COMPENSATION FOR LAND TAKEN UNDER THE ROADS LAW

advertisement
COMPENSATION UNDER THE ROADS LAW
(Previously published in the Caymanian Compass and Real Life Magazine)
With the increase in road building in Cayman in recent years, many landowners are unsure of
Government’s rights to take their land and in turn their right to compensation for their loss. In this
article we set out the basis of Government’s rights in this regard and offer guidance on how the
compensation due to the affected landowner can be assessed and where they can seek further
professional advice on this matter.
The right to take land for use as a public road is granted to the Highway Authority under The
Roads Law (Revised). This law requires the Government to serve two notices to the landowners
before first entering onto and then classifying the land as a public road.
The first notice is known as the ‘Section 3’. This notice indicates the Government’s intention to
take land, or part of it, for the layout of a new road or the widening or diverting of an existing road.
The law requires the notice to be published in the Cayman Islands Gazette, published twice a
week for three consecutive weeks in a daily newspaper and sent by registered post to the
registered proprietor of the land at the address on the Land Register. This notice should state
Government’s intention to construct the road, the Block and Parcel numbers of the land affected
and the approximate area of the land to be taken from each parcel under the road scheme. It is
the Section 3 notice that gives the Highway Authority the right to enter on to the land and sets the
valuation date with respect to the assessment of compensation.
The second notice, the ‘Section 5’ is gazetted once the Highway Authority has completed the
‘prescribed composite map’ on which the road is defined, thus fixing the actual area of the land to
be taken. This is usually undertaken once the actual construction of the road has been
completed.
Once served with the relevant notices, an affected landowner is required to submit two forms to
the Highway Authority in order to claim compensation for any loss suffered. The ‘Notice of Intent
to Claim Compensation’ should be submitted within ninety days from the date of the Section 3
notice and the ‘Claim for Compensation’ should be submitted within one year of the date of the
same notice.
In completing these forms the landowner must decide on whether they wish to make a one or two
stage claim. A one stage claim means that compensation will be assessed entirely on the area of
land stated in the Section 3 notice, whilst a two stage claim means that although an interim
payment will be made based on the area stated in the Section 3 notice, full and final
compensation will be made based on the final area set out in the Section 5 notice.
The amount of the compensation to be paid to the claimant under the law is assessed on six
basic heads of claim, as follows;
1)
Market Value of Land Taken; This is the market value of at the land taken under the road
scheme, as of the date of the Section 3 notice.
2)
Compensation for Loss of Crops; The value of any damage to the claimant’s crops or
trees which were on the affected land at the time the Highways take possession.
3)
Compensation for Severance; Any loss in value to the claimants remaining land holdings
at the time of taking possession of the land, by reason of the severing of such land from
his other land.
4)
Compensation for Injurious Affection; Any damage sustained by the claimant at the time
of the taking of the portion of land, by reason of the loss injuriously affecting his other
property.
5)
Compensation for Disturbance; Any reasonable expenses arising from the claimant being
compelled to change his residence or place of business as a result of the land being
taken.
6)
Compensation For Loss Of Profits; The loss of profits from the land between the date of
the Section 3 notice and the date of the Highway’s Authority actually taking possession of
the land.
We have tried above to provide a brief background of the basis of compensation under The
Roads Law, however calculation of compensation can be a complex matter. Therefore anyone
served with a notice under The Roads Law is advised to obtain further advice from a Chartered
Valuation Surveyor, all of whom are specifically trained in the assessment of compensation for
such claims. Claimants will of course be pleased to hear that any professional fees they incur as
a result of their land being taken under a road scheme can be claimed back as part of their heads
of claim and so they will not suffer any out of pocket expenses for seeking such professional
advice.
Simon J. Watson is a Director of Charterland, a Chartered Surveying practice based in the
Cayman Islands but offering professional property services throughout the Caribbean. Simon is a
Fellow of The Royal Institution of Chartered Surveyors (FRICS), a founding Board member of
RICS Caribbean and the Caribbean representative to RICS Americas. Simon has over 20 years
experience as a Chartered Surveyor, with much of that experience gained in the Caribbean
region. Charterland provide a comprehensive range of services including valuations and
appraisals, quantity surveying and cost management, property management and agency &
leasing services.