UNDP PROJECT DOCUMENT The Royal Government of Cambodia United Nations Development Programme The Ministry of Agriculture, Forestry and Fisheries, Ministry of Environment and Provincial Authority of Preh Vihear Province Establishing Conservation Areas Landscape Management (CALM) in the Northern Plains The Northern Plains of Cambodia are the largest remaining extensive intact block of a unique landscape of exceptional global importance for biodiversity conservation. The area is either a last refuge for, or maintains a key population of 36 species on the IUCN Red List, including six listed as Critically Endangered. The project addresses the problem of escalating biodiversity loss across the Northern Plains, caused by increasing human land and resource use. This is achieved through a seven-year, three-pronged approach: (1) the introduction of biodiversity considerations into provincial level land use processes; (2) the demonstration of specific mainstreaming interventions at four key sites (including community landuse tenure, community contracts and incentives for biodiversity supportive land-use practices, as well as work to mainstream biodiversity into the forestry and tourism productive sectors); and (3) strengthen biodiversity management by government at the four key sites. The Landscape Species Approach has been used to identify the four sites. The CALM project is consistent with the GEF Strategic Priority BD-2 (Mainstreaming Biodiversity in Production Landscapes and Sectors). The project intervention will work to introduce biodiversity values into landscape level land-use planning processes. Implementation will focus particularly on building the capacity of provincial departments and authorities and integrate specific projects initiatives established provincial planning processes (supported through the Seila/PLG Programme).The project will mainstream biodiversity conservation in relevant sectors such as tourism, forestry, agriculture etc within that landscape. 1 Table of Contents SECTION I : ELABORATION OF THE ANALYSIS ............................................................. 5 PART I: SITUATION ANALYSIS ............................................................................................ 6 Background ..........................................................................................................................................................6 Problem to be Addressed .....................................................................................................................................9 Underlying Causes ............................................................................................................................................. 11 Current Situation (Baseline) .............................................................................................................................. 13 PART II: STRATEGY .............................................................................................................. 17 Project Rationale (The Alternative) ................................................................................................................... 17 Relevance to UNDP Outcomes .......................................................................................................................... 23 National Support for the Alternative .................................................................................................................. 23 Project Sustainability, Partnerships and Linkages ............................................................................................ 26 Implementation Strategy .................................................................................................................................... 33 Risks and Risk Management Strategy ................................................................................................................ 34 Result Frameworks ............................................................................................................................................ 45 PART III: MANAGEMENT ARRANGEMENTS ................................................................... 49 Execution............................................................................................................................................................ 49 Implementation (see Annex 7 for Terms of Reference) ...................................................................................... 49 Adaptive management ........................................................................................................................................ 51 Audit ................................................................................................................................................................... 52 PART IV: MONITORING AND EVALUTION PLAN AND BUDGET................................. 54 Conservation Impact Monitoring ....................................................................................................................... 54 Project Inception Phase ..................................................................................................................................... 55 Monitoring responsibilities and events .............................................................................................................. 56 Work plan and Reporting requirements ............................................................................................................. 57 Evaluation .......................................................................................................................................................... 59 Learning and Knowledge Sharing...................................................................................................................... 59 PART V: LEGAL CONTEXT .................................................................................................. 62 SECTION II : STRATEGIC RESULTS FRAMEWORK AND ............................................ 63 GEF INCREMENT .................................................................................................................... 63 PART I: INCREMENTAL COST ANALYSIS ................................................................................... 64 PART II: LOGICAL FRAMEWORK ANALYSIS ................................................................................ 68 SECTION III: TOTAL WORKPLAN AND BUDGET .......................................................... 84 FINANCING PLAN ................................................................................................................. 85 SUMMARY .................................................................................................................................. 85 WCS .......................................................................................................................................... 85 SEILA/PLG ................................................................................................................................ 85 DETAILED BUDGETS............................................................................................................ 87 WORKPLAN ............................................................................................................................ 94 SECTION IV : ADDITIONAL INFORMATION ................................................................. 100 PART I: OTHER AGREEMENTS ................................................................................................ 101 PART II: TERMS OF REFERENCES FOR KEY PROJECT STAFFS AND MAIN SUB-CONTRACTS ....... 101 ANNEX 1.7: TERMS OF REFERENCE (TOR) ............................................................................... 101 PART III: STAKEHOLDER INVOLVEMENT PLAN ...................................................................... 114 STAKEHOLDER CONSULTATIONS AND PARTICIPATION PLAN..................................................... 114 2 ABBREVIATIONS AAH APR ASEAN BPAM CALM CARERE CBD CCF CDC CG CITES CTIA DAFF DNCP DoE FA FAO GAP GEF GEF-SEC GIS GTZ IA ICF IUCN KPWS LMAP LSA MAFF MDGs MLMUPC MoE MOU MRC MRD MWRM MYFF NBSAP NBSC NEAP NGO NREM NTFPs OP PA Action Against Hunger Annual Project Review Association of South-East Asian Nations Biodiversity and Protected Areas Management Project Conservation Areas through Landscape Management Cambodia Area Reconciliation and Rehabilitation (UNDP) Convention on Biodiversity Country Co-operation Framework Council for the Development of Cambodia Consultative Group meeting (RGC and International Donors) Convention on International Trade in Endangered Species of Wild Fauna and Flora Cambodia Timber Industry Association Department of Agriculture, Forests and Fisheries Department of Nature Conservation and Protection Department of Environment Forest Administration of MAFF United Nations Food and Agriculture Organization Government Action Plan Global Environment Facility Global Environment Facility Secretariat Geographical Information System German Technical Corporation Implementing Agency International Crane Foundation International Union for the Conservation of Nature Kulen Promtep Wildlife Sanctuary Land Management and Administration Project (of MLMUPC, funded by GTZ) Landscape Species Approach Ministry of Agriculture, Forests and Fisheries Millennium Declaration Goals Ministry of Land Management and Urban Planning and Construction Ministry of Environment Memorandum of Understanding Mekong River Commission Ministry of Rural Development Ministry of Water Resources and Meteorology Multi-Year Funding Framework National Biodiversity Strategy and Action Plan National Biodiversity Steering Committee National Environmental Action Plan Non-Government Organisation Natural Resource and Environment Management Non-timber forest products Operational Programme Protected area 3 PDF PDP PEG PIR PLG PLUP PRDC RCAF RGC SEDP II Seila SEG STAP TOR TPR TWG-FE UN UNDAF UNDP UNDP-GEF WB WCS WS Project Development Facility Provincial Development Plan Project Executive Group Project Implementation Review Partnership for Local Governance (component of Seila funded by UNDP) Participatory Land Use Planning Provincial Rural Development Committee (chaired by Governor) Royal Cambodian Armed Forces Royal Government of Cambodia Socio-Economic Development Plan 2001-2005 Social Economic Integration in Local Administration (‘Foundation Stone’ in Khmer) Sub-Executive Group Scientific And Technical Advisory Panel (of the GEF) Terms of Reference Tri-partite review Technical Working Group on Forestry and Environment United Nations United National Development Assistance Framework United Nations Development Programme UNDP’s Global Environment Facility Office (with the Bureau for Development Policy) World Bank Wildlife Conservation Society Wildife Sanctuary 4 SECTION I : ELABORATION OF THE ANALYSIS 5 PART I: SITUATION ANALYSIS Background 1.Since 1995 Cambodia has been a ratified signatory of the Convention on Biological Diversity (CBD). As part of its response to the CBD Cambodia has developed a National Biodiversity Strategy and Action Plan (NBSAP), with support from a GEF Enabling Activity through UNDP. The strategy provides a framework for action at all levels, which will enhance Cambodia’s ability to ensure the productivity, diversity and integrity of its natural systems and, as a result, its ability as a nation to reduce poverty and improve the quality of life of all Cambodians. Specifically, the NBSAP highlighted the importance of the Northern Plains landscape. 