Directorate for Planning and Environmental Appeals Report to the Scottish Ministers ELECTRICITY ACT 1989 Report by David Russell, a Reporter appointed by the Scottish Ministers Case reference: IEC/3/105/3 Site Address: Bardnaheigh Farm, Westfield, by Thurso Application by Baillie Wind Farm Ltd for consent under Section 36, dated 12 July 2004 The development proposed: erection of a wind farm Planning authority lodging objection: Highland Council Dates of inquiry: 17 to 26 March 2009 Date of this report and recommendation: August 2009 Scottish Government: Directorate for Planning and Environmental Appeals 4 The Courtyard Callendar Business Park Callendar Road Falkirk FK1 1XR The Scottish Ministers Edinburgh File reference: IEC/3/105/3 August 2009 Ministers 1. In accordance with my minute of appointment dated 16 December 2008, I conducted a public local inquiry in connection with an application for consent under Section 36 of the Electricity Act 1989 to erect a wind farm, known as the Baillie wind farm, at Bardnaheigh Farm, Westfield, by Thurso. I now submit my report on that application. 2. The application was submitted by Baillie Wind Farm Ltd in July 2004, and the proposed development was the subject of environmental impact assessment. The development as now amended would consist of 21 wind turbines, each 110 metres high, with a combined generating capacity of 52.5 megawatts. Arrangements for the application to be considered at a public local inquiry were made after the local planning authority, Highland Council, notified the Scottish Ministers on 30 January 2008 of its objection to the proposed development. 3. On 23 May 2008, the case was passed to the Directorate for Planning and Environmental Appeals and on 1 September 2008 the Relevant Notice was issued. On 5 November 2008 I held a pre-inquiry meeting at which the arrangements for the public local inquiry were discussed and subsequently confirmed. Public notice of the inquiry was published in the local press on 6 February 2009. 4. The inquiry was held in Thurso, sitting for seven days between 17 and 26 March 2008. I conducted an accompanied inspection of the application site and surrounding viewpoints; and I also conducted an unaccompanied inspection to other more distant viewing points, including routes where existing wind farms elsewhere in Caithness can be seen. 5. Oral evidence was presented to the inquiry by witnesses on behalf of the applicant, Highland Council, the Caithness West Action Group, Historic Scotland and by a number of individual members of the public, and was tested under crossexamination. A full list of those who spoke at the inquiry is provided in Appendix 2. 6. My summary of the cases for each party takes account of the precognitions and any written statements which were lodged, together with the answers given by witnesses during the inquiry and the closing submissions made on behalf of that party. 7. I have also taken account of the environmental information within the environmental statement and the additional information provided to the inquiry, and of the written representations which were submitted by a number of organisations and by individual members of the public. Copies of all these submissions are available on the case files. CONTENTS Page Summary Report Section: 1. Site description and application background 2 2. Legislative framework and planning policy context 4 3. Summary of the applicant’s case 12 4. Summary of the cases for Highland Council and the Caithness West Action Group 26 5. Summary of the case for Historic Scotland 31 6. Summary of the cases of other third parties 33 7. Consultation Responses and Written Representations 36 8. Findings of Fact 39 9. Conclusions and Recommendations 53 Appendices Appendix 1: Conditions 57 Appendix 2: Appearances 64 Appendix 3: Documents 65 IEC_3_105_3 1 1. SITE DESCRIPTION AND APPLICATION BACKGROUND 1.1 The application site is located in an area of mainly open undulating countryside, comprising mixed farmland and elements of forestry plantation and moorland vegetation. It lies some seven kilometres west of Thurso and about three kilometres south-east of Dounreay. It extends to around five square kilometres, bounded to the south by the C1 road from Westfield to Shebster, to the west by the minor road from Shebster to Forss, and by the Forss Water to the east. However the turbines would occupy a smaller area extending west from Bardnaheigh farm and north towards Stemster Hill. Most of the wind farm site would also be visible from the minor road from Westfield to Forss, which runs in an elevated position to the east of the Forss Water. 1.2 To the west of the site, the land rises to the low ridge that runs north from Hill of Shebster which reaches a height of 133 metres. A cairn there, and two further north along the ridge at Cnoc Freiceadain, are scheduled ancient monuments. Dounreay is visible from the ridge, but not from the application site. There is an existing wind farm at Forss, about three kilometres north of the application site and close to the coast, which comprises six turbines, reaching to 75 metres in height. 1.3 The settlement pattern has scattered housing and there are a number of houses both within the application site and nearby which lie within a few hundred metres of the proposed position of the nearest wind turbine. None would lie between two or more turbines. 1.4 When the application was submitted to the then Scottish Executive by Baillie Wind Farm Ltd in June 2004, it sought the Scottish Ministers’ consent under Section 36 of the Electricity Act 1989 for the erection of a wind farm, then, of 25 wind turbines. The application had been the subject of environmental impact assessment, and an environmental statement was submitted with the application in July 2004. 1.5 Following the statutory consultation process in relation to both the application and the environmental statement, the applicant amended the scheme and the environmental statement in the light of the responses submitted and additional information obtained. As amended, the scheme which is before the Scottish Ministers is for 21 wind turbines, each capable of generating between 2.5 and 3 megawatts. All would have a hub height of 70 metres, with a total height to blade tip of 110 metres. 1.6 The wind farm layout would mainly comprise linear rows, although potentially subject to micro-siting variations, with a minimum separation distance between turbines of 300 metres. Seven turbines would stand within or adjacent to the woodland plantation towards the south-west corner of the site. Four turbines to the west of Bardnaheigh Farm would also stand to the south of, and parallel to, an existing line of pylons and 132kV overhead wires which lead over the Hill of Shebster ridge from Dounreay and cross the application site. 1.7 The proposed sub-station for the wind farm would be adjacent to one of these pylons, immediately north of Bardnaheigh Farm, and the proposed laydown area and contractor’s compound would be in the same vicinity. Two anemometer masts would IEC_3_105_3 2 also be erected, and some 10.6 kilometres of access tracks and underground cabling would be installed. The wind farm is proposed to be operational for 25 years. 1.8 Consultation responses were submitted by or on behalf of a wide range of organisations, and over 1,000 representations were also submitted either in paper or electronic form, with 210 objecting and 839 supporting the proposal. 1.9 In its response to consultation submitted on 30 January 2008, Highland Council notified the Scottish Ministers of its objection to the proposal on five grounds, which in summary are: It is contrary to the presumption against development set out in the Caithness local plan, as part of the site is covered by PP3 designation; It is contrary to SPP6, due to the proximity of the wind farm to existing houses Its impact on tourism would be unacceptable due to its cumulative effect along with other wind farms; Its adverse visual impact is contrary to the Highland Renewable Energy Strategy; It should be the subject of an appropriate assessment carried out to the satisfaction of Scottish Natural Heritage and to address issues raised by the Royal Society for the Protection of Birds and by Historic Scotland. 1.10 Where the planning authority has lodged an objection to a wind farm application under Section 36, the Scottish Ministers are required to hold a public local inquiry. In May 2008, the case was forwarded to the Directorate for Planning and Environmental Appeals and I was subsequently appointed by the Scottish Ministers to hold the inquiry. My initial minute of appointment confirmed that the Scottish Ministers had requested that the inquiry should be restricted to five matters but, following subsequent correspondence, that restriction was later removed and an amended minute of appointment was issued. IEC_3_105_3 3 2. LEGISLATIVE FRAMEWORK AND PLANNING POLICY CONTEXT 2.1 Applications for consent under Section 36 of the Electricity Act 1989 are subject to the requirements of Schedule 9 ‘Preservation of amenity and fisheries: Scotland.’ Section 3 of that schedule states that: (1) In formulating any relevant proposals, a license holder or a person authorised by an exemption to generate or supply electricity— (a) shall have regard to the desirability of preserving natural beauty, of conserving flora, fauna and geological or physiographical features of special interest and of protecting sites, buildings and objects of architectural, historic or archaeological interest; and (b) shall do what he reasonably can to mitigate any effect which the proposals would have on the natural beauty of the countryside or on any such flora, fauna, features, sites, buildings or objects. (2) In considering any relevant proposals for which their consent is required under Section 36 or 37 of this Act, the Scottish Ministers shall have regard to (a) the desirability of the matters mentioned in paragraph (a) of subparagraph (1) above; and (b) the extent to which the person by whom the proposals were formulated has complied with his duty under paragraph (b) of that subparagraph. (3) Without prejudice to sub-paragraphs (1) and (2) above, in exercising any relevant functions each of the following, namely, a licence holder, a person authorised by an exemption to generate or supply electricity and the Scottish Ministers shall avoid, so far as possible, causing injury to fisheries or to the stock of fish in any waters. 2.2 Schedule 8, at section 7, provides that: (1) On granting a consent under section 36 or 37 of this Act in respect of any operation or change of use that constitutes development, the Scottish Ministers may direct that planning permission for that development and any ancillary development shall be deemed to be granted, subject to such conditions (if any) as may be specified in the direction…… (3) The provisions of the Planning Act (except Parts VII and XII) shall apply in relation to any planning permission …deemed to be granted by virtue of a direction under this paragraph as if it had been granted by the Scottish Ministers on an application referred to them under the relevant section of that Act. 2.3 The power of the Scottish Ministers, on granting consent under Section 36 of the Electricity Act for an operation that constitutes development, also to direct that planning permission for that development shall be deemed to be granted, is reiterated in Section 57(2) of the Town and Country Planning (Scotland) Act 1997. Section 57(3) also confirms that the provisions of the Act apply to such a deemed planning permission, as if it had been granted by the Scottish Ministers for an application referred to them under Section 46. However, in the case of a Section 36 application, there is no application for planning permission, and the provisions of the Act are only applied once the Scottish Ministers have directed that planning permission shall be deemed to be granted. IEC_3_105_3 4 2.4 As the application seeks consent for the construction of a generating station under Section 36 of the Electricity Act 1989, the development falls within Schedule 2 of the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2000. This requires the applicant to submit an environmental statement for the proposal, setting out the information which is reasonably required to enable the environmental effects of the development to be assessed. The regulations set out requirements regarding publicity and consultation in relation to the environmental statement, as well as the matters to be taken into account and the contents of the environmental statement. The Scottish Ministers cannot grant consent unless they take into consideration the environmental information and state in their decision that they have done so. 2.5 The development plan in relation to the application site comprises the Highland Structure Plan and the Caithness Local Plan. [Documents: CD8 and CD9] In the structure plan, the key policies of potential relevance to this proposal are: General Policy G2: ‘Design for Sustainability’ which states: “Proposed developments will be assessed on the extent to which they: are compatible with service provision (water and sewerage, drainage, roads, schools, electricity); are accessible by public transport, cycling and walking as well as car; maximise energy efficiency in terms of location, layout and design, including the utilisation of renewable sources of energy; are affected by significant risk from natural hazards, including flooding, coastal erosion, land instability and radon gas, unless adequate protective measures are incorporated, or the development is of a temporary nature; are affected by safeguard zones where there is a significant risk of disturbance and hazard from industrial installations, including noise, dust, smells, electro-magnetism, radioactivity and subsidence; make use of brownfield sites, existing buildings and recycled materials; impact on individual and community residential amenity; impact on non-renewable resources such as mineral deposits of potential commercial value, prime quality or locally important agricultural land, or approved routes for road and rail links; impact on the following resources, including pollution and discharges, particularly within designated areas: o habitats freshwater systems o species marine systems o landscape cultural heritage o scenery air quality; demonstrate sensitive siting and high quality design in keeping with local character and historic and natural environment and in making use of appropriate materials; promote varied, lively and well-used environments which will enhance community safety and security and reduce any fear of crime; accommodate the needs of all sectors of the community, including people with disabilities or other special needs and disadvantaged groups; and IEC_3_105_3 5 contribute to the economic and social development of the community. Developments which are judged to be significantly detrimental in terms of the above criteria shall not accord with the Structure Plan.” General Policy G3 ‘Impact assessments’, which states: “Where environmental and/or socio-economic impacts of a proposed development are likely to be significant by virtue of nature, size or location, The Council will require the preparation by developers of appropriate impact assessments. Developments that will have significant adverse effects will only be approved if no reasonable alternatives exist, if there is demonstrable over-riding strategic benefit or if satisfactory overall mitigating measures are incorporated.” General Policy G4 ‘Community benefit and commitment’, which states: “The Council will expect developments to benefit the local community and contribute to the wellbeing of the Highlands, whilst recognising wider national interests. The Council will seek to enter into agreements with developers as appropriate on behalf of local communities for environmental and socio-economic purposes as indicated below: o where a development will have a long term impact on the environment contributions will be sought towards a fund for local community initiatives; o where as a result of a development new infrastructure proposals require to be implemented by The Council or other agencies, or existing programmes brought forward, developers will be expected to pay those costs as an integral part of that development; and o in appropriate circumstances The Council will expect a financial bond to be secured for long term environmental restoration and/or socioeconomic stability.” General Policy G6 ‘Conservation and promotion of the Highland heritage’, which states: “The Council will seek to conserve and promote all sites and areas of Highland identified as being of a high quality in terms of nature conservation, landscape, archaeological or built environment.” General Policy G8 ‘Precautionary principle’, which states: “In the relatively rare situation of assessing development proposals where the potential impacts are uncertain, but where there are scientific grounds for believing that severe damage could occur either to the environment or the wellbeing of communities, The Council will apply the precautionary principle.” Policy E1 ‘Distributed renewable energy developments’, which states: “The Council supports the utilisation of the region's distributed renewable energy resource, including hydro, wind, wave and tidal stream power. Proposals will be assessed against the provisions of the General Strategic Policies. Approvals for renewable energy developments will normally be for a temporary period only (tied to the lifetime of a project), with provision where appropriate for the removal and reinstatement of affected areas. Earlier action for removal and reinstatement will be required in the event of premature permanent cessation of energy production.” Policy E2 ‘Wind energy developments’, which states: “Wind energy proposals will be supported provided that impacts are not shown to be significantly IEC_3_105_3 6 detrimental. In addition to the General Strategic Policies, wind energy proposals will be assessed in respect of the following: o visual impact; o noise; o electro-magnetic interference; o roads, bridges and traffic; o aircraft flight paths/MOD operations; and o cumulative effects.” Policy L4 ‘Landscape character’, which states: “The Council will have regard to the desirability of maintaining and enhancing present landscape character in the consideration of development proposals, including offshore developments.” Policy T6 ‘Scenic views’, which states: “The Council will protect important scenic views enjoyed from tourist routes and viewpoints, particularly those specifically identified in Local Plans. There will be a presumption against development in narrow areas of land between roads and railways and open water.” Policy BC3 ‘Preservation of archaeological sites’, which states: “Archaeological sites affected by development proposals should be preserved, or, in exceptional circumstances where preservation is impossible, the sites will be recorded at developers’ expense to professional standards. Provision will be made in Local Plans for the appropriate protection, preservation and enhancement of archaeological sites.” Policy N1 ‘Nature conservation’, which states: “New developments should seek to minimise their impact on the nature conservation resource and enhance it wherever possible. The Council will seek to conserve and promote all sites according to the following hierarchy: sites and species of international importance - Developments which would have an adverse effect on the conservation interests for which a site has been designated will only be permitted where there is no alternative solution and there are imperative reasons of over-riding public interest, including those of a social and economic nature. Where a priority habitat or species (as defined in Article 1 of the Habitats Directive) would be affected, prior consultation with the European Commission is required unless the development is necessary for public health or safety reasons. sites of national importance - Developments will only be permitted where the objectives of designation and the overall integrity of the area will not be compromised or any significant adverse effects on the qualities for which the area has been designated are clearly outweighed by social and economic benefits of national importance. sites of local importance - Developments will be assessed for their effects on the interests of sites of local conservation importance and will be resisted where these are judged to be unreasonably detrimental.” IEC_3_105_3 7 2.6 In the Caithness Local Plan, the following provisions are of potential relevance: At paragraph 6, it states that the council “will seek to support the development of renewable energy opportunities in suitable locations that accord with the Structure Plan and National Planning Policy Guidance.” At paragraph 3 (page 15), it states that: “The Council will promote the A9, A99 and A836 roads as tourist routes and identify key strategic sites for new facilities.” At paragraph 46 is states: “The Council will seek to identify and safeguard scenic views from unsympathetic development. Views from public roads to open water are particularly important for amenity and tourism. To aid appreciation of scenic views the Council will favour improved lay-by parking, visitor interpretation and view point features, notably on the A9, A99 and A836.” On the Proposals Map, the appeal site is covered partly by Primary Policy PP2, which states that “The Council will favour development, unless this would significantly affect important features”; and partly by Primary Policy PP3, which states that: “The Council will presume against development, particularly where there is significant damage to heritage, amenity or public health.” Strategic Objective 8 of the local plan includes the safeguarding and enhancing of the cultural heritage of Caithness by protecting archaeological sites. The strategy map identifies a Heritage Area of National or International Interest for archaeology and a potential archaeology visitor centre, both on the south side of Caithness. It does not refer to the scheduled ancient monuments on the ridge leading from Shebster Hill. An annex to the local plan contains policies which the council applies throughout Highland, including Supporting Policy SP1, which states that development proposals must be compatible with adjoining uses and take into account amenity of neighbouring buildings. Scottish Government policy 2.7 In November 2007, the Scottish Government announced a new target of generating 50% of Scotland’s electricity from renewables by 2020, with an interim target of 31% by 2011. It estimates that around eight gigawatts of installed renewables capacity will be necessary to meet the 50% target; while the 2011 target implies around 5 gigawatts of installed capacity, which is almost double current levels at that time. 2.8 In Scottish Planning Policy 6 ‘Renewable Energy’, the Scottish Government has set out its planning framework to help ensure the delivery of its renewable energy targets. It states that: “Spatial policies should not be used to restrict development on sites where the technology can operate efficiently and environmental and other impacts can be addressed. In all instances, development plans should provide clarity on the criteria that should be met to enable development IEC_3_105_3 8 to take place in a satisfactory manner. Plans should, however, use spatial policies to afford significant protection to areas designated for their national or international natural heritage value, green belts and those areas where further development would result in unacceptable cumulative impacts.” 2.9 The policy is that the 2020 target “should be met by a range of renewable technologies. Hydro and onshore wind power are currently making the most significant contribution. This is expected to continue although these technologies will increasingly operate as part of a renewables mix as other technologies come on line.” 2.10 While supporting renewable energy developments, it also confirms the Scottish Ministers’ commitment to: meeting international and national statutory obligations to protect designated areas, species and habitats and protecting the historic environment from inappropriate forms of development ensuring impacts on local communities and other interests are satisfactorily addressed. 2.11 Annex A provides planning authorities with advice on preparing spatial frameworks for guiding wind farm developments of over 20 megawatts. The frameworks are intended to identify broad areas of search, areas to be afforded significant protection, and criteria for assessing proposals in other areas. The section dealing with “communities” states: “Broad criteria should be used to set out the considerations that developers should address in relation to local communities. These should ensure that proposals are not permitted if they would have a significant long term detrimental impact on the amenity of people living nearby. When considering spatial policies, planning authorities may consider it helpful to introduce zones around communities as a means of guiding developments to broad areas of search where visual impacts are likely to be less of a constraint. PAN 45 confirms that development up to 2 km is likely to be a prominent feature in an open landscape. The Scottish Ministers would support this as a separation distance between turbines and the edge of cities, towns and villages so long as policies recognise that this approach is being adopted solely as a mechanism for steering proposals to broad areas of search and, within this distance, proposals will continue to be judged on a case-by-case basis.” 