. JLAB-TN-07-024 12 GeV Accelerator Upgrade, 2007 Dipole and Corrector Magnet Design Summary R. Wines, R. Michaud Abstract: The CEBAF beam transport magnets were designed to support 6 GeV operation of the accelerator. Design studies have been done to determine the changes required to facilitate operation of the five pass machine at 11 GeV and the addition of a sixth-pass for 12 GeV beam delivery to Hall D. Magnetic measurement and FEA modeling have been used to determine the performance of the accelerator magnets at the required specifications for 12 GEV. The accelerator dipole magnets are catagorized into regions : Arc, Hall Transport, Spreader and Recombiner, Extraction, Injection/Reinjection Chicanes, Arc10 and Hall D. Requirements Budget limitations of the upgrade project require the approach of reusing as many of the existing magnets in the accelerator as feasible. Engineering and design time is also minimized by use of existing designs and design principles for fabrication of new magnets. The beam transport magnets are to facilitate operation of the machine from 12 GeV settings down to 50% of this range. To reuse the power supply and control scenario the spreader and recombiner magnets will be powered by the Arc magnet power supplies, with their current settings within the use of 20A shunts. The upgrade to 12 GeV will require using existing magnets at 4x the power, thus hotter temperatures. For engineering purposes the temperature limit of dT < 40C has been set for magnets with water cooled conductors. This limit was determined from temperature and life cycle studies conducted on existing magnets. At the time of required evaluation of the upgrade magnets only the field quality specification for Arc 10 had been defined. Since this is the region with the largest beam, this specification was applied to all other regions as a conservative approach. The field quality aperture limits are defined by the size of the upstream/downstream quadrupole magnet apertures. The Arc 10 field quality specification is defined by evaluation of dB’L/BL along the curved beam trajectory with limits as defined in Figure 1. 12 GeV Dipole Specification 0.300% 0.200% d (B'L)/BL 0.100% 0.000% -0.100% -0.200% -0.300% -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 X (cm ) x=0 center of beam trajectory Figure 1. Arc 10 Dipole Field Quality Specification Arc Dipoles The existing Arcs consist of four lines of magnets in the West and 5 lines in the East. This sums to 256 dipole magnets. The existing Arc dipole magnets use the same core cross-section and conductor size in their design, except for the BR magnet. All Arc dipoles utilize a 40 turn count coil with the magnets varying only in length. The Arcs are comprised of 1, 2 and 3 meter dipoles. Evaluation of the existing dipoles was done by modeling the dipoles with the Vector Fields 2d and 3d FEA software. These results were then verified through measurement of prototype dipoles. The analysis results in the capability of reusing all the Arc dipole magnets with some modification. Arcs 3 through 9 will require the addition of return leg H-steel (Figure 2.) to reduce affects of saturation and allowing operation at scalable currents as exemplified in Figure 3. Current Bbase AmpFac AmpFac base w/H B w/H (A) Gauss Gauss % % 100 1969.70 1973.90 0.038 0.002 200 3936.80 3947.60 0.104 0.002 300 5890.70 5919.20 0.350 0.002 400 7713.20 7885.20 2.186 0.01 500 8879.20 9833.20 10.958 0.193 600 9711.70 11666.00 21.736 1.343 Figure 2. Prototype with H-steel Figure 3. Measured reduction in Saturation affects