood frequency across the bar varies from annual to periodic flows. Consequently, migratory fish may enter the ponds as they seek refuge during higher velocity events. Monitoring at other floodplain mine ponds on the Willamette River suggest not all migrants leave with the receding river. Fish remaining after the flood are stranded until the next flood event or perish through predation or elevated water temperatures. The plan is a series of integrated steps designed to be compatible with local flood hydrology and geomorphic trends. These actions will promote fish passage and floodplain complexity at Mahony Bar. Fish usage, water quality, geomorphic stability, and riparian plantings will be monitored for five years. Mahony Bar – Floodplain Report 2 FIGURE 1 Mahony Bar – Floodplain Report 3 The specific project objectives are: Deepen ½ acre at the downstream end of Coleman pond to expose a minimum of six feet of ground water. Extend the natural alcove and connect it to the downstream end of the Coleman pond for a fish egress channel. Remove the soil berm blocking fish and wildlife movement between excavation areas on the Coleman property. Remove silt blocking the inlet to the natural alcove. Realign the alcove inlet and bury LWD in the banks according to the design by ODFW Habitat Biologist, Joe Sheahan. Design intent is to encourage localized scouring and limit silt deposition and blinding off of the alcove inlet. Bury LWD in the alcove extension and minimize reestablishment of reed canary grass by aggressive tree and shrub plantings along alcove banks. Evaluate the biological benefits and geomorphic stability of the alcove extension. By data collection, add to body of knowledge regarding creation of fish access channels to mine ponds. Collect data on fish assemblages, fish populations, and life stages. Evaluate project benefits to other wildlife species. Monitor dissolved oxygen and temperature pre- and post-construction A table is presented in this section which lists the amount of material proposed for removal. It also details the amount of material to be placed in disposal areas within the floodway and outside of the floodway. All disposal sites within the floodway will be below the natural elevations of the floodplain and inside of the boundaries of the old mine site. The only exception to this is the silts excavated at the entrance to the natural alcove. It would require a substantial amount of tree removal and road building to access the 25 yards with haul trucks. Consequently, this material will be leveled near the alcove. The depth of fill will average less than two feet. See Table 1. Excavation and Placement Volumes Removal* (in yards) Silt Sand & Gravel Silt Placement (in yards) Alcove entrance 25 0 251 Berm removal 50 0 502 6,666 17,600 0 0 2,600 2,0662 0 3,600 3,600 0 0 1,000 Alcove extension Coleman Pond (upland mine pond) Silt disposal trench (100’ x 30’ x 12’ deep) Hop field (upland) *All sand and gravel will be removed from the site. 1 Revegetate in place above 2-year flood elevation. 2 Place adjacent to upland mine pond where soils have been excavated and removed from project site. Table 1 The proposed actions at individual locations within the project are described below along with a discussion of where the excavated material will be placed. A total of 24,800 cubic yards will be Mahony Bar – Floodplain Report 4 removed from the floodway and 6,741 yards will be relocated and placed below grade within the floodway (see Figure 2). These improvements will enhance and create fish egress out of man-made ponds (that act as fish barriers) when the river stage drops during the summer months. No alternative site or project designs are possible. The need for this project is based on the degradation by simplification of the Willamette River and its floodplain over the last 150 years. This project will enhance connectivity between the Willamette River and its floodplain. Currently, only limited information is available on the utility of constructed fish channels. Many are now proposed to meet ESA requirements for commercial floodplain gravel operations. The primary objective of this project is to monitor fish usage of the constructed channel to improve the current body of knowledge for fish passage between floodplain ponds and rivers and then disseminate that information. For fisheries enhancement, dependant upon cost and availability 10 to 30 logs with rootwads will be buried in the channel banks of the fish egress channel and at the inlet to the natural alcove. The LWD will be anchored by burial of a minimum of one third of the stem (15 to 30 foot logs) during placement to ensure the LWD will remain on the project site as habitat features. After these construction activities are finished, the site will be revegetated with native riparian species. A five year fish monitoring program will be conducted to evaluate fisheries benefits. Mahony Bar – Floodplain Report 5 Figure 2 Mahony Bar – Floodplain Report 6 3.0 HYDRAULIC ANALYSIS The hydraulic analysis was conducted to determine the impacts of the fisheries enhancement work on the 100-year flood level. Hydraulic analyses were conducted for the existing and proposed conditions, as listed below. 1. The Existing Condition model represents current conditions. River cross sections surveyed by Bernert River Towing; (May 2002) and 2002 aerial photography; and two FEMA cross sections were used to develop an existing condition model. 2. The Proposed Condition model incorporates the fish ingress/egress channel and all other aspects of the enhancement plan including placement of excavated silts in a disposal cell, placement of silt to flatten pond banks and the placement and grading of the silt excavated from the natural alcove inlet. 