2.12 Although published in 1997, National Planning Policy Guideline 14: 'Natural Heritage' remains the current statement of the Scottish Ministers’ policy on planning and natural heritage. In relation to special protection areas, it states: “Under the Habitats Directive, special protection areas and special areas of conservation are together intended to form a Community-wide network of protected areas designed to maintain or restore the distribution and abundance of species and habitats of Community interest, to be known as Natura 2000. They are identified for the purposes of protecting those habitats and species within the EU which are endangered, vulnerable, rare or otherwise require special attention. ….The Conservation (Natural Habitats IEC_3_105_3 9 &c.) Regulations 1994 place a statutory duty on planning authorities to meet the requirements of the Habitats Directive. …The Regulations require that where an authority concludes that a development proposal unconnected with natural heritage management is likely to have a significant effect on a Natura 2000 area, it must undertake an appropriate assessment of the implications for the conservation interests for which the area has been designated. Guidance on the assessment of proposals affecting Natura 2000 areas is set out in Appendix A of Annex D to Circular 6/1995. In cases where an assessment of the proposal is also required under the Environmental Assessment (Scotland) Regulations 1988, authorities should ensure that the environmental statement prepared in respect of the proposal meets the requirements of both sets of regulations. A development which would have an adverse effect on the conservation interests for which a Natura 2000 area has been designated should only be permitted where: there is no alternative solution; and there are imperative reasons of over-riding public interest, including those of a social or economic nature. Where a priority habitat or species (as defined in Article 1 of the Habitats Directive) would be affected, prior consultation with the European Commission is required unless the development is necessary for public health or safety reasons.” 2.13 The guideline also deals with landscape protection: “Scotland is fortunate in having a rich diversity of landscapes. Many areas, for example in the Highlands and Islands, possess mountain and coastal landscapes which are valued nationally and internationally for their quality, extensiveness and wild land character…. In collaboration with local authorities, SNH has completed Landscape Character Assessments for the whole of Scotland. These assessments can provide valuable local guidance on the capacity of the landscape to accommodate new development and some planning authorities have already begun to make use of them in policy development and development control casework. The most sensitive landscapes may have little or no capacity to accept new development. Some of Scotland's remoter mountain and coastal areas possess an elemental quality from which many people derive psychological and spiritual benefits. Such areas are very sensitive to any form of development or intrusive human activity and planning authorities should take great care to safeguard their wild land character. This care should extend to the assessment of proposals for development outwith these areas which might adversely affect their wild land character.” 2.14 The recently published Scottish Planning Policy 23 ‘Planning and the Historic Environment’ confirms that the Scottish Ministers’ policy for scheduled IEC_3_105_3 10 ancient monuments is now set out in the SHEP (Scottish Historic Environment Policy) published by Historic Scotland. 2.15 At paragraph 9 it gives the following advice: “The location of historic features in the landscape and the patterns of past use and activity are part of the historic environment. Setting is more than the immediate surroundings of a site or building and, for example, may be related to the function or use of a place, or how it was intended to fit into the landscape or townscape, the view from it or how it is seen from around, or areas that are important to the protection of the place, site or building.” 2.16 At paragraph 43 it confirms that: “Scheduled monuments are of national importance and they should be preserved in situ and within an appropriate setting. While the scheduled monument consent process is separate from the statutory planning process, where works requiring planning permission affect a scheduled monument, the protection of the monument and its setting are material considerations in the planning process. The current SHEP provides further detail.” 2.17 Planning Advice Note 45 ‘Renewable Energy Technologies’ gives the following advice in relation to visual impact: “Turbines in wind farms are likely to be tall, frequently located in open land, and therefore likely to be highly visible. …. It will normally be unrealistic to seek to conceal them. Developers should seek to ensure that through good siting and design, landscape and visual impacts are limited and appropriate to the location. The visual effect will be dependent on the distance over which a wind farm may be viewed, whether the turbines can be viewed adjacent to other features, different weather conditions, the character of the development and the landscape and nature of the visibility. The following is a general guide to the effect which distance has on the perception of the development in an open landscape: Figure 8: General Perception of a Wind Farm in an Open Landscape Distance Up to 2 kms 2-5 kms 5-15 kms 15-30 kms Perception Likely to be a prominent feature Relatively prominent Only prominent in clear visibility – seen as part of the wider landscape Only seen in clear visibility – a minor element in the landscape.” 2.18 Highland Council published the Highland Renewable Energy Strategy nonstatutory supplementary guidance. It places the application site within an area to which the strategy applies a presumption against development. The strategy contains a policy (S2) which requires a separation of at least one kilometre between turbines and houses. IEC_3_105_3 11 3. SUMMARY OF THE APPLICANT’S CASE The statutory framework 3.1 The appropriate approach to decision making for an application under Section 36 of the Electricity Act 1989 is to identify all the relevant considerations, and then undertake a balancing exercise. The development plan has no higher status than other material considerations. The decision about the deemed planning permission follows the decision on the Section 36 consent. 3.2 Schedule 9 requires the applicant to consider the desirability of preserving natural beauty, conserving flora and fauna, and protecting certain sites of architectural or historic or archaeological interest. Here, these matters have been addressed in the environmental statement and its addendum. The applicant is also required to do what he reasonably can to mitigate any effects on these elements. In this case, the proposed wind farm would not affect the sites of the scheduled ancient monuments, so the duty of protecting them does not arise. However, the applicant has considered the indirect effects in the environmental statement, and has mitigated the indirect effects on the monuments by relocating some of the turbines and has proposed measures to improve accessibility to the monuments and the understanding of them. Landscape and visual issues 3.3 The approach set out in the environmental statement addendum is consistent with Scottish Natural Heritage’s guidance. The layout is an ordered cluster rather than a formal grid. It takes account of the landform and minimises the extent to which it would occupy views. While the turbines would appear in rows on occasion when passing along certain routes, they do not line up in relation to particular receptors. This would not exacerbate its visual impact, and in all views it would be seen as a single wind farm. In an open landscape such as this, the wind farm would always be visible. The key in its design is to limit the extent of its visibility. 3.4 Strathy Point, Dunnet Head and Dunnet Bay all have landscape designations of some form, but the views from there would be at distances of over 19 kilometres and the wind farm would occupy only between 2 and 5 degrees of the arc of view. Other features such as Dounreay, Thurso and the existing Forss wind farm would also be visible. 3.5 The landscape which contains the application site is large in scale, exposed and windswept, and these are landscape characteristics which are recognised as being capable of accommodating wind farms. The effect on Shebster Ridge is limited, as it is only from outwith the site, to the north and the west, that it appears as a ridge in the wider landscape. 3.6 It is clear both from Scottish Planning Policy 6 ‘Renewable Energy’ and a subsequent letter [Documents CD18 and CWAG101] that the impacts of a wind farm on residential amenity have to be assessed on a case by case basis. The fact that some visibility of a wind farm can be obtained from part of a house or garden is not sufficient, necessarily, to give rise to a significant adverse effect on the amenity of IEC_3_105_3 12 the residents. Here, some of those living in houses which are in close proximity to the wind farm would have no view of it at all. 3.7 Account has also to be taken of the orientation of the buildings and of the experience on the approaches to them. While views from rooms occupied during the day are regarded as more sensitive than others, the applicant’s assessment did not restrict the sensitivity analysis to the lower rooms, but considered the orientation of the building as a whole. The impacts on the approaches to a property, or on rear gardens, can also result in a high magnitude of change being assessed, even where the houses are oriented away from the turbines. 3.8 Account also has to be taken of the scale of the landscape in which the houses are situated. Here, the landscape does not restrict views and so the wind farm would only fill a limited arc of the overall view enjoyed from each property. This significantly mitigates the impact on residential amenity. Views tend to be panoramic, and big skies form an important component of the landscape. Here, the existing overhead power lines, commercial forestry, houses and roads all tend to reduce the site’s visual sensitivity. 3.9 Road users in the area are also important visual receptors. There would be a significant effect experienced over sections of the A836, but these are already subject to significant visual intrusion arising from the Forss wind farm and from Dounreay. The road is designated as a tourist route, but is not of high sensitivity throughout. The C1 road is part of a national cycle route, but it is not a scenic route as, on the way out from Thurso, it is characterised by significant man-modified features including the T3UK building, quarrying deposits, overhead transmission lines, housing, commercial forestry and Dounreay. 3.10 The concern about cumulative impacts appears to relate generally to the overall effect of a number of wind farms located across Caithness, rather than the particular cumulative effects of this proposal in conjunction with other specific wind farms. In practice, the only significant cumulative impact which would arise with an existing or consented wind farm is with the existing Forss wind farm, and this would arise primarily in relation to the A836, and only to a limited extent. Neither the Lieurary or South Shebster wind farm proposals have been determined. 3.11 There is nothing in the cumulative impact issues which would warrant refusal. Scottish Natural Heritage has confirmed that the landscape and visual effects of the development would be acceptable. It withdrew its original objection which clearly related to the methodology which was used in the environmental statement, and it agrees with the conclusions regarding the extent of visual and sequential impacts. The key issue is the cumulative sequential views along the A9 road corridor from Dunbeath to Thurso. Scottish Natural Heritage confirms that this landscape has the capacity to absorb the proposed scale of development, although it also states that, if the Baillie wind farm proceeds, its capacity to accommodate wind farm development would be close to being reached. The council’s planning officers also considered that there was no objection to the proposal’s landscape or visual effects. 3.12 Scottish Natural Heritage’s policy on wind farm development is that it should be directed to man-modified landscapes, such as this, and away from wilder IEC_3_105_3 13 landscapes to minimise natural heritage impacts. This site also lies within a zone of least heritage sensitivity in the terms of Scottish Natural Heritage’s strategic locational guidance. 3.13 One of the consequences of this approach is that, by encouraging development in man-modified landscapes, it is likely that there will be residential properties in the area, and almost inevitable that there will be some conflict between wind farm developments and neighbouring residents (or “residential receptors”). Noise 3.14 Planning Advice Note 45 deals with operational noise associated with wind farms, and recommends that the guidance set out in ETSU-R-97 should be adopted in assessing these impacts and setting limits. That advice has been applied to all wind farms consented under the Electricity Act, and supersedes the earlier advice regarding ambient noise levels contained in Planning Advice Note 56. 3.15 There are no substantive issues at this site in relation to noise. The assessment undertaken by the applicant has been conservative and robust, and demonstrates that the wind farm can operate within the tightest limits set by ETSUR-97. These have been applied to wind farms throughout Scotland, and no significant issue in relation to noise generated by wind farms has arisen. There is an on-going issue regarding noise at only one wind farm site in the United Kingdom. 3.16 The occupiers of a number of the properties close to the wind farm have a financial interest in the development (Bardnaheigh farmhouse, bungalow and cottage; Skaill 5, 6 and 7; and Hillcrest), and the occupiers of the two closest nonstakeholders properties (Achiebraeskaill and the steading conversion at Stemster) have not objected. None of the occupiers of properties within 500 metres of a turbine has objected. 3.17 Background noise measurements were undertaken at a number of representative locations. At the inquiry criticism was made of the wind shields used for the microphones, but tests have demonstrated that this made no material difference to the results. 3.18 The 10 metres high wind monitoring mast was located within the site and close to the amended turbine locations. Readings of wind speed would not have been materially affected by the nearby tree plantation, as the trees then were only five metres tall and, as the mast stood to the south, the prevailing wind from the south-west would have been unaffected by these trees. An assertion at the inquiry that the readings from the mast demonstrated that this effect had occurred was flawed, as the masts were not synchronised. Questions regarding missing data and wrongly calibrated data had been addressed and were explained at the inquiry. 3.19 Criticisms made at the inquiry of the methodology and measurements used for assessing wind shear on the site were based on mis-understandings and were not justified. The alternative assessment undertaken on behalf of the action group was flawed, both because the measurements from the meteorological mast and the background noise measurements had not been synchronised, and as data relating to IEC_3_105_3 14 periods of rain had been retained, contrary to the guidance in ETSU-R-97. Accordingly, that assessment should be entirely discounted. 3.20 The noise emission levels from the turbines were agreed. These are based on levels warranted by the manufacturer. However the attenuating factor to be applied relating to the prevailing ground conditions, and the height of the receptors, were not. In accordance with the guidance set out in International Standard ISO 9613, the applicant’s consultant had assessed the ground condition of the appeal site as porous, and applied the appropriate factor (G = 1) at a receptor height of 1.4 metres. 3.21 The action group’s consultant asserted that a factor of G = 0.5 should be applied instead, as the standard had not been specifically devised for wind farms; and also that it should be applied at a receptor height of four metres. That height is not appropriate, as most of the houses in the area are single storey, and as the background noise measurements and any enforcement measurements would be undertaken at 1.4 metres. Actual results from an operational wind farm suggest that the use of these factors is very conservative in practice. [see Document CWAG77] This may be caused by the shielding effect of upwind turbines on those that are downwind; and also by the fact that the warranted sound levels given by manufacturers are also likely to be conservative, and possibly two decibels above the measured levels, to give themselves some commercial confidence. 3.22 In that context, the use of the G = 1 ground attenuation factor is entirely justified. On this basis, no mitigation would be required. Applying a factor of G = 0.5 at a height of 1.4 metres provides a conservative sensitivity test, and indicates that limited mitigation may be required in certain wind speeds. Even applying the factor of G = 0.5 at a height of 4.5 metres would still enable the wind farm to operate, subject to a number of constraints in different wind directions. These calculations have additional conservatism built in, as they assume that each property is downwind of every turbine, which could not occur in practice. Accordingly, the applicant’s consultant has advised that the wind farm would comfortably meet the limits set by ETSU-R-97, including the lower daytime limit of 35dB. Any uncertainties arising from the particular turbine model which would be used can be addressed through a planning condition requiring a further assessment to be undertaken in respect of the specific turbine. Shadow flicker 3.23 The effect of shadow flicker is only experienced indoors. It can occur when the sun shines through a narrow window opening of a building and is caused by the rotating blades of a turbine standing within 10 rotor diameters from it. There is no agreed level of acceptability for shadow flicker in the United Kingdom, although there are European standards. A worst case assessment has been undertaken, which takes no account of the actual position of window openings or of the shielding created by other buildings or ground cover. The findings are set out in the addendum to the environmental statement. 3.24 The turbines would be fitted with software to shut them down when the circumstances for shadow flicker occur. A suspensive condition could require its IEC_3_105_3 15 installation and implementation. In these circumstances, shadow flicker would not affect residential amenity. Other aspects of residential amenity 3.25 There would be a significant impact on the visual amenity of the occupiers of a number of properties. However, as is recognised in Policy S3 of the Highland Renewable Energy Strategy, there are circumstances where the sensitivity is reduced. Here, there are a number of other development influences in the vicinity of the site, including Dounreay, the overhead transmission lines which pass through the site, and the presence of commercial forestry. The scale of the landscape is another factor, and almost none of the objectors refers to any leisure activities being carried on within the site. 3.26 In Scottish Planning Policy 6, Annex A gives guidance in relation to “communities”. This is in the context of setting out a spatial strategy, and refers to a separation distance of two kilometres being a general guide in relation to cities, towns and villages. However it confirms that proposals would continue to be judged on a case by case basis. A stand-off distance of two kilometres from the dispersed settlement pattern on this site would not be consistent with this guidance. In the case of this proposal, subject to appropriate planning conditions being imposed, the development can operate in a manner which would not cause significant long term detrimental impact on residential amenity. 3.27 Planning Advice Note 45 ‘Renewable Energy Technologies’ recognises that in relation to many wind farms there is often concern about their impact on visual amenity at the outset, but confirms that surveys have shown that these concerns have often not been borne out after construction. 3.28 In this case, the evidence at the inquiry demonstrated that the only significant impact on residents is likely to be a visual impact in relation to a limited number of properties. Nothing in national policy indicates that this should result in the refusal of an application. Ornithology 3.29 Ornithological matters have been a key factor in the location and design of the wind farm, with a good data base enabling turbines to be located to avoid recorded geese flight activity and with a stand-off distance from feeding areas. 3.30 The consistent flight lines of Greenland white fronted geese is down the Forss valley. There is no evidence of these geese feeding within the wind farm site. Infrequent flights recorded through the site have been taken into account in the collision risk model, and the potential for night time flights has been incorporated. This resulted in the assumption that 526 geese annually would fly through the area occupied by the turbines, and the most up-to-date avoidance rate predictions were applied. The Royal Society for the Protection of Birds confirmed that it was satisfied with the results of the modelling, based on the observations undertaken. IEC_3_105_3 16 3.31 Studies have shown that there is not a significant risk of geese flying into a wind farm site and being killed, and an avoidance rate of 99% is very conservative. These studies form the background for Scottish Natural Heritage’s conclusions. The Scottish Ministers will require to carry out their own appropriate assessment of this development, and Scottish Natural Heritage is a formal consultee in that process and considerable weight should be attached to its findings, set out in its written submission of 16 February 2009. 3.32 Fears of geese all being killed by flying into the wind farm at night are unfounded, and there is no evidence of geese having flown into other vertical structures or high voltage wires. Fears of disturbance to the geese that roost on Broubster Leans are also unfounded, and feeding areas in the fields around Knockglass are beyond the distance at which disturbance could occur. Evidence from the Tangy wind farm in Argyll also suggests that fears about the impact on white-fronted geese are unjustified. 3.33 In relation to whooper swans, extensive survey work has demonstrated that these are not regularly sighted over-flying the wind farm site and the risk of collision is extremely small. 3.34 Ultimately it will be for the Scottish Government to undertake the appropriate assessment for these species, and in doing so it will be required to consider the effects on their designated populations as a whole. The current population of Greenland white fronted geese at Broubster is around 200, and this has been consistent over an extensive period. 3.35 The overwhelming evidence is that there would be an insignificant effect on these species. This would not justify imposing conditions to secure mitigation measures that would include the shutdown of turbines. Cultural heritage 3.36 The impact of the wind farm on the Cnoc Freiceadain Cairns and the stone row was a factor in the location of the turbines and the visual effect on these monuments was considered in the environmental statement, and was identified as both major and significant. The impact of the development on the cairns would be related to the visual experience of visitors, rather than to any direct functional impact on the cairns themselves. 3.37 In line with the purpose of environmental impact assessment, the applicant has therefore considered the potential to mitigate these impacts. The issue of considering alternatives has been addressed through the iterations made to the layout of the turbines, and the option of alternative sites is not a genuine one as there is no cap on the number of wind farm which could be approved. 3.38 The impact on the setting of the monuments would be an indirect one, and it would also be temporary as the consent being sought would be limited to 25 years, in line with national and structure plan policy on wind farms, and any extension beyond that would be the subject of a separate consent procedure. As the impact IEC_3_105_3 17 would also be reversible, this should be considered a lesser impact than one which is permanent and irreversible. 3.39 Assessing the impact of a development on the setting of a scheduled ancient monument is a matter of judgement. No advice on methodology was proffered by Historic Scotland’s witnesses. The advice within the Scottish Historic Environment Policy and Scottish Planning Policy 23 indicates that function and how the monument was intended to fit into its landscape are relevant factors in defining its setting, but reference is also made to how it is now seen within the existing landscape. 3.40 It is accepted that indirect effects on a monument, such as an impact on its setting, could reduce the cultural value of the monument. The applicant’s archaeological consultant has an extensive background in Neolithic monuments and great weight should also be placed on the conclusions of Henshall and Ritchie [Document BWL102, paragraph 3.7] that proximity to settlement, rather than their outlook or visibility from afar, is likely to have been the prime consideration in their siting, as the landscape at that time would have retained much open woodland which would have obstructed distant viewing. 3.41 The wind farm would not be directly in the view between the Shebster Cairn and the Cnoc Freiceadain Cairns, and would have no effect on their intervisibility. At present there are overhead lines and the Forss wind farm within that view. No other specific points of intervisibility in the landscape were referred to in evidence which could lead to the conclusion that the integrity of the setting of these monuments would be affected. 3.42 The wind farm could also affect the aesthetic qualities of the monument’s setting. Historic Scotland considers that this has to be assessed against the current landscape in which it is situated. Here it includes the combined effects of the industrial complex at Dounreay and the associated overhead lines which run just to the south of the Cnoc Freideadain Cairns, and regard should also be had to the scale of this landscape and its capacity to absorb change. 