WITHAM FOURTH DISTRICT INTERNAL DRAINAGE BOARD MINUTES of the proceedings of the Board at a Meeting held at the Board's Offices, 47 Norfolk Street, Boston on Wednesday 13 February 2013. ------- Present:J.E. Grant Esq. (Chairman) Messrs: J. A. Allen P. Bedford C. Crunkhorn H. C. Drake R. Hall-Jones C. Hardy A. Harrison R. Harvey R. F. Leggott F. Pickett P. Richardson D. Richmond T. W. Roberts A. Saul Mrs M. Dennis Apologies for non-attendance were received from: Messrs: B. Bowles K. Smith Mrs J. Ashton Mrs J Harrison Mrs M. Wright 1. 1.1 CHAIRMAN'S ANNOUNCEMENTS East Lindsey District Council Membership Following Stephen Doughty’s resignation as a Board Member, the Chairman was delighted to announce that Janet Harrison has been appointed to represent East Lindsey District Council but she had given her apologies for the meeting. 1.2 Heavy Rainfall event – December 2012 The Chairman said he was pleased to see IDBs mentioned in the local press and would like to thank Peter Bedford for the appreciation he recorded in the paper on 23 January 2013. These together with the thanks expressed by the Board in December 2012, were passed onto operatives at the works meeting on 25 January 2013 and the Chairman paid particular thanks to those operatives who had worked over Christmas and New Year. 1.3 Bryan Bowles The Chairman reported that Bryan had undergone surgery and that he would pass on the Board’s good wishes to him for a speedy recovery. 1.4 Eric Pickles The Chairman referred to an article on 31 January 2013 where IDBs were unfairly criticised for being secretive and pushing up Council Tax. He had drafted a strong response to Eric Pickles, Secretary of State for Communities & Local Government, as had ADA and would share any response with the Board. J Allen asked if a copy of the letter had been sent to Mark Simmonds MP and the Chairman confirmed that this would be done. 1.5 Triennial Review of the EA A response by ADA has been circulated by email to members which promoted the split of the Environment Agency between its environmental and maintenance functions. 2. DECLARATION OF INTEREST ON ANY GENERAL ITEM H Drake declared an interest in any discussion on bridges that might arise. 118 3. 3.1 3.1.1 MINUTES Board Meeting – 12 December 2012 The Minutes of the Meeting of the Board held on 12 December 2012 were submitted and signed by the Chairman. Matters Arising:Reglone – Page 84 The Chairman reported that the Chemical Regulations Directorate (CRD) has acknowledged receipt of the application for 2013 and 2014 and they were aware of the critical timing of the application. Dr J Newman had spoken to the Chief Executive and confirmed that new herbicide trials were planned for 2013 and 2014 using the funds raised by Lincolnshire IDBs and others. 3.1.2 Rate Arrears – Use of Commercial Debts Act – Page 94 The Chief Executive confirmed that this legislation did not apply to the Board as it was not deemed to be a commercial organisation. 3.1.3 Bridge Repair at Barlode Bridge Cottage The Chief Executive confirmed that the occupiers of Barlode Bridge Cottage were obtaining quotes for the bridge repair in order that the bridge could be transferred to the owners for a commuted sum. Once these quotes were confirmed, the Works Committee would convene to discuss this bridge and other bridges. He confirmed that there was FDCiA indicative funding for one bridge in 2013/14 which would also need to be discussed. 3.1.4 Parking Spaces – Update – Page 103 The Board were currently allowing two charity workers to use the Board’s car park on a trial basis, which the charity would be able to declare as a contribution in kind. 3.1.5 Toynton Works R Leggott reported back from the Lincolnshire Flood Risk Management Scrutiny Committee that the list of actual 2012 flooded properties in Lincolnshire was a concern and needed to be sorted out as soon as possible. He said the Committee was in favour of improving standards of protection across Lincolnshire and that there was, perhaps, a case for a national revision of ‘standards’. The Engineering Manager stated that he had requested that the LCC consider including Toynton St Peter in the next round of grant applications. 3.1.6 New Representative on the LGPS for Lincolnshire The Chairman highlighted the fact that ADA would shortly need a new representative on the LGPS for Lincolnshire. Interested Members were encouraged to speak to the Chief Executive. 3.1.7 Defra Study into IDB Indicators The Defra study into IDB indicators needed to prioritise the headings. The Chairman suggested putting flood protection and management ahead on environmental indicators. 3.2 Minutes of Finance & General Purposes Committee – 23 January 2013 Minutes of the Finance and General Purposes Committee held on 23 January 2013 were submitted and signed by the Chairman. 3.2.1 Matters Arising:Adoption of Officer’s Estimates – Page 106 The Chief Executive went through the estimates shown in the Agenda pack, but also circulated a revised schedule showing some amendments. Further to the Finance Meeting, discussions with Lincolnshire County Council over the cause of the many slips incurred over the last two months led to concern that 100% of the slip repairs may not be met by LCC, where the slips were caused by highways run-off. The Engineering Manager circulated a schedule of slips showing the LCC repair cost to be £80,000 and it was felt prudent to provide £40,000 in the estimates being 50% of this figure. The Chief Executive had also increased the amount to be put into the pumping station renewals fund by £25,000 to £50,000, in common with previous years. This additional £65,000 of cost had been mitigated by a £57,000 increase in Agricultural Drainage Rates as a result of significant revaluations in 2012. Although the amount raised through Special Levies had not changed as a result of the above, an additional £8,000 (net) would need to come from reserves. 119 3. 3.2 3.2.1 MINUTES - Continued Minutes of Finance & General Purposes Committee – 23 January 2013 - Continued Adoption of Officer’s Estimates – Page 106 - Continued The Chairman then asked members for comments: H Drake said he felt uneasy setting a budget with a negative outcome. The Chairman responded that the Board did have other reserves which meant that the overall level of resources was not of concern. R Leggott was concerned that the Board may be reducing the level of maintenance activity in order to balance the books. The Chief Executive assured members that this was not the case and the Engineering Manager confirmed that the Board were in a better position than before with better plant and were more efficient at the delivery of maintenance. However, the Board still has to be reactive to issues rather than proactive, owing to the loss of effective herbicides. Therefore grass has to grow and look untidy before we are able to go in and cut it. Members then discussed the issue of slips and the financial implications for 2013/14: D Richmond asked if the Board were able to plan ahead to avoid more slips happening but the Engineering Manager explained that this would be cost prohibitive. Members expressed concern about the steepness of some of the banks and related issues: A Saul asked if the low water levels had contributed to the