with H-steel Other modifications to the existing magnets resulted from inspection of the present condition of the magnet fabrication materials and the results of a life cycle test. These modifications are shown in Figure 4. Material Issue Solution Hoses beyond manufacturer's recommended use replace as part of CEBAF maintenance Support Wedges become loose and coil allowed to move flexibility decreases with extended use at elevated temperature, may result in crack Epoxy Leads modify center wedge to lock in place Low Risk, Reviewed 11/06, new magnets will have modified epoxy formulation silver polish degraded need stored energy device to prevent Belleville washers loosening of connections Silver polish leads during rebuild Mylar tape check and replace as needed loose in spots washers added during rebuild Urethane spacers failed at elevated temperatures replace during rebuild with EPDM Klixons replace during rebuild as needed operating at higher temperatures Figure 4. Modifications to Existing Dipoles for Upgrade The design and operating parameters for the upgrade of the Arc dipoles are summarize in Figure 5. ARC Magnet L #/Arc (m) 1A 2A 3A 4A 5A 6A 7A 8A 9A BE BR BEH BBH BBH BBH BAH BAH BAH 1 2 1 2 2 2 3 3 3 16 16 32 32 32 32 32 32 32 BdL BdL Nominal TOSCA AmpFac Current VOLTAGE Resistance # cooling Power circuits kG-cm kG-cm % (A) (V) (ohm) (kW) 794.5 1508.4 1111.1 1468.1 1825.0 2182.0 2538.9 2895.9 3252.8 799.0 1512.6 1122.1 1471.1 1822.7 2182.6 2532.4 2899.9 3256.4 2.8% 5.4% 0.7% 1.0% 1.0% 1.0% 0.7% 1.0% 1.3% 411 405 570 368 457 552 432 495 560 16.3 26.4 23.4 21.5 27.4 31.9 37.4 43.3 49.7 0.04 0.065 0.041 0.058 0.06 0.058 0.087 0.088 0.089 6.70 10.69 13.34 7.91 12.52 17.61 16.16 21.45 27.83 Figure 5. Arc Dipole Upgrade Parameters dT o 2 2 2 2 2 4 4 4 4 Water Water Flow Velocity ( C) (GPM) (ft/sec) 16.9 34.1 33.6 24 38 18.9 17.7 23.7 31.2 1.5 1.2 1.5 1.2 1.2 3.5 2.9 2.9 2.9 6.6 5.2 6.6 5.5 5.5 7.7 6.3 6.3 6.3 The field quality specification defined for Arc 10 dipoles was applied to all Arc dipoles and evaluated through the use of the 3d simulations. With the limits of the quadrupole aperture applied, the Arc dipoles meet the requirements of this specification. ARC1 BE 427A 0.300% 0.300% spec 0.300% 0.200% 0.100% dB'L/BL dB'L/BL 0.000% 0.000% -0.100% -0.100% -0.200% -0.200% -0.200% -0.300% -2.5 -0.300% -1 -0.5 0 0.5 1 1.5 2 -2.5 2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 -0.300% -2.5 2.5 0.000% -0.100% -0.200% -0.200% -0.200% -0.300% -0.300% 1.5 2 -2 -1.5 -1 -0.5 ARC7 BAH 434A 0 0.5 1 1.5 2 2.5 -2.5 0.000% 0.000% -0.100% -0.200% -0.200% -0.200% -0.300% -0.300% 2.5 -0.300% -2.5 -2 -1.5 -1 -0.5 X (cm) 0 0.5 1 1.5 2 -2.5 2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 X (cm) X (cm) Figure 6. Field quality specification evaluated for Arcs 1 through 9 A sample evaluation of the field quality specification for an Arc 5 dipole at 50% activation for the upgrade requirement is shown in Figure 7. ARC5 BBH 182A 0.300% spec 0.200% 0.0cm dB'L/BL 0.100% 0.000% -0.100% -0.200% -0.300% -2.5 -2 -1.5 2.5 0.0cm -0.100% 2 2 0.100% dB'L/BL dB'L/BL 0.000% 1.5 1.5 spec -0.100% 1 1 0.200% 0.100% 0.5 0.5 0.0cm 0.100% 0 0 spec 0.200% -0.5 -0.5 ARC9 BAH 560A 0.0cm -1 -1 0.300% spec -1.5 -1.5 ARC8 BAH 495A 0.200% -2 -2 X (cm) 0.300% -2.5 0.0cm X (cm ) X (cm ) 0.300% 2.5 -0.300% -2.5 2.5 2 0.000% -0.100% 1 1.5 0.100% dB'L/BL dB'L/BL 0.000% 0.5 1 spec -0.100% 0 0.5 0.200% 0.0cm 0.100% -0.5 0 ARC6 BBH 563A 0.200% 0.100% -1 -0.5 spec 0.0cm -1.5 -1 0.300% spec 0.200% -2 -1.5 X (cm ) 0.300% -2.5 -2 ARC5 BBH 468A ARC4 BBH 376A 0.300% dB'L/BL 