3.43 Their prominence in the landscape is another factor. The Shebster ridge is not a significant feature when viewed from the south or the east. It is only prominent from the north, and when travelling south on the unclassified road to Shebster. 3.44 Although the wind farm would have a significant impact on the visual experience of visitors to the scheduled ancient monument, there would be clear separation between the wind farm and the visitors. The experience of walking to the monuments from the unclassified road would be unaltered. When at the monument, there would be a clear topographical separation from the wind farm, with the monuments being located above and beyond the wind farm site. The turbines would be viewed in the context of a large scale landscape with a big sky. 3.45 At present, as the number of visitors to the Cnoc Freiceadain cairns is very limited, it is clear that the present arrangements are not effective, despite their potential interest. At present visitors have to park in a passing place, and access involves the use of a stile which presents a barrier to less-able bodied people. The IEC_3_105_3 18 mitigation proposals would relocate the car parking to an existing woodland to minimise visual intrusion and that, together with improved access and linkages, could be addressed through a suspensive planning condition. The promotion of archaeology within Caithness has the potential to increase visitor numbers. 3.46 Further mitigation could be achieved through a three dimensional LIDAR laser screening survey which the applicant would be willing to undertake. That work could answer some of the outstanding questions about long cairns, enhancing our knowledge and understanding. Although it is an expensive operation, it is effective when compared with traditional field work and would place Caithness at the forefront of archaeological investigation and promotion, securing benefits both for education and for visitor experience. 3.47 Together these measures would result in better promotion of the Cnoc Freiceadain Cairns, with modern facilities and better accessibility for the benefit of both lay and specialist visitors. There would also be the opportunity to connect the cairns with both the wind farm and Dounreay, thus providing a tourist destination that enables renewable energy to be linked to cultural heritage. Health and safety 3.48 A number of statements given in evidence by the Caithness West Action Group were incorrect. Properties south of the wind farm would not be affected by shadow flicker. Concerns raised about epilepsy had been investigated, but the turbine blades do not operate at a rate which could trigger a fit. The layout complies with government guidance in relation to the stand-off distance from roads. 3.49 National guidance on wind farm safety has been published, but was not referred to by the action group’s witness, although he was aware of it. His argument that wind farms are extremely dangerous and constitute a significant safety risk to all concerned is not borne out by the evidence: International and British standards are applied to the structural integrity of turbines; In relation to fire and flame spread, previous problems with back up power have been addressed; Issues relating to ground stability and lighting were addressed in the environmental statement; Issues relating to falling objects are addressed in turbine design and referred to in Planning Advice Note 45 ‘Renewable Energy Technologies’; The issue of ice throw was addressed in the environmental statement, and evidence was given that a sensor can be fitted to ensure turbine shutdown in conditions when there is a risk. 3.50 Reference had been made to the mechanical operating and maintenance manual of a particular turbine model. The statements within it have to be considered in that context. It is advice for mechanical operating and maintenance staff on procedures to be followed when maintenance is being carried out, and does not apply generally. Also, much of the evidence given of fatal accidents relating to wind turbines concerns smaller agricultural turbines in America. IEC_3_105_3 19 3.51 The action group’s witness attempted to portray wind farms as potentially causing significant health effects. The studies referred to have not been peer reviewed, and this demonstrates the danger of an unqualified individual pulling information off the internet and presenting it as established fact. Many wind farms are operating in Scotland, and there appears to be no evidence of adverse health effects. 3.52 Here, shadow flicker only arises in certain circumstances and would be addressed through a condition. Blade glint is not a widespread problem in Britain, and the turbines would have a matt rather than the gloss finish would could cause the effect. Turbine noise has been addressed, and low frequency noise does not occur at commercial wind farms. Transportation 3.53 The site is well located in close proximity to a port from which all components can be delivered. Construction of the wind farm would involve 189 abnormal roads on the route from Scrabster along the A836 and then the C1 road to the site. These would be undertaken during off-peak hours and with a police escort, but not at night, and the relevant authorities are aware of the proposals. Additional import of stone to the site is unlikely to be necessary, as the underlying stone within the site would be used. Tourism 3.54 The Moffat Report was sponsored by the Scottish Government with the purpose of replacing the myths about the impact of wind farms on tourism in Scotland with evidence. No tourist interviewed in Caithness or Sutherland responded by saying that the presence of a wind farm would affect their decision to return, and the Baillie wind farm was listed as one of the potential developments. As many visitors indicated that they would be encouraged to return, as indicated that they would be deterred. 3.55 The report conservatively estimated that the impact of all the proposed wind farms on tourism in Caithness would equate in total to a decrease of up to £700,000 in the gross value added to its economy over the period to 2015, equating to 30 “annual” jobs in total over that time. 3.56 The only tourism business which lodged an objection to this wind farm was the Castle of Mey, which did so by a generic objection through the Caithness Windfarm Information Group. The Forss House Hotel is the only recognised tourist business in the vicinity of the site, and it lodged no objection. This part of Caithness is not a significant tourist destination, with the only attraction being the Cnoc Freideadain Cairns which are visited by only a few hundred people each year. There is no evidence that golfers playing the Reay golf course would be adversely affected. 3.57 This proposed wind farm would not affect the “brand image” of Caithness. A wind farm is depicted on a mural that greets visitors arriving at Wick Airport; it is a key theme on display at the Caithness Horizons Centre in Thurso which depicts the evolution of industry from atomic to renewable energy. The proposed Baillie wind IEC_3_105_3 20 farm would assist this promotion. It is well away from the main tourist destinations and its intervisibility with Dounreay would send a powerful message, in line with the new image of Caithness. This would be enhanced by the proposed mitigation measures for the Cnoc Freiceadain Cairns which provide the potential to place Caithness at the forefront of archaeological investigation and promotion. Public opinion 3.58 Many letters of support and objection have been lodged. Those supporting the development focus on the benefits of renewable energy, while those opposing it raise site specific issues. The Caithness West Community Council objected at the scoping stage as it did not wish any wind farms to be located in Caithness, and this attitude has pervaded its approach throughout. Its chairman wrote a letter to the local newspaper which sought to alienate any individual who promoted a wind farm development; and when the officer’s recommendations on the application were published, it held a poll over the Christmas period which contained a flawed question. It was submitted on behalf of the applicant that the purpose of the poll was to try to put pressure on the councillors, and that little weight should be attached to it. Benefits 3.59 The main benefits of the scheme would be its contribution to meeting the Scottish Government’s targets in relation to renewable energy generation. The wind resource at this site is over 30% better than the average in Scotland, and will be reflected in the wind farm’s electricity output. The efficiency of the location and the scale of the output are considerable factors in its favour. In evidence, the company’s representative indicated that, based on a conservative estimate and assuming an operating capacity factor of 38%, the wind farm would save some 75,000 tonnes of carbon dioxide each year. 3.60 It was submitted that the suggestion made on behalf of the council and the action group that the applicant should enter an agreement that the wind farm should be dismantled if the target output is not achieved is absurd. Its benefits relate not only to CO2 savings, but also more widely to sustainable development. The savings are unmeasurable, and such an agreement would make the development unbankable. There was no evidence before the inquiry that the energy from wind farms would simply displace hydro generation. 3.61 This scheme benefits from a firm grid connection agreement which is currently dependent on the upgrade of the Beauly-Denny link taking place. However a grid optimisation process is currently occurring, as a result of which the National Grid Company has been able to advance consented projects; and it is also prepared to provide a connection on a non-firm basis, under which the operator would not receive payments in the event that it was necessary for the wind farm to be “constrained off” the system because of grid issues. The development would be fundable under such arrangements, and in practice the issue of constraint has not occurred to date. IEC_3_105_3 21 3.62 This site also benefits from its ease of grid connection. The current agreement is that a cable would be run underground to Dounreay. In addition, this project would boost the security of national energy supplies. 3.63 The benefits which would arise in relation both to tourism and the scheduled ancient monuments have been highlighted above. There would also be public access to the wind farm site. It was also stated in evidence that the rental income would support five local farming and land-owning businesses, and that the applicant was committed to paying an annual contribution to the West Caithness Community Fund to provide support for local projects. Construction of this £75M - £80M project would benefit local business and create about 30 jobs at that time. In relation to permanent jobs, there would be two running the operating company and three or four involved in maintaining the wind farm, all locally based. Policy 3.64 In terms of Government energy policy, this provides overwhelming support for this proposal, with Scottish Planning Policy 6 highlighting the Scottish Government’s commitment to achieving challenging targets for renewable energy generation and supporting a thriving renewables industry in Scotland. The applicant’s planning consultant confirmed that the interpretation of the advice in Annex A of Scottish Planning Policy 6 in relation to communities [see Document CWAG101], which was contained in a letter from the Scottish Government written on behalf of the Energy Minister, does not mean that there would be an automatic refusal for a proposal which would have a significant long term detrimental impact on the amenity of people living nearby. 3.65 In submissions it was stated that compliance with the structure plan in this case will depend on the findings made in respect of the evidence. However a number of policies are of direct relevance: Policy G2 requires both the positive and the potentially negative aspects of the development to be balanced. Non-compliance with an individual criterion would not render the development contrary to this policy. Policy G3 is contrary to Scottish Planning Policy 6. It automatically requires developers to look for alternative sites, as all wind farms have significant adverse effects. Also, it states that development will only be permitted where “no reasonable alternatives exist”. Its wording cannot be supported and little weight should be attached to this policy. Policy G4 can be satisfied as the applicant has entered into discussions with a local community group. Both the positive and the negative aspects are relevant to Policies G5 and G6. While there is no issue in relation to the protection of cultural heritage sites, there would be impacts on the setting of the monuments, but the mitigation proposals would enhance the understanding and promotion of the area’s cultural heritage. In relation to Policy G8, there is no scientific uncertainty about the issues raised at the inquiry. Policy H3 forms the basis for the approach set out in the local plan under Policies PP1-4. IEC_3_105_3 22 The proposal is not contrary to the tourism policies of the structure plan, or with Policy A2 which supports diversifying farm incomes through non-farming enterprises. Policy E1 supports the concept of temporary development and Policy E2 introduces criteria. The evidence given to the inquiry is that all matters can be addressed satisfactorily. It is accepted that there would be some negative visual impact. Policy L4 deals with landscape character and supports the approach undertaken by the applicant. None of the other landscape policies are engaged. There is general compliance with specific policies relating to impacts on cultural heritage, and the mitigation proposals strongly accord with Policy BC2. 3.66 In the Caithness Local Plan, paragraph 1.34 defers matters relating to renewable energy to the structure plan. In these circumstances, little weight should be attached to the other policies of the local plan. However, the development does not appear to compromise any aspects identified on the strategy map. 3.67 Policies PP1-4 derive from Policy H3 of the structure plan and do not relate to wind farm development. Policy PP1 relates primarily to built up areas and is supportive of development. Policy PP2 favours development in areas linked to local road corridors outwith the areas of restraint around Thurso and Wick, which derive from Policy H3 of the structure plan. Neither of these locations would generally be favoured for wind farm development. 3.68 Outwith these areas, Policy PP3 provides a general presumption against development and Policy PP4 creates a very strong presumption against development. These policies were not designed for wind farm developments. They fly in the face of the approach advocated in Scottish Planning Policy 6, and no weight should be attached to them. 3.69 Limited weight should also be attached to the Highland Renewable Energy Strategy, which was adopted prior to Scottish Planning Policy 6 being finalised, and has not had regard to the guidance contained in it, or in Annex 2 to Planning Advice Note 45. The strategy embargoes vast areas of the Highlands with a presumption against development, contrary to the approach of Scottish Planning Policy 6. In these circumstances, limited weight should attach to the fact that this application site is in an area with a presumption against development. 3.70 At a previous appeal, it was noted that political influences played their part in the finalisation of the strategy, and that the council accepted that more weight should attach to Scottish Planning Policy 6. The blanket restriction on developments within one kilometre of a residential receptor flies in the face of the general approach that developments should be assessed on a case by case basis. 3.71 There are four key national planning policy documents. Scottish Planning Policy 6 gives very strong support for the development of renewable energy, and its targets have since been increased. Renewable energy adds to sustainable development and to the security and diversity of energy supplies, so the benefits of IEC_3_105_3 23 the scheme do not merely relate to the CO2 savings. Frameworks should be positively disposed to meeting energy targets, and the application of a sequential approach is prohibited. It highlights potential criteria for dealing with a range of issues, and confirms that all national and international designations should not be compromised. It also confirms the need to balance benefits against impacts. 3.72 It is also clear that the two kilometres stand-off distance referred to in the Annex in relation to “communities” is not to be regarded as an embargo on development. Under the local plan’s definitions, this site is not within two kilometres of any town or village and so cannot be excluded from a broad area of search. A broader definition of the term “community” is not justified. Whether there would be a long term significant impact on the amenity of people living nearby requires to be assessed in terms of the detailed evidence given at the inquiry. 3.73 The key aspects of Scottish Planning Policy 23 relate to the references to what constitutes “setting” in relation to the scheduled ancient monument; the protection of a monument’s setting being a material consideration in determining planning applications; and the need for that protection to be incorporated in planning policy. 3.74 Planning Advice Note 45 ‘Renewable Energy Technologies’ provides important guidance. It highlights that public concern over the visual impact of wind farms is a recurring feature of proposals in Scotland, but refers to the research undertaken. It confirms that there is not a blanket restriction on wind farms within two kilometres of a community, and that proposals are to be tested against criteria which seek to confirm whether issues that are raised by a proposed development can be dealt with. 3.75 The Scottish Historic and Environment Policy recognises that the opening up of monuments to public access can bring wider benefits, and that conservation is not its sole focus. In this case, Historic Scotland’s evidence to the inquiry was very narrow and failed to recognise the wider policy objectives. Thus, to the extent that there would be an impact on the protection and management of the scheduled ancient monument, this has to be balanced against the benefits which would accrue from the proposed mitigation, enabling the two additional key outcomes identified in the policy to be achieved, both through securing greater economic benefits from the historic environment, and enabling the historic environment to be valued, understood and enjoyed. Conditions 3.76 Following the discussion of the suggested conditions at the inquiry, it was confirmed that the applicant would accept a condition allowing micro-siting of turbines up to 25 metres from their identified locations, and that arrangements for improved access to the scheduled ancient monuments should be the subject of a suspensive condition requiring their approval by the planning authority in consultation with Historic Scotland. IEC_3_105_3 24 3.77 The noise condition promoted by the action group would not be consistent with ETSU-R-97 as it is based on a single background noise measurement. The lower limits proposed by the council are not consistent with ETSU-R-97 either. 3.78 A suspensive condition is also suggested to deal with the issue of shadow flicker. Conclusion 3.79 Despite being identified as an area with significant capacity for wind farm development, Caithness has not proved an easy place to pursue such proposals. This site has advantages in terms of its wind resource, ease of grid connections, and good transport access. Direct natural heritage impacts are very limited, particularly on the qualifying interests of the Caithness Lochs special protection area which have been extensively analysed and have been taken into account in the design and layout of the wind farm. Cultural heritage impacts are restricted to aesthetic ones on visitors to the scheduled ancient monument. 3.80 There would be some significant impacts on the visual amenity of some residents, but that should be seen in the context of the very broad landscape within which they are located and the fact that relatively few houses would be orientated towards the wind farm. 3.81 The issues were correctly summarised by the council’s officers in the report to committee: the significant contribution towards renewable energy objectives and other benefits require to be weighed in the balance against these adverse impacts. The officers recommended that the council should not object to the application, and Scottish Natural Heritage reached the same conclusion having assessed the natural heritage issues raised by the application. The Scottish Ministers should grant consent, subject to the appropriate conditions. IEC_3_105_3 25 4. SUMMARY OF THE CASES FOR HIGHLAND COUNCIL AND THE CAITHNESS WEST ACTION GROUP 4.1 Highland Council and the Caithness West Action Group combined their representation at the inquiry. In considering the application the council had not accepted its officers’ recommendation, and had decided to object to it for the following reasons: The proposal is contrary to the provisions of the Caithness local plan, the site being covered in part by a PP3 designation, which presumes against development; The proposal is contrary to SPP6, in relation to the proximity of the wind farm to existing dwellinghouses The proposal is unacceptable in terms of its cumulative impact with other wind farms in the vicinity, and in relation to the likely adverse impact on tourism, tourism routes, and tourist destinations such as Dunnet Head and Strathy Point; The proposal is unacceptable in terms of its adverse visual impact and is contrary to the Highland Renewable Energy Strategy policy and guidance; The application should be the subject of an appropriate assessment carried out to the satisfaction of Scottish Natural Heritage and to address issues raised by the Royal Society for the Protection of Birds and Historic Scotland. It was conceded in submissions that the last of these is not a reason, and can be ignored. 4.2 Schedule 9 sets out the only statutory tests for an application for consent under the Electricity Act. However, by incorporating a deemed planning permission into the consent process, the normal development plan procedures set by Section 25 of the Town and Country Planning (Scotland) Act 1997 require to be followed. In this case, when assessed against the provisions of the development plan, it is concluded that the proposal is contrary to its terms. As there are no countervailing material considerations, it should be refused. 4.3 National energy policy encourages renewable energy developments where these can be located without undue environmental or amenity impact. The advice in the Annex of Scottish Planning Policy 6 is directed to the formulation of plans, but discloses some sensitivity among Ministers about the potential for amenity to be disturbed if substantial groups of turbines are located to close to communities and places where people actually live. It is the host communities which have to bear the brunt of any disturbance which arises after construction of a wind farm. What has to be measured is the likelihood of a significant long term detrimental impact. 4.4 The proper reading of the description of “edge of cities, towns and villages …” in Scottish Planning Policy 6 should include communities, as it cannot have been the Ministers’ intention to exclude communities simply because they are dispersed, as is common in many parts of Scotland, including Caithness. Here the community is dispersed, rather than concentrated, with seven houses within 500 metres of one of the turbines; 25 houses within one kilometre; 61 houses within two kilometres; and 158 houses within three kilometres. These are considerable numbers, and the most striking feature of this development is that every turbine would have a house within one kilometre of it. IEC_3_105_3 26 4.5 The conclusions of the report “Residential Receptor Assessment” [Document BWL41] are not credible, as it uses a narrow definition of sensitivity, lacks a full assessment of cumulative impact, and uses both selective criteria and a discredited significance matrix methodology. Account should have been taken of the sensitivity of the curtilage of dwellinghouses, not just of the expectation of views from the lower floor of the principal elevation. The grouping of dwellings into quadrants was misguided, as the position of each can be mapped. Current turbines are larger, and therefore more prominent than those available when government advice in Planning Advice Note 45 was issued. 4.6 Some of the viewpoints used for assessing visual impact are not representative, and at a number of receptors the cumulative impacts with other proposed wind farms has not been recognised. As a result the significance of the effects on residential amenity at a number of receptors would be greater than the applicant’s consultant had assessed. 4.7 Many of the landscape and visual impacts of the wind farm would also be greater than has been assessed by the applicant’s consultant due to the clustering effect of the turbine layout geometry, the poor selection of a representative viewpoint, the presence of a dark backdrop, and/or the under-stated sensitivity of road users. 4.8 The development would have an overwhelming effect on those closest to it. It is proposed for a prominent ridge-line, occupying the eastern flank of the Hill of Shebster which is in an area with a subtle landscape, devoid of stark and prominent features, where any rise in topography is the more pronounced. The site itself has a complex form of secondary ridges, plateaux and valleys. The proposed layout fails to respond to these characteristics and instead imposes a geometric grid which is constrained by proximity to dwelling houses and to transmission lines. It thus maximises the number of turbines within the area, while the turbines align without regard to the topography. It does not achieve a sympathetic or even a broadly appropriate fit with the landscape. Its visual impact is increased by the triangular grid pattern which maximises the viewpoints from which the geometry is apparent, resulting in a series of confused clusters, rather than an evenly dispersed cohesive grouping. 