2. The Northern Plains is a very remote region of Cambodia, a country that ranks amongst the poorest in South-East Asia. From the early 1970s the region was a central base of the Khmer Rouge and as a consequence experienced long periods of conflict and civil war, which only ceased in 1998. During this time the local population was translocated and forced to adopt collectivized paddy rice growing. As security improved from the 1980s onwards families returned home and, to some extent, re-established traditional livelihood practices. The region is presently sparsely populated, with densities as low as 5.5 people/km² in some areas. The vast majority of families rely on subsistence rain-fed paddy rice growing, collection of forest products and seasonal fishing. Chamkar (shifting cultivation) is practiced by many families for vegetables and either to supplement rice production from paddyfields, or as an alternative. Fish, and to some degree wildlife, is the principal source of protein. Livelihood assessments (see Annex 12 for an example) have highlighted the prevailing food insecurity in the region, which is only mitigated by the extensive availability of forest products. 3. The Northern Plains landscape is defined by the geography of the area, its boundaries being naturally delimited by the Dangrek Mountains to the north, the Mekong River to the east and the Tonle Sap Great Lake to the south and west. The total region covers over 18,000km². Land tenure in the area is complex as the Northern Plains stretches across the borders of five Provinces: Oddar Meanchey, Banteay Meanchey, Siem Reap, Preah Vihear and Stung Treng. Government authority over the majority of the area is centred on the provincial capitals and the Provincial Governors Office. Jurisdiction for natural resource issues falls under the Provincial Department of the Environment (DoE) and the Provincial Department of Agriculture, Forests and Fisheries (DAFF, particularly the Provincial Forestry Office). The DoE is responsible for Protected Areas and DAFF for forest and agricultural lands. Overall development priorities for the Province are set out in the Provincial Development Plan produced by the Provincial Governors Office in collaboration with all line departments and the Provincial Rural Development Committee (PRDC). 6 4.The Northern Plains of Cambodia are the largest remaining extensive intact block of a unique landscape of exceptional global importance for biodiversity conservation. The area is either a last refuge for, or maintains a key population of 36 species on the IUCN Red List, including six listed as Critically Endangered (see Annex 1). The 1997 National Biodiversity Prospectus lists the Northern Plains as a landscape of national and international importance, because it is the largest remaining example of a forest type that once covered large areas of Indochina. Many species that rely on these forests are known to be extinct elsewhere, thus heightening the value of this region. One, the Giant Ibis Pseudoibis gigantea, was only known from a handful of records in the 1900s, until re-discovered during the PDF-B in considerable numbers in the Northern Plains. Conservation of these species is particularly challenging because the majority of them large birds and mammals - have large spatial requirements. 5. The landscape supports one of the most intact remaining examples of the bird community of the dry forests of central Indochina. Many large bird species are dependent upon waterbodies, including Green Peafowl Pavo muticus, White-winged Duck Cairina scutulata, Sarus Crane Grus antigone, White-shouldered and Giant Ibises Pseudibis davisoni and P. gigantea, Greater and Lesser Adjutants Leptoptilus dubius and L. javanicus and Black-necked Stork Ephippiorhynchus asiaticus. These resources are spatially restricted and seasonal in nature, so the bird species rely on a few key locations during the dry season and disperse across the landscape following the rains. 6. There are strong linkages between the Northern Plains landscape, and one of the other major landscapes in Cambodia, the Tonle Sap lake. A host of globally threatened waterbirds, such as Spot-billed Pelicans Pelecanus philippensis, Painted Storks Mycteria leucocephala, Greater and Lesser Adjutants breed on Tonle Sap, but disperse across the Northern Plains in the wet season. Conversely, Sarus Cranes and White-shouldered Ibis breed in the Northern Plains and return to the large permanent wetlands on the floodplain and the edge of the Northern Plains at the beginning of the dry season. Maintenance of one landscape would be insufficient for the conservation of these species. Ang Trapeang Thmor, a man-made reservoir on the edge of the Northern Plains in Banteay Meanchey province, is the dry season feeding refuge for the largest flock of eastern Sarus Crane in Southeast Asia and has probably the single largest herd of Eld’s Deer Cervus eldi siamensis in Indochina. 7. Raptors, especially White-rumped Vulture Gyps bengalensis, Slender-billed Vulture G. tenuirostris and Red-headed Vulture Sarcogyps calvus have large home ranges and rely on extensive areas of intact habitat for their food supply. However, they also have restrictive spatial requirements for breeding, because they are dependent upon isolated tall trees. The same Gyps species have undergone > 97% declines in the last 5-10 years in the Indian subcontinent due to poisoning by a veterinary drug, and are expected to become extinct within a few years. Cambodia has one of only two existent refuge populations of these once widespread species (now listed by the IUCN as critically endangered). 8. In addition to their key value to birds, the plains are also crucial to large mammal conservation in Cambodia and, in fact, the entire Indo-Malayan Realm. Many formerly widespread species 7 are now only found in a few areas of which the Northern Plains is one of the largest and has high potential for conservation. Examples of these include Lyle's Flying Fox Pteropus lylei, Eld's Deer Cervus eldii, Banteng Bos javanicus, Tiger Panthera tigris, Fishing Cat Prionailurus viverrina and Asian Elephant Elephas maximus. Like the water birds, these species rely on being able to concentrate in a few key resource areas during infertile or dry times and disperse widely across the floodplains when the water enriches the soil. Range sizes are poorly known, but data from other countries would indicate that many of these species require large areas; even the spatially restricted Eld’s Deer has been recorded moving 20 km in a single night in Myanmar, crossing areas of unsuitable habitat (e.g. village rice fields and dense forests). Other large mammals, e.g. Elephants and large cats, have much more greater requirements. 9. Although the landscape is of demonstrated global biodiversity importance, current conservation efforts are inadequate to mitigate the threats to biodiversity. Such is the vulnerable nature of the environment during the seasonal extremes, that although keystone resources (permanent water bodies, semi-evergreen forest, mineral licks) are distributed across a wide area, they are small in number, localized and especially vulnerable, so that the removal of even one such resource could have significant detrimental affects on unique components of biodiversity across a large distribution. Accordingly, an integrated conservation management strategy must ensure sufficient maintenance of these resources across the landscape in order to be successful. In addition, to incorporate the range requirements of large mammal species some extensive areas of habitat, within the human-use landscape, will need to be retained. 10. All forest resources and land are technically managed by MAFF, which has very little provincial capacity for this task. For example, the Forestry Office in one province has 16 staff for 130,000 inhabitants. Historically, communities had no legal right to use forest resources, beyond some trival activities (e.g. firewood collection), and their traditional ownership systems (e.g. of resin trees) are not recognised. Further, 25 years of conflict has disrupted traditional forms of land management, and encouraged a prevailing attitude of insecurity, promoting a short-term approach to resource extraction based upon competition with other individuals or groups. The people who benefit most from this situation tend to be those who are richer and better equiped (generally people from outside or members of the military or police), at the expense of local people. 