2 X (cm) X (cm ) dB'L/BL 0.000% -0.100% -1.5 0.0cm 0.200% 0.0cm 0.100% 0.100% -2 spec spec 0.0cm 0.200% dB'L/BL ARC3 BEH 582A ARC2 BR 407A -1 -0.5 0 0.5 1 1.5 2 2.5 X (cm ) Figure 7. Field quality specification for Arc 5 dipole at half field 2.5 Hall Transport Dipoles The transport lines to Experimental Halls A, B and C require the use of 24 Arc style dipoles and an additional 2 BN dipoles. The Arc style dipoles again use the same core cross-section and conductor size. With the addition of H-steel these magnets will meet the requirements of the upgrade and be reused. Preliminary analysis indicates the BN magnets will have to be replaced with a new dipole design. Figure 8 summarizes the upgrade parameters of the transport line dipoles. Since Hall A through C can take any pass beam these dipoles have to operate from 1 to 11 GeV. Line Magnet L #/Arc (m) BAH BAH BEH (kG-cm) (kG-cm) 3 3 1 8 8 8 (%) (A) VOLTAGE Resistance (V) (ohm) # Power cooling (kW) 2752.0 2758.2 1.0% 469 40.8 0.087 19.1 2752.0 2758.2 1.0% 469 40.8 0.087 19.1 1133.0 1137.0 1.0% 578 23.8 0.041 13.8 Figure 8. Transport Line Dipole Upgrade Parameters Water Water Flow Velocity dT o circuits ( C) (GPM) (ft/sec) 4 4 2 21.1 21.1 34.6 2.9 2.9 1.5 6.3 6.3 6.6 The Arc 10 field quality specification was evaluated for the simulation of the transport line dipoles with passing results. Hall B BEH 594A Hall A& C BAH 469A 0.300% 0.300% spec spec 0.200% 0.0cm 0.200% 0.0cm 0.100% 0.100% dB'L/BL B'L/BL A C B BdL TOSCA AmpFac Current BdL 0.000% 0.000% -0.100% -0.100% -0.200% -0.200% -0.300% -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 X (cm ) Figure 9. Hall A & C dipole specification results -0.300% -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 X (cm ) Figure 10. Hall B dipole specification results Synchrotron Radiation Compensation Coils Energy loss is found to occur in the simulation of the higher energy Arcs and Hall Transport Lines due to synchrotron radiation. To keep the beam on magnetic center of the magnet through these regions compensation coils are required to trim the field. The conceptual design consists of two 8 turn, #14 AWG wire, coils wound around the poles of each dipole in Arcs 8, 9 , 10 and the transport lines. The turns of the coils will be energized such that the magnitude of the field is increased or decreased as needed to center the beam through the trajectory of the magnets. All compensation coils in each Arc will be powered in series to give an adjustment “knob” for each Arc. Spreader and Recombiner Dipoles The Spreader and Recombiner magnets carry the beam to and from the Linac regions. These 4 regions are dominated by space restrictions resulting in the use of primarily 1 meter C-style dipoles. The existing 1 meter dipoles utilize 2 core designs; a 4” pole width and a 5” pole width. Their coils are configured from the use of 2 coil designs; an 8 turn count and a 10 turn count. Various modifications to the existing 1 meter dipoles were simulated and tested to achieve the upgrade requirements. The 1 meter dipoles will be modified by adding H-steel, changing the turn count to match power supply requirements and adding shims to the pole ends to achieve the field quality specifications. The Spreader and Recombiner dipole magnets are powered by the Arc string power supplies. Shunts are used to reduce the Arc current settings to the corresponding pass Prototype testing results of these modifications is compared with the Arc 10 field quality specification in Figure 11. Unshimmed AIH prototype end shim Single shim Symmetric shims 0.25% spec 0.20% spec d(B'L/BL) (1/cm) 0.15% 0.10% 0.05% 0.00% -0.05% -0.10% -0.15% -0.20% -0.25% -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 Transverse position (cm) Figure 11. 