Report on GEG Presentation “Tunnelling Experience and Supervision of Dropshaft Construction in Hong Kong West Drainage Tunnel Project” By Ms FONG Hau-yin, Fiona Mr. Eric Chan (2008 Intake GEG) gave a presentation on his site experience in tunnelling and dropshaft construction in the Hong Kong West Drainage Tunnel Project. He discussed the details of constructing the drainage tunnel and the dropshaft on Lower Stubbs Road with emphasis on various measures of site control. Flooding has been frequent during rainy seasons in the low-lying areas of Northern Hong Kong Island due to inadequate capacity of the existing drainage system. To alleviate this problem, a new drainage tunnel spanning from Tai Hang to Cyberport is proposed to intercept and convey stormwater from the upper catchment at Mid-Levels to the sea near Cyberport. Works under this Project include the construction of 34 intake structures and the 11-km long main tunnel, as well as the associated vent pipes, dropshafts, stilling basins and adits. To reduce construction time and minimise disturbance to the public, the major part of the drainage tunnel was constructed with two double shield tunnel boring machines (TBMs). Mr. Chan described the operation of TBMs in detail and highlighted the challenges in tunnel construction. As the tunnel would run across eight fault zones, stability problems and high groundwater inflow were anticipated. Detailed mapping of the tunnel face and probing ahead of the TBM was thus carried out so that adverse ground conditions could be foreseen. The flow rate of flushing water during probing was also measured to predict the potential of groundwater inflow. When weak rocks were encountered or infiltration rate was high, grouting would be performed at an inclination of 5° to horizontal for strengthening the rock mass and reducing its permeability. Upon the formation of the tunnel face by the TBM, segmental lining was erected to support the tunnel. The advance rate of the TBM was normally 12m per day, but it could be greatly reduced where ground conditions were poor. On the other hand, dropshafts connecting intake structures and tunnel adits were constructed by means of mechanical excavation. After excavation and lateral support (ELS) works were carried out for the construction of intake structures, some small diameter pilot drillholes were drilled down from the base of excavation to the stilling basin. The reamer of the boring machine, which was transported to the site through the main tunnel and adit, would then bore upwards to form the dropshaft. This method is known as “raise boring method”. The type of temporary support to the dropshaft was determined by the Resident Geologist using the Q-system and in most cases, rock dowels with shotcrete were adopted. Ground movement and groundwater levels were continuously monitored. Should the alert, action and alarm levels be exceeded, the Contractor would be requested to review its method of construction. In the Question and Answer session, the audience questioned whether the tunnelling method would change with the decomposition grade of rock mass. Mr. Chan advised that primarily TBM was used to construct the drainage tunnel as the majority of the sections would be excavated in hard rock. Whenever fault zone was anticipated, more probe holes were drilled and the ground surface was mapped to countercheck the fault zone extent. Where necessary, grouting would be performed prior to excavation to strengthen weak rock and thicker permanent lining would be erected. When asked about the material used to backfill the annulus after tunnel excavation, Mr. Chan explained that pea gravel was chosen to fill the gap between the excavated tunnel face and tunnel lining because its round shape enabled it to be placed easily, and it also helped relieve the groundwater pressure acting on the tunnel. However, excessive groundwater inflow was prevented by tunnel grouting and effects on the regional groundwater regime were considered minimal. Furthermore, participants expressed doubts in the suitability of using the Q-system in designing temporary support for vertical dropshafts. Mr. Chan reassured the audience by quoting the answer from Dr. Nick Barton, the developer of the Q-system, in a recent workshop in Hong Kong. Although this system was originally developed for evaluating the type of support required for a horizontal tunnel, it had been applied in similar projects in Hong Kong before and the performance was found satisfactory. In conclusion, graduates learnt how the drainage tunnel and dropshafts were constructed in the Hong Kong West Drainage Tunnel Project and understood the importance of site control in tunnel construction.