4.9 The wind farm cannot be viewed as a “single element to create a simple image” in accordance with guidance issued by Scottish Natural Heritage. The withdrawal of Scottish Natural Heritage’s objection was unjustified. Its statement that, if this wind farm is approved, the threshold capacity of accepted landscape change in this area will have been reached, is extraordinary as it is not based on any known capacity study, and the same statement was made by Scottish Natural Heritage in response to another wind farm proposal at South Shebster. 4.10 Scottish Natural Heritage’s conclusion on this wind farm is unsound and unsafe. It did not take account of the proximity of the turbines to dwellings, or the relative landscape significance of the Hill of Shebster ridge, or of the effects arising from the geometric layout. The changes arising from the revised scheme were not sufficient to have justified withdrawing its previous opposition. IEC_3_105_3 27 4.11 In terms of its cumulative impact with other wind farms, additional representative viewpoints would have allowed a more comprehensive understanding and significant cumulative effects would have been apparent, particularly if projects at the scoping stage had been included. The sensitivity of viewpoints on the A836 must be regarded as high, as the road is promoted as a tourist route and forms part of the national cycle route. This is likely to magnify the most significant cumulative impacts. These are likely to arise in conjunction with the Forss wind farm and with those proposed for Hill of Lieurary and South Shebster. 4.12 There would also be sequential effects, given the visibility of this proposed wind farm together with others along the key transport routes. The impacts should be regarded as permanent because, although the turbines may have only a 25 year functional life, it is accepted that they are likely to be replaced. 4.13 In relation to the archaeological remains at Cnoc Freiceadain, the council and the action group adopt the evidence and submissions of Historic Scotland. It is quite clear that the turbines will adversely affect the setting of the cairns. 4.14 The action group’s noise consultant had analysed the data regarding background noise which had been provided by the applicant and had identified that the wind speeds recorded at the higher mast were 50% greater than those recorded by the mast sited near Hillcrest. He had not been informed until the day before giving evidence that the data was not synchronised, and conceded if that was the case then his calculations may not be accurate. 4.15 The consultant also expressed concern that the microphone windshield which had been used was inadequate, being of the wrong size and porosity; and that pieces of wind speed data were missing. Although these errors might not make a significant difference to the overall analysis, their existence results in a lack of confidence in the data, and would tend to make the background noise calculations higher than they actually are. 4.16 He also differed from the applicant’s noise consultant who considered that the methodology for calculating turbine noise should scrupulously follow the approach advocated in ISO 9613, by using the factor G = 1, because the ground here is soft, and a height of 1.4 metres, because that is the height where compliance monitoring would be undertaken. Instead, he took the empirical view that the G = 0.5 factor and a receiver at 4 metres should be used, because this has been shown to give accurate results in practice, and has been accepted recently by a Department of Trade and Industry working group. 4.17 The applicant should also be required to justify using a higher noise limit for those properties where the owner has a financial involvement in the project. It had been conceded that without that adjustment, the requirements of ETSU-R-97 would not be met at a number of these properties. 4.18 The proposed development would result in an increase in ambient noise of between 3 and 4 times, if the figures of the action group’s consultant are correct. IEC_3_105_3 28 4.19 If the calculations produced by the applicant’s consultant are correct, the wind farm’s noise effects would be at the margins of acceptability under ETSU-R-97, and are only met by adopting the night-time standard of 43 decibels. If the council’s preferred standard of 38 decibels is used, then mitigation would have to be applied by turning off three of the turbines in certain wind conditions. Further mitigation would be required if the calculated background noise measurements do prove to be too low. 4.20 If the conditions which the action group’s noise consultant considers realistic do occur in practice, then the degree of mitigation required may be so great that the wind farm might not reasonably be operable. While the imposition of a condition might ensure that noise levels are controlled to below the limits set by ETSU-R-97, the variations in noise which would result from turbines being turned off and restarted, or reduced in power, would render them more noticeable and more annoying. 4.21 In this case, the issue of noise is a direct function of the proximity of the turbines to houses, and it is a key consideration. Measurements and predictions are surrounded by uncertainty, and refusal would be justified on this ground alone. Failure to meet the parameters set by ETSU-R-97 would also justify refusal, as this would result in a significant adverse effect on residential amenity. 4.22 The predicted increases in ambient noise are such that, in cases such as this where the actual turbine model has not yet been selected, sensible precaution requires refusal of the application, since the noise levels predicted have not been demonstrated to be sufficiently robust to be able to give any reasonable degree of confidence that there would not be noise at an unacceptable level. 4.23 In relation to ornithology, it is clear that the wind farm has the potential to affect the qualifying interest of the Caithness Lochs special protection area, so that the decision maker is required to undertake an appropriate assessment to test whether the wind farm would affect its integrity. 4.24 Scottish Natural Heritage has confirmed that the population of Greenland white-fronted geese is relatively stable at around 440, although the action group’s witness indicated that it has dropped by 10%. There are two distinct flocks, and the one at risk consists of some 200 birds. Adopting the precautionary principle, an annual collision risk of 0.15% should be applied. The development of the wind farm would result in a considerable loss of feeding habitat, with the geese experiencing greater disturbance from the rotating turbine blades than from farming activities, from which they are largely shielded by the undulating topography. 4.25 In their evidence, representatives of the action group referred to strong local objections to the proposal throughout the application process, due to the size and proximity of the turbines to existing houses, with consequent detrimental effects on the amenity of local residents. A number of health and safety issues which could impact on local people were raised, including the structural integrity of the turbines, fire risk, ice throw, and the potential for effects on the health of local residents, including the triggering of epileptic fits and a “syndrome” related to the proximity of wind farms. These risks justify a greater separation distance from existing houses IEC_3_105_3 29 than is proposed. Transport arrangements during construction also posed risks to local people, and could impede emergency evacuation from Dounreay. There were also concerns that this wind farm would affect tourism locally, which is important to the economy of Caithness. 4.26 It was conceded in submissions that the planning policy which bears upon this case is not in an entirely satisfactory state, as it is now accepted that the Highland Renewable Energy Strategy does not comply with Scottish Planning Policy 6, and it is being revised. However, the site lies wholly within an area where the strategy indicates that there will be a presumption against onshore wind farm developments. The proposal is also contrary to the development plan, principally in relation to Policies G2 and E2 due to its significant detrimental impacts in terms of noise, landscape and visual effects, and its impact on cultural heritage and, potentially, nature conservation. That raises a presumption for refusal. The need for renewable energy and to meet the targets could conceivably overcome that presumption if the location of the proposed wind farm was acceptable, but it is not. 4.27 If consent is granted, it should be subject to an agreement to secure the delivery of the benefits which are claimed for the scheme by both increasing the supply of renewable energy and securing a reduction in pollution that would otherwise have been generated. While renewables can displace conventionally generated power, it should be demonstrated in every case. In Caithness, it may be hydro power that is displaced, with no saving in carbon. 4.28 This guarantee could be secured through a Section 75 agreement, with reference to a minimum base load output. This would enable everyone to see what they were getting. If that approach is not accepted, it should be found that the benefits are ill-defined and essentially guess-work, and should receive less, or no, weight. 4.29 In conclusion it was submitted that the application depends on the conclusions reached in relation to ornithology, noise, and the residential, landscape and visual impacts. For such developments to command the support of the communities within which they would be located, they should achieve environmental acceptability and should not be over-bearing, dominant, unacceptably noisy or intrusive to a point where a significantly adverse effect on residents is predicted. The Scottish Government’s policy supports renewable energy developments, but only where these are environmentally acceptable. This means that they can operate to their capacity and still achieve a satisfactory measure of compatibility with their receiving environments, whilst also avoiding significant adverse effects on the amenity of their neighbours. This proposed development fails that test. IEC_3_105_3 30 5. SUMMARY OF THE CASE FOR HISTORIC SCOTLAND 5.1 Schedule 9 of the Electricity Act requires that those formulating proposals should have regard to the desirability of protecting sites, buildings and objects of architectural, historical or archaeological interest. 5.2 In this case, the issue for Historic Scotland is whether the proximity of the wind farm would have an adverse effect on the setting of the scheduled ancient monuments of Cnoc Freiceadain and Hill of Shebster. The former contains two cairns, known as Cnoc Freideadain and Na Tri Sithean. 5.3 The applicant has departed from the assessment of the significance of the impacts on these monuments which was set out in the environmental statement and the addendum, so no weight should be placed on that assessment. Also, intervisibility as a factor in understanding a monument’s setting is not an issue here. 5.4 The argument that the impact of the development on the setting of the monuments should be regarded as temporary because the application is for a time limited period is not supported by the terms of The Scottish Office Development Department Circular No. 4/1998: 'The use of conditions in planning permissions'. Paragraph 105 makes clear that the material considerations to be taken into account are the same both for a temporary and an unlimited consent. 5.5 The fact that consent is sought for a temporary period cannot be used to say that the effect on the area would be limited. Similarly, the claimed reversibility of the development is not a good argument for the impact being limited. No such suggestion is made in Scottish Planning Policy 6, and it is difficult to see how a future application to renew the permission for a wind farm would be resisted. 5.6 The policy that scheduled ancient monuments should be preserved within an appropriate setting is set out in Annex A to Scottish Planning Policy 23. There is no widely accepted or legal definition of setting, but paragraph 9 provides some assistance (quoted at paragraph 2.15 above). Paragraph 3 in Annex 5 of the Scottish Historic Environment Policy provides the following advice regarding adverse impact: “Whether any particular development will have an adverse impact on the setting of a scheduled monument is a matter of professional judgement. It will depend on such variables as the nature, extent, design of the development proposed, the characteristics of the monument in question, its relationship to other monuments in the vicinity, its current landscape setting and its contribution to our understanding and appreciation of the monument.” 5.7 To define the setting of these monuments, a good starting point is their location. The Cnoc Freideadain cairns are almost on the flat summit of Cnoc Freiceadain which, at 122 metres AOD, is a prominent feature on the skyline, with Tri Na Sithean being prominent from all directions. The cairn at Hill of Shebster is just to the north of the actual summit, and some 700 metres south of the other cairns along the ridge. IEC_3_105_3 31 5.8 There is a debate as to whether the cairns were designed to be visible. The extent of the afforestation at the time of their construction is a matter of speculation. Authors agree that tree cover was sparse in the Neolithic period, so the cairns are likely to have been more visible than might have been the case had there been heavier afforestation across the ridge. While it is not known why particular locations were chosen, each is in a prominent one. If that in itself is unique, then it may be all the more important to ensure that the integrity of the prominence setting is not adversely affected. 5.9 It was submitted that it should not be determined that the setting of these monuments is less important because, when they were constructed, they may have been less obvious because of forestation. That would be to assess the setting on a speculative basis, and would not accord with the requirements of the policy in which the current landscape setting is the context within which the assessment of impact is to be made. 5.10 In assessing the impact on the setting, regard should be had to the size and proximity of the turbines, being 110 metres to blade tip and with the closest turbine standing only 588 metres from the Cnoc Freideadain cairns. The blades would be turning most of the time, and the turbines would puncture the horizon. 5.11 If the cairns were placed in close proximity to settlements, the view from them in Neolithic times would have been of a settlement or agricultural land. It is this setting into which the turbines would intrude. The landscape has changed over time, but developments such as Dounreay do not compromise the setting of the monuments to the extent suggested by the applicant. 5.12 The applicant’s archaeological consultant accepted that the visual impact on the setting of the Cnoc Freiceadain cairns and, to a lesser extent, the Hill of Shebster cairn would be significant. He considered that the critical question is whether the wind farm would overpower the setting of the monuments. That over-states the test which is to be applied. He also stated that the “contextualisation of his appraisal” was influenced by the knowledge that the duration of the impact involved would be 26 years, and he appeared to be arguing for his own academic viewpoint. That however misses the point, as it is important for the monuments to be preserved in a manner that allows that academic debate to continue, particularly where the reasons for the location of these prominent monuments is unclear. 5.13 The two proposals suggested by way of mitigation are at the lower end of the hierarchy of mitigation. While improved access to the historic environment is supported by policy, the suggested measures have not been assessed in terms of their impact on the cultural significance of the monuments. As they were offered at a late stage and cannot be assessed for compliance with policy, no weight should be attached to them. If the development did proceed, the suggested LIDAR laser scanning would be welcome, but would not in itself justify a breach of policy. 5.14 It is not for Historic Scotland to determine whether there are any exceptional circumstances which would justify a departure from policy, but in considering this issue, regard must be had to the number and extent of wind farms, both constructed and planned. Accordingly, Historic Scotland asks that the application be refused. IEC_3_105_3 32 6. SUMMARY OF THE CASES OF OTHER THIRD PARTIES 6.1 Stuart Young confirmed that he is the chairman of the Caithness Windfarm Information Forum, but was giving evidence on his own behalf. He considers that Caithness has already passed saturation point for wind farms. He indicated that he produces large scale photomontages of wind farms and in his evidence he sought to highlight the importance of the correct distance for viewing photomontages so that the turbines are seen at the correct scale. He suggested that the photomontages in the environmental statement do not adequately represent the visual impact of the proposed Baillie wind farm, where the turbines would be taller that those at the existing four wind farms in Caithness. 6.2 Two of the images in the environmental statement were too indistinct to be representative of the views (viewpoints 25 and 04b). He also suggested that better viewpoints could have been used, as five conceal the true impact on communities, five avoid showing the impact on travellers or tourists; and the viewpoint from the Orkney ferry suggests that the wind farm would not be highly visible for the greater part of the voyage. However, viewing the existing wind farms from certain locations would eliminate any uncertainty about the true visual nature of the proposed turbines. 6.3 The nearest turbine to a green on the golf course at Reay is 4.7 kilometres away, and he suggested that the wind farm would disturb the golfer’s peaceful enjoyment of the game. In answer to questions he confirmed that he is not an expert in either photography or landscape, but that his interest is in opposing wind farms. 6.4 Russell Hayley stated that he is a resident of West Caithness, living at Reay. He had viewed the visual representations of the Baillie wind farm proposal looming over the village of Reay on the website of the Caithness Windfarm Information Forum, and the link from there to an objection letter which could be sent to the council. On the applicant’s website, the turbines appeared tiny by comparison, despite the viewpoint being a mile closer. On investigation, he found that the visual representation on the forum’s website did not follow the guidelines issued by Scottish Natural Heritage. The forum amended the website image after he drew attention to this matter. 6.5 Other photomontages produced by Stuart Young and the forum also contained errors related to cropping, field of view, and the position of certain turbines. Anyone viewing these images would have got a misleading impression of the wind farm. 6.6 He confirmed that he supports this wind farm proposal, both because of his general concerns about global warming and because he considers that it can be accommodated. He has no financial involvement in the development. 6.7 William Brown stated that he is the convenor of the Caithness West Community Council. Its duty is to ascertain, co-ordinate and express to public authorities the views of the community which it represents. It had held public meetings to discuss this proposal in February 2006 and November 2007. Questionnaires circulated at the end of these meetings identified that, at the first, IEC_3_105_3 33 23 people were against the wind farm, with only the developer in favour. At the second, 32 were against, 2 in favour and 4 abstained, with a further 32 objections submitted by letter and email by those who could not attend. 6.8 A subsequent postal ballot was held, resulting in an overwhelming vote against. The developer produced a petition with several hundred signatures in support, but only two live in West Caithness. On this basis, the community council concluded that the local community is overwhelmingly not in favour of the development. 6.9 In answer to questions, he confirmed that the community council had first expressed its concerns about the development at the time of scoping, before the application had been submitted, as its view is not to support wind farms in its area. Letters published in the local press expressing his opposition to the development had been written in his private capacity, although he accepted that their terms would not have been appropriate if he had signed them as the convenor of the community council. 6.10 John Webster stated that he opposes this development. He lives at Buldoo, to the east of Dounreay and 2.5 kilometres west of the six smaller turbines at Forss. These cause shadow flicker on residential and business properties and, being on land at the same level as the houses, generally dominate the landscape whether or not they are turning. Residents at Buldoo would face and look up to the Baillie turbines towards the south, reaching to 220 metres above sea level, and also at a distance of 2.5 kilometres to the nearest. In winter months, the rising sun would cause shadow flicker and nuisance; while in summer months, glinting may also cause a nuisance. 6.11 In view of this and other wind farm proposals, and in conjunction with the controversial issues in the immediate nuclear exclusion zone, he suggested that Buldoo is likely to be at the centre of an enormous blight issue. 6.12 Celia McDougall stated that she lives at Shebster and objects to the proposed wind farm. It would cause a major invasion of the natural landscape that would be detrimental both to the people and to the birds of the area, as well as to the scope and shape of the landscape. If there were government guidelines for identifying the most suitable sites, this would not be one of them. 6.13 Caithness is known for its big skies, resulting from the uninterrupted expanses of high skies above a low, undulating horizon. The turbines would intrude into this landscape which allows long distances to be seen from every viewpoint. The application site is only between 70 to 100 metres above sea level, so that these tall turbines would double the landscape height and in conjunction with other existing and further proposals, wind farms would be visible in every direction. 6.14 There would be clusters of houses close to the wind farm, some within 500 metres of the nearest turbines, with potential impact on householders through noise and from shadow flicker due to the low angle of the sun for much of the year. It would also be close to the national cycle route, to a number of distinctive IEC_3_105_3 34 archaeological sites, including the chambered cairns, and to feeding areas and flight paths of white fronted geese. 6.15 Two precognitions were taken as written submissions, as the authors were unable to attend the inquiry on the day. Letitia Dungavel stated that she lives at Bardnaheigh farmhouse, adjacent to the proposed wind farm and some 400 metres from the nearest turbine. She and her family support the development due to its long term benefits for global warming, and it would provide alternative job opportunities to Dounreay. She knows many people who feel the same. The proposal is fully detailed, with great attention to the landscape and would fit well with the existing pylon line. The Forss wind farm would cause no detrimental effects to local people in combination with this proposal, while the Causewaymire wind farm is 18 kilometres away. 6.16 The adjacent road is the back road between Thurso and Reay, which is not particularly busy and is mainly used by Dounreay workers to avoid congestion. It is also the national cycle route, but most tourists take the coastal road where the Forss House Hotel, the area’s only tourist facility, is located. A visitor centre at the Baillie wind farm would be of educational benefit both to local people and visitors. 6.17 Children enjoy seeing turbines, and there is a pleasing tranquillity about them as they slowly revolve. The wind farm would not detract from the scheduled ancient monuments, and few Caithness people or visitors know of, or visit, the cairns. 6.18 David Mason stated that he supports the development, and that the employment opportunities, equivalent to between five and six full-time equivalent jobs, that would be created are especially important in Caithness, due to the decline in employment in agriculture and the nuclear industry. Caithness is well located to take advantage of the development of technologies in the renewable energy industry. In Scottish Planning Policy 6 the Scottish Ministers confirm that a thriving renewables industry in Scotland has the potential to develop new indigenous industries, particularly in rural areas. IEC_3_105_3 35 7. CONSULTATION RESPONSES AND WRITTEN REPRESENTATIONS 7.1 Four organisation submitted responses relating to air safety: the Highlands and Islands Airports Authority indicated that the proposal is unlikely to impact on operations at Wick Airport; National Air Traffic Services confirmed that it has no safeguarding objection; the Civil Aviation Authority advised that there may be a need to install aviation obstruction lighting; and the Ministry of Defence confirmed that it has no objection. 7.2 Ofcom advised that two telecommunications operators may be affected and the applicant should have clearance from them. The Scottish Environment Protection Agency has no objections, subject to the imposition of conditions requiring a pollution prevention plan and protection of watercourses. Caithness West Community Council confirmed its objection to the proposal, principally in relation to its visual impact, the effects on residential amenity and on birds. 