slips. The Chairman confirmed this but stated that levels did not go down to the lowest winter level over Christmas owing to the continued rainfall. C Crunkhorn asked who would make the decision regarding slip repair payment by LCC. The Chairman said that the risk to road users was all LCC Highways risk, the Board only needed to ensure the drain was clear. P Bedford then proposed that the revised estimate be adopted and that the Drainage Rates and Special Levies be set as shown in the revised estimate, this was seconded by D Richmond and unanimously i) the Chief Executive’s Estimates be adopted. RESOLVED 3.2.2 Drainage Rate & Special Levies 2013/14 – Page 106 Following the above discussions it was:- RESOLVED i) that the rate be levied in the Sub District 1 (the former Borough Area of Boston) to be one half of the full rate: 7.34p ii) that the rate be levied in Sub District 2 (the remainder of the Internal District) be the full rate: 14.68p iii) that the Special Levies on Local Charging Authorities be set as follows: iv) Boston Borough Council East Lindsey District Council 120 £967,326.93 £336,679.63 4. CONSULTATION ON A PROPOSAL TO USE A LEGISLATIVE REFORM ORDER TO SIMPLIFY PROCEDURES IN THE LAND DRAINAGE ACT 1991 The following letter from Defra was circulated together with the Agenda for this meeting: T: 020 7238 6332 helpline@defra.gsi.gov.uk www.defra.gov.uk Date: 21 January 2012 Consultation on a proposal to use a Legislative Reform Order to simplify procedures in the Land Drainage Act 1991 Dear Consultee , I am writing to invite your views on a proposal to make a Legislative Reform Order to simplify a number of procedures in the Land Drainage Act 1991. Some Internal Drainage Boards (IDBs) may wish to make structural changes to improve their operational effectiveness and benefit from efficiencies of scale. However, the process contained in the Land Drainage Act 1991 is lengthy and bureaucratic. Defra is keen to remove any unnecessary regulatory burdens which make it harder for IDBs to operate or adapt to changing circumstances. We are consulting on proposals to streamline the Order making process for IDB structural reforms under section 3 and Schedule 3 of the 1991 Act. The changes would remove unnecessary delays and reduce burdens for IDBs. The consultation also sets out proposals to amend specific sections of the 1991 Act relating to advertisement of notices in newspapers by IDBs and the Environment Agency. The changes would allow more flexibility in the way notices are advertised so IDBs and the EA can choose appropriate cost effective mechanisms to reach their target audience. The following documents are available to view at: http://www.defra.gov.uk/consult/open . Consultation letter Consultation document Separate copy of the response form Impact Assessment List of Consultees We would welcome your views and comments on the proposals contained in the consultation document. Please see the questions in the response form in Annex B which is also attached separately to the consultation document. Responses Responses should be received by 18 March 2013. These should be sent by email to floodreports@defra.gsi.gov.uk, or by post to: Kilie Mpopo, Flood Management Team, Defra, 2D Ergon House, Horseferry Road , London SW1P 2AL. In your response, please provide your full name and appropriate contact details, including whether your response is on behalf of an organisation. All responses will be given due consideration. If you would like a hard copy of the consultation document, please contact Kilie Mpopo by email at kilie.mpopo@defra.gsi.gov.uk This consultation is in line with the Government’s Consultation Principles. These can be found at www.bis.gov.uk/policies/bre/consultation-guidance. When this consultation ends, we intend to put a copy of the responses in the Defra library at Ergon House, London. This is in order that the public can see them. Also, members of the public may ask for a copy of responses under freedom of information legislation. If you do not want your response - including your name, contact details and any other personal information – to be publicly available, please say so clearly in writing when you send your response to the consultation. Please note, if your computer automatically includes a confidentiality disclaimer, that won’t count as a confidentiality request. Please explain why you need to keep details confidential. We will take your reasons into account if someone asks for this information under freedom of information legislation. But, because of the law, we cannot promise that we will always be able to keep those details confidential. We will summarise all responses and place this summary on our website at www.defra.gov.uk/consult/. This summary will include a list of names of organisations that responded but not people’s personal names, addresses or other contact details. 121 4. CONSULTATION ON A PROPOSAL TO USE A LEGISLATIVE REFORM ORDER TO SIMPLIFY PROCEDURES IN THE LAND DRAINAGE ACT 1991 - Continued To see consultation responses and summaries, please contact the library at: Defra Information Resource Centre Lower Ground Floor Ergon House 17 Smith Square London SW1P 3JR Telephone: 020-7238-6575 Email: defra.library@defra.gsi.gov.uk Please give the library 24 hours’ notice. There is a charge for photocopying and postage. If you have any comments or complaints about the consultation process, please address them to Defra Consultation Co-ordinator, Area 2D Ergon House, Horseferry Road, 17 Smith Square, London SW1P 3JR, or email consultation.coordinator@defra.gsi.gov.uk. Thank you for your help in this matter. If you have any queries, please contact us as above. Yours faithfully, Carol Tidmarsh Flood Risk Management Team Department for Enviroment, Food and Rural Affairs Email: carol.tidmarsh@defra.gsi.gov.uk The Chief Executive said he would circulate the consultation findings when they were available. 5. WITHAM FOURTH DISTRICT IDB DIFFERENTIAL RATING HISTORY At the Finance and General Purposes Committee on 23 January 2013, some members asked for an explanation as to why the rateable property in District 1 (Boston Town) had a rate 50% of that in the remainder of the district. A History of the Board’s Differential Rating is shown below: Date 20 Jul 1935 Meeting Finance & GP Recommendation/Resolution Districts 1 to 4 at full rate, District 5 (Boston Town) at 3/4 rate but no reason given as to why. A prior proposal for this to be 2/3 was rejected 1 Aug 1935 Board Above confirmed 26 Sep 1935 Board Differential Rating Order had been submitted and confirmed by MAF Order dated 14 September 1935 24 Sep 1936 Board Rate set at the same level with rates for districts 1-4 due by 16 October and for District 5, 11 December (!) 