11. Hunting of wildlife (particularly turtles and lizards) is an important seasonal protein source for local people. Commercial hunting of large mammals and waterbirds is undertaken by a limited group of people who either have guns, or rent them from the police or army. Substantial declines in the populations of large mammals in the last 10 years have probably reduced the number of people engaged in this activity. Wildlife is principally sold to Thailand, or occasionally Laos PDR. Two border crossing points to Thailand (one of which is not recognised) are the main exit points for wildlife products. The prices paid are comparatively high - e.g. $50 for a Sarus Crane chick, $150 for an Eld’s Deer, and $2500-3000 for a Tiger. In comparison, average family resin-tapping income is around $150/year. 8 12. Commercial activities are limited. The principal legally traded product is the resin of dipterocarp trees, which is transported to Vietnam or Laos PDR for processing. Historically, resin-tapping was a traditional activity undertaken for fuel and lighting and it became commercially widespread only since the late 1980s. The tapping is probably sustainable (Evans et al. 2002 A study of resin-tapping and livelihoods in southern Mondulkiri, Cambodia, with implications for conservation and forest management, WCS Report), and is undertaken by the families that are recognized, by the community, as owning a particular group of trees. Studies have indicated that resin income is particularly important for livelihood security - families use resin income to buy food, in times of shortage, or are able to borrow money from the trader against future tapped resin. In recent years conflicts have arisen between the tappers and loggers (either concessionaires or illegal logging by armed forces), who do not recognize the communities’ traditional ownership system. The implication of the removal of family resin income on livelihood security is the subject of a present study (by the Cambodia Development Resource Institute and WCS). The communities surrounding the Chendar Plywood concession organized themselves into a local NGO as a consequence of logging of resin trees in 2000. 13. Logging was undertaken by various groups in the 1980-1990s, and more recently by concessionaires. The concessionaire system was established in the late 1990s, with 5 concessions across the Northern Plains (TPP, Chendar Plywood, Timas, Samrong, Pheapimex Fuchan, see Map 1). Cambodia declared a ban on all logging in 2001, following which all concessionaires were required to submit revised management plans and environmental and social impact assessments. Five concessions have been re-approved, including Chendar Plywood in the centre of the Northern Plains and logging is anticipated to re-commence in 2005. In the meantime, illegal logging by armed forces (police or military) has been widespread. Community involvement is restricted to acting as guides to show the armed teams the locations of the best trees, for which they are paid around $2.5/day. Problem to be Addressed Problem Statement 14. Escalating land and resource use across the Northern Plains is leading to competing humanwildlife requirements and loss of key biodiversity values. Human land and resource use has increased partly as a result of increasing human population and in-migration, although population densities remain fairly low, but also because as security returns to the area there is much greater potential for resource exploitaiton. The conflicts are exacerbated by the current “open-access” management system of natural resources across the Northern Plains, which manifests through the following threatening processes: a) Over-exploitation of wildlife resources 15. Local communities do not rely on large mammal or bird species for their food security, although they do hunt other wildlife species (e.g. monitor lizards) at particular times of the year. Most protein consumed in villages comes from fish. Hunting equipment is relatively small-scale 9 such as wire or rope snares and activities tend to accompany trips for other purposes - such as resin-tapping or fishing. As such, disturbance is primarily focused in areas that are also critical for wildlife (dense forest areas, rivers and seasonal waterbodies). Invariably, people are accompanied by dogs on these trips, which is one of the principal causes of disturbance and incidentally hunting of wildlife. Dogs are a particular threat to the globally threatened Whitewinged Duck when they are moulting or have young, flightless, chicks. 16.Uncontrolled commercial hunting has led to a massive decline in many species across the landscape. Hunting of large mammals mainly requires guns and metal snares and is performed by a relatively small group of people who have access to this equipment (generally connected to police or military). The peak hunting season follows the first rains, when large mammal species are attracted by new grass shoots in burnt, low-lying, regions of the landscape that are adjacent to denser forest areas (used for hiding, such as the Chendar concession). Later in the wet season large mammals can be attracted by the new rice growth in paddyfields and shifting cultivation plots, and are easy targets for hunters. Large waterbirds start to nest in the wet season, and are particularly susceptible to collection of eggs and chicks. Some of this collection is opportunistic (e.g. Giant Ibis), whilst for other species hunters undertake specific trips (e.g. Sarus Cranes). Large-scale hunting with guns and snares and collection of eggs and chicks is driven by their commercial value from the wildlife trade. Wildlife is sold through a series of middlemen either for the national markets, or the international trade, principally across the Thai border. These border crossings are controlled by the police and military on both sides. In the wet season traders will periodically visit villages to buy eggs and chicks, again mainly for sale to Thailand or Laos PDR. b) Over-exploitation of forest resources 17. Strong economic incentives promote logging, recently by military and police, and historically by concessionaires. Logging occurs in areas of dense, evergreen, forest also used by large mammal species for shelter and browsing, and by some species of birds for breeding (e.g. Whitewinged Duck nests in tree-holes, Adjutants and Vultures nest in large trees). Whilst logging activities do not directly threaten these species it does contribute to a high level of disturbance and removal of too much of the forest canopy which can lead to forest degradation, soil erosion and an insufficient number of large trees for nesting purposes. More importantly, the construction of logging roads opens up new areas and poor salaries given to loggers (concessionaire and military) create ideal opportunities for hunting to supplement income and food. Logging can have major implications for local villagers, who rely on timber and the products that the forests provide. In particular, the loss of resin trees removes the major cash income source for local people and the livelihood security that this provides. Present logging by the military is on-going in the Kulen Promtep Wildlife Sanctuary, the Preah Vihear Protected Forest, the Chendar Plywood concession, Phnom Tbeng and surrounding several communities in the region. 18. Shifting cultivation by communities and the associated forest clearances is not a major problem for biodiversity conservation, especially as these activities are generally located near 10 settlements and key biodiversity resources are mostly further distant. All communities complain of over-exploitation by outsiders as the principal factor creating the present situation, and they benefit little from these activities. For example, a villager may be paid $2.5/day to show military loggers suitable trees for felling. However, under present land management systems the communities have no tenure or title over land or natural resources adjacent to their villages and accordingly have no legal right to prevent exploitation by outsiders. Forest land and resource management resembles an ‘open-access’ system where there is no barrier, other than capacity, to anybody exploiting the resource in any particular way. c) Seasonal destruction of key water bodies 19. Waterbodies are a critical resource in the Northern Plains, and most of the key components of biodiversity are dependent upon them for some of the year for food, water and habitat. Human use of waterbodies is also essential for local livelihoods, as people are dependent upon fish for protein, and traveling groups rely on particular watersources along forest trails. In the late dry season, when only a few locations still contain water, competitive exclusion of wildlife from waterbodies by humans may have serious implications for species’ populations. 