1 meter prototype field quality comparison with modifications The 1 meter dipoles for the upgrade requirements are summarized in Figure 12. The turn counts have been changed such that no new coils will need to be purchased with the use of existing spare coils. Magnet Location AI AA AC AC AG AI AF AB AE 1S 3S 5S 7S 9S 2S 4S 6S 8S BdL (kG-cm) 1312 1060 894 707 984 1272 1244 1332 1241 Arc Current (A) 411 570 457 432 560 405 368 552 495 Shunt (A) 3 2 2 2 5 6 2 15 2 Voltage (V) 29.9 23.9 18.5 15.5 23.2 29.4 29.1 30.7 28 # Cooling Circuits 4 2 2 2 2 4 2 3 3 dT (deg C) 15 34.6 21.6 16.2 33.1 14.5 37.7 27.1 22.7 Water Flow (GPM) 3.1 1.5 1.5 1.6 1.5 3.1 1.1 2.3 2.3 Figure 12. 1 meter Spreader and Recombiner upgrade parameters Water Velocity (ft/sec) 6.8 6.5 6.5 6.9 6.5 6.8 4.7 6.7 6.8 TURNS 72 40 40 36 40 72 76 56 56 The entrance/exit to the Spreader and Recombiner regions utilizes 2 H-style magnets, referred to as BCOM magnets. Simulation of these dipoles indicates only the trapezoid dipole in these regions will need to be modified for the upgrade. The 2d analysis resulted in the addition of 6” of steel to the return leg of the trapezoid magnet to reduce the affects of saturation from the upgrade requirements as shown in Figure 13. The field uniformity is shown to be within 10-4 range over 12 cm which encompasses the affected trajectories. AX w ith 6" ad d ed 0.00E+ 00 dB /B -2.00E-05 -4.00E-05 m id -6.00E-05 -8.00E-05 -1.00E-04 40 42 44 46 48 50 52 54 56 58 60 X position across pole (cm) Figure 13. BCOM dipole layout with 6” steel addition and field uniformity The 3d simulation results for the rectangular BCOMS using the most stringent beam trajectory requirements are shown in Figures 14 and 15 as compared to the Arc 10 field quality specification. AWH 405A 10.801 Bend Angle Line 2 AQH 411A 18.578 Bend Angle Line 1 0.3% 0.3% spec 0.2% spec 0.2% 0.0cm B'L/BL B'L/BL 0.0cm 0.1% 0.1% 0.0% 0.0% -0.1% -0.1% -0.2% -0.2% -0.3% -0.3% -2 -1.5 -1 -0.5 0 0.5 1 1.5 -2 2 -1.5 -1 -0.5 Figure 14. AQ field quality specification (rectangular BCOM) AQ AS AW AX 1S 3S 2S 4S 0.5 1 1.5 2 Figure 15. AW field quality specification (rectangular BCOM) The upgrade parameters of the BCOM magnets are summarized in Figure 16. Magnet location 0 R (cm) R (cm) # cooling VOLTAGE circuits BdL Arc Current Shunt kG-cm (A) (A) (V) 1312.0 1207.0 1448.0 1193.0 411 570 405 368 4 4 1 1 38.8 64.1 49.4 53.6 Water Flow Water Velocity ( C) (GPM) (ft/sec) 22.0 38.2 30.7 36.5 2.8 3.6 2.4 2.0 6.0 6.3 5.3 4.4 dT o 4 5 4 4 Figure 16. BCOM dipole upgrade parameters The Spreader and Recombiner Septa magnet parameters are summarized in Figure 17. The 2d simulations indicate 3 of 2 meter Septas can be reused with modification. The 2 meter septas will need new coils to accommodate beam clearance through these magnets. A new 3 meter septa design will be used in all other required locations. The new design utilizes the existing 2 meter design with the addition of a wider pole. Figure 18 depicts the field uniformity of the 3 meter septa. Magnet YR7S,YR7R YR9S,YR9R YRBS YR8S,YR8R YRAS,YRAR L (meter) 3 2 2 3 3 BdL (kG-cm) 2483 984 1127 2625 2625 Current (A) 746 432 495 789 789 Voltage (V) 79 32 37 84 84 # cooling circuits dT 24 24 24 24 24 35 12.7 16.8 39 39 Water Flow (GPM) 6.6 4.2 4.2 6.6 6.6 Water Velocity (ft/sec) 11.6 7.5 7.5 11.6 11.6 Figure 17. Septa magnet upgrade parameters Figure 18. Field uniformity of