2 Feb 1938 Finance & GP Districts 1 to 4 at full rate, District 5 (Boston Town) to change to 2/3 rate but no reason given as to why. An application was made to MAFF for this change 23 Feb 1938 Board Above amendment confirmed 15 Jun 1938 Finance & GP Differential Rating Order had been submitted and confirmed by MAFF Order 20 Mar 1940 Finance & GP Districts 1 to 4 at full rate, District 5 (Boston Town) to change to 3/5 rate but no reason given as to why. An application was made to MAFF for this change 27 Mar 1940 Board Above amendment confirmed 122 5. WITHAM FOURTH DISTRICT IDB DIFFERENTIAL RATING HISTORY – Continued 23 Apr 1941 Finance & GP The District had been amended to have sub-district 1 (Boston Town) and sub-district 2 the remainder of the district. Subdistrict 1 (old District 5) to change to 1/2 rate but no reason given as to why. An application was made to MAFF for this change 14 May 1941 Board Above amendment confirmed 17 Sep 1941 Board Differential Rating Order had been submitted and confirmed by MAFF Order on 27August 1941 There have been no changes made to this last order over the last 71 years A map showing the extent of the district was displayed in the Boardroom. The Chief Executive explained that the original Differential Rating Order reflected the fact that Boston Town was not a pumped catchment, as was the remainder of the District. 6. 6.1 6.1.1 MEETINGS WITH OUTSIDE ORGANISATIONS - December 2012 – January 2013 (Part) Reports Lincolnshire County Council Flood and Drainage Liaison Meetings - ELDC area, - 11th December 2012. Attended by the Engineering Manager In addition to discussing flood and drainage issues these meetings have been expanded to include pre-application discussions with developers to ensure that flood and drainage matters have been satisfactorily addressed. Discussion also took place in respect to IDB works adjacent to footpaths. This provided an opportunity to highlight Highways activities that impact on IDBs. 6.1.2 Environment Agency & IDB FDGiA Workshop - 17 December 2012 - ELDC Offices, Manby Attended by the Chief Executive Designed to provide IDBs with practical assistance with the issues that grant claims generate. The main unresolved issue was “Double Counting”, where separate Risk Management Authorities (RMAs) claim the same properties or other assets when demonstrating the area of benefit protected by new schemes. This is a current issue with Hobhole refurbishment as the Boston Barrier is claiming all of the properties in Boston Town, when some of these are actually protected by our Board. The EA have failed to provide any practical guidance on this issue. The Chief Executive attended a subsequent meeting with the EA to iron out this point on 7 January 2013 and the Project Appraisal Report for Hobhole is being amended in light of these discussions. 6.1.3 Lincolnshire FRM Partnership Management Group Meeting-18 December 2012 - Anglian Water Offices , Lincoln Attended by the Chief Executive The main topics covered were: The LLFA have nearly completed their review of Sect.19 flooding instances from summer 2012. Witham Fourth only have one incidence which has been discussed by the Board at Toynton. Community Reliance Funding is being offered by DEFRA for any schemes or initiatives that do not include actual flood defences. It was suggested that ‘Community Flood Stores’ be put forward whereby up-to 50 Lincolnshire communities would be provided with a flood store container, managed by the Parish Council, that would contain wheelbarrows, shovels and sand bags to ensure fast & local resilience to flood risk. (This was submitted on 15 Jan). Anglian Water’s engagement and attendance at Partnership meetings had been poor in the 2 years since it was formed. This was however, improving with the appointment of Jonathan Cummins who was keen to increase engagement with partners at all levels. 123 6. 6.1 6.1.4 MEETINGS WITH OUTSIDE ORGANISATIONS - December 2012 – January 2013 (Part)-Cont: Reports - Continued Anglian Water, Covenham to Boston Water Main, 18th December 2012 Attended by the Engineering Manager This project has been delayed by wet weather but work has now commenced on Phase 2 from Miningsby to Boston. The meeting enables IDBs and the EA to discuss consenting issues with the consultants and contractors working on behalf of Anglian Water. The Engineering Manager said that the project had run into operational difficulties as there were different versions of GIS Mapping being used by contractors for Anglian Water and the project had stalled for a moment. 6.1.5 ADA Policy & Finance Meeting - 16 January 2013 - Farmers’ Club, London Attended by the Chief Executive The main outcomes were: 6.1.6 DEFRA have commissioned two studies looking at a) IDB Beneficiaries and b) Performance indicators. IDBs have had direct input into the studies and ADA is assisting with the analysis. A Report is due out by the end of January 2013 which will be circulated to Boards. ADA have prepared a very useful chart (seen on the front of the last ADA Gazette) which shows partners the many beneficiaries of IDB work. This will be sent to Boards to send out with Annual Rate Demands/Special Levy notices. Governance and Accountability – The Audit Commission have drafted a replacement to the Practitioners Guide for IDBs which the Chief Executive is developing on behalf of ADA. The new Guide will be a one-stop-shop for all sizes of IDB informing them of their governance responsibilities and the form that their financial information should take. It will also provide a new suite of ADA approved policies e.g. Members’ Code of Conduct that all Boards should be following. This is being welcomed by DEFRA in light of the recent damning Caldicott & Wentlooge IDB Report. In Wales, The Forestry Commission, EA and Natural England will shortly amalgamate into one Environmental body from 1 April 2013. The Triennial Review of the EA and Natural England in England is currently out for consultation and ADA are suggesting an alternative to the status quo or a similar amalgamation. They suggest that the Environmental functions of the EA be amalgamated with Natural England to set policy and police environmental matters, but that the FCERM functions of the EA be reorganised on a catchment basis, similar to the old River Authorities. This alternative was supported by committee members. ADA Environment and Technical Committee - 16th January 2013 - London Attended by the Engineering Manager Matters covered included: 6.2 6.2.1 Discussion with a representative of Defra in respect to updating the IDB model byelaws, in particular in relation to works underneath a watercourse Increasing Section 23 consent charges ADA Demonstration 2013 Chemical control of aquatic vegetation Climate Change Act 2008 – ADA are to report on behalf of IDBs in respect to climate change adaptation Health and Safety – of particular note, given the weather, was the findings of the case involving the death of an EA contractor. His machine overturned into a watercourse in icy conditions. Appointment of Delegates – Future ADA Meetings Lincs ADA Branch Meeting – 21 February 2013 Any Members wishing to attend were asked to inform the Chief Executive. 124 6. 6.1 6.2.2 MEETINGS WITH OUTSIDE ORGANISATIONS - December 2012 – January 2013 (Part)-Cont: Reports - Continued Lincs ADA Annual General Meeting – 17 April 2013 The Chief Executive explained that the AGM would be held at The Bentley Hotel in Lincoln and would include a tour of the new Seimens site and Whisby Nature Reserve. Members wishing to attend were asked to inform the Chief Executive. 7. 