20. The same open-access system that is causing degradation of the forest resource has similar implications for the management of water bodies. The driving incentive is to maximise returns as quickly as possible. This encourages over-exploitation of water resources and the use of unsustainable methods. The most obvious and destructive include the illegal use of bomb, poison and electric fishing techniques. These are generally used by temporary migrants (sometimes military or police), who enter an area to remove all the fish and then leave. Communities have more limited availability to such techniques, and are more aware that the use of these methods reduces future yields in their area. All communities complained of reductions in fish yields resulting from the use of unsustainable fishing methods by outsiders, although communities are known to be increasing the use of electric fishing methods. Underlying Causes 21. The threatening processes outlined above are caused by main “production sectors” operating across the Northern Plains: the wildlife trade; NTFP collection; timber production; and fishing. Biodiversity conservation or sustainable use considerations are clearly not factors shaping the operation of these “sectors”. Partly this is a function of the fact that these sectors can barely be considered established sectors: They operate in and outside of the Royal Government of Cambodia’s legislative framework and rule of law. The wildlife trade is not only on the whole illegal, but is also in contravention of international agreements, such as the CITES. The timber production sector has historically included legal as well illegal elements. However, currently logging is undertaken in the shadow of the 2001 ban. Electric, poison and bomb fishing methods are technically illegal. They operate at commercial and subsistence levels. As has already been explained, much of the productive activity of local communities is at the subsistence level – or at 11 least at non-commercial levels. This applies to the timber production and fishing sectors. Commercial scale production logging and fishing takes places (generally by outsiders) and while destructive, only a small proportion of these operations are formal (and legal). Resin tapping has been a commercial activity since the early 1990s, but it is unclear how many potential sources remain (i.e. most trees are now tapped). Even where productive activities are legal, they have been undertaken largely in an “open-access” regime. This is a consequence of the short history of democratic governance in the Northern Plains and the debilitatingly low baseline of systemic, institutional and individual capacity that the long periods of conflict have created. The resultant insecure tenures and rights shorten the planning horizons and promote the pursuit of short-term rents at the expense of sustainability. Changes in land-use practices to incorporate conservation impacts will involve a loss of short-term earnings (from wildlife trade, timber etc…) in favour of long-term gain (e.g. income from wildlife tourism, sustainable resin-tapping, community forests, etc…). Encouraging these changes will require not only an increase in security of tenure, but also positive incentive measures to replace the short-term loss of production income. 22. As a result, the Northern Plains are characterized by varying land and resource use gradients, creating an ad-hoc mosaic of biodiversity pressures and exploitations. Given the distribution of relatively limited keystone resources that the globally significant large mammals and waterbirds require, this invariably leads to an escalation of human-wildlife conflicts across the Northern Plains –with a corresponding loss of biodiversity. 23. Further, tourism is a growing “production sector” for the Northern Plains. In 2003, the Royal Government of Cambodia set a new policy to transform the Northern Plains into a new Tourism Zone Destination through a Triangle Tourism Development Strategy between Cambodia, Laos PDR and Thailand. This will require a significant level of infrastructure rehabilitation and development, potentially contributing further to biodiversity conflicts. 24. A final underlying cause of biodiversity decline relates to populations of key species of carnivores and scavengers (e.g. Tigers and Vultures). Research in other countries has shown that these species are critically dependent upon abundant prey populations. The maintenance of these species in the landscape can only, therefore, be achieved by addressing the threats outlined (above) and ensuring that populations of prey species return to previous levels. The present low numbers of these species across the Northern Plains is one of the major threats to carnivore and scavenger species. Research during the PDF-B revealed that populations of Vultures are critically low. 12 Current Situation (Baseline) Legal Setting 25.Environmental management and biodiversity conservation in Cambodia has the potential to build upon a strong, developing, base of legislation, policies and institutional structures. Articles 58 and 59 of the Cambodian Constitution (Rot Tommanuoen) relate specifically to the natural environment, and Article 59 states in part: “The State shall protect the environment and balance of abundant natural resources and establish a precise plan of management [of environmental resources]”. 26.The legislative framework governing the management of land and forestry has been improved greatly by the RGC within the past three years (see Annex 8). This includes Cambodia’s first land law (2001), the new forestry law (2002), and sub-decrees on community forestry and wildlife protection (2003). The Commune Administration Law (2001) established, through local elections, authorities to manage small groups of villages (communes), government funds for their work, and a local development planning process. Together this framework provides, for the first time in Cambodian history, sufficient legislation to address issues of land tenure, community rights and participation in management of natural resources. The framework substantially improves laws regarding the enforcement of forest crime, wildlife hunting and wildlife trade, and will be strengthened further with new sub-decrees on wildlife protection. These laws apply both inside and outside protected areas and forests, and therefore have the potential to be implemented across the whole of the Northern Plains landscape. However, there is no current facility to ensure that all stakeholders are aware of these new laws and it will be necessary for NGOs and other agencies to help increase understanding of the implications and possibilities arising from these laws if they are to be implemented. 27.The new land law establishes a clear classification system for land, both public and private (see Appendix 3 of Annex 8) and the usufruct rights of communities - the right to use natural resources. A process of participatory land-use planning (PLUP) has been adopted by the Ministry of Land Management, whereby facilitators assist communities to identify and map the land that they use and to develop plans for its improved management. PLUP maps can eventually be registered, achieving formal ownership (land title and resource tenure). Several projects, supported by a variety of donor agencies including GTZ, UNDP and FAO are using PLUP to improve natural resource management in Cambodia, although outside of the Northern Plains. 28.The new forestry law (2002), follows and respects the community title of the Land Law and goes further in ensuring user rights for forest products to local communities living in or near forests, even those who may not be able to obtain title under the land law (see Annex 8). The mechanism defined in the forestry law to protect these community rights is a Community Forest Agreement between the Forestry Administration and the local community for a specific area within state forest land that the community traditionally uses for subsistence uses. The new subdecree on community forestry (2003, see Appendix 1 of Annex 8) sets out the required 13 procedures. Whilst this is a marked improvement over previous legislation, the complexity and novelty of the law, and the relative inexperience of provincial authorities with regard to law, require that support be given to all stakeholders in the coming few years. Further, the Community Forest Agreement only covers the use of forest NTFPs, one of the three threats identified (above). Additional tools would be required to improve management of waterbodies or hunting and trade of wildlife. 29. Seila (see below) is the principal promotion agency of decentralization, including the transfer of implementation responsibilities over national programs included in the new laws. However Seila has only recently started to function in some of the provinces within the Northern Plains landscape, and initiatives relating to the new land and forestry laws are only being implemented in one of the four provinces, Siem Reap. LMAP (see below) is the principal implementation project of the new land law, however only Siem Reap belongs to the priority provinces. Some assistance will still be provided to non-priority provinces, including support for a provincial land conflict resolution committee. Agencies can, however, be informed by Seila projects in other areas - particularly the provinces of Ratanakiri and Mondulkiri (with LMAP). Without the assistance from another Agency the implementation of the new legislative framework in the Northern Plains would be weak. 30. Some existing legislation contains minor provisions on hunting and trade of wildlife issues. However they fail to address several key issues or provide MAFF with incentives necessary for adequate enforcement. Inside a protected area, enforcement is governed by MoE. A series of wildlife protection sub-decrees is currently being enacted, developed by the Forest Administration, with technical legal assistance from WCS. 31. Despite substantial improvements in Cambodia’s legal framework within the past three years there is no current facility to ensure that all stakeholders are aware of these new laws and it will be necessary for many agencies to help increase understanding of the implications and possibilities arising from these laws. In addition, without positive incentives to encourage changes in land use that are allowed for by the new laws current patterns of land management may not be altered, despite implementation. Seila programme and LMAP (see Annex 9) 32. Seila Programme is an aid mobilization and coordination framework in support of the Royal Government’s decentralization and deconcentration reforms, and its goal is to contribute to poverty alleviation through good governance. The core Seila component is PLG (Partnership for Local Governance), which provides technical assistance and funding to provincial government, provincial departments and district and communal authorities in support and implementation of development plans. PLG is entirely funded by UNDP. At the province level, the Provincial Rural Development Committee (PRDC) chaired by the Governor and including all Department Directors, District Chiefs and senior officials from the military and police, are responsible for the administration and management of the provincial territory. At the Commune level the Commune