7.3 Scottish Natural Heritage has withdrawn its earlier objections to the proposal in relation to its landscape and visual effects and to its impact on the ornithological interests of the Caithness Lochs special protection area and the Loch Calder Site of Special Scientific Interest. 7.4 In a further written submission dated 16 February 2009 and lodged prior to the public inquiry, it confirmed its advice that, although the proposal is likely to have a significant effect on the special protection area and therefore that an ‘appropriate assessment’ is required, it is also possible to ascertain that the proposal would not have an adverse effect on its integrity. It also advised that it is not necessary to impose any conditions on the consent in order for this conclusion to be reached with certainty. 7.5 Caithness Lochs special protection area comprises six lochs, including Loch Calder, and Broubster Leans which is a mire. The three qualifying birds species of the special protection area are the whooper swan, greylag goose and Greenland white-fronted goose. The conservation objectives for the special protection area are: to avoid deterioration of the habitats of the qualifying species, or significant disturbance to the qualifying species, thus ensuring that the integrity of the site is maintained; and to ensure for the qualifying species that the following are maintained in the long term: The population of the species as a viable component of the site The distribution of the species within the site The distribution and extent of habitats supporting the species The structure, function and supporting processes of habitats supporting the species No significant disturbance of the species. 7.6 The potential causes of a likely significant effect arising from the proposed wind farm are that: there would be short term disturbance to the birds during the construction period; there would be long term disturbance to the birds’ feeding areas arising from the sight of the operational turbines; and there would be the risk of collision with the moving blades of the turbines as the birds fly between their feeding and roosting areas. IEC_3_105_3 36 7.7 Scottish Natural Heritage had re-calculated the collision risk for each of the three qualifying birds species using an up-dated avoidance factor of 99% for the geese, and 95% for the swans. Its estimate of the risk to the greylag geese and whooper swans was the same as the applicant’s, respectively eleven and one birds annually, while for the Greenland white fronted geese it had estimated an annual collision risk of 0.3 birds, compared with the applicant’s estimate of 0.2 birds, but confirmed that this difference has no implications for Scottish Natural Heritage’s position. 7.8 The combined effects with other wind farm proposals was also taken into account. For each of the species, Scottish Natural Heritage stated its reasons for finding that, taking account of the effects of the wind farm in relation to both disturbance and collision, both on its own and in conjunction with the other wind farms, the five conservation objectives listed above would all be met and that, in relation to each species, the proposal would not adversely affect the integrity of the special protection area. 7.9 A substantial number of written representations both in favour of and in opposition to the proposed development were submitted to the council and/or to the Scottish Ministers. There were over 230 objections submitted, mainly from local people, and highlighting the impacts of the proposed development. There were over 800 representations in support of the development. These were drawn from a wider area, with some from other countries, but the majority were from addresses within Highland including over 100 from Wick and the eastern area of Caithness, and also more than 100 from Thurso and other villages in the western part of Caithness lying near to the wind farm. Some of those who occupy the individual houses closest to the proposed wind farm also confirmed their support. Those in favour of the proposal generally highlighted the wider benefits arising from wind energy generation which this development would help to achieve. The key issues raised in the written representations were reflected in the evidence given to the inquiry. 7.10 The Royal Society for the Protection of Birds also submitted a detailed written statement prior to the inquiry in support of its objection to the proposal. It contended that there might be an adverse effect on the integrity of the Caithness Lochs special protection area. Assumptions made in the environmental statement are questionable, and the reliability of the data is reduced by the use of a single vantage point observer in the fieldwork surveys. While the society accepts that the collision risk model has been used accurately, it considers that the increased mortality of the three species has been under-estimated. It also states that it is unsatisfactory for Scottish Natural Heritage to rely wholly on the results of the modelling, as there is limited data and under-recording was likely. It should also have had more regard to a recommendation made in one of its commissioned reports that there should be a presumption against wind farms within 5 kilometres of roost sites of the qualifying species of a special protection area. 7.11 The society concludes that an appropriate assessment is required to determine the significance of the impact. While it does not consider that loss of feeding areas due to land take is a cause for concern here, research suggests that IEC_3_105_3 37 displacement from feeding areas in the vicinity of the wind farm is likely and Greenland white fronted geese are particularly susceptible to disturbance. 7.12 If consent is granted, measures to mitigate these adverse impacts, including a habitat enhancement package, monitoring proposals and a construction method statement, should be secured either by imposing conditions or through a Section 75 agreement made prior to works commencing. The most effective measure would be turbine shutdown during periods of greatest bird activity, possibly using radar survey to establish thresholds of activity. A monitoring programme linked to postconstruction contingency measures should also be used to allow additional shutdown if the development is having an adverse effect on the designated sites. IEC_3_105_3 38 8. FINDINGS OF FACT 8.1 I find the following facts, the test applied being the balance of probability. 8.2 I adopt as fact the site description and application background in relation to the proposed development, as set out in Section One; and the legislative framework and planning policy context, which are set out in Section Two. 8.3 To enable the development to proceed, the Scottish Ministers would require not only to issue a consent under Section 36 of the Electricity Act, but also to issue a direction that planning permission shall be deemed to be granted. Only if it is first decided that consent under Section 36 is to be granted does the question arise as to whether the Scottish Ministers should direct that planning permission shall be deemed to be granted also. 8.4 Schedule 9 of the Act sets out specific obligations on the Scottish Ministers in their determination of an application for consent under Section 36: they require to have regard to the desirability of preserving natural beauty, of conserving flora, fauna and geological or physiographical features of special interest and of protecting sites, buildings and objects of architectural, historic or archaeological interest; but also to have regard to the extent to which the applicant has complied with the duty to do what he reasonably can to mitigate any effect which the proposals would have on the natural beauty of the countryside or on any such flora, fauna, features, sites, buildings or objects. 8.5 Schedule 9 also requires both the applicant and the Ministers to avoid, so far as possible, causing injury to fisheries or to the stock of fish in any waters. 8.6 The Act does not state that these are the only matters to which regard should be had. In these circumstances, a decision maker should not fail to take account of matters which would be material to a decision to grant consent for such an application. As this is an application to erect a wind farm, I consider that government policy, along with the environmental effects identified in the submitted and amended environmental statements and in the additional environmental information submitted to the inquiry, are among the material considerations to which regard should be had. So too are the relevant provisions of the development plan, but what differentiates the determination of an application under Section 36 from the determination of a planning application, is that the decision making process specified under Section 25 of the planning Act is not a statutory requirement. 8.7 That distinction is largely academic, as it is for the decision maker in each case to determine the weight to be attached to each of the material considerations, which would inevitably include the relevant provisions of the development plan. 8.8 The Scottish Ministers are also not required by statue to apply Section 25 of the planning Act to their determination as to whether to direct that planning permission shall be deemed to be granted. While it may be theoretically possible to attach different weight to the same considerations in determining whether to direct that planning permission should be deemed to be granted, having already IEC_3_105_3 39 determined that Section 36 consent should be granted, it is not apparent why, or in what circumstances, that would be justified. The need for and benefits of the proposal 8.9 Within the wider context of UK government energy policy, the policies of the Scottish Government specifically promote the development of further renewable energy generation capacity and confirm, despite a range of other initiatives and technologies, that onshore wind farms are expected to continue to make a significant contribution towards that objective. 8.10 This wind farm would provide an installed capacity of approximately 52.5 megawatts, providing a useful contribution towards meeting the Scottish Government’s target of generating 50% of Scotland’s electricity from renewables by 2020. The current grid connection offer is for 2012, but the option of a non-firm connection before that date offers the prospect of an earlier contribution. The characteristically windy nature of the Caithness climate indicates that this wind farm’s contribution would be more sustained and therefore more effective than those in many other parts of Scotland. 8.11 The extent to which it would replace fossil fuel generated electricity, and thereby reduce CO2 or other emissions which contribute to climate change, is inevitably uncertain, not just because of the nature of the wind resource, but also because the sources used for energy generation are also liable to constant change from a variety of factors. While government anticipates that such emissions will be reduced through increased renewable energy generation, there is no basis in policy for making the granting of consent for an individual project dependent on a condition or other legal mechanism which would purport to guarantee the delivery of these emission reductions. 8.12 For the local economy, outwith the construction period direct additional employment would be small, although the development would contribute to a growing role for Caithness in developing renewable energy industries and technologies. This offers an alternative to the decline in employment opportunities in both the nuclear industry and in agriculture. Clearly the main long term beneficiary would be the applicant company and its partners, and also the local residents who have a financial stake in the development. To the extent that generated revenues are retained locally, this would be likely to help support local businesses and services. Improved access, education and promotion regarding the scheduled ancient monuments, if secured as mitigation through a planning condition or agreement, could also make a useful contribution to tourism locally. 8.13 Despite mention in General Policy G4 of the structure plan and the Highland Renewable Energy Strategy, any payments made by the developer into a local community fund cannot be sought by the planning authority, whether it be Highland Council or the Scottish Ministers, where those payments would not address any particular need or impact arising from the development. Nor should they be secured through a planning condition or a Section 75 agreement. Such payments would be a matter entirely for the applicant’s discretion. IEC_3_105_3 40 Landscape and visual effects 8.14 The government’s advice is that, as wind turbines are tall and frequently located in open land, they are likely to be highly visible. This is particularly apt in relation to Caithness, where the large scale, open and relatively flat landscape enables any wind farm, particularly one such as this with 110 metre high turbines, to be seen over great distances, and often from many directions. They can therefore be highly prominent, because of their height and the open landscape; but may not be dominant, except when viewed at close distances, because they occupy only a small proportion of a wide, or even 360 degree, panoramic view which is largely uninterrupted by hills or deep valleys. 8.15 In these circumstances, some may consider the landscape wholly inappropriate for wind farm development, while others would judge that it has considerable scope to accommodate them. Each position could be justified by the visual evidence of the existing wind farms which are constructed and operational In Caithness. Although the impact on this landscape of a wind farm such as Baillie would undoubtedly be major and significant, and properly regarded as adverse, nonetheless I would not regard it as unacceptable. This is because I consider that the large scale, open and largely horizontal character of the landscape is capable of accommodating, but not disguising or concealing, such an element; and it does not have particular scenic qualities which are recognised by any formal landscape designation. 8.16 This site’s surrounding topography provides a small degree of containment, although this is relatively insignificant in relation to the wider landscape setting. From the north-west, the wind farm would be seen as standing beyond the Shebster ridge which separates the site from Dounreay and the coastline of the Pentland Firth. In nearer views, it would be seen to occupy the land between the Forss valley and the Shebster ridge, although the relative gentle changes in topography would be largely over-powered by the scale of the turbines. The concentrated and compact layout would, to a degree, contribute to that element of containment. 8.17 When viewed from the Shebster ridge in the vicinity of the Cnoc Freiceadain cairns, the turbines would clearly be standing on the lower ground to the east of the minor road from Shebster to Forss, but the blades would be turning at a height level with the viewer and would be highly prominent, resulting in a significant and adverse visual impact on those visiting the ridge and its scheduled ancient monuments. 8.18 The site lies within a settled lowland agricultural landscape, which has a pattern of scattered housing, some in clusters, but mainly reflecting the nature of the farm holdings. Wind turbines appear as alien industrial elements in any landscape in Scotland, and would do so here too. One of the key features of this proposed wind farm is the nearby presence of houses all around it, in some cases within the application site itself, and also the proximity of some of the houses to particular turbines. 8.19 For instance, houses at Hillcrest and Bardnaheigh are within the application site, and 250 and 300 metres respectively from the nearest turbine to them. In total, six houses would be within 500 metres from the nearest turbine, almost 30 within IEC_3_105_3 41 one kilometres, and over 60 within two kilometres. The residents of those houses which have the windows of main ground floor rooms orientated directly towards the wind farm, would experience a major and significant visual impact, but it would not be restricted to them as the effect would also be experienced by others who would view the wind farm from other rooms, their gardens, or on approach to or departure from their houses. 8.20 I consider that in these circumstances this visual impact should be treated as an adverse one, although I recognise that in this case the residents of some of these houses are stakeholders in the proposed wind farm or are supporters of it, and could therefore be expected to respond positively to the visible presence of the rotating blades of the turbines, even those closest to their own houses. 8.21 Setting aside the other potential impacts which might arise for nearby residents from the presence of a wind farm, the issue that arises here is whether the significant adverse visual impact on local residents would be so great as to render the development unacceptable. The occupier of any house does not have a right to a view. Here, the view from nearby houses would not be lost or wholly obstructed, but would be dramatically altered. The height of the turbines and the rotating motion of the blades, combined with their proximity, would result in the wind farm becoming a dominant element in certain views particularly when the windows of the principal rooms face towards it. This effect would be reduced to some extent by the limited arc which it occupies in the wide overall field of view. 8.22 Any assessment of acceptability in these circumstances relies on judgement rather than measurement. Different conclusions would be reached by different residents or outside observers. Government guidance provides limited assistance. The advice in Scottish Planning Policy 6 to planning authorities preparing spatial strategies for large wind farms states that criteria should be adopted in relation to local communities, to ensure that proposals are not permitted if they would have a significant long term detrimental impact on the amenity of people living nearby. However it appears to define “communities” as comprising cities, towns and villages. This would exclude scattered rural communities such as this. 8.23 In further suggesting that a two kilometres separation distance could be adopted from the edge of cities, towns and villages as a tool to help direct development to the areas of search, it also confirms that any proposals within that distance would continue to be judged on a case by case basis. I consider that even if such a separation zone from the edge of cities, towns and villages was adopted, there are few locations outwith upland Scotland where a wind farm could be sited more than two kilometres from any house. 8.24 Such an approach would represent a real barrier to achieving the government’s renewable energy objectives, although I recognise that a letter produced at the inquiry [Document CWAG101], which was written on behalf of the Energy Minister, appears to confirm this, stating that Scottish Planning Policy 6 “confirms that, in all instances, proposals should not be permitted if they would have a significant long term detrimental impact on the amenity of people living nearby. This principle applies to houses within and outwith two kilometres of the proposed IEC_3_105_3 42 development and regardless of whether they are single dwellings or part of a settlement.” 8.25 Given that I have found that this wind farm, because of its visual prominence and proximity, would have a significant detrimental impact on the visual amenity of some of the people living nearby, and as the impact would be long term, that interpretation would appear to preclude the granting of consent for this application. However, the guidance also confirms that proposals are to be considered on a case by case basis, and I consider that this inevitably requires a judgement to be reached on the acceptability of the impacts identified. 8.26 In reaching that judgement here, I find that the issue to be addressed is whether the adverse effects which would be experienced by some of the residents of the 60 or so houses which are within two kilometres of the nearest turbines is sufficient to outweigh the wider public benefits which the development is designed to achieve. In my judgement, on the merits of this case, I find that these adverse effects are not so great as to be unacceptable, due to: the relatively small number of houses involved; the support expressed by some of these residents, whether through financial involvement or otherwise; the separation distances from the turbines; the compact layout of the wind farm and its position within an open landscape; and the capacity of the landscape to accommodate the wind farm. 8.27 Those using the local road network would also experience some significant visual impact from the proposed development. The A836 is the main coastal road leading west from Thurso and is designated as a tourist route. However its main attribute in that regard is the views which can be obtained towards the Pentland Firth and Orkney. In the vicinity of Forss, while the proposed wind farm would be fairly prominent in views to the south, I consider that this would not detract significantly from the interest which principally arises on the northern side of this route from such features as the local hotel in its woodland setting, the small existing wind farm and, further to the west, the various nuclear energy facilities at Dounreay which are now being de-commissioned, together with the coastal features and the sea views. 8.28 On approach from the west, when seen from viewpoints at Strathy Point or Drum Hollistan, the wind farm would be a noticeable feature, but the eye would tend to be drawn more towards the coastal features and to Dounreay. To the east of Thurso, from vantage points such as Dunnet Head, the wind farm would not appear prominent because of the distance, and the Pentland Firth coastline and views towards Orkney would tend to attract most attention. Neither would it impinge greatly into views of northbound travellers towards Thurso on the A9 or, even less so, on the railway. 8.29 Perhaps the main visual impacts on road users would be on those travelling west from Thurso on the inland C1 route which passes south of the site and is also a national cycle route, and on those travelling north on the minor roads on either side of Loch Calder, where the wind farm would appear as an increasingly prominent focal point in the view. While the visual effect would be significantly adverse, and the wind farm may appear as a dominant feature on some stretches, I do not consider that to be sufficient to render it unacceptable. IEC_3_105_3 43 8.30 Turning to the cumulative landscape and visual effects, it is the Forss wind farm which would be most often and most clearly seen in conjunction with the Baillie wind farm. Although at about 2.5 kilometres it would be relatively close, its coastal location, fewer turbines and lower height would clearly differentiate it, whether in distant or near views, and I do not consider that the combined landscape and visual effects would be unacceptable. In relation to other proposals in this part of Caithness, concerns about further proliferation of wind farms would require to be addressed when each of these is determined, and I do not consider it appropriate to pre-judge the assessments which would require to be made for those in the event that consent is granted for this wind farm. 8.31 In the context of the other wind farms elsewhere in Caithness which have been constructed or approved, I consider the distance from this site to be so great that the cumulative landscape and visual impacts arising from approval of this proposal would not be significant. That finding also relates to the sequential cumulative impacts which would arise, for instance for those travelling north on the A9 to Thurso. Some have expressed concern that too many wind farms might be constructed in Caithness, and Scottish Natural Heritage in its consultation response suggested that some sort of landscape capacity may be approached in this area if this, and perhaps another proposed wind farm south of Shebster, are built. Such a wider assessment of the landscape’s capacity for further wind farm development was not part of the remit of this inquiry. Tourism 8.32 The impact of this wind farm on tourism would mainly be related to its effects on the landscape. Based on my above findings in that regard, I consider that it is unlikely to have a significant effect. Many visitors who would see the wind farm would be passing it as part of a longer journey, either on the coastal route around the north of Scotland or travelling to and from Orkney via Scrabster. The only substantial tourist facility nearby is the Forss House Hotel, already situated very close to an existing wind farm, but well located on the coastal route to draw trade from passing traffic, business related visitors to Dounreay, and those spending longer in the north of Caithness. No objection has been lodged from its owners, and I consider that no significant effect on its business is likely to arise from the presence of the proposed wind farm. 8.33 Effects on other tourist businesses in Caithness, such as the Castle of Mey, are also unlikely, and I have found no compelling evidence to suggest that there would be any significant deterrence effect from this wind farm, particularly as wind energy is being reflected in the re-branding of Caithness which is already evident to those arriving at Wick Airport and in the new visitor centre in Thurso. Ornithology 8.34 With regard to its impact on natural heritage, the key issue in the case of this wind farm relates to the Caithness Lochs special protection area which has been designated to conserve three bird species: Greenland white-fronted geese, greylag geese and whooper swans. The designated area covers six lochs, including Loch Calder to the south, and an area of mire known as Broubster Leans. Although the IEC_3_105_3 44 application site is outwith the designated area, the wind farm would have the potential to impact on these species through direct collision, disturbance, or displacement. 