7.1 7.1 CHIEF EXECUTIVE AND FINANCE MANAGER’S REPORT BOARD’S DEPOSITS Bank Balances 26 January 2013 General Account Special Interest Account Money Market Deposits £ £ £ 7.2 Account Type National Westminster Lloyds TSB (Apr 2013) Lloyds TSB (Aug 2013) Instant Access 12 Month Bond 12 Month Bond TOTAL £ £ £ £ 10,000 524,268 1,498,529 2,032,797 Cr Cr Cr Cr Investment £ 190,428 500,000 500,000 Interest Earnt 1.15% 3.15% 3.25% 1,190,428 Fixed Term Deposit – Reinvestment The Board were requested to grant Delegated Powers to the Chairman and the Chief Executive to re-invest the £500,000 Bond, due to mature in April 2013, at a suitable rate, and it was:RESOLVED i) ii) 7.2 Cr Cr Cr Cr Lloyds Bank Fixed Term Deposits Bank 7.2.1 26 January 2012 902,074 1,190,428 2,092,502 that the £500,000 bond due to mature in April 2013 be reinvested for a further 12 months at the best interest rate available at the time. that the Chief Executive advise the Chairman of the details as soon as they are available in accordance with the Board’s Investment Policy. PAYMENTS MADE BY ACCOUNTS COMMITTEE 2012 November (£32K Cowbridge Lock) 2012 December (£138K Atlas) £ £ 183,152 306,191 7.3 CLAIMS FOR COMPENSATION None. 7.4 7.4.1 EXPENDITURE TO 31 DECEMBER 2012 Statement of Expenditure A statement of expenditure from 1 April 2012 to the 31 December 2012 is shown below for Members information. Expenditure Summary EXPENDITURE Annual Estimate 2012/2013 1 April 2012 to 31 March 2013 £ Administration Employees Establishment Charges Computer Development Revaluation of Agricultural Land & Buildings Elections £ Actual 9m Expenditure 2012/2013 Target 75% 1 April 2012 to 31 December 2012 £ £ % 271,500 190,212 70% 65,500 9,500 1,000 2,000 54,423 0 0 816 83% 0% 0% 41% 125 7. 7.4 7.4.1 CHIEF EXECUTIVE AND FINANCE MANAGER’S REPORT - Continued EXPENDITURE TO 31 DECEMBER 2012 - Continued Statement of Expenditure - Continued Annual Estimate 2012/2013 EXPENDITURE Actual 9m Expenditure 2012/2013 1 April 2012 to 31 March 2013 £ 85,000 50 Pensions (Employers Contributions) Bank Charges 1 April 2012 to 31 December 2012 £ £ 63,667 298 309,416 % 75% 596% 71% 1,348,933 1,102,068 97% 62% 180% 38% 68% 79% 82% 100,210 10,000 25,000 50,000 61,000 310,000 43,075 7,790 44,221 68,722 154,879 0% 113% 50% 2,339,693 1,730,171 74% 434,550 Maintenance Weed Control Cleansing Asset Improvements - Urban Watercourses Asset Improvements - Ordinary Watercourses Pumping Stations Depot 562,500 222,000 35,000 20,000 469,433 40,000 Environment & Conservation Additional Plant Bridge replacements Cowbridge lock repairs Pumping Station Replacement Fund Loan Charges Environment Agency Precept Target 75% £ 544,466 137,385 62,848 7,675 318,111 31,583 43% 78% 0% 7.4.2 Observations of the Expenditure Account to Date The observations for this period are as reported to the Finance and General Purposes Committee on 23 January 2013 7.5 Revaluation of Assessments The Board are requested to determine the following ‘in house’ new values in respect of Agricultural Assessments A/c No Assessment No Reason Present Value £ 56 52010103 52010104 52010105 52010106 52012345 Appealed against separate value for Poultry Unit 7793 6082 18924 5980 43456 7943 6199 19288 1256 11242 482 53010498 53010499 1011.53 1454.02 1031.76 1483.10 614 51010156 Buildings on on Filed No.2445 -Poor Condition Erection of Cattle Shed 450sq metres (incl P.Unit) Recommended Value £ £16,980 17,307 126 Comments Back dated to 1.4.12 Ratepayer/ agent disputed poultry unit being rated separately (23.693ac @£50 +6%) 0 to 2% Increased from 4% to 6% If built. (Land prepared Jan’13) 7. 7.5 CHIEF EXECUTIVE AND FINANCE MANAGER’S REPORT - Continued Revaluation of Assessments - Continued A/c No Assessment No 1697 28011492 28011493 28011494 Ag Build on site 60’x65’ 1101 29011112 Buildings on site 1174 08010193 08011038 08011039 180sq.m. Extension to existing building NB Not previously charged for any building Erection of Agr. Store shed 2139 20010754 78 52010152 52010154 52010156 52010157 53010073 Reason Buildings on TF4253-3467 Present Value £ Recommended Value £ 71 23 106 2% added 72 23 108 181 185 1235 1499 662 1260 1529 675 351 358 94.54 187.82 78.83 354.47 892.66 94.39 191.58 80.41 361.56 910.51 Comments 0 to 2% Increase from 0 to 2% 0 to 2% Foundations in Jan’13 0 to 2% RESOLVED that the above recommended values be determined. 7.6 Rate Arrears Update 31.3.12 22.5.12 8.8.12 14.9.12 9.10.12 20.11.12 12.12.12 26.1.13 Debts from 31.3.2012 + prior £137,262 £109,090 £94,870 £94,147.90 £81,209.57 £81,045.01 £81,069.29 £70,645.87 Percentage 100% 79% 69% 68.59% 59.16% 59.04% 59.06% 51.47% 1.4.12 22.5.12 8.8.12 13.9.12 9.10.12 20.11.12 12.12.12 26.1.12 £1,090,878.33 £1,038,196.33 £420,427.14 £339,257.90 £282,954.43 £157,659.90 £111,524.38 £89,755.12 100% 95% 38.50% 31.10% 25.94% 14.45% 10.22% 8.23% Debts for 2012/13 (Aug 2011 = 53%) RESOLVED that the above Rate Arrears Update be noted. 7.7 Pay award for 2013/14 The Pay & Conditions Committee have not yet discussed this with the Union, but it is expected that IDBs, as small public bodies, will comply with the Government’s 1% cap on public sector pay for 2013/14 and 2014/15. 7.8 Night-working terms and Conditions The intense working over the Christmas period threw up an anomaly whereby pump operatives working at night (6pm – 6am) at weekends, receive the same rate of pay as those working during the day (6am – 6pm). This needs to be rectified in accordance with the provisions in the white book. RESOLVED that the rate be amended to fall in line with provisions in the White Book. 127 7. 7.9 CHIEF EXECUTIVE AND FINANCE MANAGER’S REPORT - Continued FDGiA Progress FDGiA Progress at 28 January 2013 Code Key Date % applie Grant d Costs £ Grant £ 2011-12 Vertical Door at Cowbridge Emergency CM Apr-11 45% 44,000 10,000 Approved and claim in progress 2011-12 Hobhole Tidal Door W4CAP11(A) DEF Jul-10 100% 42,000 42,000 FDGIA approved in 2011/12 but not able to claim as merged into project W4CAP 11(B) in 2012/13 2012-13 Culverted Watercourse lining W4CAP9 CM Jun-12 100% 45,000 45,000 PAR with E.A. for Approval 2012-13 Hobhole Refurbishment W4CAP11(B) DEF Jun-12 100% 577,000 577,000 Attended PAB Meeting on 27 June 2012. PAR re-written. Now with EA for final approval. Year Project Status The Chief Executive highlighted the Hobhole Refurbishment project which had still not received EA approval. The latest hold-up was in respect of Fish & Eel Pass Regulations following a case-study report by consultants Royal Haskoning, working for the Environment Agency. They had suggested £1.6m of work at the Pumping Station on the back of a £577k project which was understandably being resisted by the Board. The Chief Executive expected to be able to reach a compromise in order that the project could be approved but the report had only just been received. RESOLVED that the Chief Executive and Finance Manager’s Report be adopted and approved. 8. 8.1 8.1.1 ENGINEERING MANAGER’S REPORT NO: 1/13 Works carried out during November, December & January (part) 2012 Maintenance Works Weed Control The bulk of the weed control work is complete with flailing of drains and sewers finished. Weedcutting (herder basket) work will continue into February. Hand roding (scythe work) is complete. 8.1.2 Sunken Tunnels A number of the Board’s watercourses pass beneath the Environment Agency Catchwater system. As carriers of highland run-off it is particularly important that the upstream ends of the “sunken tunnels” are kept free of debris. These were inspected and cleared during December. 