1.1.1. CRRP Feasibility Study Final Report 1.1.2. 2/18/20162/18/2016Abbreviations COAG Road Reform Plan 4 November 2011 CRRP Feasibility Study Final Report to COAG COAG Road Reform Plan – Document Title | 1 COAG Road Reform Plan T (03) 9095 4409 E crrp@transport.vic.gov.au W roadreform.gov.au Level 6, 121 Exhibition Street Melbourne VIC 3000 COAG Road Reform Plan – Final Feasibility Study Report to COAG | Table of Contents Abbreviations .....................................................................................................................2 Executive summary ...........................................................................................................3 1. Introduction .............................................................................................................8 2. What is the CRRP Feasibility Study? ....................................................................9 2.1. The context for the COAG Road Reform Plan .................................................................................................. 9 Box 1: Phase 1 of the COAG Road Reform Plan (CRRP)............................................................................... 10 The Feasibility Study process ......................................................................................................................... 11 Box 2: Principles guiding the Feasibility Study ............................................................................................. 12 2.2. 3. Consultation ..........................................................................................................13 3.1. 3.2. 3.3. How did the CRRP project engage with stakeholders? ................................................................................. 13 What were the key stakeholder messages? ................................................................................................... 14 Continued engagement with industry ............................................................................................................. 15 4. Why reform arrangements for heavy vehicle charging and funding? ..............16 4.1. 4.2. 4.3. The challenge to achieve productivity in the road freight industry.............................................................. 16 Improving productivity of the road freight industry ...................................................................................... 17 The role of road reform in improving productivity......................................................................................... 18 5. The feasibility of mass, distance and location based charges .........................20 5.1. What pricing options have been considered?................................................................................................ 21 Box 3: Charging principles ............................................................................................................................. 21 What costs are associated with heavy vehicle traffic? ................................................................................. 21 What are the benefits of more direct heavy vehicle charging? .................................................................... 22 Estimating the benefits of pricing reform alone............................................................................................. 24 Options to collect information for more direct road use charges ................................................................ 25 Box 4: Technologies available to measure key pricing parameters ............................................................. 28 Estimated costs of implementing more direct pricing options ..................................................................... 28 Feasibility of implementing more direct heavy vehicle charges .................................................................. 30 Box 5: Additional potential opportunities from the use of in-vehicle units to measure mass, location and distance ............................................................................................................................................................. 32 5.2. 5.3. 5.4. 5.5. 5.6. 5.7. 6. Feasibility of alternative funding and expenditure arrangements ....................33 6.1. What funding and expenditure options have been considered? .................................................................. 33 Box 6: Funding and financing principles ........................................................................................................ 33 What does funding and expenditure reform need to address? .................................................................... 34 What are the benefits of heavy vehicle funding and expenditure reform? .................................................. 36 Box 7: Case Study – Cost efficiency from improving road funding certainty ............................................. 36 The options to improve incentives for more efficient maintenance and provision of roads ..................... 38 The net benefits of introducing more direct road use charges and associated funding and expenditure reforms .............................................................................................................................................................. 40 6.2. 6.3. 6.4. 6.5. 7. Achieving the benefits of reform – the next phase of CRRP .............................42 7.1. What challenges will need to be addressed in the next phase of CRRP? ................................................... 42 Appendix A: CRRP reports and supporting models ....................................................44 Appendix B: Glossary ....................................................................................................47 Appendix C: Explanation of heavy vehicle segment definitions .................................51 COAG Road Reform Plan – Final Feasibility Study Report for COAG | 1 Abbreviations ATA Australian Trucking Association ATC Australian Transport Council BITRE Bureau of Industry, Transport and Regional Economics COAG Council of Australian Governments CRRP COAG Road Reform Plan CSO Community Service Obligation GPS Global Positioning System GSM Global System for Mobile Telecommunications HML Higher Mass Limits IAG Industry Advisory Group IAP Intelligent Access Program NFF National Farmers Federation NHVR National Heavy Vehicle Regulator NTC National Transport Commission PAYGO Pay As You Go PBS Performance Base Standards RUC Road User Charge SCOTI Standing Council on Transport and Infrastructure COAG Road Reform Plan – Final Feasibility Study Report for COAG | 2 Executive summary Road freight transport is an integral part of Australia’s economy; it enables goods and services to be transported to markets, raw materials to reach processing sites, exports to reach rail heads and wharves and waste to be removed from our communities. The cost, reliability, timeliness and quality of the transport sector has a measurable impact on the nation’s international competitiveness. The efficient functioning of the road transport sector contributes to the growth of the economy in the short term by reducing the time and cost of transporting people and goods to destinations and markets and indirectly as savings flow through and compound in the economy in a multiplier effect. Poor investment decisions can, and do, constrain Australia’s productivity growth and the nation’s living standards. Getting reform right is important for the productivity and efficiency of Australia’s economy both in the short and long term. Road freight transport faces challenges There are a number of current and emerging challenges that are driving the case for reform to delivery of road freight infrastructure and improving the direct pricing of that infrastructure. Foremost among these is the plateauing of national productivity. However, government’s capacity to fund productivity enhancements that are sustainable, safe and efficient is limited. There are significant challenges in achieving social, economic and environmental objectives through provision and use of road infrastructure when the incentives and revenue certainties which underpin client focused service provision are absent. Road transport infrastructure is one of the only remaining public sector assets yet to undergo major economic reform. While there have been considerable steps forward along the reform path, including the Model National Laws and the agreement to the National Heavy Vehicle Regulator (NHVR), comprehensive structural reform has not taken hold in the sector. Technical and structural issues can seem all the more insurmountable when you consider the intrinsic difference between the road transport sector and the sectors reformed in the 1990s. Businesses and private individuals have always directly paid for their consumption of electricity, gas and water and the network infrastructure used to provide these services are orders of magnitude less complex than the road network. It is clear that progressing charging reforms in the transport sector can be expected to be a significant challenge for any government prepared to take it on. Australia’s road freight task is continuing to double every 20 years. However, unlike in previous decades, this growth is placing increasing pressure on an already strained road network, degrading road assets, increasing emissions (both air quality and carbon equivalents) and contributing to congestion. Road providers have faced pressures to maximize the use of their road assets in the face of these increasing demands. To the extent that these demands are unable to be accommodated, this has resulted in higher vehicle operating costs, reductions in productivity and consequential costs and lost opportunities to the economy and community at large. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 3 There are also a number of other key emerging issues and challenges which will impact the ability of governments to effectively fund and supply road transport infrastructure into the future. The Australian Government’s 2010 Intergenerational Report1 noted that these pressures and challenges are likely to come from: population growth demographic change and an ageing population greater urbanisation climate change. In addition, and largely as a consequence of these issues, governments are likely to increasingly face constraints in their capacity to fully fund road construction and maintenance expenditure from general taxation revenue. Such constraints will continue to limit heavy vehicle productivity and efficiency. Road revenue is part of the taxation base. The vast majority of road transport infrastructure operates, in effect, as a government owned monopoly. Roads that are privately owned on government land and provide public services are fully regulated by governments. Road user revenues from fuel excise, registration, stamp duty, licence fees and tolls, in most jurisdictions, are not linked with public expenditure on roads. Generally, income from fees and charges goes into the consolidated revenue of the jurisdiction that collects it (Commonwealth or state). There is no universally direct link between road revenue and expenditure on maintenance and new infrastructure. Investment in road infrastructure is a result of complex funding arrangements between Commonwealth, state and local governments. In general, state governments are the responsible road manager for arterial roads while local governments are responsible for local roads. The Commonwealth Government plays an integral role in planning, constructing and maintaining road infrastructure through its funding relationship with state and local governments through nation building and local road grants. Road funding is determined through annual budgetary processes at all levels of government. Funding out of general revenue means investment in road infrastructure is balanced against other competing government priorities. Road infrastructure investments generally require long lead times and have large and lumpy costs resulting in a long lived asset. This is not conducive to the traditional decision making timelines of government which often focus on a 2-5 year time frame rather than a 10-50 year time horizons. The CRRP Feasibility Study In April 2007, the Council of Australian Governments (COAG) asked the then Australian Transport Council (ATC) – now the Standing Council of Transport and Infrastructure Ministers (SCOTI) – to undertake a study into the feasibility of introducing more direct pricing for heavy vehicles and to examine future funding arrangements for roads. This 1 Commonwealth of Australia, Australia to 2050: Future Challenges, 2010. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 4 remit stemmed from COAG’s consideration of the Productivity Commission’s 2006 study into Road and Rail Freight Infrastructure Pricing and recommendations from phase 1 of the COAG Road Reform Plan (CRRP). The establishment of dedicated resources under the guidance of a Board to undertake this reform complemented the parallel initiative of the establishment of the NHVR. In both instances the Boards comprised senior officers from transport and roads agencies and the National Transport Commission (NTC). The Feasibility Study (the study) was assisted by an Industry Advisory Group (IAG) comprising major freight shippers, retailers and fleet owner representatives. Their input was critical in identifying pragmatic issues affecting users and clients of the road networks. The current focus on heavy vehicle pricing reform being undertaken as part of this study under COAG Road Reform Plan, has as its principal objectives to: 1: Promote the more efficient, productive and sustainable provision and use of freight infrastructure. 