3. The lower limit of the study reach is river section 63.23. The hydraulic model includes 8 cross sections through the study reach, encompassing approximately 2.5 miles of the river. Cross section locations are shown on Figure 3. The site is located within the 100-year floodplain and floodway of the Willamette River, as determined by the Federal Emergency Management Agency (FEMA). 3.1 EXISTING CONDITIONS The United States Army Corps of Engineers (USACOE) HEC-RAS computer program Version 2.1, was used to perform the hydraulic analysis for this study. FEMA cross sections 63.23 through 68.98 were copied from the original FEMA HEC-2 model and incorporated into an Existing Condition model. Cross section 65.95 was generated using information from upstream and downstream FEMA cross sections and available USGS quadrangle map contours. The 100-year flood flows, channel roughness characteristics, and starting water surface elevations were obtained from the FEMA HEC-2 model. The flow values for the study reach are shown in Table 2. 100 YR Water Surface Elevation Comparison Cross Section ID 63.23 64.63 65.58 65.95* 66.32 67.45 68.12 68.98 Q Total (cfs) 253,000 253,000 253,000 253,000 253,000 253,000 253,000 253,000 100 Year Water Suface Elevation Existing Proposed Condition Condition (ft) (ft) 105.48 105.94 106.47 106.82 107.06 107.79 108.07 108.45 105.48 105.94 106.47 106.81 107.06 107.78 108.06 108.44 Table 2 Mahony Bar – Floodplain Report 7 Figure 3 Mahony Bar – Floodplain Report 8 3.2 PROPOSED CONDITION A hydraulic analysis was also conducted for the Proposed Condition. The Proposed Condition model incorporates the floodplain alterations that will be constructed as part of this fisheries enhancement plan. This includes the following: Construct a fish egress channel and connect it to a natural alcove Enhance constructed fish egress channel with LWD and native riparian plantings Remove silts from alcove entrance and burial of LWD to keep the entrance open Construct a disposal trench for excess silt overburden Deepen the Coleman pond Relocate a silt berm adjacent into the Coleman pond to flatten banks The locations of the removal and fill activities are shown on Figure 2. Figure 4 is a typical detail of the proposed fish ingress/egress channel. A brief description of the proposed activities is presented in the following section. The proposed construction activities are located in the floodway. Figure 5 is a cross-section which illustrates all proposed activities in the floodway. Figure 4 Cross sections 66.32 and 65.95were modified to reflect the proposed enhancement plan. These modifications were used to evaluate the potential impact to the 100-year water surface elevation. The HEC-RAS modeling analysis indicated that there would be no net rise in the 100-year water surface elevation for the proposed fisheries enhancement. Table 2 presents the water surface profiles generated by the HEC-RAS modeling for the existing and proposed conditions. 4.0 RESTORATION PLAN Following is a brief summary of the proposed floodway enhancement activities including estimated cut and fill volumes. Berm Removal This area contains angle of repose soil piles perpendicular to the movement of flood water. The berm is a fish barrier between the pond segments. It is vegetated with annual and perennial grasses and small patches of blackberries. A total of 50 cubic yards will be removed to accommodate fish passage. Mahony Bar – Floodplain Report 9 Figure 5 Mahony Bar – Floodplain Report 10 Alcove Extension This area is 900 feet long by 200 feet wide at elevation 87 feet. All of the vegetation in this area is reed canary grass. The dimensions of the proposed extension will be 4:1 (H:V) cutslopes in silts and 2:1 (H:V) cutslopes in sand and gravel with a bottom width of 20 feet. Approximately 6,666 cubic yards of silt will be excavated; 3,600 cubic yards will be hauled and placed at or below grade in the scalped area within the upland mine disturbance; and 1,000 cubic yards will be removed from the floodway and stockpiled for use on the hops field located on an upper terrace. The remaining silt (~2,066) will be placed within the upland mine disturbance. Approximately 17,600 cubic yards of sand and gravel will be excavated from the alcove extension and removed from the site. Alcove #1-Inlet Reshaping This is a natural alcove that is a barrier to fish passage during the summer months. A maximum of 25 cubic yards of silts will be removed from the inlet. The excavated material will be placed and leveled in an open area downstream of the inlet and above ordinary high-water elevation. Pond Deepening and Silt Disposal To provide year-round ponding of ground water, a half-acre area of the Coleman pond will be deepened by an additional 10 feet to provide a minimum of 6 feet of water during low-flow conditions. In the deepening process, all pond banks steeper than 3:1 (H:V) will be flattened with an excavator. The excavated material will be sand and gravels. The volume proposed for removal from the floodway is 2,600 yards. Within the mine area, where silts have been scalped, a disposal trench 100’ by 30’ wide by 15’ deep will be excavated and filled with silts. All silts will be placed below grade of the FEMA floodway elevation of 86 feet. Care will be taken to minimize the disturbance to surrounding areas during construction of the proposed features. DOGAMI will be on site to manage the construction activities. 5.0 SUMMARY – HYDRAULIC ANALYSIS The hydraulic analysis indicated that the Mahony Bar enhancement project will result in no net rise in the 100-year water surface elevation. Also, the hydraulic modeling evaluation indicates that there will be no adverse impact to adjacent structures or landowners. This is a rural area and there are no structures in or near the floodway for several miles. 6.0 PROJECT SCHEDULE All construction work will be conducted during September 2004. Revegetation will take place during November 2004. Mahony Bar – Floodplain Report 11