8.1.3 Bush and Tree Control Bush removal has taken place on the Twenty Foot Drain. Programmed bush and tree clearance on the Bellwater and Houghbridge drains has been postponed due to priority work on slip repairs (see below). 8.1.4 8.1.4.1 Slip Repairs Fodderdyke Drain The repairs to a slip just upstream of Midville railway crossing was completed on 20th December. As the slip was caused by a burst water main the cost of this work is to be met by Anglian Water. 128 8. 8.1 8.1.4 8.1.4.1 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Maintenance Works - Continued Slip Repairs - Continued Fodderdyke Drain - Continued Fodderdyke Drain upstream of Midville railway 8.1.4.2 Winter Slips 2012/13 Following the heavy rainfall over Christmas there have been a lot of slips in drains and sewers ranging from small slips that can be removed with a digger to much larger requiring piling. Whilst preliminary site work commenced on the repair of slips on the upper Hobhole Drain the ongoing problems with waterlogged ground and January snowfall meant it was unsafe to continue due to bank stability concerns. The slips on the Gride at Old Leake have undermined the highway resulting in a road closure and diversion as there is a risk of collapse of the road. The closure is almost universally ignored by the public and in particular lorries that are most at risk, however the Lincolnshire County Council are taking steps to improve the situation. A meeting was scheduled for 21st January with officers of the LCC to discuss slips near highways however it was postponed at their request due to overnight snowfall and has yet to be rescheduled. A summary table of slips is shown below: Number of slips No. Location Description/cause /Total Length 1 2 3 4 5 6 7 3/115, The 4 No, 95m Highways run-off, no verge Gride approx25m Upper Hobhole Saturated batters, poor 3 No, 80m various ground conditions Upper Hobhole Saturated batters, poor To be confirmed various ground conditions Fodder Dike, Saturated batters, poor 80m New Leake ground conditions Lower Hobhole, Saturated batters, poor 50m Nunns Bridge ground conditions Anglian Water, burst water Castle Dyke 15m main 2/70, Cannister 3 slips, highways run-off, no 20m Lane, Frithville verge 129 Repair method Priority Timetable/ Notes P High Jan/Feb LCC to pay? P High Jan/Feb S Med Feb/Mar P Med Mar/Apr tbc Low Autumn F Med tbc Low Before April AW to pay. Summer LCC to pay? 8. 8.1 8.1.4 8.1.4.2 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Maintenance Works - Continued Slip Repairs - Continued Winter Slips 2012/13 – Continued No. 8 9 10 Location 1/27b, New York Rd, Dogdyke 1/33, Castle Dyke Bank 4/22, Off Church Rd, Frieston Number of slips /Total Length Description/cause Repair method Priority Timetable/ Notes 50m Highways run-off, no verge tbc Med Spring/summer LCC to pay? F Low Summer F Low Summer F Med tbc Low tbc Low tbc F Low tbc F Low tbc tbc 11 West Fen Drain 12m 12 Faunt Bridge 7m 13 14 15 4/22, West of Church Road 2/64, Trader Bank 3/106, Trader Bank Saturated batters, poor ground conditions 3 slips, saturated batters, poor ground conditions 10m Anglian Water contractors 25m – 2 slips 25m Anglian Water, burst water main Saturated batters, poor ground conditions Saturated batters, poor ground conditions 16m, 8m, 8m 3 slips, Spring, AW to pay Summer, AW to pay Repair method – P = piling, S = stoning, F = faggoting Note – Priority is determined in respect to drainage. Highways Authority may view priority differently. Agreement has been reached with Anglian Water in respect to payment for slip repairs but at the time of writing this report we are still waiting for a response from the LCC. It is expected to find more slips in smaller watercourses over the coming year. A number of small slips in sewers have already been repaired. . Large slip on the Hobhole Drain 130 8. 8.1 8.1.4 8.1.4.2 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Maintenance Works - Continued Slip Repairs - Continued Winter Slips 2012/13 – Continued Collapse of bank adjacent to highway on The Gride. Note undermining of carriageway. Typical patch repair to highway on The Gride. Note encroachment of the highway on to the verge, getting ever closer to the drain edge. J Allen asked if the Board had closed the Gride? The Engineering Manager stated that this was done by LCC Highways. 131 8. 8.1 8.1.4 8.1.4.2 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Maintenance Works - Continued Slip Repairs - Continued Winter Slips 2012/13 – Continued C Hardy asked what was there to stop another slip happening in the same place? D Richmond was concerned that without a proper kerb, articulated lorries would continue to drive near or over the edge of the road. The Chairman summarised by saying that he and the Engineering Manager would shortly meet LCC to discuss the way forward and establish a principle for future slips and highway maintenance. 8.2 8.2.1 Rainfall Monthly Rainfall Totals – Lade Bank Total Rainfall (mm) Average Nov Dec Jan 79.7 117.9 44.2 53.78 50.79 47.28 148 232 94 Total 241.8 151.85 159 Month 2012 % of Average Rainfall was recorded on 26 days out of 31 in December at Lade Bank. It was the third wettest December on record. 8.2.2 2012 Rainfall 2012 was the second wettest year on record at 794.5mm (1883 saw 852mm). At least two nonmet office rain gauges reported rainfall in excess of that amount with E W Bowser recording 951mm. If you disregard the drought at the start of the year, the period April to December was the wettest on record at 720mm (160% of average of 450.45mm) and exceeds any year in living memory by at least 70mm. Met Office Data for 2012 shows that by March 2012 rainfall was 50 to 75% of average but during the summer it had increased to between 110 and 170% of average across our catchment. Details of the 2012 Annual Rainfall are shown on the following pages. 132 Lade Bank - Rainfall Statistics at 31 December 2012 JANUARY Maximum Minimum YEAR Mm YEAR mm 1956 133.15 1953 17.53 1943 105.45 2005 16.20 1948 97.32 1901 14.23 1999 95.30 1905 13.98 1960 91.98 1997 13.40 AVER. 47.28 2012 33.70 2007 1979 1967 1937 1937 1889 AVER. 2012 MAY 108.10 105.10 104.69 103.67 103.67 95.54 44.39 48.20 1883 1896 1965 1993 1991 AVER. 2012 SEPTEMBER 205.57 1915 138.99 1996 106.47 1969 102.70 1959 102.40 1898 47.99 42.20 1947 1959 1935 1970 1989 FEBRUARY Maximum Minimum YEAR mm YEAR mm 1900 110.03 1947 5.59 1977 109.00 1886 5.34 1958 85.89 1959 5.08 1966 81.57 1891 1.78 1980 75.90 1985 1.70 AVER. 36.39 2012 13.40 10.67 6.35 5.59 5.34 4.00 2012 2007 1966 1978 1978 1997 AVER. 2012 JUNE 129.80 126.70 123.49 122.90 122.90 120.00 46.94 129.80 10.16 6.70 6.35 4.57 4.07 1903 1960 1885 1892 1891 AVER. 2012 OCTOBER 145.35 133.15 121.97 119.17 104.44 55.60 74.10 Wettest month in 2012 1976 1887 1960 1962 1925 7.90 7.62 7.62 4.57 2.03 1920 1965 1978 1947 1972 10.93 9.40 8.90 5.84 4.32 MARCH Maximum Minimum YEAR mm YEAR mm 1947 96.56 1929 7.11 1981 92.20 1944 6.61 1909 79.53 1935 6.61 5.08 1988 77.60 1938 4.50 1951 75.47 2011 AVER. 37.48 2012 27.40 1915 1936 1888 2007 2002 AVER 2012 JULY 168.47 151.70 138.23 136.30 125.30 54.00 67.00 1921 1952 1911 1906 1982 NOVEMBER 1970 115.11 1889 1946 115.11 1896 2000 100.10 2011 1939 99.10 1909 1969 98.34 1920 AVER. 53.78 2012 79.70 APRIL Maximum Minimum YEAR mm YEAR mm 2012 117.50 1974 5.30 2000 106.00 1938 4.32 1970 81.57 2007 4.30 1983 79.00 2011 3.90 1981 77.40 1893 2.54 1981 77.4077 AVER. 37.20 2012 117.50 10.42 9.66 8.13 6.10 3.90 1912 1917 1903 1927 1927 1992 AVER. 2012 AUGUST 156.27 1983 113.07 2003 110.53 1995 107.48 1913 107.48 1947 106.00 58.67 43.60 20.33 18.30 18.10 17.02 11.43 1915 1965 2012 1978 1914 AVER. 2012 DECEMBER 124.76 1941 121.71 1913 117.90 1933 117.00 1890 112.06 1932 50.79 117.90 5 Wettest months recorded Driest month in 2012 TOP 10 ANNUAL RAINFALLS RECORDED Maximum YEAR mm 1883 852.00 2012 794.50 1960 761.54 1903 733.08 1966 730.28 2000 711.25 1912 705.89 1886 704.37 1965 703.60 1992 701.50 Minimum mm YEAR 1921 337.19 1887 393.35 1890 396.14 1995 428.80 1947 438.32 1934 439.59 1964 443.66 1959 444.68 2011 446.60 1905 450.77 AVER. 569.51 2012 794.50 Maximum Daily Totals YEAR MONTH DATE mm 1883 SEP ? 