Adobe Creek Upper Reach 5 Proposed Project Elements Table May 17, 2006 No. 1 2 3 4 Project Element Construction staging area at Edith Park Existing sanitary sewer line upstream of West Edith Avenue Bridge. Channel invert between existing sewer line and upstream face of West Edith Avenue Bridge. Sediment removal under West Edith Avenue Bridge 5 Existing wing wall on Los Altos creek 6 Existing wing wall on Los Altos Hills creekside. 7 Construct one step pool downstream of West Edith Avenue Bridge. 8 Construct new channel with 1:1 slopes on LAH side. Cross section will intersect existing ground on LA side (see typical section A). 9 Abandon existing channel on Thies property (see typical section B). 10 Construct new channel with 1:1 slopes on LAH side with bank protection due to truncated cross section (see typical section C) 11 Construct new channel with 1:1 slopes on LAH side. Cross section will be a truncated cross section (see typical section C) 12 13 Temporary creek access from Fremont Road Construction staging area on Los Altos Hills creekside. by: Tony Ndah May 17, 2006 Page 1 of 2 Status Resolution Sewer line to remain Regrade channel invert Remove 1.5 feet of sediment underneath West Edith Avenue Bridge. Existing wing wall to remain. Extend wing wall to Millar/Levis property line. Remove existing wing wall and construct new retaining wall from downstream face of West Edith Avenue bridge to limits of blue line on Los Altos Hills creek bank. Existing hardscape on Los Altos creekside to remain. Cutoff walls for the existing gunite will be reinforced. Existing wood bank protection at Millar and Wittner property to be removed. Chain link fence at Lippe property to be removed. Construct new channel with 1:1 bank slopes and abandon existing channel on Thies property. Need TCE from Thies prior to performing work. Cross section at this location is constricted i.e. 2 BF width is NOT achieved. This section needs bank slope protection for the LAH side. Staff to discuss impacts of bank slope protection on trees of value with property owner and resource agencies. Cross section at this location is constricted i.e. 2 BF width is NOT achieved. Bank slope protection to be provided on LAH creekside. Type of protection to be discussed with property owner and resource agencies. No. Project Element 14 Construct new channel with step pools (see typical section D). 15 16 17 18 19 20 21 22 23 24 Remove portion of storm drain and reconstruct outlet. Planting limits outside of blue line on Los Altos Hills side Modify invert from existing concrete drop structure to 160 feet downstream. Existing concrete block to remain. Protect bank toe on Moos property between existing rock slope protection and existing sackcrete protection. Fill cavity behind existing gunite at Remmel property with concrete material or similar. Repair bank erosion at Remmel property with rock slope protection from end of existing gunite to property boundary with Robinwood Pool. Bank slope protection at Robinwood Pool property Reinforce cutoff wall at existing sackcrete slope protection on Moos property. Reinforce cutoff wall at existing sackcrete slope protection on Robinwood pool property. Reinforce cutoff wall at existing sackcrete slope protection on Van Horne property. 25 Repair bank erosion at Van Horne property downstream of existing sackcrete slope protection. 26 Repair bank erosion at Van Horne property at existing storm drain on property. 27 28 29 Crib wall at Ward property Temporary access for creek downstream of Robleda storm drain outlet Assarson's erosion concerns at patio by: Tony Ndah May 17, 2006 Page 2 of 2 Status Resolution Existing bank on LA side to remain. Reinforce cutoff wall for existing gunite. Cross section exceeds blue line near storm drain outlet. Issue has been resolved with property owner. Portion of storm drain to be removed to match proposed channel banks. Pending review by District biologist to determine ecological benefit. Provide equivalent level of protection at existing rock slope protection along Moos property. Provide toe protection up to 3 feet above channel invert (2 BF height). Height of rock slope protection to resolved with property owner and resource agencies. Protect creek invert and provide toe protection 3 feet above creek invert (2 BF height) Use concrete material or similar Use concrete material or similar Use concrete material or similar Height of rock slope protection to resolved with property owner and resource agencies. Height of rock slope protection to resolved with property owner and resource agencies. Crib wall to be replanted, and irrigated.