8.35 In these circumstances, the habitats regulations require the planning authority (in this case the Scottish Ministers) to consider the potential impact of the proposed development on those species. As they have been observed flying both through and near the site, and feeding in relatively close proximity to the proposed position of some turbines, I consider that it must be found that the proposed wind farm is likely to have a significant effect on them. Therefore the Scottish Ministers would be precluded from granting consent without first undertaking an “appropriate assessment” to establish whether the development would have an adverse effect on the integrity of the special protection area, having regard to its conservation objectives in relation to each of those species. 8.36 In its written submission dated 16 February 2009, Scottish Natural Heritage set out why, in making its own assessment, it had concluded that the wind farm would not have an adverse effect on the integrity of the special protection area, and why it had concluded so with sufficient certainty also to recommend that it would not be necessary to impose conditions to require appropriate mitigation measures to be undertaken in the event that an adverse effect did occur in relation to one or more of the species. In undertaking their own assessment, the Scottish Ministers are required to consult Scottish Natural Heritage, and as its adviser in this regard, I consider that significant weight must be attached to its view. 8.37 However that assessment is based on a recognition that the wind farm would result in collision fatalities, albeit at a level which would not impact significantly on the population of the species supported by the special protection area. There is inevitably a degree of doubt about such calculations, based as they are on a mathematical collision risk model derived from limited human field observations over a limited period of years. 8.38 Given the legal duties imposed on national governments by the European Union in relation to the protection of such key species through the mechanism of special protection areas, I consider that a precautionary approach should be adopted in these circumstances. This could be achieved by imposing a suspensive condition to ensure the prior approval, before development starts, of a monitoring programme linked to a scheme of mitigation through turbine shutdown for periods which would vary depending on the scale and nature of the impact, as suggested by the Royal Society for the Protection of Birds. This would be consistent with the government’s obligations and, in view of its confidence in its own assessment of the risk, should not be prejudicial to the viability or successful operation of the applicant’s development. The scheduled ancient monuments 8.39 Scheduled ancient monument consent would not be required for this development, as it would not have any direct effect on either of the scheduled ancient monuments at Hill of Shebster or Cnoc Freiceadain. However, any impact on the setting of a scheduled ancient monument would be a material consideration to IEC_3_105_3 45 be weighed in determining whether consent should be granted. Unfortunately, there is no unambiguous definition of what the setting of a scheduled ancient monument is meant to consist, either generally or in relation to particular monuments. 8.40 Here the monuments are located, respectively, just off the summit of the Hill of Shebster, and almost on the crest of the ridge which runs north from it. The scheduled area is tightly drawn around the cairns. The hill and the associated ridge lie entirely to the west of the minor road which connects Shebster and Forss, and from which access to the monuments is gained by a stile adjacent to a passing place that is used for parking purposes. This road also marks the western extent of the application site, and when viewed from the cairns the nearest turbines would be located within or beyond the forestry plantation on that side of the road, at a minimum distance of over 580 metres. 8.41 I consider that it is the Hill of Shebster and the associated ridge running northwards which is the essential setting of these monuments. This conclusion is without prejudice to the academic debate as to the relationship which the cairns may have had with the wider landscape and the people who lived there at the time of their construction. That landscape has undoubtedly evolved over centuries, with power lines, forestry, nuclear and renewable energy establishments, roads, housing and agricultural buildings all evident, and I find no compelling reason why the proposed wind farm would prejudice the setting of the monuments or the ability to appreciate alternative theories regarding its function or relationship with the different environment in which the cairns would first have been set. 8.42 That finding is not affected by my earlier conclusion that the wind farm would have a significant detrimental visual impact on visitors to the ridge and, therefore, also to the cairns. I regard that as a separate matter. I also consider that the mitigation measures proposed by the applicant to improve the physical access to the Cnoc Freiceadain monuments for visitors, combined with the proposed LIDAR survey work and interpretation, offer the opportunity to enhance the understanding and interpretation of the monuments and thus the visitor experience. The unique opportunity provided by the vantage point on the ridge to connect the Neolithic monuments with iconic elements of recent energy industry initiatives which would be represented by Dounreay, Forss, Baillie and the Pentland Firth, has the potential to engage the interest of visitors and residents alike. Noise 8.43 The noise generated by wind turbines can cause disturbance to residents in nearby houses. In this case, the proximity of the houses on all sides of the wind farm requires that careful assessment is made to ensure that appropriate protection would be provided for residents where necessary. 8.44 Planning Advice Note 45 advises that the approach set out in ETSU-R-97 should be adopted for wind farm proposals, and this has been followed by the applicant’s consultant. There is no persuasive evidence that this has proved insufficient elsewhere. The methodology makes provision for a small relaxation in standards in relation to any houses where the occupants have a financial interest in the development. That is reasonable, and it is relevant to this wind farm. IEC_3_105_3 46 8.45 While a number of criticisms were made of the method of data collection employed and subsequent calculations made in the applicant’s assessment, many of these were based on mis-understandings and I am satisfied that the assessment has incorporated a number of conservative assumptions which give confidence that its results are robust and fit for purpose. It has identified that there is the possibility of noise disturbance at some properties, dependent on wind speed and direction, and that it is necessary to impose planning conditions to require monitoring and mitigation measures to be implemented to reduce noise output to acceptable levels in those circumstances. I am satisfied that such reductions can be achieved at specified wind speeds and directions through turbine shutdown or by adjustment to the angle of the blades to reduce power output. Shadow flicker and blade glint 8.46 Similarly, due to the position of the wind farm and its proximity to a number of houses, there is the possibility of shadow flicker being experienced in some of the houses at those times when the sun is positioned behind a turbine, causing the moving shadows cast by the rotating blades to result in a flicker effect being experienced within those rooms where windows face the particular turbine. 8.47 The days of the year and times of day when this effect could be caused in individual houses can be calculated, and the applicant confirmed that sensors attached to a turbine can trigger shutdown to avoid this occurring. I find therefore that this matter can also be addressed by imposing a condition which would avoid nearby occupiers experiencing that potential source of nuisance. 8.48 The potential for nuisance to be caused by the sun’s reflection glinting off the rotating blades of the turbines can addressed by the use of a matt, rather than a gloss, finish. This can be secured through a planning condition. Health and safety issues 8.49 Risks of various types are inevitably associated with any form of development, not least with electricity generation. Here concerns have been raised about the health and safety of those who would be living near to the wind farm. However, the applicant has confirmed that the speed of rotation of the blades would not be at a rate that triggers epileptic fits; and that sensors can be fitted to ensure shutdown on the infrequent occasions when icing of the blades may occur and give rise to the potential for ice throw. 8.50 Public access is generally allowed to wind farm sites, and I am satisfied that the safety advice to staff undertaking maintenance is not directly applicable to members of the public visiting at other times. Other regulatory regimes deal with matters relating to structural integrity and fire risk, while a suggestion that there may be a health “syndrome” experienced by some living close to wind farms is uncorroborated and has not been subject to peer review. Records of accidents relating to all kinds of wind turbines elsewhere in the world do not demonstrate that this wind farm would be inherently unsafe. IEC_3_105_3 47 Transport 8.51 The proximity of this site to the harbour at Scrabster would enable the long and heavy loads associated with the construction of wind turbines to be delivered to the site with the minimum of inconvenience to other road users, as these short journeys would be made under police escort and during off-peak periods. Works at some junctions to allow clearance would be required, notably at Bridge of Isauld, but from the evidence I am satisfied that there is a reasonable prospect of this being achieved. There is no evidence that the proximity of Dounreay, and the requirement for contingency arrangements in the event of an emergency there, would preclude the local road network from being used for these deliveries. 8.52 While the sub-soil availability of stone on site is likely to avoid the need to import stone for construction purposes, I consider that the additional lorry journeys which could be required for that purpose can be accommodated on the local road network without undue congestion or disturbance. Other effects 8.53 I find no evidence that, subject to the imposition of appropriate conditions, the construction and operation of the proposed wind farm would have any other significant adverse effects. The development plan 8.54 The Caithness Local Plan defers to the structure plan’s provisions for assessing the merits of any wind farm application, by stating that the council will seek to support the development of renewable energy opportunities in suitable locations that accord with the structure plan and national planning policy guidance. In these circumstances I am satisfied that very little weight can attach to the terms of Primary Policies PP2 and PP3 which the proposals map of the local plan indicates apply to different parts of the site, and which apply support for development and a presumption against development respectively. These policies derive from the structure plan’s approach to housing development, and not from its provisions relating to renewable energy developments. 8.55 The key policy of the structure plan which is directly relevant to wind farm proposals is Policy E2, giving support to those which are not shown to be significantly detrimental, and stating that they are to be assessed against the plan’s general strategic policies, and in relation to visual impact; noise; electro-magnetic interference; roads, bridges and traffic; aircraft flight paths/MOD operations; and cumulative effects. 8.56 Based on my above assessment of these potential impacts, and on the consultation responses, and subject to the imposition of appropriate conditions, I find that the proposed development would not be significantly detrimental in these regards, or inconsistent with any of the additional criteria in relation to sustainability which are set out in General Policy G2. IEC_3_105_3 48 8.57 The impacts of this proposal have been assessed as required by General Policy G3, but while a number of significant adverse impacts have been identified, mitigation measures have either been incorporated into the scheme or would be imposed by planning conditions, or I have found these to acceptable. The expectation on developers to make community contributions, set out in General Policy G4, is not relevant to the determination of this application as they would not be necessary to enable the development to proceed or to address a particular impact. 8.58 In relation to General Policy G6 regarding the conservation and promotion of Highland heritage, I find that the impact of the development in relation to nature conservation, landscape and archaeology would not be so great as to be inconsistent with its aims. In addition, and again subject to the imposition of appropriate planning conditions, I find that there are no scientific grounds for believing that severe damage could be done to the environment or to the well-being of communities, such as to justify applying the precautionary principle as outlined in General Policy G8. 8.59 In relation to other provisions of the structure plan which may be relevant, Policy E1 gives general support to renewable energy developments, and planning conditions to limit the duration of the consent and provide for de-commissioning and site restoration would ensure that its other terms would also be satisfied. In addition the approach set out in Policies L4, T6, BC3 and N1 in relation to landscape character, scenic views, archaeological sites and nature conservation would not be contravened either. Government policy 8.60 The Scottish Government’s policies give strong and clear support to schemes such as this which would increase the amount of electricity which is generated from renewable sources. However that support is not over-riding. It is clear that proposed developments also require to be environmentally acceptable, and Scottish Planning Policy 6 and Planning Advice Note 45 set out advice on assessing particular impacts and highlight the importance which the government attaches to meeting its international obligations with regard to nature conservation. 8.61 As set out above at paragraphs 8.22 to 8.26, there is some ambiguity in the interpretation of the policy advice contained in the Annex to Scottish Planning Policy 6 as it relates to communities and whether individual houses in the countryside are to be afforded the same degree of protection as cities, towns and villages, and whether the identification of a significant long term detrimental impact automatically precludes consent being granted. Subject to that, and to the imposition of conditions to mitigate any potential impact on the local populations of the three birds species which are protected by the designation of the Caithness Lochs special protection area, I find that the Baillie wind farm would be supported by government policy. IEC_3_105_3 49 Highland Renewable Energy Strategy 8.62 The Highland Renewable Energy Strategy includes the application site within an area to which it suggests that a presumption against the development of wind farms should apply, although this does not preclude consent being granted if it can be shown that constraints can be addressed. As I have found above that the impacts of this proposal can be avoided or mitigated, I do not consider that this presumption should continue to apply. 8.63 This finding is re-inforced by the acceptance by the council that this nonstatutory guidance is not consistent with national policy set out in Scottish Planning Policy 6 and its confirmation that the strategy is to be replaced. Requirements under Schedule 9 of the Electricity Act 1989 8.64 I find that the applicant has had regard both to the desirability of preserving natural beauty, of conserving flora, fauna, geological and physiographical features of special interest and of protecting sites, buildings and objects of architectural, historic or archaeological interest; and also to do what can reasonably be done to mitigate the effects which the proposals would have on the natural beauty of the countryside or on any such flora, fauna, features, sites, buildings and objects. This has been demonstrated through the environmental impact assessment undertaken in relation to the original proposal; the subsequent modifications made to the proposal; the environmental impact assessment undertaken in relation to the revised proposal; the additional environmental information provided to the inquiry; and the preparation of conditions suggested for imposition on any planning permission which the Scottish Ministers may direct should be deemed to be granted. 8.65 While it is the duty of the Scottish Ministers to have regard to the extent to which the applicant has complied with the above duty, they themselves are also required to have regard to the desirability of preserving and conserving the same elements. In relation to the desirability of preserving natural beauty, the above findings have identified that the site of the proposed wind farm is not within any area designated for its qualities of scenic or natural beauty, such as a national scenic area; and that while it would have some significant adverse visual impacts, I have found these to be acceptable and the landscape to be capable of accommodating the wind farm. 8.66 In relation to the desirability of conserving flora, fauna, geological and physiographical features of special interest, the above findings have identified that the proposed wind farm would be likely to have significant environmental effects on the three bird species for which the Caithness Lochs special protection area has been designated. In these circumstances the Scottish Ministers would be required, under the terms of the habitats regulations and the EU Birds Directive, to undertake an “appropriate assessment” to ascertain that the development would not have an adverse effect on the integrity of the special protection area, having regard to its conservation objectives in relation to each of those species. 8.67 They would be required to consult Scottish Natural Heritage and have regard to its advice, which is referred to above. Based on all the evidence, I have found IEC_3_105_3 50 that, subject to the imposition of a condition to ensure monitoring and any mitigation shown to be necessary, such an adverse effect would not occur and, accordingly, that the effects on the natural heritage would be acceptable. Subject therefore to the Scottish Ministers undertaking their own appropriate assessment based on the evidence, I find that this duty under Schedule 9 would be satisfied. 8.68 In relation to the desirability of protecting sites, buildings and objects of architectural, historic or archaeological interest, the above findings have identified that the effects on the historic environment would not be significant, as I have found that the wind farm would have no direct effect on either of the scheduled ancient monuments at Hill of Shebster or Cnoc Freiceadain, or on what I have identified to be their setting; and the imposition of planning conditions in relation to the development site would ensure that any features of architectural interest are protected. 8.69 Schedule 9 also requires both the applicant and the Scottish Ministers to avoid, so far as possible, causing injury to fisheries or to the stock of fish in any waters. Subject to the prior approval of the construction method statement and to protection for watercourses in the event of micro-siting adjustments to the positions of the turbines being incorporated in conditions, damage to burns and their fish populations is unlikely to be significant. I therefore find that this requirement of Schedule 9 would also be met. Conditions 8.70 In the event that the Scottish Ministers decide not only to grant consent for the application under Section 36 of the Electricity Act, but also to direct that planning permission is deemed to be granted for the proposed development, I find that the conditions set out in Appendix One should be imposed. These derive originally from those suggested by the council and discussed with the parties at the inquiry, but account has also been taken of the changes to the duration of planning permissions brought into force on 3 August 2009 following the implementation of the Planning etc. (Scotland) Act 2006. Additional conditions are proposed to deal with other issues raised at the inquiry or in written submissions, including protection from ice throw and blade glint, and a potential need for aircraft navigation warning lights. I find that each condition would meet the six tests for planning conditions set out in The Scottish Office Development Department Circular No. 4/1998. Section 75 agreement 8.71 I find that the issuing of any direction that planning permission shall be deemed to be granted should not be made subject to the prior conclusion under Section 75 of the planning Act of any agreement between the applicant, landowner and the local planning authority, as matters concerning provision for restoration and off-site works can be addressed through imposing suspensive planning conditions. Similarly, a suspensive condition can address the requirement to protect the fabric of the public road network from the effects of construction traffic. IEC_3_105_3 51 8.72 The Scottish Ministers’ decision on the application should not be dependent on securing in advance, through a legal agreement, any payments for the benefit of the local community, as that is a matter entirely for the applicant. IEC_3_105_3 52 9. CONCLUSIONS AND RECOMMENDATIONS 9.1 Based on the evidence given to the inquiry, the environmental information contained in the original and revised environmental statements and that provided to the inquiry, the written submissions, the site inspections, and my findings of fact at Section 8 above, I consider that the determining issues in relation to the application for consent under Section 36 are: 1. Whether the obligations which Schedule 9 of the Act places on the both the applicant and the Scottish Ministers have been met; and if so, 2. Whether the other material considerations indicate that consent under Section 36 should be granted or not. 9.2 With regard to the first determining issue, for the reasons set out in my findings at paragraphs 8.64 to 8.69, I conclude that these obligations have been met. I therefore turn to the second determining issue. 9.3 As the wind farm application seeks approval for a form of development, the relevant provisions of the development plan are an important material consideration in relation to the Section 36 consent. Here, the development plan comprises the Highland Structure Plan and the Caithness Local Plan, and their relevant provisions are set out above at paragraphs 2.5 and 2.6. For the reasons set out in my findings at paragraphs 8.54 to 8.59, I conclude that the proposed development would be consistent with the relevant provisions of the development plan. 9.4 Relevant government policy is also a material consideration, and the key elements are summarised at paragraphs 2.7 to 2.17 above. For the reasons set out in my findings at paragraphs 8.60 and 8.61, I conclude that the development of this wind farm would be supported by government policy. 9.5 In relation to Highland Council’s Highland Renewable Energy Strategy, the key provisions of which are summarised at paragraph 2.18, for the reasons set out in my findings at paragraph 8.62, I conclude that the presumption against development of wind farms, which the strategy indicates in relation to the application site, should not apply. For the reasons given at paragraph 8.63, I consider that little weight can be attached to the non-statutory guidance contained in this strategy particularly where, as in this case, the proposal is found to be in accordance with the relevant provisions of the development plan and consistent with government policy. 9.6 With regard to other material considerations, my consideration of the proposal’s landscape and visual effects and its effects on tourism, ornithology and the scheduled ancient monuments are set out at paragraphs 8.14 to 8.42, and my findings in relation to the impact on the amenity of local people arising from noise, shadow flicker, blade glint, health and safety issues and transport are set out at paragraphs 8.43 to 8.52. Where relevant, I have incorporated these findings in my assessment of the proposal in relation to the relevant provisions of the development plan. Subject to appropriate conditions being imposed, I conclude that none of these effects, either alone or in conjunction with others, would justify refusal to grant consent. IEC_3_105_3 53 9.7 As confirmed at paragraph 8.53, I have found no evidence that would lead me to conclude that any other significant effects would arise from the construction and operation of the proposed wind farm. 9.8 For the reasons set out in my findings at paragraphs 8.9 to 8.12, I conclude that the need for and benefits of the proposal are both significant, and are material considerations which support the granting of consent. However, for the reasons set out at paragraph 8.13, any payments by the applicant into a community fund cannot be required through the imposition of a planning condition or prior inclusion in a Section 75 agreement, and no weight should be attached to any such payments. 9.9 I have found no other material considerations which would indicate that consent under Section 36 should be refused. 