91.00 1968 JUL 10 63.75 1993 OCT 12 59.10 1912 AUG 26 57.15 1956 JAN 8 54.61 2002 JUL 30 53.40 1931 AUG 8 51.05 1967 AUG 10 48.51 1900 DEC 31 48.26 1978 JUN 29 47.50 2012 24.8 1894 - 2012 (excluding 1901) data unavailable for missing year 133 9.20 6.30 3.00 0.76 0.51 15.75 15.75 13.47 12.45 8.64 5 Driest months recorded Rainfall 2012 Rainfall Station Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec Total (mm) Lade Bank Hobhole Carrington Estates New York Leverton 33.7 37.0 38.3 36.0 49.4 13.4 21.5 12.4 16.2 8.7 27.4 25.9 30.8 35.4 22.0 117.5 130.0 113.9 112.7 120.6 48.2 36.3 52.2 48.0 47.4 129.8 109.6 135.4 128.8 113.9 67.0 107.6 52.5 51.9 66.1 43.6 50.9 66.9 49.8 49.1 42.2 40.3 47.7 42.9 39.5 74.1 78.2 59.8 53.3 80.2 79.7 82.9 75.7 72.5 84.5 117.9 100.5 114.9 98.2 106.1 794.5 820.7 800.5 745.7 787.5 Av. (mm) (ins) (mm) (ins) Monthly Av. (mm) Monthly Av. (ins) 38.88 1.53 14.44 0.57 28.30 1.11 118.94 4.68 Monthly Average Lade Bank 1883 to 2011 (129 years) (mm) 47.28 36.39 37.48 37.2 (ins) 1.86 1.43 1.48 1.46 2012 Average/Lade Bank 129 Year Average % 82.2% 39.7% 75.5% 319.7% 46.42 1.83 123.50 4.86 69.02 2.72 52.06 2.05 42.52 1.67 69.12 2.72 79.06 3.11 107.52 4.23 Yearly 789.78 31.09 44.39 1.75 46.94 1.85 54 2.13 58.67 2.31 46.99 1.85 55.6 2.19 53.78 2.12 50.79 2.00 569.51 22.42 104.6% 263.1% 127.8% 88.7% 90.5% 124.3% 147.0% 211.7% 138.7% 2006 552.33 21.75 96.0% 2007 685.3 26.98 119.1% 2008 616.8 24.28 107.2% 2009 580.57 22.86 100.9% 2010 551.7 21.72 95.8% 2011 446.6 17.58 77.6% The 30 Year International Standard Average at Lade Bank (1961 to 1990) Lade Bank - Previous years Year Av. Total for Area (mm) Av. Total for Area (ins) % Int. Standard Av. 2000 711.25 28.00 123.6% 2001 652.48 25.69 113.4% 2002 709.92 27.95 123.3% 2003 529.03 20.83 91.9% Total (ins) 138.0% 142.6% 139.1% 129.5% 136.8% 575.62** 2004 672.18 26.46 116.8% 2005 545.58 21.48 94.8% 134 % International Standard Av. at Lade Bank** 2012 789.78 31.09 137.2% 137.2% 135 8. 8.3 8.3.1 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Water Level Management Pumping and Sluicing Heavy rainfall saw diesel pumping at Lade Bank and Hobhole Pumping Stations at the beginning of November and then again at the end of the month into the first week in December. By this time the catchment had become very wet and almost any extra rainfall resulted in diesel pumping. Twenty four hours a day diesel pumping commenced on 21 December 2012 continuing through the holiday period ceasing at Lade Bank on 27th December 2012 and at Hobhole on 1st January 2013. During 2012 the Board had pumped around 29 billion gallons of water which was enough to fill Rutland Water. R Leggott suggested that this was a fact we ought to put in the press, highlighting the reason why Boston had been prevented from flooding. A Saul queried the rainfall difference between Benington and Leverton but the Engineering Manager said that this showed the impact of severe localised weather events. Due to the 24 hr pumping at Hobhole the station was using a tank full of diesel in about 5 days. Of the 4 diesel tanks on site two have been drained down in preparation for their replacement so stocks of diesel over the holidays were of concern. We were able to secure regular re-supply however contingency plans were put in place to obtain fuel via the Black Sluice IDB and Board Members in an emergency. All pumps performed satisfactorily throughout however at the completion of operations a small number of repairs were necessary at Hobhole Pumping Station. Sluicing at Cowbridge has been continual since the start off winter but the heavy rainfall of December saw all three sluice doors wide open for long periods. At one point one door became stuck open due to a piece of wood jammed in the door recess but this was successfully removed. During the period the telemetry system proved most useful permitting all operatives engaged in water level management to monitor and control levels. Problems with the telephone line were experienced at Wrangle Pumping Station resulting in a loss of data communication and consideration will need to be given to switching to mobile telephone technology for this location. The weekend of 26th and 27th January, snowfall followed by rainfall and a rapid thaw resulted in a rapid raising of water levels and all pumps operational again. Water levels were higher than those experienced over the holidays for a very short period of time. 8.3.2 Operational Issues Over the holiday period a number of localised problems were reported. These mostly related to blocked culverts or weed blockages resulting in problems with septic tanks or localised high water levels. The District Foremen responded to these problems over the holiday period. No problems with property flooding were reported. 8.4 8.4.1 Pumping Stations Routine Maintenance Routine maintenance and inspections have been carried out at all sites. 8.4.2 Hobhole Pumping Station A number of faults were reported at the December Board meeting. The current position is as follows: Pump Fault Current Status Pump 2 Very noisy in operation. Control panel fault – door interlock fused switch failed. Pump repaired and installed. Pump 3 Control panel fault - temperature overload detection unit faulty Repaired. Pump 4 Seized up causing panel capacitors to fail Pump repaired and installed. Capacitors renewed. 136 8. 8.4 8.4.3 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Pumping Stations - Continued Pumping Station Annual Statistics Total Pump Hours 2012 Total Volume 2012 (Million m3) Hobhole Oil Electric 1100 6738 88.28 41.60 (54 yrs) 212 Lade Bank Oil Electric 831 3099 32.70 23.15 (72 yrs) 141 Wrangle 1645 5.22 3.32 (51 yrs) 162 Leverton 1301 2.20 1.59 (36 yrs) 138 Benington 1963 3.32 1.97 (36 yrs) 169 Station 8.5 Annual Average Volume Y/E 2011 (Million m3) 2012 % of Annual Average Planning Matters No. of Applications November December January (pt) Returned with Comments Boston Borough Council East Lindsey District Council Lincolnshire County Council 9 1 - 10 3 - 4 - Returned ‘No Observations’ Boston Borough Council East Lindsey District Council Lincolnshire County Council 1 - 1 1 - 1 - TOTAL 11 15 5 8.6 Waste Management Fly-tipped rubbish has been collected around the District. The following expenditure has been incurred: November Detail December January Labour 116 Plant 44 Misc Fly Swat 1,000 TOTAL 1,160 8.7 Commercial Management of Fish Stock in Board’s Drains The Board has been approached by Mainstream Fisheries Ltd based in Spilsby, with a view to the managed netting and sale of fish from the Board’s watercourses in a sustainable manner. Mainstream Fisheries Ltd is a major supplier of coarse fish to the Environment Agency, coarse fishing lakes and for the restocking of watercourses following environmental accidents. Whilst they have commercial breeding programmes they also have a regular demand for fish from natural waterways. Mainstream are regulated by the Centre for Environment, Fisheries and Aquaculture Science (agents of Defra). Removal of fish from the Board’s system would be carried out following fully licensed, audited and monitored procedures on a sustainable basis. 