the 3 meter septa Due to space limitations the Spreader and Recombiner regions require the use of curved dipoles in some portions of the beam transport. The curved dipoles are configured with the coils wound around the return leg of the core rather than the pole. Analysis results indicate these magnets cannot be modified for reuse in the upgrade. The design of the new curved dipoles is based on adding 1” of steel to the core of the existing design, widening the pole by ½”, changing the curvature to match the beam path and changing the turn count of the coils. Figures 19 and 20 show the 2d simulation results to be within 10-4 range over 3 cm for these modifications. AU modified at549A 0.00E+00 dB/B -1.00E-04 -2.00E-04 -3.00E-04 -4.00E-04 -5.00E-04 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 X position along pole (cm) Figure 19. AU modified Figure 20. Field uniformity for AU modified The upgrade parameters for the curved dipoles is summarized in Figure 21. Magnet location AM AN AV AU 3S 5S 4S 6S BdL (kG-cm) 2499 2487 2635 2628 Current (A) 570 457 368 552 Shunt Voltage (A) (V) 10 42 5 42.2 1 45 3 47.2 # cooling circuits Water Water Flow Velocity (GPM) (ft/sec) 3.1 6.8 2.8 6.1 2.4 5.3 2.9 6.4 dT 4 4 4 4 28.7 26 25.8 33.7 Turns 48 60 76 52 Figure 21. Upgrade parameters of the curved dipoles The 5th pass line to Arc 10 and the line to Hall D require additional 2 meter magnets (XH, XK) not present in the current machine. The design of these dipoles uses the same conductor and turn count coils as the existing Arc magnets. The core is similar to the Arc BR magnet with a 5.125” pole width. The 3d analysis gives the field quality specification results as shown in Figure 22 and 23 compared to the Arc 10 dipole specification. XK at 550A XH at 480A 0.300% 0.3% spec spec 0.2% 0.200% 0.0cm 0.0cm 0.100% d(B'L)/BL d(B'L)/BL 0.1% 0.0% -0.1% -0.200% -0.2% -0.300% -0.3% -2.5 0.000% -0.100% -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 transverse position (cm) transverse position (cm) Figure 22. XH 2meter field quality specification Figure 23. XK 2 meter field quality specification The XH and XK 2 meter magnets use the same core cross-section and conductor differing only in total turn count. The parameters of the new 2 meters are summarized in Figure 24. Magnet XH XK location BdL Current (kG-cm) (A) AS,AR,AT 2624 495 BS 2111 560 # cooling Shunt Voltage circuits (A) (V) 15 41.2 6 10 31.8 4 Water Water dT Flow Velocity (GPM) (ft/sec) 14.2 5.3 7.7 18.8 3.5 7.7 Figure 24. New 2 meter XH and XK upgrade parameters. Turns 60 40 2.5 The 1st pass of these regions utilizes a 1 meter dipole with the coils configured around the return leg of the core. Simulation shows this magnet design will meet the requirements of the upgrade by lengthening it to a 1.5 meter magnet, referenced as the XL. The 2d analysis shows the field uniformity to be within 10 -4 over 5 cm for the geometry of this magnet as shown in Figure 25. 1.5 meter AL at 385A 0.00E+00 dB/B -5.00E-05 -1.00E-04 -1.50E-04 -2.00E-04 -2.50E-04 -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 X position along pole (cm) Figure 25. XL 1.5 meter cross-section and field uniformity Figure 26 summarizes the upgrade parameters for the 1.5 meter XL dipole. Magnet XL location 2S BdL 1448 Current 405 # cooling Shunt Voltage circuits 20 33.2 4 dT 16.9 Water Water Flow Velocity 2.9 6.3 Turns 60 Figure 26. XL dipole upgrade parameters Extraction Dipoles The upgrade of the Extraction region will reuse existing magnets. Additional BP and YA magnets will be added to the lines to meet the upgrade