9.10 Drawing these matters together, my conclusions in relation to the determination of the application for consent under Section 36 are: 1. That the obligations which Schedule 9 of the Act places on both the applicant and the Scottish Ministers would be met; 2. That the proposed development would be in accordance with the relevant provisions of the development plan; 3. That the development would be supported by government policy; 4. That, subject to appropriate conditions being imposed, none of the effects of the proposal would justify refusal to grant consent; 5. That any payments by the applicant into a community fund cannot be required through the imposition of a planning condition or prior inclusion in a Section 75 agreement, and no weight should be attached to any such payments; and, 6. That there are no other material considerations which would still justify refusing to grant consent under Section 36, subject to the Scottish Ministers confirming in their decision that they have taken account of the environmental information submitted. 9.11 In the event that the Scottish Ministers decide to grant consent under Section 36, they may also direct that planning permission shall be deemed to be granted, and may specify the conditions to which the permission is subject. This is a separate determination, to which the obligations set out in Schedule 9 of the Electricity Act 1989 do not apply. While there does not appear to be a statutory duty to apply the approach prescribed by Section 25 of the Town and Country Planning (Scotland) Act 1997 to this determination, it appears to me to be both prudent and reasonable to do so. 9.12 Accordingly, again based on the evidence given to the inquiry, the environmental information contained in the original and revised environmental statements and that provided to the inquiry, the written submissions, the site inspections, and my findings of fact at Section 8 above, I consider that the determining issues in relation to the Scottish Ministers’ decision on whether to direct that planning permission shall be deemed to be granted are: 1. Whether the proposed development would be in accordance with the relevant provisions of the development plan; and, IEC_3_105_3 54 2. Whether the other material considerations indicate that planning permission should be deemed to be granted, or not. 9.13 My conclusions above (at paragraphs 9.3 to 9.9) on these matters, in respect of the Section 36 application, apply equally here in relation to the deemed planning permission. Accordingly, my conclusions in relation to the determining issues are: 1. That the proposed development would be in accordance with the relevant provisions of the development plan; 2. That the development would be supported by government policy; 3. That, subject to appropriate conditions being imposed, none of the effects of the proposal would justify not directing that planning permission shall be deemed to be granted; 4. That, although no weight should be attached to any payments by the applicant into a community fund, the need for and benefits of the proposal are both significant, and are material considerations which support a direction that planning permission is deemed to be granted; and, 5. That there are no other material considerations which would still justify not directing that planning permission shall be deemed to be granted. 9.14 With regard to the conditions to which any deemed planning permission should be subject, for the reasons set out in my findings at paragraph 8.70, I conclude that the conditions set out in Appendix 1 should be imposed. 9.15 For the reasons given in paragraphs 8.71 and 8.72, I conclude that the Scottish Ministers’ direction that planning permission is deemed to be granted should not be made subject to the prior conclusion of an agreement under Section 75 of the Town and Country Planning (Scotland) Act 1997, or any other legal agreement. Recommendations 9.16 I recommend that the Scottish Ministers should grant consent for the application under Section 36 of the Electricity Act 1989, and I also recommend that they should direct that planning permission for the proposed development shall be deemed to be granted, subject to the conditions set out in Appendix One. DAVID A. RUSSELL Principal Inquiry Reporter August 2009 IEC_3_105_3 55 APPENDIX ONE: PLANNING CONDITIONS 1. The planning permission hereby deemed to be granted lapses at the end of a three year period beginning on the date of this consent, unless the development to which the permission relates has begun. Reason: To limit the duration of the deemed planning permission, as required by Section 58 of the Town and Country Planning (Scotland) Act 1997, as amended. 2. This permission shall endure for a period of 25 years from the date of final commissioning of the development. That date is to be notified in writing to the planning authority within three months of final commissioning. At the end of this period, unless the express approval in writing of the planning authority is given, all wind turbines, buildings and ancillary equipment, shall be dismantled and removed from the site, and the ground fully re-instated in accordance with the approved scheme referred to in condition No. 6 below. Reason: In order to clarify the terms of this permission and to ensure restoration of the site. 3. Except as otherwise provided for and amended by the terms of this consent, the development shall be constructed and operated in accordance with the provisions of the Section 36 application, the amended plan submitted, and the Environmental Statement (as revised by the Addendum and Supplementary Information to the Environmental Statement). This permission shall be for a maximum of 21 turbines, 2 anemometer masts and 1 substation and control building, to be sited as shown on the amended section 36 application plan showing the amended overall wind farm (Application Boundary and Proposed Site Layout (rev u), figure number 1.2). The access track leading to turbines 4 and 10 will be amended as shown on the revised plan forming part of the Second Addendum (Application Boundary and Revised Layout (rev x, figure 1.2) as agreed with the Scottish Environmental Protection Agency. The prior written approval of the planning authority in consultation with Scottish Natural Heritage and the Scottish Environment Protection Agency shall be required for the proposed micro-siting of any wind turbine or access track more than 25 metres in any direction from the approved location. For the avoidance of doubt, no turbine shall be located closer to a non-stakeholder property than the minimum distance between any turbines and that property as detailed in the Addendum to the Environmental Statement dated 2006, and no turbines shall be located within 20 metres of a water body. Other than at watercourse crossings, there shall be no construction works within: 10 metres of a headwater stream less than two metres wide; 20 metres of a stream or water body wider than two metres; and 50 metres of any watercourse in areas of peat. Any such micro-siting submission by the developer shall include a revised site layout for the location of all turbines and access roads. Reason: In order to clarify the terms of this permission and to ensure restoration of the site; and to protect local residents and the water environment. 4. Prior to development starting, the final specification of the wind turbine details shall be submitted for the prior approval in writing of the planning authority, including the make, model, design, power rating and warranted sound power levels; the IEC_3_105_3 56 colour and matt paint finish; and the mechanism to avoid potential ice throw. The developer's noise assessment shall be updated as necessary to reflect the turbine specification chosen, and shall be submitted to the planning authority prior to the commencement of development. In the event of predicted exceedance of ETSU-R97 levels or as otherwise agreed, the developer shall submit mitigation measures to the planning authority for their prior written approval in advance of the commencement of development. Reason: In order to clarify the terms of the permission and retain effective control over the development; to avoid nuisance to nearby residents arising from noise or blade glint; and to avoid the possibility of ice throw. 5. Prior to development starting, details, including means of access, fencing, design, materials and colours/external finishes and construction, of all ancillary elements to the development, including in particular details relating to the substation and control building, shall be submitted to and be approved in writing by the planning authority. Reason: In order to ensure a high standard of design in the interest of visual amenity. 6. Before the development starts, an indicative scheme for the ultimate reinstatement of the site, including the removal of all wind turbines and ground reinstatement, shall be submitted to and be approved in writing by the planning authority in consultation with Scottish Natural Heritage and the Scottish Environment Protection Agency. The scheme shall be reviewed and amended as necessary, and the amended scheme shall be approved in writing by the planning authority, at least 12 months prior to actual de-commissioning and re-instatement works. No work shall commence on the site until the developer has provided documentary evidence that a bond or other financial provision to cover all decommissioning and site restoration costs is in place and written confirmation has been given by the planning authority that the proposed bond or other financial provision is satisfactory. The developer shall ensure that the approved bond or other financial provision is maintained throughout the duration of this consent. The bond or other financial provision will be subject to a five yearly review from the commencement of the development, to be conducted by a competent independent professional who has relevant experience within the wind energy sector and provided to the applicant, operator, landowners, and the planning authority. Reason: To ensure that the restoration of the site is achieved after decommissioning. 7. Prior to development starting, a construction method statement shall be submitted to and be approved in writing by the planning authority in consultation with Scottish Natural Heritage and the Scottish Environment Protection Agency. The statement shall detail contractor arrangements for the following: (i) The appointment, at the expense of the developer, of a suitably qualified ecologist to supervise construction activities. (ii) Detailed justification for any culverting elements and design of any such culverting. (iii) Measures to prevent entry of cement or any other pollutant materials to watercourses. IEC_3_105_3 57 (iv) The source of all fill and bulk materials. (v) Identification of waste streams arising from the works, such as peat, spoil and other excavated material, and the means of dealing with these. (vi) Excavation and make-up of internal access tracks and hardstanding, including measures to address silt-laden run-off from temporary and permanent access tracks, soil storage and other engineering operations. (vii) Construction arrangements for turbine foundations including concrete batching and de-watering arrangements to treat potentially sediment-laden water. (viii) Cable laying within the site. (ix) Construction management operations including site lighting, temporary servicing for workers, vehicle storage and other storage arrangements. (x) Associated vehicle movements and routeing for different phases of construction. (xi) Proposals for phasing of operations, including the provision of information on the construction timetable which takes into account the implications of times of the year when high rainfall is more likely. (xii) The detailed siting and design of the construction works compound together with associated concrete batching areas including a strategy for their eventual removal and satisfactory re-instatement. (xiii) Re-instatement of ground post-construction, including re-vegetation of access track edges and hardstanding areas, together with monitoring and maintenance arrangements. (xiv) Arrangements for fuel storage and fuelling, the storage and handling of oils and lubricants, and the handling of cement materials all to prevent any entry to watercourses with contingency plans in the event of spillage. (xv) Measures to prevent erosion, sedimentation or discolouration of watercourses, together with monitoring proposals and contingency plans. (xvi) Measures to monitor pre- and post-construction surface water run-off and, where necessary, further mitigation measures to be implemented to manage surface water flow. (xvii) Surface water drainage arrangements, to comply with "Sustainable Urban Drainage Systems” (SUDS) principles, including provision of calculations of pre- and post-development run-off to equivalent of predevelopment run-off, and sensitivity testing of the effect of large return period rainfall events. (xviii) Provision of welfare facilities on site during construction and the means of disposal of sewage effluent. (xix) Mechanisms to ensure that sub-contractors and all other parties on the site are managed and aware of issues and provisions relating to pollution, including emergency procedures. (xx) Contingency measures for periods of unexpected bad weather. (xxi) Avoiding excavation close to watercourses where possible, especially in wet weather. (xxii) Avoiding construction activity near watercourses suitable for spawning/juvenile fish habitat in sensitive periods. (xxiii) Measures for monitoring fisheries during construction. (xxiv) Measures including the installation of box culverts, rams and covers over excavations to minimise potential impacts on otters. IEC_3_105_3 58 Reason: In order to ensure satisfactory construction arrangements and any necessary mitigation. 8. Prior to development starting, an ornithological impact monitoring scheme shall be submitted to and be approved in writing by the planning authority, in consultation with Scottish Natural Heritage. The scheme shall deal with the three bird species for which the Caithness Lochs special protection area has been designated, and shall provide for bird flights through the wind farm site, and feeding activity in proximity to the wind farm, to be monitored together with any adverse effect on the integrity of the local populations of these species arising from collision or disturbance. The approved scheme shall incorporate measures to ensure turbine shutdown to mitigate the impact of the wind farm on these bird populations where necessary, such measures and periods of shutdown to reflect the cause, level and nature of the impacts identified, and to ensure that the integrity of the special protection area is maintained. Reason: To ensure that the wind farm will not have an adverse effect on the integrity of the Caithness Lochs special protection area. 9. Prior to development starting, arrangements for an archaeological watching brief to cover site clearance and excavation works shall be submitted to and be approved in writing by the planning authority. All site clearance or excavation works shall be implemented in accordance with the approved arrangements. Reason: In order to protect any features of archaeological importance. 10. Prior to the development starting, the following sites of archaeological or historical interest shall be identified and physically marked out on the ground for the duration of the construction works: (a) The sheepfold (ND06NW0100); (b) The enclosure (ND06NW0099); (c) The two cairns and sheepdip on Stemster Hill (ND06NW0037). Reason: In order to protect known features of archaeological importance and to avoid accidental damage. 11. Unless otherwise agreed by the planning authority, the wind farm shall be wholly constructed and commissioned within one construction period in accordance with this approval. Reason: To minimise the period of disturbance to local residents and to avoid prolonged uncertainty. 12. Access to the site by heavy goods vehicles shall be restricted to 07:00 to 19:00 hours on Mondays to Fridays and from 07:00 to 12:00 on Saturdays with no such access/egress on Sundays or Bank Holidays (except for the delivery of abnormal loads under escort). Unless agreed in writing by the planning authority in advance, any construction activity involving audible noise at any nearby house shall also be subject to the foregoing hours restrictions. Reason: In order to minimise noise and disturbance during construction. 13. The development shall be carried out in accordance with a road safety and traffic management plan to be submitted to and agreed in writing by the roads authority prior to the development starting. This plan shall cover: IEC_3_105_3 59 Allowing traffic to pass on at least 3 occasions during the transportation of abnormal loads; Utilising optimal size abnormal load convoys to reduce incidences of delay; Appropriate route and signage for contractors and public safety; Co-ordination of abnormal loads with Network Rail and rail operators, if appropriate; Appropriate contingency plans in the event of breakdown; The avoidance of potential combined effects with other wind farm construction traffic; Details of a liaison group which shall inform and consult local residents regarding traffic movements; and A scheme of monitoring and repair, to ensure that any adverse impact of construction on the fabric of the public road network is rectified. Reason: In order to minimise the impact of construction of the development on the public road network and its users. 14. Prior to the development starting, a scheme of mitigation for shadow flicker shall be submitted to and be approved in writing by the planning authority, based on a detailed assessment of the impact of each turbine on nearby houses. The approved scheme shall be implemented prior to the commissioning of the wind farm. Reason: To protect the occupiers of nearby houses from the effects of shadow flicker. 15. Prior to the commencement of development, the developer shall submit to the planning authority for approval a TV & radio reception mitigation plan. The plan shall provide for a baseline TV reception survey, to be carried out prior to commencement of turbine installation, the results of which shall be submitted to the planning authority. Within 12 months of the commissioning of the development, any claim by any individual person regarding TV picture loss or interference at their house, business premises or other building, shall be investigated by a qualified engineer and the results submitted to the planning authority. Should any impairment to the TV signal be attributable to the wind farm, the developer shall remedy such impairment so that the standard of reception at the affected property is equivalent to the baseline TV reception. Reason: To ensure that any effect on TV or radio reception is rectified. 16. Before the development commences, an archaeological mitigation scheme shall be submitted to and be approved by the planning authority, in consultation with Historic Scotland. The scheme shall include measures to improve public access to the Hill of Shebster and Cnoc Freiceadain scheduled ancient monuments; and for improved interpretation of the cairns, incorporating the results of a LIDAR laser scanning survey to be undertaken on behalf of the applicant in consultation with Historic Scotland. Reason: To secure improved access to and interpretation of the scheduled ancient monuments, in mitigation of the visual impact of the wind farm on visitors. 17. Prior to development starting, the applicant shall provide the Ministry of Defence (Defence Estates – Safeguarding) and the Civil Aviation Authority with the following information, a copy to be submitted to the planning authority: Proposed date of commencement of construction; IEC_3_105_3 60 Estimated date of completion of construction; Precise location and height above ground level of the tallest structure; Maximum extension in height of any construction equipment; Position of the turbines in latitude and longitude plus eastings and northings. Reason: In order to ensure aviation safety. 18. Within one month of the commissioning of the final turbine, the applicant shall provide the Civil Aviation Authority and Ministry of Defence (Defence Estates – Safeguarding) with written confirmation of the date of completion of construction, the height above ground level of the tallest structure and the latitude and longitude of that structure, with a copy to be submitted to the planning authority. Reason: In order to ensure aviation safety. 19. Details of any proposal to install aircraft navigation warning lights on any turbine shall be submitted to and be approved in writing by the planning authority prior to installation. Reason: In the interests of aviation safety and visual amenity. 20. The wind farm operator shall log wind speed and wind direction data continually and shall retain the data which has been obtained for a period of no less than 12 months. The data shall include the average wind speed in metres per second for each 10 minute period. The measuring periods shall be set to commence on the hour or in 10 minute increments thereafter. The wind speed data shall be made available to the planning authority on request on a Microsoft Excel spreadsheet in electronic format. Where the wind speed is measured at a height other than 10 metres, the data shall be supplemented by adjusted values which allow for wind shear, normalised to 10 metre height. Details of the wind shear calculation shall be provided. At wind speeds not exceeding 12 metres per second, as measured or calculated at a height of 10 metres above ground level (at the location of the meteorological mast shown at location easting 302610 northing 965639 on the approved layout plan) the wind turbine noise level at any house or other Noise Sensitive Premises shall not exceed:(a) During night hours, 43 dB LA90,10min, or the night hours LA90,10min background noise level plus 5 dB(A), whichever is the greater; (b) During quiet waking hours, 35 dB LA90,10min or the quiet waking hours LA90,10min background noise level plus 5 dB(A), whichever is the greater; and (c) At all times 45 dB, LA90,10min or the (day/night as appropriate) hours LA90,10min background noise level plus 5 dB(A), whichever is the higher in respect of any house where the occupier is a stakeholder in the development; providing that this condition shall only apply to dwellings or other noise sensitive premises lawfully existing at the date of this planning permission. At the request of the planning authority and following a valid complaint to the planning authority relating to noise emissions from the wind turbines, the wind farm operator shall measure or calculate, at its own expense, the level of noise emissions from the wind turbines. The measurement and calculation of noise levels shall be undertaken in accordance with "The Assessment and Rating of Noise from Wind IEC_3_105_3 61 Farms", September 1996, ETSU report number ETSU-R-97 having regard to paragraphs 1-3 and 5-11 inclusive, of The Schedule, pages 95 to 97; and Supplementary Guidance Notes to the Planning Obligation, pages 99 to 109; and calculations of noise made using the approach reported in the environmental statement submitted with the planning application. The assessment approach shall be approved by the planning authority prior to undertaking the detailed assessment. In comparing measured wind turbine noise levels with background noise levels, regard shall be had to the prevailing background noise levels as measured at specified properties and shown by the best fit curves in the environmental statement submitted with this Section 36 application. In the event of a complaint from a property other than one of the specified properties in the environmental statement, the measured wind turbine noise levels at that other property shall be compared to the prevailing background noise levels at the specified property which is most likely to have similar background noise levels. "Wind turbine noise level" means the rated noise level due to the combined effect of all the wind turbines, excluding existing background noise level but including any tonal penalty incurred under the methodology described in ETSU-R-97, pages 99 – 109. "Background noise level" means the ambient noise level already present within the environment (in the absence of noise generated by the development) as measured and correlated with wind speeds. "Wind speeds" means wind speeds measured or calculated at a height of 10 metres above ground level on the site at a specified Ordnance Survey grid reference agreed with the planning authority. "Night hours" means 23:00 – 07:00 hours on all days. "Quiet waking hours" means 18:00 – 23:00 hours on all days, plus 07:00 – 18:00 on Sundays and 13:00 – 18:00 hours on Saturdays. "Noise sensitive premises" means existing premises, the occupants of which could be exposed to noise from the wind farm. Should the noise levels be exceeded, the wind farm operator shall take immediate steps to ensure that noise emissions from the wind farm are reduced to the aforementioned noise levels or less, and obtain written confirmation of that reduction from the planning authority. Reason: In order to control noise in the interest of residential amenity. 