137 8. 8.7 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Commercial Management of Fish Stock in Board’s Drains - Continued Average income from managed waters is approximately £1800 per acre, with Bream selling for £2 per pound and specimen Carp worth between £233 (20lb) and £1258 (over 35lb) each. The Board can only sell fish from watercourses that it owns (i.e. the majority of the main drains) and not all channels will be suitable for management in this way but the West Fen Drain alone covers about 20 Acres with potential for significant income to the Board. The Board are requested to consider this matter. RESOLVED that the sale of fish should be permitted, perhaps for a 12 month trial period, but that extraction area should be away from those drains with fishing rights. 8.8 8.8.1 Plant Replacement Plant Renewals On 9th January 2013 the Board took delivery of an Atlas 160LC tracked hydraulic excavator to replace its JCB JS130 purchased in 2001. The new machine was purchased from T D L, Tankersley, South Yorks at a price of £115,000 and has just had its first service. 8.8.2 Sale of Plant A list of plant items replaced during the year and other equipment no longer required has been prepared and advertised for sale by tender, with sealed bids to be received by the 21 February 2013. 8.9 Cowbridge Lock On 3rd January 2013 the Board’s lorry driver was driving home past Cowbridge Lock in the early evening. He spotted lights and activity around the lock. The matter was brought to the attention of the Engineering Manager who immediately went out to see what was happening. As the activity was still taking place he called the Police who came out within about 10 minutes but the persons involved had by then left. An inspection around the lock found 3 dead fish in the lock and another on the lock side but no damage to the lock itself. Details of a van seen at the location were given to the Police who subsequently found the vehicle parked near the West Fen Drain in Frithville. No further response or information has been received from the Police. 8.10 Water Framework Directive The Engineering Manager met with officers of the Environment Agency on 16 th October to discuss Water Framework Directive Mitigation Measure Investigations. The purpose of the investigations was to look at potential changes to watercourse morphology (e.g. creation of riffles, 138 8. 8.10 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Water Framework Directive - Continued meanders, etc) to provide environmental enhancement. The investigations affected parts of the Newham Drain, Bellwater Drain and watercourses in the West Fen. The outcome of the discussions was that change to morphology is not appropriate for the affected IDB watercourses and no further action is required. The EA are considering a fish pass at a flow gauging site at Tumby Woodside on the West Fen Catchwater Drain. 8.11 Lead Local Flood Authority Investigations The Lincolnshire County Council are in the process of finalising their investigations into flooding of properties in 2012. Only one property was reported to have experienced internal flooding in the Board’s area at Holland Lane, Toynton St Peter. The LCC have to determine if the Risk Management Authorities responsible for managing the incident are exercising their duties and have concluded that the Witham 4th have done so. 8.12 8.12.1 Health & Safety Accident Reporting No accidents have been reported for the period of the report. 8.12.2 Lifting Operations and Lifting Equipment Regulations All lifting gear has been inspected in accordance with the regulations. 8.12.3 Electrical Safety All electrical equipment has been inspected and tested (“PAT” testing). 8.12.4 Pressure System Safety Regulations All pressure vessels (i.e. workshop compressors, pumping station compressors and air starter bottles, etc) have been inspected in accordance with the regulations and Board’s written scheme of examination. 8.12.5 Training Two operatives have been trained in the safe use of rodenticides for the control of rabbits and moles. This is due to changes in legislation that require users to have a relevant qualification in order to purchase as well as use certain vermin control products. 8.12.6 Employee Meeting At a meeting with all District Operatives and Pumping Station Staff on 25th January, new additions to the employees handbook were issued. Employees also appointed their safety representatives for the coming year. 8.13 Rechargeable Works Rechargeable works invoiced for the period 1st November to 31st December 2012, are shown below: Hire of Low Loader Witham Third IDB Black Sluice IDB Environment Agency M Belton Hire of Pick-up Establishment Expenses Energreen UK Ltd (Show Sponsorship) Stock Purchase R Collin Ltd £ 1,434.23 1,722.65 3,069.02 382.80 21.84 83.33 163.86 139 8. 8.13 ENGINEERING MANAGER’S REPORT NO: 1/13 - Continued Works carried out during November, December & January (part) 2012 Rechargeable Works - Continued Commercial Hire of Low Loader Eastern Harvesters Ltd 170.51 Works Carried out Anglian Water Mr P Cade W Bradley and Sons The Occupier 632.57 163.03 162.30 191.04 RESOLVED that the Engineering Manager’s Report No: 1/13 be adopted and approved. 9. 9.1 9.2 ENVIRONMENT OFFICER’S REPORT Biodiversity Updates: Subject Boston Borough Council Local Wildlife Site review Details The Borough recently commissioned ecologists to conduct a 5 yearly survey of their designated LWS’s. While the final report has yet to be issued, the Greater Lincolnshire Nature Partnership has since been in touch regarding the important marsh mallow in sewer 4/23. This survey revealed that as a result of the Boards management regime for this sewer, many more plants are now established on 650m downstream in 4/22. This reflects the positive management the Board implements during its routine operations. In March the GLNP LWS panel will meet to decide if this additional 650m should be an extension to the existing LWS. Woodland management Tree and bush management is tentatively programmed for the Bellwater Drain in February which will involve closing one lane of the adjacent highway to work under live power lines. LWT have also agreed to further tree management of the hawthorn thicket LWS on the lower Hobhole if time allows. Other tree management work planned for West Fen and Houghbridge Drains has been postponed due to inclement weather and ground conditions. Hedge Grant 50% £787.34 In October, the