To the householder FEBRUARY 2013 Hunter Expressway, Kurri Kurri to Branxton - Construction update February 2013 The $1.7 billion Hunter Expressway is jointly funded, with the Australian Government providing $1.5 billion and the NSW Government contributing up to $200 million. The new four-lane Hunter Expressway is being constructed under two contracts, with the western section (Kurri Kurri to Branxton) being built by Abigroup, covering a distance of 27 kilometres. This letter outlines Abigroup’s construction activity for February 2013. Construction in the 27 kilometre western section has been divided into the following four zones: Zone 1 - Kurri Kurri to Old Maitland Road, Sawyers Gully. Zone 2 - Old Maitland Road, Sawyers Gully to Tuckers Lane, Greta. Zone 3 - Greta (north of Tuckers Lane) to Branxton. Zone 4 - Branxton to west of Black Creek, Lower Belford. The following activities are scheduled for February 2013. Zone 1 - Kurri Kurri to Old Maitland Road, Sawyers Gully Construction will continue at the future Kurri Kurri interchange with the bridge to the south of Main Road being poured in early February. This will involve some out-of-hours work. Finishing work will continue on the bridge to the north of Main Road with the installation of throw screens and parapets. Earthworks will be completed on the embankments and ramps at the Kurri Kurri interchange. During February there will be intermittent haulage of material across McLeod Road, Loxford. Traffic control will be in place to safely direct traffic around this activity. Drainage activities will increase between the Kurri Kurri interchange and Swamp Creek. Work will near completion at the bridge at McLeod Road, near the Kurri Kurri TAFE with the installation of throw screens, parapets and construction of the pedestrian footpath. Service work will continue along McLeod Road at Loxford, with work on the watermain being completed at the end of February. Work will continue on the construction of noise walls between the South Maitland Railway bridge and the Kurri Kurri TAFE. This activity involves intermittent lane closures along TAFE road. Construction will be completed at the bridge over Swamp Creek, near the South Maitland Railway bridge at Loxford. The traffic diversion at Hart Road around the future Loxford interchange will continue to operate and be in place until early May 2013. In addition to the Hart Road diversion the temporary road adjacent to Hart Road (south of the existing road) will remain in place until May 2013 to divert traffic around the Loxford interchange bridge tie-in work onto McGarva Avenue. In February the bridge girders will be erected at the Loxford interchange bridge at Hart Road. Paving activities will start in February between Old Maitland Road towards the Loxford interchange. For further enquiries: Abigroup Hunter Expressway Community Relations Manager, Angela Hazell 1054 Old Maitland Road, Sawyers Gully NSW 2326 Hex_kk2b@abigroup.com.au I 1800 001 267 Hunter Expressway – Western section construction update – February 2013 Hunter Expressway – Construction activities Zone 2 - Old Maitland Road, Sawyers Gully to Tuckers Lane, Greta Material will be hauled out of the western side of Lovedale Road, Allandale and along the local road network to the location of the future Loxford interchange and the future Kurri Kurri interchange. Work at the future Allandale interchange bridge off Lovedale Road will be completed and opened to traffic before Easter. Once this traffic switch takes place construction will start on the removal of the old section of Allandale Road. Shoulder paving activities will continue on the main alignment of the expressway from Allandale east to Tuckers Lane, Greta. All paving activities may require out-of-hours activities including saw-cutting. The batching facility at Allandale will continue to operate for paving and bridge pour activities. Between 6am and 7am Monday to Friday the activities may include: starting the mainline paver and shoulder/kerb paver and moving them into position, warm up of the batching facility, batching, loading concrete into concrete agitators and paving trucks. Washing out paving trucks may also take place if required. Between 6pm and 7.30pm Monday to Friday activities may include: batching, loading concrete into concrete agitators and paving trucks, the wash down of the paver and batching facility, washing out paving trucks, concrete curing, the removal of the waste from the paving machine and walking the paver to the next required location. Zone 3 - Greta (north of Tuckers Lane) to Branxton The installation of noise walls will continue to the north and south of Tuckers Lane. Crushing and haulage of material along the project alignment will continue from north of Tuckers Lane. Earthworks will be completed on the batters and embankments at Tuckers Lane. Bridge work will continue at the future Branxton interchange with the removal of false work and abutment extensions. In mid-February the second cast