Development Committees (CDC), chaired by the commune chief and elected representatives are 14 responsible for the administration and development of the commune. This includes management of natural resources (including forests), however in general these issues are afforded lower priority than those relating to health, education, and so on. 33. Seila/PLG also provides support to provincial departments in their decision-making and implementation, especially where it is relevant to national strategies. Recently, support as been provided to the provincial Department of Environment, in establishing a community forestry area inside the Kulen Promtep Wildlife Sanctuary, and the provincial Department of Agriculture, Forests and Fisheries to establish a community forest. However, capacity constraints mean that these initiatives are likely to remain localized, and will not consider the landscape priorities in the allocation of future funding. Institutional Framework 34. Two ministries, MAFF and MoE, are responsible for the management of components of biodiversity. Planning in both ministries does not incorporate landscape conservation values. For example, the Kulen Promtep Wildlife Sanctuary contains 20,000 people in 4,000km². Recently the provincial department of the environment has requested that several villages be moved, for conservation purposes. However, these villages are located in areas with few of the key components of biodiversity, or resources that they depend upon. Further, the villages are located along a main road and are being settled by people moving out of a region that contains several species of key conservation concern. 35. Enforcement of laws governing logging and the hunting and trade of wildlife is the authority of Forest Administration (FA) of MAFF, and, inside a protected area only, MoE. The capacity for MoE for enforcement is weak, mainly due to a lack of training, equipment, infrastructure and (particularly) provincial-level support. 36. The new FA structure has created a four-tiered hierarchy of administration units from Sangkats (covering several communes), Divisons (one or more districts), Cantonments (effectively Provinces) and Inspectorates (each governing approximately a quarter of Cambodia). This decentralization has led to large numbers of staff being relocated to provincial areas, and has led to an increase in law enforcement and regulation. The new Sangkat boundaries do not particularly reflect forested regions or conservation priorities. In addition, in a similar manner to MoE, staff lack training, equipment, infrastructure and provincial-level support. In some cases, FA staff have been involved in the confiscation of small-scale hunting gear and logging equipment used by local communities and of incidental trade of lizards of turtles. However, these activities ignore areas of much greater importance for biodiversity and much more serious threats (hunting with guns, large-scale logging, wildlife trade to Thailand, activities by armed forces etc.). Some activities, for example placement of small traps around rice fields, may be illegal but have little impact on the key components of biodiversity, which are generally found further from villages. 15 37. In the past few years development projects have begun to transform the landscape. New roads have been built bisecting the Kulen Promtep Wildlife Sanctuary and a road is planned across the Preah Vihear Protected Forest. One road through the wildlife sanctuary split an area that, in the wet season, supports a colony of breeding large waterbirds. A logging concession (TPP) was declared that included a steep-sided plateau, Phnom Tbeng. However, logging of the slopes would seriously increase the risk of landslides and floods and would have implications for the quality of the water supply to one of the provincial capitals. 38. In general, Government capacity to address conservation issues at the landscape scale still remains very weak at all levels, although it is improving. The capacity at provincial level to implement and enforce laws is still low. Coordination between government agencies and with relevant stakeholders is lacking. The capacity of the local community and provincial departments to participate in decision-making and in land use planning and management is limited. The only exception is the management of Ang Trapeang Thmor reservoir. This site was declared a Crane Reserve by Royal Decree in 2001, under the responsibility of MAFF. Subsequently, ICF (the International Crane Foundation) has provided financial and technical support to MAFF site officers, including land use planning. Given this continued support the importance of at least one landscape feature for biodiversity conservation should be recognized. Summary of Baseline 39. The baseline response to the threats and underlying causes can best be characterized as having a strong new legislative framework, but very little implementation of that framework with consideration of conservation objectives would be achieved for the following reasons: Government staff and institutions are not yet using the new framework; partly because it is a new development, but also largely because they lack the capacity for implementation. There is little awareness amongst government staff and institutions regarding the globally significant biodiversity values of the Northern Plains, and how these could be incorporated into implementation of the new laws. Implementation of the new framework would be slow and fragmented, with different government institutions promoting particular aspects (e.g. land rights, enforcement, and so on). Although changes might be achieved these would probably be too late to sustainably manage the keystone landscape resources that wildlife populations require. Low incentives for armed forces to participate in implementation of the new legislative framework. Low incentives for alternative land use options amongst local communities means that present land use management may not change, despite implementation of the new legal structure. Existing management support to MAFF at Ang Trapeang Thmor means that this is the only key site in the landscape recognized for biodiversity values. 16 Consequently, exploitation of the landscapes’ natural resources will continue through unrestrained and unmanaged land use and development. This will lead to increased conflict with wildlife movements across the Northern Plains and their reliance on keystone resources. PART II: STRATEGY Project Rationale (The Alternative) 40. The CALM project applies a three-pronged approach to augmenting the baseline efforts in order to achieve global environmental outcomes: (i) introduce biodiversity into provincial-level land use processes (using PLUP, land tenure and the implementation of new Laws). These interventions will occur across the Northern Plains by virtue of the fact that they will be strengthening provincial level institutional capacities. This will be done through Component 1. (ii) “road test” more specific mainstreaming interventions at 4 key sites - community land-use tenure; community contracts and incentives for changes in land-use practices, biodiversityfriendly resin tapping, and - most importantly - working to mainstream biodiversity into 2 production sectors; forestry (in the concession sites) and tourism. This will be done through Components 2. They can be scaled-up by contributing to Component 1. (iii) strengthen biodiversity management at 4 key sites within the landscape mosaic by ensuring the needs of the landscape species (waterbirds and large mammals) are understood and addressed. This will be done through Component 3. An additional Component 4 will cover Project Management and Evaluation, including adaptive management, project reviews and reporting to GEF. 41. The second and third prongs will be developed under the “Landscape Species Approach” to achieving biodiversity results at the landscape level. The approach is consistent with the GEF Strategic Priority BD-2’s rationale of integrating biodiversity conservation into the broader development agenda through capacity building and demonstration1. Introducing Biodiversity at the Provincial Level 42. The project intervention will work to introduce biodiversity values into landscape-level landuse processes. Implementation will focus particularly on building the capacity of provincial departments and authorities and integrating specific project initiatives with established provincial planning processes (supported through Seila/PLG ). These specific project initiatives include the direct implementation of the new land law and sub-decree on community forestry to develop management plans for natural resource areas that include conservation of key components of biodiversity. The project will also work with the forestry and tourism sectors, and the provincial 1 GEF/C.21/Inf.11 17 departments of agriculture and environment, to enhance the recognition of key components of biodiversity in planning and management strategies. These activities are described in Component 1 of the full project. The aim of the work will be to ensure biodiversity considerations are incorporated into the new land use planning and management regimes anticipated under the land law and forestry law. The project therefore is in line with objective (a) of the GEF Strategic Priority: facilitate the mainstreaming of biodiversity within production systems. Additional Measures to Achieve Biodiversity Results Across Production Landscapes – the LSA 43. The earlier explanation of the underlying causes of biodiversity loss (see paragraph 21) set out the marginal nature of “production” sectors across the Northern Plains. The ramifications of this are that landscape-level biodiversity outcomes are unlikely to be achieved by mainstreaming biodiversity considerations into the production systems alone. 