requirements. Two meter YR magnets will be relocated from other regions of the machine to be reused in the Extraction upgrade. The upgrade Extraction region configuration is shown in Figure 27. Figure 27. Upgrade Extraction region configuration The 1st and 2nd passes are unchanged from the existing machine. The operating parameters of the extraction magnets are within the tested limits of the existing magnets, except for the 5th pass BP. Simulation of the BP indicates the field integral can be achieved with this higher current. Energy requirements of the Extraction region are summarized in Figure 28. Pass 1 2 3 4 5 Proposed Element MYA2T01 MYB2T02 MBP2T03 MBQ2T04 MYA4T01 MYB4T02 MBP4T03 MBQ4T04 MYA6T01 & MYA6T01A MYR6T02 MBP6T03 & MBP6T03A MBP6T04 MYA8T01 & MYA8T01A MYR8T02 MBP8T03 & MBP8T03A MBP8T04 MYAAT01 & MYAAT01A MYRAT02 MBPAT03 & MBPAT03A MBPAT04 Energy (MeV) 2281.21 2281.21 2281.21 2281.21 4440.94 4440.94 4440.94 4440.94 6600.67 6600.67 6600.67 6600.67 8760.40 8760.40 8760.40 8760.40 10920.13 10920.13 10920.13 10920.13 BdL (kG-cm) -10.120 -257.115 564.272 -284.888 -19.702 -500.507 1098.463 -554.591 -14.642 -743.319 816.211 -824.284 -19.432 -986.531 1083.273 -1093.989 -24.223 -1229.744 1350.336 -1363.693 Required Current Max Current Upgrade (Amps) Tested dT degC 20.1 60 219 475 221 475 223 475 39.1 60 427 475 429 475 433 475 29.1 & 29.1 60 324 640 319 & 319 475 322 475 38.6 & 38.6 60 439 640 423 & 423 475 427 475 48.1 & 48.1 60 547 640 528 475 30.2 533 475 30.9 Figure 28. Extraction region upgrade requirements The Extraction region requires a 3 channel septa magnet for extraction of beam to the 3 experimental halls. The 3 channel septa, Lambertson, bends 2 beams with the center beam unaffected. Thermal analysis results in the recommendation of replacing the existing coils in this magnet with a new 24 turn/coil to lower the dT below 40C. The additional turns will require the core to be machined out. The magnetic performance of B = 4.9 kG has been verified by 2d simulations. Injection and Reinjection Chicane Dipoles The Injection/Reinjection region consists of chicane and mini-chicane regions. The upgrade of the chicane will reuse the existing 3 BL magnets plus a new fourth one. Figure 29. compares the parameters of the existing to the upgrade BL magnet requirements. Existing MBL(max) Upgrade MBL Length 30.5 cm 30.5 cm Turns (10AWG) 330 330 BdL 36.62 kG-cm 39.399 kG-cm Current 10 A 12.9 A (20A supply) Voltage 22V 29V Power 220W 374W Coil dT 6C 10 C Current Density 1.33 A/mm 2 1.71 A/mm2 •Solution: use existing MBLs with 20 A trim cards Figure 29. BL magnet comparison •Replace MDK with MBL, higher energy will be sufficient for synchrotron radiation Themonitoring upgrade mini-chicane requirements are achieved by replacing the existing magnets with 3 new CB magnets and use the Chicane BL magnet, as shown in Figure 30. The CB magnet design is based on •MBL designed with indirect water cooling lengthening the existing BK magnet design and using a 20A supply with a dT in the coil of 8C. The mini•Currentsare verified by 2D TOSCA modelling chicane parameters summarized in Figure 31. Figure 30. Mini-Chicane Upgrade layout Magnet MBD2R07 MBK2R09 MBK2R10 MBL0R04 Length (cm) 16.2 15.2 15.2 30.5 Current (A) 10 10 10 10 BdL BdL needed 12 GeV Magnet Current (kG-cm) (kG-cm) (A) 18.456 39.399 CB 14.6 17.85 39.399 CB 14.6 17.85 39.399 CB 14.6 36.62 39.399 BL 12.9 Current Density (A/mm2) 2.73 2.73 2.73 1.71 Length (cm) 30 30 30 30.5 Turns 152 152 152 330 Figure 31. Mini-Chicane magnet parameter comparison Arc 10 and Hall D Dipoles