insitu bridge pour will occur at the Branxton interchange. During February material will be hauled from the location of the future Branxton interchange up the alignment and across to both the western side of Wine Country Drive and along the New England Highway to the location of the future heavy vehicle rest areas. There will be an increase in truck movements in the Branxton area. Material will also be hauled along the alignment and across the railway bridge to be used as fill for the link road to the New England Highway. Deck finishing and asphalting work will be completed on the Wine Country Drive bridge with the traffic switch expected to take place before Easter. Construction will continue on the installation of noise walls along the south side of Wine Country Drive, Branxton and will start on the north side at the beginning of February. At the twin bridges over the Main Northern Railway north of Wine Country Drive, formwork will continue, the reinforced earth walls will be completed and work will start on barrier extensions. In February paving activities will continue on the main alignment of the expressway from the Main Northern Railway bridge through to Black Creek. During February there will be some out-of-hours bridge work and concrete pours at the Branxton interchange and the twin bridges over the Main Northern Railway. Concrete will be transported to site along the project alignment. Affected residents will be notified directly of this work. Hunter Expressway – Western section construction update – February 2013 Hunter Expressway – Construction activities Zone 4 - Branxton to west of Black Creek, Lower Belford Earthworks will continue from Black Creek to west of Standen Drive, Lower Belford. Heritage sieving at Black Creek will continue and is expected to be completed before Easter. This site will continue to be monitored during construction activity at this location. Work will continue at the twin bridges over Black Creek with deck pours and work on the approach slabs and abutments. Toward the end of February scaffolding will be removed. Drainage and culvert work will continue around the location of the new service road from Standen Drive heading east toward Branxton. Sub base asphalting will start in late February along the main alignment as part of the paving operation at this location. General earthworks General bulk earthworks, installation of fencing and the relocation of existing utilities such as electricity, gas and telephone, will continue at various locations along the 27 kilometres of the western section of the project. Traffic and access Short-term traffic restrictions including temporary lane closures, speed limit reductions and minor traffic diversions will be required to build the Hunter Expressway between Kurri Kurri and Branxton. When driving in these areas, please follow the signs and directions of traffic controllers, including reduced speed limits. Working hours Normal working hours are between 7am and 6pm, Monday to Friday and between 8am and 1pm Saturdays. We thank residents and business owners for their patience during the construction of the Hunter Expressway. Nearby residents will be notified and consulted for any work outside these hours, as required. Out-of-hours activity There will be some out-of-hours activity during 2013. This activity is either already approved under the project Construction Environment Management Plan or being carried out in locations where the work is inaudible at nearby properties or where written agreement has been obtained from noise affected property owners. Upcoming community information session for February 2013 The Hunter Expressway holds monthly community information sessions at different locations in the Hunter region. Project information, including maps, artist impressions and a 3D computer model are displayed and representatives from Roads and Maritime Services (RMS), Abigroup and the Hunter Expressway Alliance are present to answer your questions. Details of the upcoming community information session are: Date: Time: Location: Friday 15 February 9.30am to 12.30pm Maitland Room Maitland City Council Building High Street, Maitland This construction update was based on the most up-to-date information at the time of printing. However, the activities are subject to change due to weather or technical issues that may arise. For Hunter Expressway – Western section construction update – February 2013 Hunter Expressway – Construction activities enquiries, complaints and further information about the project, please call toll-free 1800 001 267 or visit www.rms.nsw.gov.au/hex. Aerial view of the Newcastle interchange Above: Cast insitu concrete pour for the bridge at the future Kurri Kurri interchange. Left: The main alignment of the Hunter Expressway looking south from the Allandale interchange. Below Left: Tuckers Lane overbridge at Greta that was opened to local traffic on Tuesday 15 January 2013. Below Right: Twin bridges over Black Creek at Lower Belford.