21. In the event that any wind turbine fails to produce electricity supplied to a local grid for a continuous period of 12 months (not due to it being under repair or awaiting replacement), then it shall be deemed to have ceased to be required and, unless otherwise agreed in writing by the planning authority (whose consent shall not be unreasonably withheld), that wind turbine and its ancillary equipment shall be dismantled and removed from the site within the following six months and the ground fully re-instated to a specification agreed in writing by the planning authority. Reason: In order to protect visual amenity.. IEC_3_105_3 62 APPENDIX TWO: APPEARANCES For Baillie Windfarm Ltd, Colin Innes, Solicitor, of Shepherd & Wedderburn appeared. He called: Steven Pottinger, of Baillie Windfarm Ltd Alex Schlicke, of Geddes Consulting Darran Humpheson, of RPS Planning and Development Ltd Simon Zisman, of RPS David Bell, of Jones Lang LaSalle John Barber, of AOC Archaeology Group For Highland Council and the Caithness West Action Group, John Campbell, QC, appeared. He called: Cllr David Bremner, Member of Highland Council Mark Steele, of Mark Steele Consultants Dick Bowdler, of New Acoustics Stan Laybourne, resident of Halkirk Ian Kelly, of Graham & Sibbald David Craig, of the Caithness West Action Group Alasdair McDonald, of the Caithness West Action Group For Historic Scotland, Colin Boyd, QC, of Dundas & Wilson, Solicitors appeared. He called: Adele Shaw, of Historic Scotland John Raven, of Historic Scotland Other inquiry participants: Stuart Young, self-employed construction consultant Russell Hayley, resident of Reay William Brown, Convenor of the Caithness West Community Council John Webster, resident of Buldoo Celia McDougall, resident of Shebster IEC_3_105_3 63 APPENDIX THREE: DOCUMENTS (Note : Document numbers not listed where that document was not referred to in evidence to the inquiry.) CORE DOCUMENTS : Proposal CD 1 CD 2 CD 3 CD 4 CD 5 Planning CD 6 CD 7 CD 8 CD 9 CD 10 CD 11 CD 12 CD 13 CD 14 CD 15 CD 16 CD 17 CD 18 CD 19 CD 20 CD 21 CD 22 IEC_3_105_3 Application Letter Baillie Windfarm Environmental Statement comprising: Baillie Windfarm Environmental Statement comprising: A(i) - Original Environmental Statement, July 2004 A(ii) – Non-Technical Summary, July 2004 A(iii) - Technical Appendices, July 2004 B(i)– Addendum, January 2006 B(ii) – ES Addendum, Non-Technical Summary, January 2006 C(i) – Second Addendum covering letter, dated 17 October 2007 enclosing Peat Slide Non–Technical Summary and Revised Site Layout C(ii) – Peatslide Hazard and Risk Assessment Factual Report, October 2007 C(iii) - Peatslide Hazard and Risk Assessment Interpretive Report, October 2007 Consultation Responses in relation to original ES and Addendums Objections in relation to original ES and Addendums Report to Highland Council Planning Committee dated 22 November 2007 The Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2000 The Conservation (Natural Habitats, &c.) Regulations 1994 (as amended) Highland Council Structure Plan (2001) Caithness Local Plan (2002) Highland Renewable Energy Strategy and Planning Guidelines (HRES) (May, 2006) National Planning Framework for Scotland, 2004 National Planning Framework (Discussion Draft), January 2008 Draft revised National Planning Framework, January 2008 (2) National Planning Framework (December 2008, as laid before Parliament) National Planning Policy Guidance 14 – Natural Heritage SPP – Scottish Planning Policy November 2008, Parts 1 and 2 SPP 2 – Economic Development SPP 6 – Renewable Energy SPP 15 – Planning for Rural Development SPP 23 Planning and the Historic Environment Scottish Historic Environment Policy (October, 2008) Planning Advice Note 42 – Archaeology and The Planning Process 64 CD 23 CD 24 CD 25 CD 26 CD 27 CD 28 CD 29 CD 30 CD 31 CD 32 CD 33 CD 34 Tourism CD 35 PAN 45 – Renewable Energy Technologies and all Annexes PAN 56 – Planning and Noise PAN 58 – Environmental Impact Assessment PAN 60 – Planning and Natural Heritage Circular 10/1999 – Planning and Noise Town and Country Planning (Inquiries Procedure) (Scotland) Rules 1997 Circular 17/1985: Development Control Priorities and Procedures Circular 4/1998: The Use of Conditions in Planning Permissions Circular 6/1990: Awards of Expenses in Appeals and Other Planning Proceedings Circular 17/1998: Code of Practice For Public Inquiries Circular 12/1996: Planning Agreements Circular 6/2000: Nature Conservation: Implementation in Scotland of EC Directives on the Conservation of Natural Habitats and of Wild Flora and Fauna and the Conservation of Wild Birds ( The Habitats and Birds Directives ) The Economic Impacts of Wind Farms on Tourism in Scotland – A Report for Glasgow Caledonian University, March 2008 (The Moffat Report) Landscape CD 36 Caithness and Sutherland Landscape Character Assessment CD 37 Guidelines for Landscape and Visual Impact Assessment, 2nd Edition 2002. CD 38 SNH Guidance: Cumulative Effect of Windfarms (Version 2 revised 13.04.05) CD 39 SNH Guidance: Visual Assessment of Windfarms Good Practice Guidance, 29 March 2006. CD 40 SNH Guidance: Visual Assessment of Windfarms – Best Practice – 2002 (Report F01AA303A) University of Newcastle. CD 41 SNH Policy Statement 02/02: Strategic Locational Guidance for Onshore Wind Farms in respect of the Natural Heritage , (Update May 2005) CD 42 Countryside Agency Topic Paper 6: Techniques for Judging Capacity and Sensitivity Noise CD 43 Guidelines for Community Noise, World Health Organisation Noise (2000) CD 44 BS 8233:1997 Sound Insulation and Noise Reduction for Buildings, Code of Practice. BSI CD 45 BS 4142:1997 Method for – Rating industrial noise affecting mixed residential and industrial areas. BSI CD 46 BS 5228 parts 1 to 5 – Noise and Vibration Control on Construction and Open Sites. 1994 1997 CD 47 ISO 9613 1 Attenuation of Sound During Propagation Outdoors Part 1 CD 48 ISO 9613 2 Attenuation of Sound During Propagation Outdoors Part 2 IEC_3_105_3 65 DOCUMENTS FOR BAILLIE WINDFARM LTD: Community Engagement on Behalf of Baillie Windfarm Limited – Consultation Report –Executive Summary; January 2007 BWL 2 Community Engagement on Behalf of Baillie Windfarm Limited – Consultation Report – Final Report; January 2007 BWL 3 CWIF papers A Caithness Wind Farm Information Forum: Objections BWL 4 Newspaper articles: STUART YOUNG: A (i) Press & Journal November 21 2007: Stuart Young admits error in photomontage on CWIF website, agrees image cropped and 88ft too high. A (ii) Caithness Courier November 21, 2007: Stuart Young admits error in photomontage on CWIF website, agrees image cropped and 88ft too high. BILL BROWN: B (ii) John O'Groat Journal August 20, 2004: Letter expressing "contempt" for local windfarm developers. B (iii) John O'Groat Journal January 25, 2008: Editor prints apology following "slanderous" comment by Community Council Chairman (Bill Brown)- "developer…has been going round lobbying and offering people money if they support his scheme". DAVID BREMNER: C (iii) Letter dated 3 October 2007 from Cllr David Bremner, Highland Council, to Michael Russell MSP, regarding the withdrawal of SNH's objection to the application, expressing the concern of constituents that SNH was under "pressure" from the Scottish Government. BWL 5 OS Maps of Caithness: A OS Landranger Map: 10 "Strath Naver, Bettyhill & Tongue" B OS Landranger Map: 11 "Thurso & Dunbeath" C OS Landranger Map: 12 "Thurso & Wick, John O'Groats" Renewable Energy BWL 10 Proposal for a Directive of the European Parliament and of the Council on the promotion of use of Energy from Renewable Sources, Commission of the European Communities (January 2008) BWL 11 The EU’s Target for Renewable Energy: 20% by 2020, Volume 1 Report, 27th Report of Session 2007-08, European Union Committee, House of Lords (HL paper 175-I) BWL 12 Draft Framework for the Development and Deployment of Renewables in Scotland, 'Making Scotland and Leader in Green Energy', Forum for Renewable Energy Development, The Scottish Government (2008) BWL 13 Renewable Energy Policy Paper, prepared for Baillie Wind Farm Limited, Jones Lang LaSalle (February 2009) Planning BWL 14 Baillie Wind Farm, Access Enhancement Report, Jones Lang LaSalle (2009) BWL 1 IEC_3_105_3 66 BWL 15 Letter from Baillie Windfarm Limited to Highland Council submitting docs BWL 16, 17 and 41 BWL 16 Baillie Windfarm Limited, "Highland Renewable Energy Strategy and Planning Guidelines: Meeting the Policies", 29 September 2006 BWL 17 Baillie Windfarm Limited, "Demonstration of Compliance with HRES Constraint Features", 29 September 2006 BWL 18 Baillie Windfarm Limited document entitled, "Notes on Highland Renewable Energy Strategy" BWL 19 Letter from Baillie Windfarm Limited to Highland Council, dated 12 January 2006 BWL 20 Baillie Windfarm and Spittal Hill Windfarm Representations to the Highland Council Renewable Energy Strategy, 13 January 2006 Archaeology BWL 23 Wind Energy and the Historic Environment (English Heritage Guidance, 2005) BWL 24 Cultural Heritage Wireframes and Photomontages F Viewpoint-Cnoc Freiceadain (View East)(showing turbines 121) G Viewpoint-Cnoc Freiceadain (View West) BWL 26 AOC Archaeology Group, 2009. Baillie Wind Farm: Impacts on Cultural Heritage. Report BWL 28 Ancient Monuments and Archaeological Areas Act 1979. (c.46). London. BWL 29 Burra Charter 1999 [Online] ICOMOS Australia. Available at: http://www.icomos.org/australia/burra.html [Accessed 19/12/2008] BWL 30 Guidelines to the Burra Charter: cultural significance. 1988. [Online]. ICOMOS Australia. Available at: http://www.marquiskyle.com.au/bcsignificance.html [Accessed 19/12/2008] BWL 31 Convention Concerning the Protection of the World Cultural and Natural Heritage (World Heritage Convention) 1972 [Online] UNESCO. Available at: http://whc.unesco.org/en/conventiontext/ [Last accessed 20/01/2009]. BWL 33 Planning Guidelines. 2006. [Online] The Department of the Environment, Heritage & Local Government, Ireland. Available at: http://www.environ.ie/en/Publications/DevelopmentandHousing/Planning/F ileDownLoad,1633,en.pdf [Last accessed: 21/01/2009] BWL 36 Davidson, J. L. & Henshall, A. S., 1991. The Chambered Cairns of Caithness. Edinburgh: Edinburgh University Press. BWL 38 Corns, A., Fenwick, J. & Shaw, R., 2008. More than meets the eye. Archaeology Ireland, Vol 22, 3 (85) pp. 34-38. BWL 39 Archaeology Ireland. 2008. Tara, Co. Meath, A guide to the ceremonial complex. Heritage Guide No. 41. Landscape BWL 40 Cumulative Impact Assessment (January 2009) Geddes Consulting BWL 41 Residential Receptor Assessment (January 2009) Geddes Consulting BWL 42 Assessment of Visual Amenity from Houses, 29 September 2006 BWL 43 Review of Guidance on the Assessment of Cumulative Impacts of Onshore Windfarms – Phase 1 Report’ September 2008, Entec, Report for DBERR BWL 44 SNH letter, Response to THC on South Shebster Windfarm, 16 March 2006 BWL 45 SNH Policy Statement 01/02: Renewable Energy IEC_3_105_3 67 BWL 46 BWL 47 BWL 48 BWL 49 Noise BWL 60 SNH Commissioned Report No. 070: Study into Landscape Potential for Wind Turbine Development in East and North Highland and Moray (ROAME No. F02AA302) SNH Commissioned Report No. 087: Landscape strategy and assessment guidance for wind energy development within Caithness and Sutherland (Contract no. 1995–NW27) Report to the Highland Council by Aquatera Ltd: Strategic Renewable Energy Resource Assessment for the Highland Area Ornithology RPS Collision Risk Modelling Data 2008 The Assessment and Rating of Noise from Windfarms, DTI Working Group on Noise from Wind Turbines: ETSU-R-97, 1996 Tourism, Recreation and the Economy BWL 61 Scottish Government Press Release on Wind farms and Tourism 12 March 2008 BWL 62 "The Impact of wind farms on the Tourist Industry in the UK", prepared by BWEA for the All-Party Parliamentary Group on Tourism (May 2006) Planning & Other Appeal Decisions BWL 67 Drumderg Windfarm Appeal decision letter and expenses letter awarding expenses against Perth and Kinross Council, 25 September 2006 BWL 68 Clyde Windfarm, South Lanarkshire (2006) (IEC/3/90). Report Available at: http://www.scotland.gov.uk/Resource/Doc/917/0063580.pdf [Last accessed 19/01/2009] BWL 69 St John's Hill Windfarm Appeal decision letter, 26 November 2007 (P/PPA/110/634) BWL 70 Langhope Rig Windfarm Appeal decision letter, 13 May 2008 (P/PPA/140/337) BWL 71 Drone Hill Windfarm Appeal decision letter, 26 November 2008 (P/PPA/140/357) BWL 72 Toddleburn Windfarm Decision letter, dated 11 January 2007 (P/PPA/140/262) BWL 73 Ardrossan Extension Decision BWL 74 Historic Scotland's response to Ardrossan Extension Additional Documents BWL 78 SNH, Survey Methods for Use in Assessing the Impacts of Onshore Windfarms on Bird Communities, November 2005. BWL 79 Context Photographs 1. View from Shebster Cairn to the East. 2. View from Shebster Cairn to Cnoc Freiceadain. 3. View from Cnoc Freiceadain northwest to Dounreay. 4. Cnoc Freiceadain Display Board. 5. View looking at the east end of Na Tri Sithan. 6. View from Cnoc Freiceadain looking northeast. 7. View from Cnoc Freiceadain to the south. 8. View from Na Tri Sithan to the east. 9. View of Na Tri Sithan from the southwest. BWL 80 Duff House Decision, dated 25 June 2007 (P/NID/96/G/59) IEC_3_105_3 68 BWL 83 Letter from Historic Scotland to Dumfries and Galloway Council relating to Application 07/p/4/0364 BWL 85 RPS Letter to SNH dated 18 June 2007 BWL 86 Noise Document comprising – noise emission data for Nordex N80, wind shear analysis, ground effect sensitivity test, and wind rose data BWL 88 Letter from Historic Scotland to Ofgem, dated 20 December 2002 BWL 89 Schedule 9 Statement by SP Distribution Limited BWL 90 Ardrossan Extension Layout BWL 91 AO Visualisation VP 13 BWL 92 AO Visualisation VP 21 BWL 93 AO Visualisation VP 25 BWL 94 St John's Hill Wind Farm, Figure 3.1-Site Layout BWL 97 British Wind Energy Association (BWEA), ‘Low Frequency Noise and Wind Turbines’, BWEA website, available at: http://www.bwea.com/ref/lowfrequencynoise.html (created January 2005). Technical Annex: http://www.bwea.com/pdf/lfnannex.pdf(created February 2005) BWL 98 Department for Business, Enterprise and Regulatory Reform, 'Research into aerodynamic modulation of wind turbine noise', report by University of Salford, August 2007 http://www.berr.gov.uk/files/file40570.pdf BWL 99 Government Statement in relation to the above -July 2007 http://www.berr.gov.uk/files/file40571.pdf BWL 100 DTI 'The measurement of low frequency noise at three UK wind farms' 2006 (Hayes MacKenzie for DTI) http://www.berr.gov.uk/whatwedo/energy/sources/renewables/explained/wi nd/onshore-offshore/page31267.html BWL 101 Government advice on findings of Hayes MacKenzie Report http://www.berr.gov.uk/files/file35592.pdf BWL 102 Henshall, A.S. and Ritchie, J.N.G 2001. CH3 The land, the environment and the locations. In: The Chambered Cairns of the Central Highlands. Pp.29-35. Edinburgh: Edinburgh University Press p29-35 BWL 103 Wheatley D & Gillings M, 2002. Spatial Technology and Archaeology: The Archaeological Applications of GIS. London: Taylor & Francis. pp 201-216 + references BWL 104 The Highland Council Committee Report of 28 May 2008 http://www.highland.gov.uk/yourcouncil/committees/strategiccommittees/plann ingenvironm entanddevelopmentcommittee/2008-05-28-ped-min.htm BWL 105 Minute of The Highland Council Committee Meeting 28 May 2008 http://www.highland.gov.uk/NR/rdonlyres/B0C92282-6E5D-4012AE644160B375EF63/0/Item14Ped4008.pdf BWL 106 PPS 22 – Companion Guide -extract p171 BWL 107 Achany decision, dated 13 December 2007, PPA/270/438 BWL 108 Windshield Performance Test Report, Supplementary Information – Darran Humpheson BWL 109 Bill Sheridan supplementary precognition in response to Dick Bowdler's Precognition – Toddleburn Inquiry BWL 110 IHB 44.10 – Production from Toddleburn Inquiry including: photograph of windshields; noise data from GRAS windscreen IEC_3_105_3 69 BWL 111 BWL 112 Table of Calculated Turbine Noise Levels (Agreed by Bowdler and Humpheson) 18th March 2009 Updated Table of Results based on ES Addendum assessment of Nordex N80 using manufacturer's warranted sound power level data – calculated turbine data as agreed between Humpheson and Bowdler DOCUMENTS FOR HIGHLAND COUNCIL: THC1 THC2 THC3 THC4 THC5 THC6 THC8 THC9 THC10 THC11 Committee Report 19 September 2003 Committee Minute 19 September 2003 Notice of Refusal 1 October 2003 Highland Council Structure Plan 2001 Caithness Local Plan 2002 Caithness and Sutherland LCA. Landscape and Visual Impact Report, Assessment and figures by Mark Steele Consultants. The Highland Council. Position statement on the Highland Renewable Energy Strategy, 4 March 2009-08-05. Decision letter. Lochluichart wind powered energy station. 22 December 2008. Guidelines on the environmental impacts of wind farms and small scale hydroelectric schemes. DOCUMENTS FOR THE CAITHNESS WEST ACTION GROUP: Birds CWAG1 CWAG2 CWAG3 CWAG4 CWAG5 Transport CWAG10 Safety CWAG20 CWAG21 IEC_3_105_3 Greenland White-fronted Geese and Whooper Swans in Caithness during the 1994/95 winter. Report to SNH. Nigel Harding and Stan Laybourne, 1996 South Shebster Proposed Wind Farm and Visitor Centre – SNH Ornithological Queries Report, Volume 1, April 2008 South Shebster Proposed Wind Farm and Visitor Centre – SNH Ornithological Queries Report, Volume 2, July 2008 Numbers and behaviour of Greenland White Fronted Geese in Caithness with special reference to daily routines of roosting and feeding. Winter 1993/94 with update of records from 1986/87. Report to SNH. S Laybourne and MIH Legg, 1994. Survey of Winter Wildfowl using Caithness Lochs proposed Special Protection Area and RAMSAR Site, Winter 1996/97, Report to SNH. S Laybourne, 1997. Strathy South Wind Farm environmental statement Volume 4 – Appendices. June 2007 The Health and Safety Risks and Regulatory Strategy Related to Energy Developments, Health and Safety Executive, June 2006. BWEA Guidelines for Health & Safety in the Wind Energy Industry, October 2008 70 CWAG22 CWAG23 CWAG24 CWAG25 Health CWAG30 CWAG31 CWAG32 CWAG33 CWAG34 CWAG35 Planning CWAG40 CWAG41 CWAG42 Wind Turbine Accident Compilation, database of wind turbine accidents and incidents. Wind Turbine Ice Throw Studies In The Swiss Alps, René Cattin et. al. 2007 Vestas Mechanical Operating and Maintenance Manual, V90 – 3.0 MW, VCRS 60 Hz, Ref 964106.R00 , 29 June 2007 Tables and figures to accompany precognition by David Craig Health Effects of Wind Turbine Noise, Dr N Pierpoint, March 2006 Wind Turbine Syndrome: Noise, shadow flicker and health, Dr N Pierpoint, August 2006 Wind Turbines, Noise and Health, Dr A Harry, February 2007 Le retentissement du fonctionnement des eoliennes sur la santé de l'homme, Academie nationale de medicine, Mars 2006 [The effects of wind turbine operations on human health, National Academy of Medicine, France, March 2006] Looking into the ‘noise’ about wind turbines, National Wind Watch, 5 December 2008 Noise Radiation from Wind Turbines Installed Near Homes: Effects on Health; Barbara Frey and Peter Hadden, June 2007 04/00178/FULCA Erection of Sixty meter high anemometer mast (retrospective) at Baillie Hill, Shebster, Thurso; Report C/P/184/04, 9 August 2004 06/00185/FULCA Renewal of Planning Consent (04/00178/FULCA) for the erection of 60 metre high anemometer mast and ancillary equipment at the Site of Stemster Hill, Shebster, Caithness, KW1 6XJ, report C/P/119/06, 15 May 2006 Letter 04/00342/s36CA DM/CC dated 30 January 2008 from David Mudie, Highland Council, to Lesley Rush, Scottish Government Energy Consents Unit, and accompanying minutes of Highland Council planning meeting 15 January 2008 Carbon savings CWAG50 Promoters overstated the environmental benefit of windfarms, Daily Telegraph, 21 December 2008 CWAG51 Windfarm lobby bows to ASA and cuts CO2 saving figures Spinners' numbers overblown , The Register, 23 December 2008 CWAG52 Calculations for wind energy statistics, BWEA CWAG53 Non-broadcast Adjudications: Renewable Energy Systems Ltd; 21 December 2005, Advertising Standards Authority Opinion CWAG60 IEC_3_105_3 Letter January 2008 from David Sutherland, Highland Council Ward Manager for Thurso, Wick and Landward Caithness, to Derrick Milnes, Secretary, West Caithness Community Council, regarding the Postal Ballot for Baillie Wind Farm conducted in December 2007. 71 CWAG61 CWAG62 CWAG63 CWAG64 Noise CWAG70 CWAG71 CWAG72 CWAG73 CWAG74 CWAG75 CWAG76 CWAG77 CWAG78 CWAG79 CWAG80 CWAG81 CWAG82 CWAG83 CWAG84 CWAG85 Residents say NO to wind farm , John O'Groats Journal, 11 January 2008 Baillie decision hailed as a victory for democracy , John O'Groats Journal, 18 January 2008 Example of Baillie support petition Tables and Figures in support of precognition of Alastair MacDonald ETSU R 97 – The Assessment and Rating of Wind Farm Noise BSEN 61400-11 – Wind Turbine Generator Systems. Acoustic Measurement Techniques. Mountboy Wind Farm Environmental Statement Bullmore – Precognition to the Tillyrie Public Inquiry. ETSU-W-13-386 – Noise Measurements in Windy Conditions Main Specification NM80 Turbine J H Bass, A J Bullmore, E Sloth. Development of a Wind Farm Noise Propagation Prediction Model. Contract JOR3-CT95-0051, pages 155 and 156 Bullmore et al. Wind Farm Noise Predictions – the Risk of Conservatism. Second International Conference on Wind Turbine Noise. Decision on Rossie Farm Wind Farm, Auchtermuchty (Ref P/PPA/250/675) BS8233 – Sound Insulation and Noise Reduction for Buildings, page 1. Developer’s Noise Data Files (On CD only) Barmoor Wind Farm Environmental Statement, Section 11, Noise, RPS Group plc, 2006 Barmoor Wind Farm Environmental Statement, Volume 3, Technical Appendix 11.6, RPS Group plc, 2006 Tables and figures to accompany precognition by Dick Bowdler Night Shear GRAS Windshield Tests (Sheridan – Toddleburn/Montreathmont) Other relevant reports CWAG90 Planning Appeal by CRE Energy: proposed development of wind turbines and associated infrastructure at Borrowston Mains, Dounreay, Thurso, Caithness , P/PPA/270/285, WMH Patterson, Reporter, Scottish Executive Inquiry Reporters Unit, March 2005 CWAG91 Planning Appeal: proposed erection of three 3MW wind turbines at Hill of Lieurary, by Thurso, Caithness , P/PPA/270/369, David N Gordon, Reporter, Scottish Executive Inquiry Reporters Unit, March 2006 CWAG92 Proposed windfarm at Bardnaheigh and Stempster, Environmental Statement, RPS Cairns Limited, for NGT (Scotland) Limited, July 1994 CWAG93 Baillie Wind Farm Scoping Report, prepared for Dudley Developments by RPS Consultants Ltd, CS/SGP 5004 \Scoping Report, Final version, 27 June 2003 CWAG94 Baillie Wind Farm Scoping Opinion, a response by the Scottish Ministers, 18 August 2003 CWAG95 The European Convention on Human Rights, Article 8 CWAG96 A selection of various press cuttings, articale and correspondence IEC_3_105_3 72 CWAG98 CWAG99 CWAG100 CWAG101 Caithness Wind Energy and Poll, May 2006 Caithness & North Sutherland Regeneration Plan – snapshot 3, June 2008 VisitScotland – Position Statement on Wind Farms, August 2008 Correspondence to/from Jim Mather MSP regarding SPP6 and 2km separation distance from dwellings, December 2008 DOCUMENTS FOR HISTORIC SCOTLAND: HS1 HS2 HS3 HS4 HS5 HS6 HS7 HS8 HS9 HS10 HS11 HS12 HS13 HS14 HS15 HS16 HS17 HS18 HS19 IEC_3_105_3 Historic Scotland Framework Document (2008). The Electricity Act 1989 Ancient Monuments and Archaeological Areas Act 1979. Scottish Government (2000) Guidance on the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations. Institute of Environmental Management and Assessment (IEMA) (2004) Guidelines for Environmental Impact Assessment. IEMA. Lincoln (Sections 1, 3, 11, 13 and 14). Historic Scotland (2008) Annex: Scoping of Development Proposals; Assessment of Impact of the Setting on the Historic Environment Resource – Some General Considerations. Historic Scotland’s Consultation Response: Letter dated 28 October 2003 (to Request for Scoping Opinion). Historic Scotland’s Consultation Response: Letter dated 13 June 2005 (to Environmental Statement). Historic Scotland’s Consultation Response: Letter dated 24 March 2006 (to Addendum). Historic Scotland’s Consultation Response: Letter dated 14 June 2006. Historic Scotland’s Consultation Response: Letter dated 17 January 2007. Historic Scotland’s Consultation Response: Letter dated 29 January 2008. RPS Baillie Wind Farm ES Addendum – Additional Information (submitted to Historic Scotland on 1 September 2006). Highland Council Archaeology Unit (13 September 2004) Memorandum to Head of Development Council: Baillie Wind Farm 04/00342/S36CA. Entry in the Schedule of Monuments (1994) Cnoc Freiceadain, Long Cairns. Entry in the Schedule of Monuments (1933) Hill of Shebster, Chambered Cairn. Historic Scotland (23 December 2003) Interim Statement of Cultural Significance: Cnoc Freiceadain, Long Cairns. Extracts from Davidson, J L & Henshall, A S (1991) The Chambered Cairns of Caithness: An Inventory of their Structures and Contents. Edinburgh University Press. Edinburgh. Extracts from Henshall, A S (1963) The Chambered Cairns of Caithness: An Inventory of their Structures and Contents. Edinburgh University Press. Edinburgh. 73 HS20 HS21 HS22a) HS22d) HS22e) HS22h) HS22i) HS23 HS24 HS25 HS26 HS27 Extracts from Close-Brooks, J (1995) The Highlands. HMSO. Edinburgh. Extracts from Philips, T (2002) Landscapes of the Living, Landscapes of the Dead: The Location of Chambered Cairns of Northern Scotland. BAR (British Series), 328. Archaeopress. Oxford. Photograph: Viewpoint 1: Cnoc Freiceadain – 50mm lens. Photograph: Viewpoint 1: Cnoc Freiceadain – Panorama. Photograph: Viewpoint 2: Hill of Shebster, Chambered Cairn – 50mm lens. Viewpoint Location Map. Photograph: Viewpoint 2: Hill of Shebster – Panorama. Alan Macdonald (30 January 2009) Photomontages from Historic Scotland Scheduled Monument Sites of the Proposed Baillie Wind Farm. Scottish Government (2003) Securing a Renewable Future: Scotland’s Renewable Energy. Minister for Enterprise, Energy and Tourism, Jim Mather speech to the All-Energy 08 conference. Extracts from Scottish Government (2005) Choosing Our Future: Scotland’s Sustainable Development Strategy. Report to Scottish Ministers on Notification of Application for Erection of a Dwellinghouse at 43 Callanish, Isle of Lewis (26 January 2009). DOCUMENTS FOR STUART YOUNG: SY/Baillie/1 Photograph of Causeymire Windfarm display SY/Baillie/2 Photomontage – Lieurary and South Shebster Windfarms from A836 near Cnocan Dubh. Viewing distance 2056mm SY/Baillie/3 Wirefame-based photomontage – Baillie Windfarm from A836 near Cnocan Dubh. Viewing distance 380mm SY/Baillie/4 Wirefame-based photomontage – Baillie Windfarm from A836 near Cnocan Dubh. Viewing distance 500mm SY/Baillie/5 Wirefame-based photomontage – Baillie Windfarm from A836 near Cnocan Dubh. Viewing distance 1000mm SY/Baillie/6 Acetate sheet with wireframe image of turbines extract from ES Figure 4.53 SY/Baillie/7 Photomontage – Lieurary and South Shebster Windfarms from A836 near Cnocan Dubh. Viewing distance 500mm SY/Baillie/8 Composite image – Buolfruich Windfarm and Baillie Turbines. Viewing distance 500mm. SY/Baillie/9 Photomontage – Alternative Viewpoint to ES Figure 4.21 SY/Baillie/10 Photographs of Causeymire Windfarm from ND 12984 54633, Old Schoolhouse near Achies. Viewing distances 380mm and 500mm. SY/Baillie/11 Photographs of Causeymire Windfarm from ND 19080 54443, near Crofts of South Dunn. Viewing distances 380mm and 500mm, SY/Baillie/12 Photograph of Causeymire Windfarm photographs of various viewing distance sizes, and of their display frame. SY/Baillie/13 Copy of e:mail from Ms Lesley Cranna of Scottish Natural Heritage dated 1st March 2006. SY/Baillie/14 Extract from e:mail correspondence – S Young/R Hayley IEC_3_105_3 74