44. As a result of these ramifications, the GEF alternative will also deliver biodiversity outcomes at the production landscape level through the application of innovative landscape-level conservation tools. This is in line with objective (c) of the GEF Strategic Priority: demonstration. New and better land use management practices are required to help people and wildlife share the same landscapes. The project will apply the “Landscape Species Approach” (LSA) – a wildlife-based strategy used to define conservation landscapes, identify threats and achieve conservation outcomes at the landscape scale in a cost-effective manner (by prioritizing conservation investments). LSA helps identify where human and biological landscapes intersect. It is a tool to mainstream biodiversity values into human uses of landscapes (i.e. productive processes). 45. Pioneered internationally by WCS through its Living Landscapes Program, the LSA centres on preserving the ecological integrity of a large area or wilderness through understanding and conservation of a suite of “landscape species”, selected as being ecologically representative of that landscape. The Living Landscape philosophy is to develop strategies for the conservation of large, complex ecosystems that are integrated in wider landscapes of human influence which includes, but is not restricted to, protected areas, community land, forestry concessions, plantations and other areas of economic importance. For landscape scale conservation to be socially as well as ecologically sustainable, strategies must succeed in a mosaic of different land uses that not only conserve biodiversity, but also allows people to make a living. 46. The focus on landscape species (wildlife) allows the landscape to become geographically tangible and ecologically meaningful and makes the targets for, and outcomes of, conservation investments explicit and measurable. In other words, the approach guides where interventions should “touch the ground” in order to have broader landscape-level impacts. The Northern Plains are ideally suited to this approach as the main biodiversity values reside in populations and unique assemblages of large mammals and waterbirds. Both groups include very good “landscape species”. 18 47. Simple decision rules were used to select a suite of 10 landscape species (or species groups) that had particular habitat requirements and were threatened by particular human behaviours (see Annex 1). The Living Landscape philosophy states that interventions designed for the conservation of these species will be sufficient to address the threats faced by and habitat requirements of the other key components of biodiversity found across the landscape. During the PDF-B the distribution of each species was mapped across the Northern Plains (see Map 2). This distribution was analysed in comparison with the human threats (see Map 3) and used to select four key sites for conservation (Map 4), comprising a total of 12 core and 8 buffer areas (see Annex 2). A fifth key site, Ang Trapeang Thmor, was not included due to the existing strong management support to MAFF provided by ICF. 48. The selection of these key sites implies that the successful management of each, for all of the key species, will result in the maintenance of all components of biodiversity across the Northern Plains landscape. However, only one of the key sites, Kulen Promtep Wildlife Sanctuary, lies within a formal PA, and, in addition it has a population of over 20,000 people. Another is within the Preah Vihear MAFF-designated ‘protected forest’ for which management guidelines are yet to be established but will include conservation objectives together with productive uses. Ang Trapeang Thmor is a Protected Area by Royal Decree, although again management regulations are unclear. ICF is currently working with MAFF to develop a management structure. The remaining sites are the O’Scach and O’Dar rivers within the Chendar Plywood logging concession, which is contiguous with the Preah Vihear Protected Forest, and the Phnom Tbeng plateau, inside the TPP logging concession. The CALM project is designed to integrate biodiversity values within the human land-use systems found in these key sites, with the aim of maintaining local populations of key species. If the assumptions of the Living Landscape approach are valid then the suite of sites selected will (importantly) be sufficient for the successful conservation of all key components of biodiversity across the landscape. 49. At the four key sites the project will test specific project initiatives that aim to mainstream biodiversity values into the human use of the landscape. These initiatives will include the use of PLUP with communities and authorities to map and approve community land-use areas and establish management plans for these areas that recognize biodiversity values (Component 2). Community land-use will include the establishment of security of tenure for the owners of resin trees, in order to promote this sustainable form of forest use. A program of ‘contracts’ will provide direct incentives to those communities that incorporate measures for the conservation of key biodiversity components into their management plans, and lead to tangible changes in resource-use behaviour (Component 2). An education and awareness program (Component 3) will be necessary to increase the capacity of communities to plan and manage natural resources with consideration of the impact of decisions on biodiversity components. The products of Component 2 will be integrated into provincial-level (and hence landscape-level) processes through Component 1. 50. Lack of know-how has been identified during the PDF-B phase as a key barrier to sustainable natural resource management that needs to be addressed - in addition to securing tenure and user rights. Simple usufructual rights will not promote sustainable management if communities are 19 unaware of the alternatives to short-term over-exploitation. The project will support the removal of some of the key knowledge barriers to sustainable natural resource management through Component 2: a) Economic and financial viability The conditions necessary for the economic and financial viability of sustainable natural resource management have not been elaborated in the Northern Plains. Clear guidelines are needed for practitioners and planners to be able to recognize the conditions under which the new legislative framework can provide adequate incentives for communities to adopt sustainable practices. This will be evaluated by activity 4.2. b) Technical know-how Provincial authorities and local communities need to understand appropriate harvesting systems and management strategies for forest NTFPs and water resources. In addition, they lack the technical knowledge of how to use the results of community-based monitoring to define sustainable harvesting limits. c) Financing Provincial authorities and local communities lack appropriate knowledge of accounting systems and the costs and benefits of sustainable natural resource management. d) Enforcement Practitioners need to know what types of internal and external enforcement/control/oversight mechanisms to recommend for sustainable natural resource management and how to maintain these functioning systems. 51. In some cases improved knowledge may be insufficient to encourage a change to sustainable management practices, particularly if they are viewed with suspicion, or require foregoing financially attractive but highly unsustainable alternatives. If the new land-use management regime is to be effective in achieving biodiversity conservation outcomes and sustainable livelihoods it will have to generate much more substantial incentives for local communities. Support in protecting their natural resources from illegal activities will help, but it is expected that additional incentives will be required. 52. The incentive scheme and the community contracts (Component 2) are therefore essential requirements of the intervention. Recent reviews of Integrated Conservation and Development Projects have shown that there are very few incidences where increasing peoples livelihoods or meeting developmental needs has contributed to conservation objectives (e.g. Wells, M., S. Guggenheim, A. Khan, W. Wardojo, and P. Jepson. 1999. Investing in Biodiversity. The International Bank for Reconstruction and Development, Washington D.C.). Many conservation projects around the world are emphasizing more direct incentives approach or in some cases a direct payment for biodiversity conservation. These might be in the form of easements for nonuse and performance payments based conservation outcome. These payment plans are based on a person or group of people producing conservation outcomes in exchange for a payment in cash or exchange (Ferraro, P. J., and A. Kiss. 2002. Direct Payments to Conserve Biodiversity. Science 298). In the Northern Plains, these incentives will replace income lost through reductions in current exploitation patterns in the short-term whilst long-term sustainable practices are developed (including wildlife tourism, resin-tapping, community forests and fisheries). Options will be investigated during the first year of the project, but might include: 1. The leasing of keystone watersources in the short-term, replaced by a tourism observation platform in the longer term. 20 2. Payments for reductions in incidences of poison fishing in the short-term, in the longerterm the establishment of community fisheries and the recovery of fish populations would demonstrate the clear benefit of the cessation of unsustainable fishing methods. 53. An evaluation system would be established for the incentives scheme, and rewards only provided if the community contract is upheld. During the PDF-B CALM established a pilot project that serves as an example of how the incentives scheme might work. The village of Tmatboey was selected as an eco-tourism site. An agreement was made with the village whereby CALM would facilitate tourist visits to see Giant Ibis, in exchange for a commitment not to hunt with guns, collect eggs or chicks (or assist others with these activities). Each tourist group was levied a fee, and the agreement states that this money will be dispersed to the village at the end of the 2004 wet season, if the agreement has been upheld. Village meetings will be held before this time for the community to decide how the funds should be spent. 