The addition of Arc 10 requires 32 new 4 meter dipoles. Simulation results achieve the specification requirements of field integral of 3600 kG-cm with a H-style dipole, as depicted in Figure 32. The coil is configured as four 10 turn pancakes operating at 460A and a dT of 38C. The transport line to Hall D utilizes two more of this design to bend the beam up to Hall D. Figure 33 shows the field quality specification of the 4 meter dipole. Curved Integral H-ARC10 @ 460 amps 0.30% B'L/BL (1/cm) 0.20% 0.10% Integral 0.00% Specification -0.10% -0.20% -0.30% -3 -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 3 Position (cm) Figure 32. 4 meter dipole simulation Figure. 33 4 meter dipole field quality Correctors Given the upgrade field integral and location requirements for corrector magnets, existing corrector capabilities is evaluated. Figure 34 and 35 summarize the upgrade requirements and existing corrector designs. Family Existing Max Currents 12 GeV Max Current Max BdL Issues MAT 3.0 amps (poly) 4.0 amps (poly) 7.0 amps (aluminum) 1000 G-cm (poly) 1686 G-cm (aluminum) MAT8S10H upgraded to aluminu m holder, and wire mesh cover added for safety. MBT 3.5 amps 8.5 amps 5500 G-cm MBT1S08V will use shunts to correct MBC 3.5 amps 8.5 amps 22000 G-cm Limited to 16000 G-cm. Water cool MBC’s going to 22000 G-cm. 4T09DV compensated using AV dipole MBM 3.0 amps 7.0 amps 16175 G-cm MBD 9.5 amps 9.5 amps 18500 G-cm Issues at 6T09V, 8T07V, and 8T09V. Figure 34. Corrector upgrade parameters. From the evaluation three complications exist with the corrector solution in the transport recombiner region; MBD 6T09V, 8T07V and 8T09V. The 6T09V solution is to replace the BD magnet with a new CB magnet as used in the mini-chicane. The 8T07V solution is to add a 2nd BD magnet in series. The 8T09V solution is to replace the BD with a new CB magnet. The upgrade requires the addition of 4 girders in the Injection region and 5 new girders in each of the North and South Linacs. 19 new FEL style horizontal and vertical correctors will be used in these region. Arc 10 and Hall D will utilize 136 new BD correctors to meet the requirements of the upgrade. Summary Figure 35. summarizes the modifications and requirements for new dipole magnets to meet the specifications of the 12 GeV upgrade. New Magnets Magnet and Location 1 2 3 4 5 6 7 8 9 10 11 12 XK XH XL XU XV XM XN 4 meter 3 meter Septa CB YA septa BP dipole BS06 AR, AS, AT 2S,2R,2T 6S,6R,6T 4S,4R,4T 3S,3R 5S,5R Arc10,Hall D S/R Chicane Extraction Extraction Modified Magnets 13 1 meter dipoles S/R 14 2 meter YR septa BS05 15 Lambertson Extraction 16 1meter dipoles Arcs, Line B 17 2 meter dipoles Arcs 18 3 meter dipoles Arcs,Line A & C Total Needed Description 1 3 3 3 3 2 2 37 8 3 2 7 2 meter dipole, existing coil design 2 meter dipole, existing coil design, same core as XK, replaces 2 magnets existing design lengthened curved dipole curved dipole curved dipole curved dipole H-style dipole extend existing septa design existing design lengthened existing design existing design 45 1 1 40 96 112 add H-steel, change turn count, add end shim, rebuild new coils, modify core new coils, modify core add H-steel, rebuild add H-steel, rebuild add H-steel, rebuild Figure 35. Summary of new and modified dipole upgrade magnet References 1. Leigh Harwood and Ken Baggett, Analysis of field quality specification and magnet measurement data spreadsheet data. 2. Mike Spata, Scope of Extraction region for 12GeV upgrade. 3. 2006 and 2007 Beam Transport 12GeV Upgrade design reviews of each region, powerpoint presentations.