Board secured a Lincolnshire County Council hedge planting grant for 1,800 native British mixed species saplings to fill a 450m gap along the lower Hobhole western bank. Our Operatives, local volunteers and perhaps a few inmates from HMP North Sea Camp will assist with planting in early February. Boston Borough Council Operation Fly Swat On behalf of the partnership, in December, the Environment Officer submitted an entry for the Environment Agency’s ‘Project Excellence Awards 2013’ in the Partnership and Sustainability category. “The Project Excellence Awards will allow those project teams who are making a significant contribution to the realisation of delivering more for the environment, taking a positive approach, embracing diversity and helping deprived communities to be held up to others as examples of how we [the Agency] want to work in the future. This will also include how the teams have demonstrated a commitment to enhancing habitats and tackling the challenges of the Water Framework Directive”. Many Fly Swat partners have been complimentary of the entry, the winner of which will be announced in March. Operation Fly Swat has also been short listed for a national local government public sector partnership award. The winner will be announced at a formal ceremony in London on March 13th. 140 9. 9.2 ENVIRONMENT OFFICER’S REPORT - Continued Boston Borough Council Operation Fly Swat - Continued Also on March 13th, Jen Moore, Boston Borough Council’s Environment and Sustainability Officer, will give a presentation alongside Ian Warsap, Black Sluice IDB Operations Engineer, on Fly Swat partnership working at the ADA Executive Meeting in Peterborough. 9.3 Greater Lincolnshire Nature Partnership (GLNP) Following the successful GLNP launch on November 8th, the Biodiversity Services Officer, Catherine Collop, who played a significant strategic role in the partnership, left to undertake a PhD leaving a significant post vacant. No suitable candidates were interviewed after an initial advertisement of the post but a second attempt proved a success. Amy Robinson, an experienced and qualified wildlife officer will fill this position in April. 9.4 Fens for the Future – update After a positive launch in November, this initiative is now seeking to appoint a part-time Project Officer to move the strategy forward. Considerable momentum has gathered since the launch (detailed on P.34 in the Winter 2012 ADA Gazette), with the Department of Ecology at the University of East Anglia proposing to model existing data on flora and aquatic plant diversity in fenland ditches and drains to create an index of ditch quality. This data will be entered into a Geographical Information System (GIS) detailing IDB watercourses, Environment Agency main rivers, and those remaining riparian watercourses covering 350,000ha. This data will used determine if 1) whether particular IDB's contain better ditch quality better than others due to differing management regimes 2) whether riparian ditches in the arable landscape are better quality when they are located closer to, or further from, IDB main drains, or the fen terrestrial boundary, or buffer strips 3) and what effect soil type (e.g. peat depth) has in determining habitat using soil survey data under licence from the University of Cranfield. Potentially, this model can determine if IDB watercourse management practices are of benefit or detriment to ditch biodiversity in comparison to main rivers and riparian watercourses. The Environment Officer has recently been approached by Natural England to assist the UEA in acquiring this GIS data from fenland IDBs. This data has been acquired and sent to the UEA. No single map detailing the location of all such IDB watercourses has ever been produced before, so the results of this research will form an important resource and benefit further work and our understanding of this vital IDB network. ADA have been approached to see if they would be willing to act as a creditable and central repository for any IDB GIS data relating to the Fens, as there are bound to be more data requests for IDB watercourse locations in the future regarding catchment modelling and academia. 9.5 Hobhole Pumping Station Eel and Fish Passage Report The Environment Agency commissioned scoping report on provision for eel and fish passage produced by Royal Haskoning in Peterborough amounted to a prohibitively expensive scheme costing £1,700,000. Communication has been maintained with Royal Haskoning since the report emerged and a further meeting is due to take place with their engineers in February to discuss the wider implications for disproportionate schemes at IDB coastal pumping stations, particularly relating to inappropriate screening that risks blocking in high flows and for stations due for replacement in coming years. Other more cost effective and practical innovations continue to emerge in the UK and Europe and several local engineering fabrication firms are capable of fabricating necessary equipment. The Engineering Manager attended an ADA Technical & Environment Committee Meeting on January 16th and a copy of the Hobhole report was requested for circulation amongst members. ADA is seeking to develop a template Eel and Fish Passage Management Plan for IDBs, in order for Boards to take steps to prioritise their own structures and take ownership of the issue so this report may assist. 9.6 Owl box relocation Covenham to Boston Anglian Water Pipeline The preferred route for the pipeline will require relocation of the owl box on sewer 3/118 on the Hilldyke as it passes within 6m of the easement route. The barn owl is a Schedule 1 and 9 species of the Wildlife and Countryside Act, 1981 and as such, the birds, their nests, eggs and young are fully protected at all times throughout the UK. A fine of up to £5,000 and/or a custodial sentence can be issued if they or their nest sites are disturbed. A licence from DEFRA is required to move an owl box in such circumstances. Despite this multi million pound project going ahead, Anglian Water and their consultant engineers at Mott Mac Donald have sadly refused to provide owl expert Colin Shawyer of the Wildlife Conservation Partnership a few hundred pounds in mitigation to relocate the box or provide a few others elsewhere on the pipeline route. Instead, the box will be blocked off shortly to deter any owl nesting in 2013 for the works duration. Rather disappointing really, as the barn owl is a key species in the Boards Biodiversity Action Plan and the Lincolnshire BAP. 141 9. 9.6 ENVIRONMENT OFFICER’S REPORT - Continued Owl box relocation Covenham to Boston Anglian Water Pipeline - Continued R Hall-Jones asked if there had been any more reports of mink in the area. A Saul said he had seen one and the Environment Officer said the Board would provide a mink trap for this. 9.7 Meetings Attended 30/11/12 ~ Boston Borough Council Operation Fly Swat 06/12/12 ~ Black Sluice IDB Environment Committee 12/12/12 ~ Cablesafe Forum 10/01/13 ~ Dr Peter Chowne regarding his new pending book on Lincolnshire RESOLVED that the Environment Officer’s report be noted. 10. 10.1 ANY OTHER BUSINESS Retired Assistant Engineer A Saul asked if the Board could write to Don Fletcher, as he was poorly. Chairman 142