2: Ensure that national heavy vehicle road prices promote the efficient, safe and sustainable use of infrastructure, vehicles and transport modes. Pricing and funding are inextricably linked The initial emphasis in the study was on evaluating pricing reforms. That is whether shifting from the current system of registration and fuel based road user charges to a more direct pricing regime for heavy vehicles was technically feasible, capable of implementation and likely to result in net economic benefits to the community. The study involved some significant research into how changes in charges might impact on operators’ choices and in turn result in more efficient use of roads and the vehicle fleet. On the cost side, work undertaken for Austroads and supplemented by internal research provided best estimates of the costs and effectiveness of current technologies in implementing direct pricing options. All the research was subject to review by a panel of technical and economic experts and the subsequent working papers were shared with the Industry Advisory Group. During the course of the study, and as with earlier reports to COAG, it was evident that a broader focus on reform of road funding, provision and use would result in benefits well in excess of those from reform of heavy vehicle pricing alone. Indeed the study now estimates that reforms to funding could deliver net benefits in the order of $5 billion to $7 billion (in present value terms) whereas undertaking direct pricing reform alone is likely to result at best in a small benefit, but more likely, a small economic loss. This finding is broadly consistent with the Productivity Commission’s findings although they had slightly higher estimates of the relative benefits of pricing reform compared to broader supply reform. As a consequence, steps were taken to identify options for examining how an integrated package of pricing, funding and expenditure reforms could be evaluated and implementation pathways developed for COAG’s consideration. It was evident that any shift in pricing would require a related shift in how road funds might flow to and through road providers. This close link between pricing and funding reform was considered to have wider implications that would require input from central agencies as well as COAG Road Reform Plan – Final Feasibility Study Report for COAG | 5 transport agencies. For this reason, the CRRP Board has established a joint working Group with the Deputy Heads of Treasuries to refine the funding and supply side issues for the consideration of COAG. Recommendations Recommendation 1: Recommendation 2: An integrated package of pricing, funding and expenditure reforms should be pursued where benefits outweigh the costs and that takes into account that: more direct pricing of heavy vehicles without funding and expenditure reform is not economically feasible; changes to the existing system of heavy vehicle charging will have consequential impacts on funding arrangements; and transitional arrangements will be required to manage the impacts on industries and communities. The next phase of CRRP should include development of a package of reforms, where benefits outweigh costs, that support the COAG Road Reform Plan objectives and address: the mechanism by which road user revenue would be transparently linked to road funding including transitional arrangements to take into account the impact on affected groups; economic incentives and accountabilities for road providers, including local government; mechanisms to ensure services that promote social objectives or benefits to the broader community beyond those a commercial road owner would provide are transparently funded; and new arrangements for price setting. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 6 Recommendation 3: The new arrangements for heavy vehicle road funding and expenditure and direct pricing for heavy vehicles should be developed by December 2012 for consideration by COAG along with the preparation of any necessary agreements to give effect to those arrangements. Any decision by COAG to proceed to implementation will follow consideration of a Regulatory Impact Statement (RIS). In short, there are considerable benefits to be reaped from economic and structural reforms to the planning, provision and maintenance of roads and consequential shifts to more direct pricing. There are also significant concerns that the current system of road provision and charging for heavy vehicles is not sustainable for the future. If pursuing reforms recommended by the Feasibility Study is approved by COAG, further work will be necessary to prepare a package of reforms that incorporate appropriate agreements and supporting cost benefit analysis of options for implementation. The expanded work program required to meet the recommendations of the Feasibility Study is expected to require a reconsideration of the most recent COAG Reform Council timetable for delivery of the implementation phase of CRRP.2 The CRRP Board and project team acknowledges the contribution from industry representatives, particularly those who participated in the CRRP Industry Advisory Group, representatives of local government and officers from all levels of government who participated in developing, reviewing and commenting on the work of the Feasibility Study. 2 COAG Reform Council, National Partnership to Deliver a Seamless National Economy – Implementation Plan, 17 August 2010. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 7 1. Introduction This paper is the final report of the COAG Road Reform Plan (CRRP) Feasibility Study (the study) from the Standing Council on Transport and Infrastructure (SCOTI) to the Council of Australian Governments (COAG). The SCOTI was tasked with determining the feasibility of introducing more direct heavy vehicle road use charges and associated funding arrangements, in order to promote a more efficient, productive and safe heavy vehicle industry. The study was undertaken by a Board of senior transport officials and representatives of all levels of government. The Feasibility Study involved detailed analysis and investigation into heavy vehicle pricing options and funding reform opportunities, in order to promote the CRRP objectives to: 1. promote the more efficient, productive and sustainable provision and use of freight infrastructure. 2. ensure that national heavy vehicle road prices promote the efficient, safe and sustainable use of infrastructure, vehicles and transport modes. At the outset of this study there was anticipation that the introduction of more direct pricing3 of heavy vehicle would yield significant economic benefits to the industry, government and the community. The principal conclusion of the study is that it will not do so if separated from integral funding and expenditure reforms. This paper sets out the findings and basis for the recommendations arising from the COAG Road Reform Plan (CRRP) Feasibility Study. Section 2 describes the COAG Road Reform Plan and the process followed to complete the Feasibility Study. Section 3 outlines the consultation activities undertaken by the CRRP project. Section 4 sets out the reasons why reforming arrangements for heavy vehicle charging and funding is required to meet the increasing demands being placed on Australia’s road network. Section 5 describes the analysis of options for more direct heavy vehicle charges. Section 6 describes the analysis of options for more efficient maintenance and investment in roads. Section 7 outlines the risks, uncertainties and impediments for implementing the key recommendations of the feasibility study and outlines recommendations to support the next phase of road reform. 3 Direct pricing may be described as pricing a vehicle for the use of roads by using actual measures that reflect the costs of that use. These measures include such variables as the mass of a vehicle, the distance it travels, and the location (or road type) of its travel. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 8 2. What is the CRRP Feasibility Study? The CRRP Feasibility Study represents the current phase in Australian governments’ commitment to create a more productive, safe and efficient road freight transport industry. It is complementary to current reforms to establish national heavy vehicle and rail regulators, and efforts to develop a national freight strategy.4 2.1. The context for the COAG Road Reform Plan The CRRP is the COAG’s response to the recommendations made in 2006 by the Productivity Commission in its Road and Rail Freight Infrastructure Pricing inquiry. The Productivity Commission found that road charges and regulatory arrangements for heavy vehicles impeded the efficient use and development of transport infrastructure, and consequently imposed unnecessary costs on both industry and government.5 The Productivity Commission highlighted that there are good reasons for reforming road charging and road provision arrangements:6 averaged charges under PAYGO (which are more like taxes) convey negligible signals to road users about the costs of using particular roads, or to infrastructure providers about the demand for different roads the disconnect between road charges and future road spending can lead to inefficient decisions, including holding back efficient road projects and encouraging public sector road providers to preserve road assets government provision of road infrastructure is unlikely to provide an incentive framework for providing road infrastructure services efficiently. The recent review of Australia’s Future Tax System (the Henry Review) further identified opportunities for reform to road transport taxes to address Australia’s future transport challenges.7 Transport pricing was also considered at the October 2011 Tax Forum. Emerging from the work of CRRP and other bodies is that significant structural reform of pricing and more fundamentally funding and investment of road infrastructure, has the potential to deliver significant economic efficiency and productivity gains. While arguably more complex than other infrastructure areas, road infrastructure provision is one of the last infrastructure areas to undergo significant structural reform. The first phase of the CRRP involved a number of research and evaluative tasks, as a precursor to investigating the feasibility of additional heavy vehicle reforms – See Box 1. 4 See www.nhvr.gov.au for further information about the National Heavy Vehicle Regulator; www.nrsrproject.sa.gov.au for information about the National Rail Safety Regulator, and www.infrastructureaustralia.gov.au/freight/ for information about the proposed national freight strategy. 5 COAG Road Reform Plan Funding and Implementation Issues Paper, page 1. 6 Productivity Commission, Road and Rail Freight Infrastructure Pricing, Productivity Commission Inquiry Report No. 41, December 2006, p.xxxix. 7 Australia’s Future Tax System Review Panel, Australia’s future tax system: Report to the Treasurer, December 2009 COAG Road Reform Plan – Final Feasibility Study Report for COAG | 9 Box 1: Phase 1 of the COAG Road Reform Plan (CRRP) Phase 1 of the CRRP involved: an independent review of policy relevant externalities of heavy vehicle road use and cost-effective policies for attaining efficient abatement of external costs an independent review of heavy vehicle road use and costs to refine PAYGO, improve investment decision making and provide an information base for examination of location-based charging8 government research to identify road spending to meet Community Service Obligations (CSOs) to assist transparency of funding for CSOs and help inform future charging arrangements a detailed review and trials of the impact and feasibility of incremental pricing schemes for higher mass and other innovative vehicles that allow access to parts of the road network from which they are currently excluded. The Phase 1 analysis concluded that: direct pricing of externalities (e.g. for air pollution, greenhouse gases, crashes and congestion) is not considered optimal at this time, but should be reassessed if a direct charging system is established there are a number of possible refinements to the existing PAYGO system, to address some of its disadvantages CSOs should be defined with reference to services that would not otherwise be provided by a road provider acting commercially CSOs are able to be measured, and should be separately identified as part of the investment framework for road infrastructure there are likely to be beneficial opportunities from incremental pricing that warrant the continuation of trials. The CRRP Feasibility Study (Phase 2 of CRRP), focused on investigating the feasibility of introducing more direct road use charges for heavy vehicles, (defined as vehicles 4.5 tonnes gross vehicle mass and above) as a foundation for considering alternative models of road pricing and funding and institutional matters. The study considered charging relating to the whole road network inclusive of local roads. 8 GHD Meyrick, (2008), Alternative Approaches to Estimating the Road Cost Base. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 10 2.2. The Feasibility Study process In May 2009, the Australian Transport Council (now SCOTI) appointed a CRRP Project Board to conduct the Feasibility Study on its behalf. The Project Board was accountable for the delivery of all pricing, funding and related institutional issues associated with the CRRP.9 The Feasibility Study builds upon the initial work of the Productivity Commission in its inquiry into Road and Rail Freight Infrastructure Pricing, and the research conducted as part of Phase 1 of the CRRP. It has focused on: developing alternative direct pricing options to current heavy vehicle charges, and understanding the likely implications on heavy vehicle road use of adopting those charges analysing the technical feasibility of implementing a charging system capable of satisfying the likely performance requirements of each alternative charging option investigated investigating alternative funding options determining the economic feasibility of each heavy vehicle charging option in combination with funding options legal and regulatory feasibility. It is important to note that the estimates of benefits and costs outlined in this report are based on high level analysis and data which is limited to providing estimation of aggregate benefits and costs to Australia of reform and as such for the completion of the feasibility study. Key assumptions and limitations related to the study are detailed in the COAG Road Reform Plan Evaluation of Options paper and include: The road network that was modelled is considered broadly representative of the overall road network, however, the actual variation of costs of road provision that vary across jurisdictions were not modelled. Detailed road usage estimates were not available and therefore the results should be considered representative of expected aggregated (Australia wide) outcomes. Road agencies were assumed to not be budget constrained for the purposes of cost estimation. Cost estimates were only available for sealed roads. The net benefits of funding and expenditure reform should be considered representative of expected aggregate (Australia wide) outcomes. These assumptions and limitations should inform more detailed assessment of costs and benefits and the implementation of reform options. The implementation issues that will need to be addressed in the next stage are discussed in Section 7 of this report. 9 Terms of Reference for the CRRP Project Board, page 1. A complete list of Project Board members is attached in Appendix A. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 11 The development of options considered by the Feasibility Study has been guided by a number of principles – See Box 2. Box 2: Principles guiding the Feasibility Study The Feasibility Study options should: 1. support the delivery of a national seamless economy 2. support efficient provision and maintenance of roads 3. support productive and efficient use of roads 4. support staged implementation of recommended reforms, where practical difficulties preclude near term implementation 5. be implemented having regard to the impacts on all road users and other affected parties 6. not foreclose or be conditional on possible additional future reforms in the road industry. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 12 3. Consultation This section outlines how stakeholders were engaged during the CRRP project. The key messages from industry are summarised below: Industry message 1: Industry will only support pricing reform that is linked to complementary funding and expenditure reforms that will demonstrably deliver productivity by incentivising road providers to be more responsive to the needs of heavy vehicle users. Industry message 2: Industry will benefit from certainty in the regulatory environment, particularly in relation to pricing changes where uncertainty creates risks for doing business and impact upon investment decisions. Any new arrangements for heavy vehicle pricing would require a transitional period. Industry message 3: Industry experiences a range of approaches to road service delivery across local and state jurisdictions. In general, heavy vehicle road users accept that they should ‘pay their way’. They are prepared to meet efficient costs incurred in improving service levels. Industry message 4: Industry acknowledges that some operators are advantaged under the existing cross-subsidies where for a given class of heavy vehicle, registration charges are the same regardless of distance travelled, mass carried or type of road used. Industry message 5: Industry recognises that the use of local, regional and rural roads by heavy vehicle users can impose significantly greater costs than major freeways and arterials. Industry has indicated that heavy vehicle traffic on those roads should not be disadvantaged under a more direct charging regime. CRRP Finding 1: Continuing engagement with industry and other stakeholders is essential to ensuring the success of the next stage of heavy vehicle road reform. 3.1. How did the CRRP project engage with stakeholders? The CRRP Project Board has released a number of papers on relevant issues, met with government and industry stakeholders, and conducted industry forums to consult on the matters considered over the course of the study.10 The CRRP Industry Advisory Group (IAG) was set up to give industry a platform to provide its views throughout the study to the team and Project Board and to provide a forum for findings from the Feasibility Study to be discussed. Input was also sought from a number of industry, economic and finance experts, to ensure that the analysis drew upon the best information and expertise available. In June 2011, the Project Board released a consultation paper setting out its preliminary findings, for the review and comment of stakeholders.11 To explain the preliminary findings and get direct feedback from stakeholders the Project Board conducted 11 forums around Australia. These were held in Sydney, Adelaide, Launceston, Dubbo, Perth, Townsville, Brisbane, Canberra, Melbourne, Darwin and 10 All of the consultation papers and documents can be found at www.roadreform.gov.au. 11 COAG Road Reform Plan, Preliminary Findings Consultation Paper, 27 June 2011. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 13 Mount Gambier. Twenty-eight written submissions were also received. Between the forums and written submissions, a wide range of stakeholder views were obtained. During the last 18 months, members of the Board and project team members gave presentations at over 20 conferences and seminars on the project progress and work to date. The information and opinions obtained from submissions and other consultation activities has been used to inform the development of the final findings and recommendations. 3.2. What were the key stakeholder messages? 3.2.1. Trucking associations The Australian Trucking Association (ATA) identifies itself as the peak body representing the trucking industry. The ATA strongly opposes more direct pricing using technology and has put forward a ‘fuel only’ pricing option, which was included in the Feasibility Study analysis. It suggests the fuel-based option is the most cost effective to implement due to absence of technology costs, minimal administrative costs and a low regulatory burden on industry. The ATA supports cross subsidies and states that the industry sees no need to repeal the ‘welfare inducing’ policy. The ATA does support pricing reform and believes that COAG’s first reform should be of the supply side agencies that deal with road provision and providing more access. The ATA suggests that “if the government can reform this important role in road provision, the heavy vehicle industry can improve its capability for efficiency and productivity”. 3.2.2. Other associations, excluding road transport associations Stakeholders including freight and logistics councils, rail and bus associations, automobile associations, farmers’ federations and various other livestock carriers voiced a broad range of views related to pricing reform. Rail associations and some freight and logistics councils supported a direct pricing scheme because in their view it eliminates cross subsidies and promotes competitive neutrality with other modes of transport. However, the bus industry raised the issue that buses and coaches should be differentiated from trucks as they generate substantial social and environmental benefits that are not as relevant for trucks. Farmers’ interests and livestock carriers rejected direct pricing and any form of mandated technology required for such a scheme. These stakeholders operate in rural and remote areas where the marginal cost of the use of rural roads by heavy vehicles is the highest. The farmers’ federations opposing technology believe it will be a cost burden12 to farmers who do not operate their trucks full time and who already pay registration and rates. It was also suggested that the in-vehicle technology required for more direct pricing should not be used as a compliance tool. There is general support for heavy vehicle revenue flowing back to the road networks where there is greater transparency and accountability in how that revenue is invested. However, submissions called for further investigation of funding models and methods of data collection other than through direct pricing to support fund distribution. The National Farmers Federation (NFF) suggests “… a significant shift would also be required in the expertise and culture of road asset managers, to move away from a philosophy of protecting road assets to a situation where investment in road assets occurs in response to their use and strategies to maximise productivity”. 12 In fact more direct pricing removes the concerns of lumpy registration and rates payments. This appears to not have adequately been explained in CRRP consultation with industry. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 14 3.2.3. Owner/drivers and transport companies The majority of feedback from owner/drivers was received in the nationwide forums. There was strong support for a fuel-only pricing option due to administrative simplicity and the fact that fuel indexation is recognised in a number of existing cartage contracts. A number of submissions from the industry called for a harmonised review process to avoid confusion. The 2010 Henry Tax review, the introduction of the National Heavy Vehicle Regulator, Infrastructure Australia’s National Land Freight Strategy paper,13 the proposed carbon tax and other heavy vehicle initiatives have caused confusion amongst the industry which became evident during the CRRP forums. It was suggested that heavy vehicle reviews and proposed legislation should be presented to the industry in a holistic manner. 3.2.4. Suppliers of in vehicle technology Suppliers of technology, such as Fleet Effect support a more direct pricing scheme. Fleet Effect has requested that any technology rollout is done in parallel with existing regulatory reform processes such as electronic work diaries. Fleet Effect also suggested that any stand alone technology for distance/location charging could integrate with existing private systems and secure economies of scale and scope. 3.2.5. Local governments Local government in Australia plays an important role in the provision and maintenance of the road network for heavy vehicles, particularly in relation to ‘first and last mile’ access. Local government supports a direct charging scheme that would see revenue flow back to road providers. They are supportive of a charge using dynamic mass measurement and a charging system that is simple and transparent. Local governments are concerned with who will bear the burden of compliance and administrative costs and have called for more work to be done on how direct funding will work in practice. Funding is of particular concern as many local government roads have low heavy vehicle traffic and are not designed to carry high productivity vehicles. 3.3. Continued engagement with industry The reforms contemplated by the CRRP Feasibility Study are primarily aimed at improving productivity of the road freight sector. However, road reforms will have a significant impact on the road freight industry if they are implemented. A continuing dialog and engagement needs to be maintained with industry and other key stakeholders to ensure the success of any future road reform. 13 Infrastructure Australia, National Land Freight Strategy: Discussion Paper, 2011. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 15 4. Why reform arrangements for heavy vehicle charging and funding? This section provides an overview of the challenges facing the road freight industry and why there is a need to reform of heavy vehicle charging and funding. The following is a list of the findings followed by discussion of the reasons for these conclusions. CRRP Finding 2: Current road charging methods, funding flows and incentive arrangements for heavy vehicle users and road providers inhibit the efficient use, investment, operation, maintenance and management of road transport infrastructure. This in turn imposes avoidable costs on industry, governments and the community. In particular, current arrangements impede: the ability to minimise the whole of life costs of roads the removal of restrictions on access to the road network for high productivity vehicles at both state and local government levels efficient choices in the use of roads by heavy vehicles that reflect the true costs of their provision. CRRP Finding 3: Achieving the benefits of reform requires implementation of a new set of arrangements for both funding and charging that replaces the existing arrangements for heavy vehicles. The new arrangements should allow for a transition to more direct charging of heavy vehicles in return for measures that improve productivity including lower heavy vehicle operating costs where the benefits to the community exceed the costs. CRRP Finding 4: More efficient provision and use of roads that result in productivity benefits including lower heavy vehicle operating costs is encouraged by: CRRP Finding 5: 4.1. providing information to heavy vehicle road operators on the cost of road use through more direct charges and to road providers on the requirements for road infrastructure to meet the freight task (pricing reform) creating certainty of sufficient, long term funding by establishing a direct flow of heavy vehicle charge revenue to road providers for investment, operation, maintenance and management of the road network (funding and expenditure reform). A package which combines funding and more direct pricing reforms is expected to yield a net present value of between $5 and $7 billion dollars. The expected improvements to productivity from heavy vehicle road reform result from the interaction between reforms to heavy vehicle charges and reforms to funding of road services for heavy vehicles. These are intrinsically linked. The challenge to achieve productivity in the road freight industry The transport industry is critically important to the Australian economy. Transport costs have a direct impact on the cost of all goods and services, and so impact on business competitiveness both domestically and internationally. Key factors limiting heavy vehicle productivity include: COAG Road Reform Plan – Final Feasibility Study Report for COAG | 16 the physical capabilities of the existing road network and associated vehicle standards that limit vehicle mass and volume capacity regulatory access impediments to road access by higher productivity vehicles regulatory operational safety constraints. The physical design of a road imposes limitations on the loadings and dimensions of vehicles using that road. In general the system provides a capacity and right of access for those vehicles designated as general access vehicles. In many instances increased payloads or vehicle dimensions would yield significant economic and commercial returns. However, most of the current road network is not designed for these larger vehicles. Network constraints that result in regulation to restrict heavy vehicle access may only occur on part of the desired route of a vehicle which impacts its capacity to operate efficiently. This is sometimes referred to as the ‘first or last mile’ problem in relation to local government roads, however, these problems can occur on all parts of the network. The current approach to road planning and investment seeks to satisfy a number of objectives including improving road safety and satisfying light vehicle demands in addition to promoting heavy vehicle related productivity. Inevitably with limited funds available for road investment, many projects that could deliver net economic benefits to society cannot be undertaken. 4.2. Improving productivity of the road freight industry The value of improving productivity and efficiency has been recognised by governments, who in conjunction with industry, have embarked on reforms focusing on benefits from national harmonisation of regulation and heavy vehicle pricing and getting the most out of the existing road network. These reforms include: The establishment of a single national law and National Heavy Vehicle Regulator Performance Based Standards (PBS) – a nationally agreed process of safety and infrastructure protection standards, for assessing new and safer ‘innovative’ heavy vehicles as an alternative to the existing prescriptive system for regulating heavy vehicles 14 Incremental pricing trials for heavy vehicles to facilitate productivity initiatives using more direct pricing of heavy vehicles and maximising the existing capacity of the network 15 Ongoing changes to current heavy vehicle pricing arrangements to support various productivity initiatives. Through these reform efforts Australia has achieved significant gains in road freight transport productivity which has lead to real declines in the cost of transport. The BITRE estimate that heavy vehicle productivity improved on average approximately 6.24 per cent each year between 1971 and 14 Information Bulletin Performance Based Standards Road Network Classification, Queensland Government Department of Main Roads, p 1. 15 Incremental pricing to unlock heavy vehicle productivity - National Transport Commission (NTC) 2009. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 17 1991.16 Between 1991 and 2007 heavy vehicle productivity improvements slowed to 3.53 per cent per annum. Future increases are likely to slow even further in the absence of reform.17 The current heavy vehicle charges are based on the PAYGO (or Pay As You Go) approach, which is designed to achieve expenditure recovery at an aggregate level. PAYGO recovers heavy vehicles’ share of road expenditure, including capital expenditure, in the year it is incurred. The original policy objective of the current system was simply to set uniform national heavy vehicle charges, primarily to prevent revenue distortions from owners ‘jurisdiction shopping’ for the best registration fee. While the current pricing framework has largely met its objectives, it was never intended to send the precise pricing signals and revenue incentives to: minimise the whole of life costs of roads remove restrictions on access to the road network for high productivity vehicles at both state and local government levels encourage efficient use of roads by heavy vehicles that reflect the true costs of their provision. There is a fundamental disconnect between the collection of heavy vehicle road user charges and the allocation of funds required to maintain roads for heavy vehicle use and investments to promote a more productive heavy vehicle industry. The Commonwealth collects revenue from the fuel based road user charge and the states collect registration revenue from heavy vehicles. These sources of revenue are intended to recover the historical costs of road provision, however, there is no transparent flow of funds back to the road provider responsible for covering the cost of heavy vehicle road use. In the absence of guaranteed funding sources there are limited incentives for road providers to grant access to higher productivity vehicles and insufficient incentives to optimise network maintenance and investment to improve heavy vehicle productivity. This is particularly so for the majority of local governments which do not currently directly receive any component of the current heavy vehicle charges.18 Given the increasing freight task, there are significant concerns that the current system of road provision and charging for heavy vehicles is not sustainable for the future. Governments now recognise that there are limits to obtaining productivity gains under the current system of heavy vehicle pricing and funding. The CRRP Feasibility Study investigated the role that reforms to heavy vehicle charging and funding might play in promoting a more productive and efficient transport industry. 4.3. The role of road reform in improving productivity The CRRP Feasibility Study has highlighted the importance of providing infrastructure that meets the needs of its users in a cost effective and sustainable way. While acknowledging the complexities 16 Bureau of Infrastructure Transport and Regional Economics (BITRE), Report 123 - Truck productivity: sources, trends and future prospects, p 19. 17 Bureau of Infrastructure Transport and Regional Economics (BITRE), Report 123 - Truck productivity: sources, trends and future prospects, p 19, 48-56. 18 Western Australian and Tasmanian local governments have some funding allocated from revenue collected from heavy vehicle registration charges. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 18 involved in providing roads for both heavy and light vehicles, there is a need to transform the road infrastructure industry to be more customer focused, particularly for heavy vehicles. Like any industry, heavy vehicle users should expect to receive a clearly defined service for the fees paid. This means that there is a need to create a mutual obligation on heavy vehicle users to pay the costs directly incurred from the use of roads and on road providers to provide roads that meet predetermined service levels. There is also an ongoing obligation for governments to fund road services that promote social objectives beyond those that a commercial road owner would provide (commonly referred to as a community service obligations or a CSO) and to ensure sufficient funds to deliver the economically efficient level of road maintenance and investment for all road users. There are two dimensions to the role of road reform in improving productivity: user pays - providing information to heavy vehicle road operators on the cost of road use through direct charges and to road providers on the demand for road infrastructure to meet the freight task (pricing reform) the money follows the truck - creating funding certainty from establishing a direct flow of heavy vehicle charge revenue to road providers for maintenance and investment in the road network (funding and expenditure reform). The costs and benefits of these aspects of reform are discussed in the following sections. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 19 5. The feasibility of mass, distance and location based charges This section provides an overview of the feasibility of options for more direct heavy vehicle charging. The findings arising from consideration of these matters are: CRRP Finding 6: Based on current estimates the net present value of more direct pricing reform alone is estimated to be low or negative. This reflects the existing productivity of the trucking industry and the expected costs of technology, enforcement and compliance, as well as the limited route and vehicle choices available to operators. However, further advances in the cost and nature of technology may change this finding. CRRP Finding 7: Some incentives for more efficient use of the road network occur as a response to information about the cost of road use. CRRP Finding 8: More direct pricing of heavy vehicles, taking into account mass and using actual location (road type) and actual distance travelled is technically feasible. CRRP Finding 9: The high cost of technology to measure mass in real time means that it is not an economically feasible basis for charging all heavy vehicles at this time. CRRP Finding 10: The direct economic benefits from pricing alone are greatest when heavy vehicle charges that take into account the mass carried, actual distance travelled and actual location (road type) for a particular trip are applied to the largest and heaviest segments of the fleet. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 20 5.1. What pricing options have been considered? The Feasibility Study examined a number of alternative combinations of mass, distance and location charging parameters against a base case representing the maintenance of the status quo arrangements. See Table 5.1. The options considered and the level of analysis undertaken reflects the purpose of the study to understand the feasibility of a range of more direct pricing options for heavy vehicles. Table 5.1: Pricing model options Model options Explanation Base case: Status quo The current road charging system comprising a fixed registration charge levied by the states and territories and a variable charge from a component of the diesel fuel excise. Option 1: Fuel-based distance price A charge collected through fuel excise taxes as a proxy for pricing for distance and mass. Option 2: Kilometre-based distance price A charge based on a system that measures the actual distance travelled. Option 3: Distance-locationbased price A charge based on a system that measures distance travelled taking into account the location (road type) of the vehicle. Option 4: Mass-distance-based price A charge based on a system that measures distance travelled taking into account the actual (real time) mass of the vehicle. Option 5: Mass distancelocation-based price The road price is based on a system that measures distance travelled and actual vehicle mass (real time) taking into account the location of the vehicle. The pricing model options were chosen to be examined against the charging principles that were developed early in the Feasibility Study process. See Box 3. Box 3: Charging principles Heavy vehicle charges should: 1. recover the efficient cost of providing, maintaining and operating roads for use by heavy vehicles. 2. be forward-looking and provide incentives for efficient and effective ‘life-cycle’ road provision and maintenance. 3. be determined with reference to: the marginal cost of road provision, maintenance and operation the transaction costs associated with the charge the extent that heavy vehicle road users are able or likely to respond to price signals minimising distortions to the efficient pattern of use of the road network. 4. be developed through a continuously improving transparent and public process. 5.2. What costs are associated with heavy vehicle traffic? Roads carry both heavy and light vehicle traffic. However, a significant component of the costs of providing, operating and maintaining roads goes towards catering for heavy vehicle road use. The costs to be recovered that relate to heavy vehicle use of the road network include an appropriate allocation of COAG Road Reform Plan – Final Feasibility Study Report for COAG | 21 the total costs of providing the road asset (common costs) and the particular costs associated with heavy vehicle use of the network (marginal costs). These costs are strongly linked to the distance travelled by a heavy vehicle and measures of a vehicle’s ‘location’ and ‘mass’. Critical cost factors affecting pavements and bridges relate to the expected heavy vehicle mass and the number of axle passes across the road or bridge.19 The dimensions of roads such as lane widths, gradients of roads, overtaking lanes and local street alignments are also designed, in part, to reflect expected heavy vehicle road use. Traffic volumes, which principally comprise light vehicles, largely determine road capacity, whether multiple carriageways are needed and much of a roadway’s traffic management and street furniture needs. Road construction costs are also affected by the need to address issues such as local amenity and safety concerns, some of which arise from heavy vehicle operation (e.g. truck parking bays, passing lanes and road gradients). The costs associated with a road also vary with external factors including the terrain, soil types and rainfall that need to be considered in its design. 5.3. What are the benefits of more direct heavy vehicle charging? The existing heavy vehicle charging scheme recovers costs associated with heavy vehicle traffic on the network. It does this using two tools: a ‘Road User Charge’ (RUC) collected through the fuel excise and a heavy vehicle registration charges. Moving to more direct heavy vehicle charging involves replacing the existing scheme with a variable usage charge calculated using the mass of a heavy vehicle and the distance and location (road type) of a trip. Better reflecting the costs of heavy vehicle traffic in a more direct usage charge is expected to deliver benefits by encouraging: the use of more efficient routes by heavy vehicles where there is a choice available, as the charge for using a road is more directly attributed to the cost of a particular heavy vehicle trip a more efficient heavy vehicle fleet mix, as operators over time make vehicle choices based on minimising the total heavy vehicle charging costs of road use. The expected benefits from changing heavy vehicle behaviour include lower total heavy vehicle operating costs for a given freight task and improvements in road safety from having fewer, more productive vehicles on the road. Some technology that could be used for a more direct charging system will also collect information on road freight movements which could be used for fleet management as well as other purposes. The size of these benefits will be affected by the design of the charge, the physical opportunity to change behaviours and the likely responsiveness of road users to changes in price. For example, rural operators and public transport providers will often have no alternative vehicle or route choice and this will need to be considered in any pricing scheme design. These factors are discussed further below. 5.3.1. Design of the charge Providing a closer link between road use charges and costs incurred by heavy vehicle road use will in principle increase the benefits. However, at some point the administrative costs and complexity of the charging system will result in a reduction in benefits. For this reason, the actual benefits will be dependent on striking the right balance between providing price signals, without creating a system of charging that is too complex and costly. 19 In addition, axle spacing and other factors are important for bridge and other structure design. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 22 5.3.2. Physical opportunity to change behaviour The expected benefits from changes to behaviour requires viable substitutes for existing routes and vehicles and sensitivity to the charge as a component of the total costs faced by a vehicle operator. In many instances (e.g. some rural, local and arterial roads) there may not be a viable alternative route meaning that heavy vehicle behaviour will not change and so the benefits (from reduced road wear costs) of direct pricing on those roads may be small. This observation might justify not having differentiated (i.e. cost reflective) charges on some routes so long as sufficient funding is provided to the road provider responsible for that route to maintain the road at an appropriate standard for the heavy vehicles using those routes. Consideration of the appropriate prices and levels of services was not undertaken as part of the feasibility study. 5.3.3. Likely responsiveness of users to price To investigate the likely change in behaviour from road pricing changes, the Feasibility Study undertook a detailed assessment of the responsiveness of heavy vehicle users to changes in price. A study was undertaken to investigate the likely heavy vehicle road use demand responsiveness of changes in heavy vehicle charges, under a number of alternative pricing options.20 The study involved the estimation of freight demand elasticities from data collected via a stated preference survey of industry participants. The results indicate that: freight travel on freeways and arterial roads is less responsive (almost three times less) to changes in heavy vehicle charges than travel on local roads the opportunity to use an alternative route is particularly limited for local roads (only 11 per cent of travel on local roads could be done on an alternative route, compared with almost 25 per cent for freeways) the opportunity for vehicle switching was also found to be low (a 1 per cent increase in heavy vehicle charges was found to only decrease the number of vehicle kilometres by at most 0.18 per cent). A key conclusion of the study was that the opportunity for both route and vehicle switching in response to location based pricing was likely to be limited. This likely reflected operational constraints, which mean that opportunities are already limited. 5.3.4. Community service obligations Consideration of more direct pricing raises the issue of who could be disadvantaged by reforms. In particular, the use of location as a charging parameter raises two principal concerns. Firstly, more direct heavy vehicle charges could cause some users of certain road network segments to have higher overall costs relative to the costs they would incur under the current charging system. A material increase in transport costs may in turn increase the cost of living and cost of goods for parts of the Australian community. The degree of the impact may necessitate consideration of overt subsidies and other transitional arrangements. 