54. Activity 2b2 of the intervention will specifically research the requirements for the incentive scheme. In particular, there will be an economic analysis of the environmental values being compensated, and the benefits of short-term over-extraction. This will be used to determine an appropriate level of payment under the incentive scheme. Activity 2b2 will also establish the mechanism (rules and processes) by which incentives are provided to communities, and the procedure for evaluation of the scheme. Finally, Component 3 will address the sustainability of the scheme, by calculating its long-term running costs and identifying the source of future revenue. 55. Within the same key sites the project will strengthen biodiversity management through support to the relevant government structure (MoE in Kulen Promtep Wildlife Sanctuary and the FA in the remaining sites). At the MoE site activities will be managed by the WS Director, with support from project officers. At FA sites local activities will be managed by the Sangkat and Division directors of the FA, with site co-ordination provided by a FA Site Manager. WCS/FA have successfully adopted this management structure for another project in Mondulkiri. This implementation structure ensures that project activities are integrated within government structures, thus increasing the sustainability of initiatives. The FA and MoE site managers will be responsible for approving and promoting agreements made with communities (including Community Forestry Agreements and PLUP maps) established during Component 2. Some immediate government action will be necessary at these sites if the threats from outside individuals and armed forces are to be reduced and biodiversity is to be maintained. However, in the longer term project initiatives (Component 2) will strengthen local community governance and reduce the need for FA and MoE management. 56. In Component 3 the project will provide site assistance to the local FA or MoE management structures - particularly through training, equipment and infrastructure to address the ‘knowledge barriers’ outlined. Site staff will be supported in the production of management plans, particularly focusing on the importance of adaptive management and the ability to respond to prioritize responses to threats across jurisdictional units. The project will ensure that there is a structure for sound management of long term activities. Site management staff will be members 21 of the appropriate authority (FA or MoE) with jurisdiction over the area including key sites. The project will not therefore create new (non-government) management structures, instead providing support to existing systems. Component 3 will also ensure that sufficient training is provided to government managers and provincial staff. Activities under this component will further establish the infrastructure and necessary equipment for long-term management of key sites. 57. At each site, the project will train and support FA or MoE staff in the legal framework and law enforcement (Component 3). Government staff will then work to address site threats and, across their jurisdictional control (FA Sangkat or MoE WS), to target threats such as the wildlife trade. Enforcement will be conducted within the limits set by agreements made between the users of key sites (such as communities or concessionaires) and the local authority (FA or MoE). The primary objective of law enforcement teams will be the mitigation of the immediate and substantive threat caused by outside individuals and the armed forces, and supporting the rights of communities established under Component 2. This threat will also be addressed through the education program (Component 3), which will operate both within key sites and for threats (e.g. military bases) across the landscape. In addition, the project will seek the active engagement of armed forces in law enforcement, through their direct involvement in enforcement teams. This model has been used at several locations in Cambodia to reduce threats caused by armed forces. 58. A monitoring program (Component 3) will establish the progress of the project in meeting the objective of maintained biodiversity, in order to inform adaptive management. The LSA implies that the successful management of each site, for all of the key species, will result in the maintenance of all components of biodiversity across the Northern Plains landscape. Component 3 will monitor populations of wildlife and their habitats across each of the sites to ensure that this objective is met. Results will be used to inform an annual process that will prioritize activities for each site (Component 4, Project Management). This will ensure that the project does not adopt a ‘site-by-site’ approach, whereby site activities are completed in isolation and without consideration of the status of other sites. For example, an immediate land encroachment problem would be solved by mobilization of PLUP teams from other sites where threats were lower. 59. Activities within Component 3 will include an initiative to monitor the remaining population of Gyps vultures in the Northern Plains. These species will become extinct in the Indian subcontinent within the immediate few years as a consequence of poisoning by a veterinary drug - a drug that is not used in Cambodia. The Cambodian and Myanmar populations will therefore represent the only wild populations in existence. Within Component 3 the project will use techniques (vulture restaurants) developed during the PDF-B to monitor the vulture populations in the Northern Plains. 60. Many project activities (Component 1, 2-3) will be completed within the 7 year project plan. For other activities (Components 2 and 3) and management support (Component 3) start-up costs will be covered by the project and long-term running costs are expected to be low. Component 3 will assess the cost of maintaining necessary project activities in the longer-term and identify funding sources (see below). The final Component 4, Project Management and Evaluation, will 22 include reporting to GEF, adaptive management across implementation units and project reviews. Relevance to UNDP Outcomes 61.The project will directly contribute to the achievement of the service line 3.5 Conservation and sustainable use of biodiversity under the second Multi-Year Funding Framework (MYFF) 2004-2007 of UNDP. The linkages that the project will build with the provincial Seila programme (see Annex 9) will help to integrate environmental concerns into the local planning process and thus will strengthen the framework and strategies for sustainable development at the local level (service line 3.1). In addition, the project will develop community land use planning, monitoring and law enforcement mechanisms, thereby helping to control deforestation and land degradation (service line 3.4). At the landscape-level the project will facilitate the incorporation of biodiversity conservation values into provincial and national planning processes, including, for example, the recognition of key sites for conservation. The project will contribute to the achievement of the target 9 of MDG 7, to “integrate the principles of sustainable development into country policies and programmes”, specifically indicators 25 (forest cover), 26 (protected areas). National Support for the Alternative 62.The Royal Government of Cambodia’s key policy documents illustrating support for the objective of the project are: (i) the Second Socio-Economic Development Plan (SEDP II) adopted in 2002; (ii) the National Environmental Action Plan (NEAP) adopted in 1997; (iii) the National Climate Change Action Plan; (iv) the Cambodia's Initial National Communication to the UNFCCC; (v) the National Biodiversity Strategy and Action Plan adopted in 2002; (vi) Cambodia Report to the World Summit on Sustainable Development (WSSD) approved in 2002; (vii) the Governance Action Plan (GAP)2 adopted in April 2001; (viii) the National Poverty Reduction Strategy (NPRS) launched in March 2003; (ix) the Cambodia Millennium Development Goals (MDG) Report; and (x) the Rectangular Strategy. The National Biodiversity Strategy and Action (NBSAP) highlighted the importance of the Northern Plains landscape and the necessity for improved management of Kulen Promtep Wildlife Sanctuary. 63. Through the development of new laws on land, forests and wildlife protection within the past three years, the RGC has demonstrated a strong willingness to improve the management of forested areas and their wildlife components. Cambodia is presently undergoing a forestry review period that includes evaluating alternatives to commercial forestry, such as community forests, the sustainable harvesting of NTFPs by indigenous communities, and biodiversity conservation. The policy of the national Forestry Administration (FA) of MAFF aims to improve forest management through the development of strategies that complement or provide alternatives for commercial forestry. The CALM PDF-B has directly informed the decision of 2 Reform of natural resources management (land, forestry and fisheries) is one of 8 priority areas to which the RGC has committed itself through the implementation of the GAP. 23 MAFF to designate the Preah Vihear Protected Forest. In other regions of Cambodia these protected forests are being used to develop models for forest management. 