20 National Transport Commission, Road Freight Demand Elasticities: Stage 2, GHD Meyrick and NERA Economic Consulting Consultancy Paper, 2011. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 23 Secondly, linking road funding to revenue raised through heavy vehicle charges could seriously impact funding of low volume roads required to maintain current service levels. This would occur if ongoing maintenance of these roads could not be funded through revenue from heavy vehicles combined with funding from other sources. However, as long as the overall level of funding to roads is maintained through transparent community service obligations there should be very limited impact to current service levels on low use roads. 5.4. Estimating the benefits of pricing reform alone Figure 5.1 shows the estimated potential benefits21 for each high level pricing option examined by the Feasibility Study, for the whole of fleet and for two groupings of the largest and heaviest segments of the fleet. The benefits estimated are the: avoided cost of road wear from more efficient use of the existing road network changes in vehicle operating costs from switching to larger, more productive vehicles, partially offset by potential increases in kilometres travelled potential fleet management operator benefits, from the use of information provided by in-vehicle units safety benefits from reduced vehicle kilometres and from the use of in-vehicle technology, resulting in lower crash costs and reduced injuries and deaths. 21 In all cases the analysis assumes a 30 year project life and uses a discount rate of 7 percent. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 24 Figure 5.1: Gross benefits from charging options implemented for selected segments of the fleet ($2011 present value) The results highlight that the largest estimated pricing benefits arise from charging options that include a measure of location and dynamic mass in addition to kilometre-based distance charges (i.e., options 3, 4 and 5). The fuel based distance charge (option 1) and kilometre based distance charge (option 2) have the lowest potential pricing benefits. This is because these options do not necessarily reflect the costs associated with different locations, and so provide less information on the costs of a particular heavy vehicle trip and reduce the likelihood of behavioural shifts. 5.5. Options to collect information for more direct road use charges The cost of introducing more direct road use charges is critically dependent on the information capabilities required to support the desired charging system. In turn, the information framework will also have an effect on the benefits generated. Options for collection of mass, distance and location information are outlined below. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 25 Table 5.2: Information collection options Component of charge Options to collect information Mass using technology to measure axle mass in real time operator nominated mass measures of mass that do not vary by the load of a trip (e.g., average gross mass). measurement of the actual distance travelled for every road user the use of an approximation for distance (e.g., fuel consumption or nominated distance) a measure of distance that does not vary by trip (e.g., average distance or capped distance). electronic tags on road entry and exit points satellite and other communications technology user nominated (e.g., for plant or mine vehicles, council vehicles, dedicated location vehicles, etc). Distance Location 5.5.1. Charging on the basis of mass Measuring mass in real time requires the installation of an in-vehicle unit capable of measuring gross vehicle or axle mass at any point in time. The feasibility study found that while technology is available to do this, the cost of such units including installation range between $550 and $1,050 per vehicle per annum for a rigid heavy vehicle, and between $850 and $2,700 for an articulated vehicle per annum. These costs far outweighed the marginal benefits. The high cost of technology to measure mass in real time means that it is not an economically feasible basis for charging all heavy vehicles at this time. The alternative approaches to estimating the mass of a vehicle are expected to be less costly than using technology to measure mass dynamically. For nominated mass, these are the costs associated with developing a compliance and enforcement regime to provide sufficient incentives for operators to nominate mass accurately.22 Given the size of the road network, and the remoteness of many vehicle trips, developing a sufficiently robust compliance and enforcement system of nominated mass has significant costs. These costs will also depend on the risk assessments of the road providers. For measures of mass that do not vary by load, the compliance costs are considered to be relatively small and the most economically feasible approach to heavy vehicle charging for all vehicles at this time. 5.5.2. Charging on the basis of distance The principal advantage of a fuel based charge over a system than measures actual distance travelled using technology that also collects location information, is that it is low cost. However, the study has found that using actual distance travelled is likely to be preferred to using fuel consumption as a proxy for distance travelled because: 22 These costs are expected to be higher than the compliance and enforcement costs needed for alternative approaches. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 26 charges more closely reflect actual road use in a way that is similar to how other utilities are charged the costs of providing and maintaining roads are better reflected in a direct charge rather than fuel use direct information on vehicle road use is collected and can be used for road planning and investment decision-making direct and transparent information is available to road users about the costs incurred from road use. The likelihood is that the road user charge (RUC) component of the fuel charge plus the proposed carbon tax may be greater than the total fuel excise. Either an additional tax above the current excise would need to be imposed on heavy vehicles or fuel excise would need to be increased. The current rebate system is relatively simple but compliance could be compromised with the substitution of an additional tax for the current rebate. Given the current system collects the majority of road user charges through a fuel based road user charge it is likely that this system would be maintained through any transition to more direct heavy vehicle charging regime or for the smaller and lighter segments of the fleet. 5.5.3. Charging on the basis of location Charging a different amount for every road to reflect the differences in marginal costs of each link in a network is neither feasible nor desirable. It would create an overly complex charging system. However, there may be merit in developing different charges for each of the principal road type categories used by road providers. For example:23 arterial roads (including freeways), which generally connect major activity or population centres, or which have other economic, tourism, strategic or other significance. These types of roads are also referred to in some jurisdictions as state roads, classified roads and Crown roads local roads, which provide access to land and do not have the significance of arterial roads. Community service obligations (discussed above) are also relevant in considering charging on the basis of location. 5.5.4. Technical feasibility The choice of approach should reflect the least cost technology given the overall package of information required to achieve the anticipated benefits and associated enforcement costs. Analysis of alternative technologies suggests that an electronic tag system is likely to be cost prohibitive because of the number of gantries that would be required to monitor the entire road network.24 This is a consequence of both the length and interconnectedness of the road network throughout Australia. The analysis indicates that charging on the basis of actual vehicle mass, the distance travelled and location of the vehicle is technically feasible in most conditions. Box 4 shows examples of technologies that are used both overseas and within Australia that measure and store relevant mass, distance and location information in real time. These could be used to support such a charging system if warranted. 23 ARRB, (2010), Cost Implications of Incremental Loads on Road Pavements, Austroads Project No. AT1394, March, pp 121-123. 24 Austroads, (2011), Feasibility Study: Heavy Vehicle Charging in Australia, AP-R384/11, June. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 27 Box 4: Technologies available to measure key pricing parameters Hubodometer – measures distance using a device on the vehicle axle to count the number of rotations. Tachometer – measures distance by recording working hours and speed through the vehicle’s gearbox. Automatic Number Plate Recognition – measures distance and location without the need for an invehicle unit by using roadside equipment and vehicle databases. Dedicated Short Range Communication (i.e. electronic tags and gantries) – measures distance and location by using on-board equipment to communicate with roadside equipment. Global Positioning System (GPS)/Cellular Network/Global Systems for Mobile Communications (GSM) – measures distance and location by using GPS and matching data with network maps. Pressure sensors – measures mass by using an in-vehicle unit to monitor the pressure caused by the mass of the vehicle. 5.6. Estimated costs of implementing more direct pricing options Table 5.3 sets out the technology assumptions made for the purposes of determining costs for the Feasibility Study. It will be necessary to undertake a more detailed assessment of costs and business system changes if there is a decision to support an alternative charging approach. If this results in a significant deviation in costs then the appropriateness of the program should be re-evaluated. It should be noted that where estimates were calculated for implementing more direct charging for only a subset of the heavy vehicle fleet it was assumed that the remainder of the fleet would be charged as for the existing regime. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 28 Table 5.3: Charging technology assumptions Charging option Technology Assumption Option 2: Distance Hubodometer / odometer Option 3: Distance-Location GPS Option 4: Mass-Distance GPS and on-board mass Option 5: Mass-DistanceLocation GPS and on-board mass Figure 5.2 sets out estimated costs for each option for the whole of fleet and largest and heaviest fleet segments. The key costs that have been quantified are: the cost of in-vehicle units (as required by the pricing option), including installation costs ongoing communications costs costs of monitoring and enforcing compliance with the charging regime additional registration, administration and billing costs. Figure 5.2: Estimated costs for selected segments of the fleet ($2011 present value) Costs vary due to the number of vehicles in each segment. Table 5.4 lists how the costs of direct pricing vary by the numbers of vehicles in the scheme. The highest cost options are mass-distance and mass-distance-location charges applied to the whole heavy vehicle fleet reflecting the significant costs of installing dynamic mass in each vehicle. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 29 Table 5.4: Costings used to assess feasibility Estimated Cost (per annum per vehicle unless otherwise stated) Cost categories Detailed description Cost driver In-vehicle unit GPS unit and installation Vehicle numbers Rigid vehicle Vehicle/trailer numbers and axle group numbers $550-$1050 Multi articulated vehicle Vehicle/trailer numbers and axle group numbers $1250-$2700 Single semi-trailer Vehicle/trailer numbers and axle group numbers $850-$1600 Enforcement and infrastructure cost Level of compliance Registration look-up Vehicle numbers Dynamic mass technology25 Compliance and billing 5.7. $230 $62.5m (whole fleet per annum) $18 Feasibility of implementing more direct heavy vehicle charges The net economic costs of the pricing options considered in the Feasibility Study are shown in Figure 5.3. The results show that the net economic benefit or present value of more direct pricing alone is estimated to be low or negative and that there is a small economic benefit in introducing a fuel based distance price. The costs of implementation of technology are not trivial and while there are some benefits from changes in heavy vehicle operator behaviour in response to price incentives the opportunities for changing routes or vehicle type are limited and fall below the current costs of implementation. 25 Dynamic mass is included separately as it requires additional technology and related costs compared to a distance and location charge which only requires the more cost effective in-vehicle GPS/GSRM units. Dynamic mass costs also vary by vehicle type as measurement technology must be fitted to each axle group. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 30 Figure 5.3: Net present value of introducing more direct road use charges for selected segments of the fleet ($2011 present value) Despite the costs involved, examples exist where technology has been introduced for the purpose of heavy vehicle charging. International examples are useful for understanding the technical feasibility of direct charging, however, the nature of overseas markets for road transport and the contexts of implementation are very different to those in Australia. In Germany an electronic road user charging system with rigorous compliance and enforcement was introduced only on major road routes, due to the high proportion of use of roads by operators with vehicles registered in another country. The large amount of ‘through traffic’ meant that it was difficult to administer a permit system to collect revenue and a large number of commercial road users were not paying for road use. In this situation it was therefore considered appropriate to make a large investment in a new system to address revenue leakage issues. In New Zealand, an electronic road user charging system is offered on an opt-in basis, where there is some industry discontent with the legacy system, which involves the use of mechanical hubodometers. In New Zealand, the electronic system is offered by a third party provider who provides a number of commercial services in addition to charging, which reduces implementation costs. The existing COAG Road Reform Plan – Final Feasibility Study Report for COAG | 31 compliance and enforcement regime was used, which meant that additional costs were not incurred in the introduction of the eRUC alternative. While this analysis has focused on considering the use of technology to facilitate the introduction of mass, distance and location charging for heavy vehicles, there might be other policy and operational benefits from introducing the technology required to measure mass, location and distance of heavy vehicles. See Box 5. However, these additional uses of the technology and potential benefits (e.g. safety benefits from using in-vehicle units to monitor compliance with fatigue laws) have only been partially quantified. The study has endeavoured to ensure that potential benefits from technology are not counted more than once and that the staging of technology implementation is properly justified. The Feasibility Study acknowledges that industry’s concerns regarding the privacy implications of in-vehicle technology and increased monitoring of compliance impact support for more direct heavy vehicle charging. Other applications of telemetry, for example, the IAP scheme and the New Zealand e RUC, which monitor the distance travelled and location of heavy vehicles have specifically excluded extensions of the technology to other regulatory purposes. These considerations should be balanced against the potential for both economic and regulatory benefits from multiple applications available using the same in-vehicle technology. Box 5: Additional potential opportunities from the use of in-vehicle units to measure mass, location and distance Introducing a system of more direct heavy vehicle road use charging, based on the mass, distance travelled, and location of heavy vehicles on roads requires the use of technology which monitors all of these parameters in some way. If real-time data is collected, then the information can be used for a number of non-charging related purposes including: monitoring vehicles carrying more than general access mass limits in certain approved circumstances, in line with the intelligent access program ensuring that heavy vehicles are not overloaded, thereby allowing operators to load vehicles more efficiently within existing limits as part of operator fleet management providing real time inventory data and, in the case of refrigerated shipments, temperature to customers providing security support and engine diagnostics. Any system of charging for heavy vehicles should be sufficiently flexible so as to not foreclose on opportunities to develop more targeted charging systems that use dynamic mass measurement where the incremental benefits outweigh the costs. Although the findings of the Feasibility Study are that gross benefits of pricing are estimated to be less than the costs of implementation, introducing more direct pricing is a recommended part of a package of pricing and funding and expenditure reforms. The role that more direct pricing could play in a new set of arrangements for heavy vehicle charging and funding is discussed in the next section. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 32 6. Feasibility of alternative funding and expenditure arrangements This section provides an overview of the feasibility of funding and expenditure reforms to promote investment, operation, maintenance and management decisions to ensure productivity benefits. The findings from consideration of these matters are: CRRP Finding 11: The most significant economic benefits are expected to be generated if incentives are created for road providers to promote the efficient long term investment and effective operation, maintenance, management and use of road infrastructure. CRRP Finding 12: Incentives for economic efficiency can be created for both road providers and heavy vehicle road users by creating a direct link between the costs incurred from heavy vehicle road use, more direct road use charges and the funds received by the providers of roads. 6.1. What funding and expenditure options have been considered? Alternative funding and expenditure models have been examined as a means to providing improved incentives for more efficient maintenance and investment decision-making. The possible models examined in the feasibility study were: a departmental model – this would retain the existing model of road supply but would improve funding certainty and strengthen accountability and transparency frameworks a dedicated road fund or funds – this would operate as an independent road fund or funds to oversight the distribution of funds and the accountabilities associated with their distribution a public utility model – this would bring the incentives and disciplines of a business to the provision of road infrastructure services. The funding options that could be supported under these models include: the allocation of funds based on a transparent formula transparent guidelines allocating money to road suppliers pass though of all revenue derived from a road provider’s network. These models are consistent with the suggestions made by the Productivity Commission26 and have been developed taking into account the funding/financing principles set out in the CRRP Policy Framework. See Box 6.27 Box 6: Funding and financing principles Funding should finance the efficient provision, maintenance and operation of roads to meet current and future demand. Revenue from heavy vehicle charges should be linked to heavy vehicle road expenditure. 26 Productivity Commission, (2006), Road and Rail Freight Infrastructure Pricing, Inquiry Report No. 41, December. 27 CRRP (2010), Policy Framework Reference Guide, July. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 33 Social obligations associated with the provision of roads should be explicitly and transparently defined and funded. Implementation of pricing reform options will likely impact the relative revenues collected by the Commonwealth and by state and territory governments. This is because revenue will be collected primarily on the basis of where heavy vehicles travel rather than where they are garaged. Any change in revenue shares could impact on the Commonwealth Grants Commission assessment of the state and territories’ revenue raising capacity and expenditure requirements (including for community service obligations) for the purposes of determining GST revenue. It should also be recognised that moving away from the current arrangements for revenue collection and fund flow would involve significant departure from the existing institutional and governance arrangements. The development of detailed options for this reform lies outside the scope of this study, however, by examining high level options for funding and governance reform a number of key elements for funding and expenditure reform have been identified. Further, engagement with central agencies has been initiated to define the options for the next phase of CRRP. 6.2. What does funding and expenditure reform need to address? Currently, road maintenance and investment decisions take into account a number of government objectives and priorities including, safety concerns, light and heavy vehicle needs, the availability of funds and the extent of earmarking these for ongoing maintenance funding versus capital funding. Road providers are typically funded for ongoing costs and new capital costs from different sources and some varying programs. There is often limited scope for road providers to optimally choose between maintenance and capital expenditure. This disconnection between funding and network management responsibilities exacerbates the tendency to emphasise ‘managing assets’ instead of ‘providing services’ to the road freight sector. The lack of flexibility in managing expenditure is compounded by a lack of sufficient and consistent information on national road use and costs. This means that there is little opportunity to benchmark road costs to determine whether the resultant heavy vehicle charges are reflective of efficient costs. That said, there has been considerable focus through earlier reforms on ensuring that proper investment decision-making frameworks are used to evaluate road investment decisions. To achieve increased heavy vehicle productivity and associated benefits for the Australian industry and broader community, the current funding and expenditure arrangements require substantial reform. Key outcomes under the current funding and expenditure arrangements that impact productivity are: Lack of long term funding certainty - Governments take into account a number of competing priorities in allocating funds in the budgetary process. This can result in asset management practices which do not promote long-term efficient maintenance (i.e. life cycle cost reduction) and efficient network expansion planning. Poor investment signals - Road providers currently do not receive cost reflective demand signals that reflect the need for additional efficient investment and maintenance. In addition, even if efficient demand-warranted road projects are identified, road providers may not receive funding for these investments under the current funding model. Unfunded financial burden resulting from high productivity vehicles – Allowing access for some high productivity vehicles to some roads can lead to an increased deterioration of the network which the road provider has not anticipated and is not directly compensated for. This COAG Road Reform Plan – Final Feasibility Study Report for COAG | 34 situation creates an incentive to restrict heavy vehicle access even though the benefits of improved productivity are not being achieved. 6.2.1. Lack of long term funding certainty Roads deteriorate over time due to a combination of climatic factors and road use, particularly by heavy vehicles. The deterioration results in road cracking, rutting, pavement deformation and potholes that result in a road becoming rougher. This increases vehicle operating costs. Pavement maintenance of the existing road network is managed through: routine maintenance, which addresses minor road defects and involves spot issues such as potholes, cleaning of drains, damaged road furniture, and rough patches as they appear periodic maintenance, which involves resurfacing and resealing roads to prevent water infiltration, shoulder maintenance, and addressing surface roughness rehabilitation, which involves removal and replacement of some or all of a road pavement to improve the structural condition of the pavement and improve the roughness to an acceptable level. In practice all road agencies regularly monitor road condition and plan maintenance to best manage roughness and other road characteristics to ensure safe, efficient and comfortable use of roads within funding limits. Considerable research has been undertaken on asset maintenance practices and regimes to ensure that road conditions are maintained over time. Under the current arrangements a lack of funding certainty means it is often easier to fund smaller routine and periodic maintenance rather than undertake the more costly yet efficient rehabilitation of a road. This means that some roads may receive only routine and periodic maintenance, even if the life cycle costs of maintaining a certain level of roughness over time would be less if more significant rehabilitation works were financed earlier. This directly results in increased road provision costs and/or the provision of lower services and network quality all else being equal. 6.2.2. Poor investment signals Some small scale capital investment projects that would deliver net economic benefits by facilitating improved heavy vehicle productivity may not be funded under the current funding arrangements due to a lack of clear demand signals and due to competing road funding priorities. Examples of these smaller projects include: bridge strengthening projects, where current restrictions exist for general access vehicles and to facilitate an expansion to higher mass limit vehicles projects that allow freight vehicles to avoid congested or speed-restricted road segments targeted small scale projects to expand the network for higher productivity vehicles. 6.2.3. Unfunded financial burden resulting from high productivity vehicles There are limited incentives for road providers to remove access restrictions where these could result in an unfunded financial burden. In particular, feedback from local government indicates that it is unlikely access to heavy vehicles will be improved when the main beneficiaries of granting this access are through traffic. This is largely due COAG Road Reform Plan – Final Feasibility Study Report for COAG | 35 to the fact that if access were granted in those circumstances, the local government is likely to be left with an unfunded financial burden. Case studies of local government funding and expenditure models show that local government funding arrangements do not create any significant incentives to improve access for heavy vehicles. 6.3. What are the benefits of heavy vehicle funding and expenditure reform? Improving confidence in the availability and sufficiency of funds creates benefits by allowing road providers to make better road maintenance and investment trade-off decisions. This has the potential to: lower costs of heavy vehicle operations through improved quality of existing roads facilitate maintenance and capital investments in road projects that directly benefit heavy vehicle operators by removing network constraints and facilitating more routes for high productivity vehicles. Improving the certainty of funding for road maintenance (at least for the component caused by heavy vehicle road use), and also providing flexibility for road providers to manage the lifecycle costs in a cost effective manner, is expected to result in: better incentives to increase routes available for high productivity vehicles by creating a certain source of revenue from heavy vehicle charges linked to the costs of providing route access for these vehicles improved road condition for parts of the road network as road providers make use of improved certainty of funding and flexibility of prioritisation to undertake those maintenance tasks that are likely to deliver benefits but which were not prioritised through current arrangements facilitating the most cost effective balance of routine, periodic and major rehabilitation expenditure so as to lower overall life cycle costs where road condition is generally satisfactory. Improved road conditions deliver benefits to heavy vehicle operators by lowering the cost of road use through reductions in the wear on vehicles and tyres, and lowering fuel costs. There has been considerable research into understanding the relationships between road roughness and operating costs and this research suggests that the impact of even small changes in road condition on operating cost is considerable.28 Box 7 provides a case study of how improving certainty of road funding might deliver road expenditure efficiencies. Box 7: Case Study – Cost efficiency from improving road funding certainty Most government supplied road funding models have funding cycles that fall short of the asset’s life cycle. The analysis attempted to identify situations where the level of maintenance funding was ‘guaranteed‘ for a greater period than the conventional annual or tri annual budget cycles. In 1999/2000, the Department of Main Roads in Western Australia entered into 10-year road and bridge maintenance contracts with a number of private maintenance providers. Payments were based on the 28 See BTE, (1991), The Cost of Maintaining the Australian National Highway System. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 36 achievement of performance criteria set out in the contracts. Each private maintenance provider bid to service a defined geographic area of the road network. The key purpose of the outsourcing approach was to deliver savings in the costs of maintaining the road network. It was premised principally on the benefits from providing long-term funding certainty to a maintenance provider, thereby allowing the provider to invest in equipment and undertake scheduled maintenance activities to minimise the overall lifecycle costs of road maintenance within the defined geographic area. Real savings have been reported through long-term maintenance contracts. While the approach adopted in Western Australia to achieve better funding certainty was an outsourced, long-term maintenance contract, such an approach is not critical to the achievement of the benefits. This is because it is the funding certainty rather than the outsourcing of maintenance to private providers that is the likely critical driver for the benefits achieved. Indeed there is a view that outsourcing has some other consequences for road providers. The expected benefits from funding and expenditure reform arise from: a decrease in the life cycle and annual costs of road provision (all else being equal) a decrease in heavy vehicle operating costs due to the removal of network constraints that currently restrict best use of the road network facilitating the uptake of higher productivity vehicles that are currently constrained because of an inability to fund upgrades to the network to allow expanded use of the network. Figure 6.1 sets out the expected potential benefits from heavy vehicle funding and expenditure reform and a range around these benefits under different charging options. The benefits that have been quantified do not include additional benefits from improving the efficiency of capital expenditure. Figure 6.1: Gross benefits from improving incentives for more efficient maintenance and provision of roads ($2011 present value) The results suggest that: there are potentially significant benefits from improving certainty of funding, with an associated incentive framework to drive efficiencies in road expenditure, and target expenditure in areas that can facilitate improved vehicle productivity COAG Road Reform Plan – Final Feasibility Study Report for COAG | 37 the largest potential benefits result from those pricing options that provide information on road usage and so result in funds being directed to road providers on the basis of road use29 a fuel only approach (the status quo approach) does not provide any information to direct funds on the basis of road use and is not expected to deliver any benefits compared to the alternatives a kilometre distance only approach (i.e., option 2) has some, but smaller potential benefits because of the inability to directly link funding to road use where distance is the only charging metric used. The potential benefits from improving incentives for more efficient maintenance and provision of roads are estimated to be the same across the distance-location, mass-distance and mass-distance-location charging options given that each of these provide improved information on the location of vehicles within the network. This outcome highlights the merits of a charging system that includes location, to facilitate the flow of funds to road providers on the basis of road use. The alternative options do not create the opportunity for the achievement of these potentially substantial benefits. 6.4. The options to improve incentives for more efficient maintenance and provision of roads The Feasibility Study has identified improved collection and use of information, improved governance accountability, and funding arrangements that facilitate the flow of revenue from heavy vehicle road user charges to road providers as being critical to improving incentives for efficient maintenance and provision of roads. Each of the high level funding and expenditure models examined by the Feasibility Study could be used to implement these elements. The departmental model essentially maintains the existing governance and institutional arrangements with the potential to allocate funds in a way that improves funding certainty for road providers through agreement of an appropriate funding mechanism and revenue stream to road providers. A road fund model involves establishment of an independent heavy vehicle road fund whereby all revenue from heavy vehicle charges is credited to the fund and then allocated to road providers on the basis of funding allocation guidelines.30 An important function of the fund is to establish transparent fund allocation that in principle results in: incrementally improved certainty to road providers about the level of road funding (i.e., those funds arising from heavy vehicle charges) improved certainty to heavy vehicle operators that charges paid to use roads are reinvested in the upkeep of roads and new heavy vehicle priority road investments. The key feature of a public utility model is that the incentives and disciplines of a business are brought to the provision of road infrastructure services. This is facilitated by the pass through of all revenue from heavy vehicle charges to the relevant road provider based on the use of its network. This ‘pay for service’ approach linking revenue from heavy vehicle charges to road use, should improve certainty of funding for providing appropriate roads for heavy vehicles. 29 For the purpose of the Feasibility Study it has been assumed that all communications based technology pricing options generate equal gross benefits from location information. It is acknowledged that incremental benefits exist for actual mass measurement to facilitate access, however, these have not been quantified in this study. 30 Productivity Commission, (2006), Road and Rail Freight Infrastructure Pricing, Inquiry Report No. 41, December, section 10.6. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 38 The analysis indicates that the feasibility of road reform is dependent on the assumption that improving certainty and sufficiency of funding will facilitate road maintenance expenditure and investments that lower the costs of road provision for heavy vehicle operators, and improve access for higher productivity heavy vehicles. Importantly, to the extent that funding reforms do not result in behavioural change in expenditure priorities then these benefits will not be realised. To facilitate the introduction of a new set of heavy vehicle charging and funding arrangements, foundation reform activities will need to be undertaken by road agencies to differing degrees. Foundation reforms include: improved transparency of decision making clear accountabilities through published benchmarks for provision of road services to heavy vehicles becoming more service oriented and responsive to the needs of heavy vehicle road users. A consequence of introducing direct user charges is that the revenue earned from the charges could flow to the jurisdiction within which the charges are incurred. Further, the benefits from any heavy vehicle charging and funding changes will have different implications in each jurisdiction. As a consequence, understanding these differences will be an important part of implementing any proposed reforms. How these funds flow to road providers within a jurisdiction, including local government, will also need to be considered further. Much of the existing road network is provided and maintained in order to satisfy wider community needs, and so it would be impractical to charge road users for the entire cost of roads. As a consequence, part of the cost of maintaining and expanding parts of the road network would need to be funded by government to meet a more explicit financial obligation to provide a community service. It is more appropriate for such funds to be sourced from government consolidated revenue, rather than specifically recovered through vehicle charges, to avoid sending incorrect pricing signals to road users about the actual cost of road use. To progress reform a model for implementing heavy vehicle pricing and funding reform needs to be investigated and agreed. Key elements of the model to support pricing and funding reform should address: How revenue from heavy vehicle road user charges is linked to funding for road providers? What governance and institutional arrangements are required? The requirements for nationally consistent data collection and reporting The requirements of the price setting function. The benefits identified in the Feasibility Study are achieved from introducing measures that help align expenditure priorities with the needs of the heavy vehicle freight industry. In introducing reforms it will also be critical to ensure that any regulatory burden on industry is minimised and that any new system is administratively simple and that transition to a new system avoids disruption to doing business in the road freight industry. How the models for funding and expenditure are implemented will determine the associated incentives for more economically efficient investment decision making. Possible options for implementation require consideration of the appropriate legal and regulatory regime to support the model and the associated costs and potential benefits. Funding and expenditure models that represent a radical change from the current model will require significant transitional arrangements to be put in place including engagement with and involvement of central agencies. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 39 6.5. The net benefits of introducing more direct road use charges and associated funding and expenditure reforms The greatest net benefit of funding and governance reforms supported by any required charging reform is expected to be between $5 and $7 billion in present value terms. These net benefits will be generated by introducing: more direct road use charges that provide information on the location of heavy vehicle road use but that do not measure mass in real time funding and expenditure reforms that provide incentives to use that information for more economically efficient investment decision-making. Figure 6.2: Net benefits of introducing more direct road use charges and associated funding and expenditure reforms for selected segments of the fleet ($2011 present value) The net benefit from funding and governance reforms is expected to be around $6.5 billion in present value terms while the net benefit of the supporting pricing reforms is expected to be up to negative $0.5 billion in present value terms. It is believed implementing direct heavy vehicle charging in the first instance for the largest and heaviest segments of the fleet would provide the best balance between promoting more efficient outcomes, and the costs involved. However, as greater experience is gained from introducing more direct road use charges, and as technologies improve over time, it might be that the incremental benefits of extending more direct road use charges to other heavy vehicle types increases. In the meantime, it is clear that existing arrangements for cost recovery through a combination of registration and fuel based charges should be maintained for the remainder of the fleet. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 40 The analysis indicates that more direct pricing of heavy vehicles needs to be part and parcel of broader reforms to funding of roads. There is no economic nor industry support for direct pricing alone. Any shift in charging arrangements will necessitate changes in fund flows. This will require an agreement between governments to address funding and governance reforms in combination with the required supporting direct pricing reforms. The fuel-only option generates a low net present value because there are diluted demand signals to road users and no credible information to support improved funding and expenditure reforms. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 41 7. Achieving the benefits of reform – the next phase of CRRP This section provides an overview of the anticipated work required to achieve the benefits of reform identified in the Feasibility Study. The key finding in relation to next phase of CRRP is: CRRP Finding 13: 7.1. Achieving the benefits of road reform requires a comprehensive program of work around the funding and expenditure reforms and a consolidation of the existing work on direct pricing for the next phase of CRRP. What challenges will need to be addressed in the next phase of CRRP? To progress reform a model for implementing heavy vehicle pricing and funding reform needs to be investigated and agreed. Key elements of the model to support pricing and funding reform should consider: refinement of the assumptions underpinning the Feasibility Study a mechanism by which road user revenue would be transparently linked to road funding transitional arrangements to take into account the impact on jurisdictions, heavy vehicle users and rural and regional communities economic incentives and accountabilities for road providers, including local government nationally consistent collection of data and reporting to support transparent and accountable decision making mechanisms to ensure services that promote social objectives or benefits to the broader community beyond those a commercial road owner would provide are transparently funded arrangements for appropriate price setting, including the extent of independence of the price setting body and the price setting processes and methodologies, that more closely links road use to costs options for the pricing of externalities, where appropriate, once more direct pricing has been implemented options for establishing an incremental pricing scheme and other voluntary opt-in schemes policy on the appropriate collection and use of heavy vehicle data, including for the purpose of compliance and enforcement. This policy should include consideration of privacy and confidentiality issues related to the collection of personal and commercial information appropriate business systems to minimise administration costs an effective legal and regulatory framework that provides sufficient long term funding and regulatory certainty. It should also be noted that work on current reforms, particularly the COAG Road Reform Plan has highlighted a lack of reliable data and the absence of this information is hampering analysis to support further reform. This includes information on the costs of providing unsealed roads. These information limitations will need to overcome in order to undertake more detailed costs benefit analysis required to underpin the case for reform options for implementation of possible funding and pricing reforms. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 42 Based on the findings of the Feasibility Study, to achieve the benefits of heavy vehicle road reform it is recommended that: Recommendation 1: Recommendation 2: Recommendation 3: An integrated package of pricing, funding and expenditure reforms should be pursued where benefits outweigh the costs and that takes into account that: more direct pricing of heavy vehicles without funding and expenditure reform is not economically feasible; changes to the existing system of heavy vehicle charging will have consequential impacts on funding arrangements; and transitional arrangements will be required to manage the impacts on industries and communities. The next phase of CRRP should include development of a package of reforms, where benefits outweigh costs, that support the COAG Road Reform Plan objectives and address: the mechanism by which road user revenue would be transparently linked to road funding including transitional arrangements to take into account the impact on affected groups; economic incentives and accountabilities for road providers, including local government; mechanisms to ensure services that promote social objectives or benefits to the broader community beyond those a commercial road owner would provide are transparently funded; and new arrangements for price setting. The new arrangements for heavy vehicle road funding and expenditure and direct pricing for heavy vehicles should be developed by December 2012 for consideration by COAG along with the preparation of any necessary agreements to give effect to those arrangements. Any decision by COAG to proceed to implementation will follow consideration of a Regulatory Impact Statement (RIS). COAG Road Reform Plan – Final Feasibility Study Report for COAG | 43 Appendix A: CRRP reports and supporting models The COAG Road Reform Feasibility Study Final Report draws on a number of subsidiary research reports produced by consultants and the Project Directorate. They are depicted in a structured hierarchy in the figure below, and are available for examination by COAG. STAGE 4 REPORT FINAL RECOMMENDATIONS TO COAG Hierarchy of Documents DECEMBER 2011 Friday, September 02, 2011 CRRP Preliminary Findings Discussion Paper (Board) CRRP Feasibility Study Report (COAG) (NERA) Evaluation of Options (CRRP Directorate PAD-0044) Policy Principles Pricing Options (PAD-0038) (PAD-0036; PRC-0007) Policy Framework (POL-0001) Pricing Principles (PRC-0000) Community Service Obligations (PRC-0006 / PAD-0034) Elasticities (PRC-0007A) Segmentation (PAD-0043) Road Use Data (PRC-0004) Supply-Side (Funding) Options Business Systems to Support Heavy Vehicle Charging (PAD-0037) (PAD-0039) (PAD-0040) Total Cost Base Project (PRC0001) Central Agency Discussion Paper (PAD-0035) Marginal Cost (PRC-0002) Road Fund Vs Departmental Model Analysis (PAD-0027) Economy Wide Assessment of Pricing Impacts (PAD-0032) Funding & Implementation issues paper (LAR-0003)* Vehicle Operating Cost Model (PRC-0007) Funding flows – Local Government case study (LAR0004) Incremental Pricing Trials (PAD0009) Heavy Vehicle Pricing Options: Development and Assessment Framework Discussion Paper (CRRP Private Intranet - NTC Australia 4 August 2010) Transition to Implementation Use of Heavy Vehicle Data Sets – Opportunities for Improvement under Direct Charging Arrangements (BAS-0001) FS 1409 Feasibility Study: Heavy Vehicle Charging Australia Final Report Legal & Regulatory framework and high level options analysis (LAR-0002) Funding & Implementation issues paper (LAR-0003)* Local Government Consultation Paper (LAR-0003) Documentation of Business Processing and Technical Design of Jurisdictional Registration Systems (BAS-0002) New Zealand Case Study (LAR-0003; PAD-0016) Final Report CRRP Multi Project System Design (BAS-0003) Funding flows – Impact of pricing options on CGC distribution (LAR-0004; PAD-0017) Intelligent Transport System (ITS) Architecture (BAS-0004) Compliance & Enforcement Issues Paper (LAR-0004) Mass Charging Options Paper (PAD-0050) Fuel Policy Issues (PAD-0041) COAG Road Reform Plan – Final Feasibility Study Report for COAG | 44 ACIL Tasman, Assessment of the Viability of Fuel Charging Options, 2011. ARRB, Cost Implications of Incremental Loads on Road Pavements, Austroads Project No. AT1394, 2010. Allens Arthur Robinson, Governance Arrangements for Implementation of High Level Pricing and Funding, 2011. Austroads, Feasibility Study: Heavy Vehicle Charging in Australia Final Report, Report FS 1409, 2011. Bureau of Transport Economics, The Cost of Maintaining the Australian National Highway System, 1991. Bureau of Infrastructure, Transport and Regional Economics, Report 123, Truck Productivity: sources, trends and future prospects, 2011. COAG Road Reform Plan, Intelligent Transport System Architecture, Consultancy Report by ARRB, 2011. COAG Road Reform Plan, Central Agency Discussion Paper, 2011 COAG Road Reform Plan, Community Service Obligations, 2011. COAG Road Reform Plan, Compliance and Enforcement Issues Paper, 2011. COAG Road Reform Plan, Documentation of Business Processes and Technical Design of Jurisdictional Registration Systems, Acache Consulting, 2011. COAG Road Reform Plan, Economy Wide Assessment of Pricing Impacts, Consultancy Paper by Centre of Policy Studies, Monash, 2011 COAG Road Reform Plan, Evaluation of Options Paper, 2011. COAG Road Reform Plan, Funding and Implementation Issues Paper, 2011. COAG Road Reform Plan, Funding Flows – Impact of Pricing Options on Commonwealth Grants Commission Distribution, 2011. COAG Road Reform Plan, Funding Flows – Local Government Case Study, 2011. COAG Road Reform Plan, Local Government Consultation Paper, 2011. COAG Road Reform Plan, Mass Charging Options Paper, 2011. COAG Road Reform Plan, Multi-Project System Design, Consultancy Paper by Acache, 2011. COAG Road Reform Plan, New Zealand Case Study, 2011. COAG Road Reform Plan, Pricing Analysis, 2011. COAG Road Reform Plan, Pricing Principles, 2011. COAG Road Reform Plan, Policy Framework, 2011. COAG Road Reform Plan, Policy Principles, 2011. COAG Road Reform Plan, Road Use Data, 2011 COAG Road Reform Plan, Road Fund Versus Development Model Analysis, 2011 COAG Road Reform Plan, Transition to Implementation, 2011. COAG Road Reform Plan, Funding and Expenditure Analysis, 2011. COAG Road Reform Plan, Compliance and Enforcement Issues Paper, 2011. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 45 COAG Road Reform Plan, Business Systems to Support Heavy Vehicle Charging, 2011. COAG Road Reform Plan, Vehicle Operating Cost Model, 2011. DLA Phillips Fox, Mechanisms for Collection of Road User Charges Under the COAG Road Reform Plan, 2011. DLA Phillips Fox, CRRP Charging Reforms: Compliance and Enforcement Issues, 2011. GHD Meyrick and NERA Economic Consulting, Alternative Approaches to Estimating the Road Cost Base, 2011. Hyder Consulting, ITS Telematics Survey, 2011. National Transport Commission, Incremental Pricing to Unlock Heavy Vehicle Productivity, 2009. National Transport Commission, Heavy Vehicle Pricing Options Development and Assessment Framework, 2011. National Transport Commission, Road Freight Demand Elasticities: Stage 2, GHD Meyrick and NERA Economic Consulting Consultancy Paper, 2011. National Transport Commission, Investigating the Development of Heavy Vehicle Road Use and Road Asset Data Sets, Consulting Report by GHD Meyrick and Adam Pekol, 2010. Productivity Commission, Road and Rail Freight Infrastructure Pricing, Productivity Commission Inquiry Report, 2006. Queensland Department of Main Roads, Information Bulletin Performance Based Standards Road Network Classification, 2010. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 46 Appendix B: Glossary Term Definition Access restrictions The restrictions different vehicles face in allowing passage on different parts of a road network. Articulated vehicle A vehicle with flexibly connected sections. Usually applied to a prime mover and semi-trailer as opposed to a truck and trailer and known as a combination vehicle. Community service obligation (CSO) A service that promotes social objectives or benefits to the community at large that would not otherwise have been provided by an infrastructure provider acting commercially. Distance charges Distance charges are based on the actual or estimated distance travelled by a vehicle. This may be supported through the monitoring of the vehicle (including through the use of onboard units), measuring time as a proxy for distance travelled, and/or the use of surveys and statistical analysis. Distance charges aim to reduce cross-subsidisation between high and low kilometre users. Distortion Refers to an impediment in a market (e.g. regulation, control of market power, externalities) that creates an economic inefficiency, producing an outcome that differs from one that would occur in a perfect market. Earmarking Refers to the assignment of funds for particular purposes. Efficient investment Refers to the efficient allocation of scarce resources. At the margin, resources should be used by the individual who is willing to pay the most for them. This should promote optimal infrastructure provision with minimal cost. Investment that allocates scarce resources in accordance with users’ willingness to pay. Enforcement costs The costs involved in ensuring that vehicles comply with laws associated with their access and use of the road network. Externalities Costs or benefits arising from an economic transaction that falls on a third party and that are not taken into account by those who undertake the transaction. Externalities may be in the form of a negative or positive COAG Road Reform Plan – Final Feasibility Study Report for COAG | 47 Term Definition externality. A negative externality occurs where consumption or production of a good generates a cost borne by someone outside of the production or consumption of that good (for example, pollution). Positive externalities occur when a benefit accrues to someone outside of the production or consumption of a good (for example, education). Freight task Refers to the aggregate movement of freight of all kinds (bulk and non-bulk) within Australia, typically measured over one year. There are several ways in which this can be measured, including in terms of tonne kilometres, tonnes, volume or value. Fuel-based charging A heavy vehicle charging system based on the application of a charge (or tax) to fuel consumption. Gross vehicle mass (GVM) The sum of the allowable gross mass of a vehicle combination. Heavy vehicle (HV) A road vehicle weighing equal to or greater than 4.5 tonnes. Higher mass limits (HML) A scheme which conditionally permits increased mass above general access mass limits, provided that the vehicle is operating with road friendly suspension. Since inception, additional state based requirements have been imposed. HV Registration charge Heavy vehicles are required to pay to State authorities an annual fixed charge in the form of vehicle registration. Life Cycle Cost The sum of all costs of an asset over its life including capital and maintenance. In includes purchase price, installation cost, operating costs, maintenance and upgrade costs, and remaining (residual or salvage) value at the end of ownership or its useful life. Location charges Location charges are levies imposed on vehicles according to their location. Maintenance costs/expenditure Expenditure incurred in preserving and retaining (repairing and rehabilitating) the existing road infrastructure at or to a predetermined level of performance standard. In the area of roads, routine maintenance and periodic maintenance (reseals, major patching and resheeting) comprise the majority of road maintenance expenditure. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 48 Term Definition Marginal cost Marginal cost refers to all costs incurred as a consequence of providing one additional unit of a good or service. In the context of heavy vehicles and roads, marginal costs would include road wear and tear included in road maintenance costs, as well as any traffic operations or safety regulatory costs, associated with the use of roads for an additional user. In short, marginal road costs are any additional cost caused by the use of a road by an additional vehicle. Mass charges Mass charges impose charges on heavy vehicles on a permass-carried basis. This monitoring can be done through weigh-in-motion stations, depots, nominated mass or on-board weighing technology. Mass charges could relate to the actual mass carried, the average mass carried, mass by axle group type or the maximum mass limit for the vehicle. Mass-distance charges Mass-distance charges impose charges according to distance travelled and by vehicle mass over a defined period. Mass-distance-location (MDL) charges MDL charging imposes charges according to vehicle mass, distance travelled and vehicle location. Mass - dynamic Dynamic mass involves measuring and using telematics to transmit the actual mass of a vehicle in real time. For the purposes of our analysis, this is assumed to require fitting telematic on-board mass measurement devices to a vehicle so that actual information on the mass carried and the resulting impact of the vehicle on the road can be recorded as the vehicle travels. Given continuous mass monitoring occurs, dynamic (or on-board) mass measurement is able to take into account different trips, and changes in mass with changes in payloads where a vehicle travels anywhere from empty to fully loaded, or makes multiple pick ups and drop offs in a particular journey. Mass - static Static mass measurement involves setting an assumed fixed mass level for a vehicle or vehicle class. Static mass measurement assumes that a vehicle is travelling at the fixed mass level for all vehicle travel. There are a number of options for how static mass levels could be set including; average mass, current mass limits (i.e. GML, CML or HML) or another agreed mass level. Static mass measures could also mean direct entry of mass into an on-board unit where there is telematic monitoring of distance and location parameters but COAG Road Reform Plan – Final Feasibility Study Report for COAG | 49 Term Definition no direct measurement of mass. More direct pricing Prices that are closer to cost relative to the status quo Net benefits/net economic benefits The value of benefits less the value of costs Net present value The value of all the net benefits in all current and future periods discounted to today. PAYGO A Pay-As-You-Go approach to estimating the cost of road service provision recovers capital and maintenance expenditure on roads in the period in which it is incurred. This means that users of roads, rather than road providers, effectively fund the investment. Present Value The value of one or more cash flows discounted using an interest rate to get a value today. Price signals A fee which influences behaviour. The period in which heavy vehicle charges prices will be reviewed and determined. Road user charge The road user charge is imposed by the Commonwealth on heavy vehicles and comprises a component of the diesel fuel excise. The road user charge represents the difference between the fuel excise (currently 38.143 cents/litre) levied against all road users, and the rebate (fuel tax credits) available to heavy vehicle operators. COAG Road Reform Plan – Final Feasibility Study Report for COAG | 50 Appendix C: Explanation of heavy vehicle segment definitions Segment Illustrative Example of a Truck in the Segment NTC Naming Convention for Example Truck Rigid truck 2 axle rigid truck Rigid truck 4 axle rigid truck Articulated truck 6 axle articulated truck Heavy truck trailer 3 axle rigid truck with 4 axle trailer Multicombination vehicle B-Double combination Multicombination vehicle Double Road Train COAG Road Reform Plan – Final Feasibility Study Report for COAG | 51