64.The Royal Government of Cambodia considers good governance as the backbone of the national strategy to alleviate poverty. The National Development Objectives outlined in the SEDP II focus on “Three Pillars”: Economic growth that is broad enough to include sectors where the poor derive a livelihood Social and cultural development Sustainable use of natural resources and sound environmental management. The RGC’s Rectangular Strategy focuses on addressing forestry reform based on the forest sector strategy that will ensure sustainable forestry management based on the three Pillars as follows: 1. Sustainable Forest Management Policy: to ensure the rational and strict monitoring of forest exploitation according to the international best practices in forest management that require adequate forest reserves for domestic consumption, protection against drought and floods as well as wetlands that serve as fish sanctuary; 2. Protected Area System to protect biodiversity and endangered species; 3. Community Forestry as a sound, transparent and locally managed program The Prime Minister Samdech Hun Sen and other senior officials of the RGC have on many occasions publicly acknowledged that achieving effective governance will be essential to Cambodia’s sustainable development including a substantial reduction in corruption, will be especially important to overcoming the aforementioned economic challenges. In particular, the Prime Minister stated on 16 July 2004 that “Good governance is the most important pre-condition to economic development with sustainability, equity and social justice. Good governance requires wide participation, enhanced sharing of information, accountability, transparency, equality, inclusiveness and the rule of law. In this regard, good governance will ensure that: corruption be reduced to the minimum, the views of minorities and the voices of the most vulnerable in society be fully heard and considered in the decision making processes. Indeed, the attainment of good governance is crucial to the proper functioning of society both in the present and the future.” 65. The latest Royal Government of Cambodia – Donor Consultative Group (CG) meeting took place on 6-7 December 2004. At the meeting government and donors, through established technical working groups, proposed the following benchmarks relevant to CALM: Area Key proposed relevant Benchmarks - Increase transparency of state management of natural resources Cross-cutting for through immediate public disclosure of existing contracts and Agriculture and compliance status (royalties and other key provisions) of contracts Natural Resources governing economic land concessions, mining concessions, fishing Management lots and continued disclosure of status of review of forest concessions - Increasing emphasis, with donor support, for local benefit sharing arrangements for management of natural resources including local 24 Forestry communities, private sector and decentralized resource management agencies - The Technical Working Group on Forestry and Environment (TWGFE) will implement its agreed work plan and benchmarks for 2005 - RGC disclose the location and legal status and process for termination of mining concessions, Military Development Zones, economic land concession and other development arrangements situated on forest land or in protected areas and inconsistent with law governing management of these areas CALM will directly assist the TWG-FE to implement its workplan, by contributing to the following indicators: Benchmark 1. Major part of the natural forests rationalized, reclassified and dedicated to their ecosystems protection and biological conservation functions. 2. Socio-economic value of forest ecosystems protection and biodiversity conservation of forest resources promoted. 3. Benefits to local people from the use and management of forest resources optimized via implementation of forestry and wildlife management concepts based on the participation of local populations 4. Capacity building, institutional strengthening and research program implemented at all levels through the adopted Overall Capacity Building Program for Forestry Sector. Indicator Item 1.1.1 Rationalization /reclassification and practical implementation of Forest Demarcation and protected areas demarcation completed for 1 mill ha, giving due consideration the claims of indigenous people and settled communities Items 1.1.2 and 1.1.3 National Forest Management and Protected Area Plans are prepared, and implemented and managed accordingly. Item 2.1.1 Sustainable increase forestry incomes and environmental services in consistent with the real forestry potentials. Item 3.2.2 Partnership forestry approach testing initiated in pilot communes for contributions to local development. Item 4.1.1 Overall Capacity Building Program implemented Demarcation of protected areas in Northern Plains (Component 3) Management Plans for Protected forest and Wildlife Sanctuary (Component 3) Improvements in forestry community livelihoods measured by CALM impact indicators (Component 2) Establishment of community natural resource management systems (Component 2) Capacity-building for government staff and local authorities (Components 1,2,3) 66. UNDP considers sustainable management and rational use of the natural resources of Cambodia a necessary supplementary prerequisite to the national strategy to alleviate poverty. Accordingly, and in line with the government’s national priorities, support to good governance in the fields of environmental and natural resource management is also a priority area for both the UN system and the RGC. This is elaborated in the first United National Development Assistance 25 Framework (UNDAF 2001 - 2005) and the second UNDP Country Co-operation Framework (CCF 2001 - 2005). Sustainable management of natural resources is one of the four programme areas of concentration in the UNDAF 2001-2005 for Cambodia. The UNDAF provides for the UN system focusing on supporting national efforts in land use planning, sustainable forestry and fisheries activities, and the promotion of environmental awareness and protection. 67.Under this overall framework, UNDP’s second CCF for Cambodia has identified the Management of Sustainable Resources as one of the three programme areas. Under the CCF UNDP’s support to Cambodia in the area of environment and natural resources, management is focused on: I. Strengthening monitoring and assessment of environmental sustainability. II. Promoting national policy, legal and regulatory framework for environmentally sustainable development III. Enhancing national capacity for participation in global conventions, regulatory regimes and funding mechanisms for environmentally sustainable development. 68.The proposed CALM project reflects on all three programme areas. By strengthening the sustainable development strategy of Cambodia through capacity development and good governance, the project is consistent with the UNDAF/CCF. Project Sustainability, Partnerships and Linkages “The Royal Government considers as a top priority the strengthening of partnerships with all development partners, including the donor community, the private sector and civil society. The mechanisms of partnership with the donor community shall be established consistent with the Resolutions of the General Assembly of the United Nations, the principles of the Organization for Economic Cooperation and Development – Development Assistance Committee, as well as the initiatives of the World Bank and the United Nations Development Programme (UNDP).... Civil society shall become an effective partner of the Government in nation building. To this end, the Royal Government will encourage the activities of the Non-Government Organizations and other duly registered associations working to serve and benefit the people and the nation. The Royal Government welcomes the participation of the NGOs in the process of socio-economic rehabilitation and development.” Statement by Prime Minister Hun Sen National Ownership 69.National ownership of project activities and outputs is critical for successful implementation. Ownership will be achieved by the fact that activities and processes will be dictated and carried out entirely by Cambodians through a series of national stakeholder consultations. 70.The project steering committee will be set up to oversee the project’s direction and strategies. The ownership of the project will be broadly linked with the current UNDP supported decentralization program (Seila/PLG). The project activities and plans will be integrated into the Provincial Seila/PLG Programme thus the project will be recognized and will operate within the 26 provincial annual planning framework. The Provincial Rural Development Committee/EXCOM will be used to provide leadership forums to discuss and coordinate to integrated landscape conservation and development into Seila/PLG. The existing National Biodiversity Steering Committee will provide an overview on how the project should contribute to the achievement of the national conservation agenda as set in the National Biodiversity Strategy and Action Plan. The National Committee on Discussion, Recommendation and Conflict Resolution of Protected Areas, which was established in 2000 will be used to resolve any institutional conflicts regarding the management objectives of Kulen Promtep Wildlife Sanctuary in particular and regarding the management of the productive landscape in general. 71.To implement Component 2 participatory land use planning (PLUP) will be used as a tool to generate consensus on how land is management and allocated to local communities. This will contribute to the objectives of conservation and sustainable use of the landscape. Commitments, Partnerships and Linkages 72.The Royal Government of Cambodia has committed to long term conservation and sustainable use of natural resources in the region through the establishment of the Kulen Promtep Wildlife Sanctuary and the Preah Vihear Protected Forest in the region. UNDP is committed to capacity building and sustainable management of natural resources in Cambodia. 73. The Wildlife Conservation Society (WCS) Cambodia Program will be the non-Governmental implementing partner, operating under its existing MoU in cooperation with both the concerned Government Ministries (MAFF and MoE). The Royal Government of Cambodia and UNDP have selected this NGO based on its proven technical, managerial, administrative and financial expertise and both global and Cambodia-specific experience in conservation and promoting a community based participation in conservation in the project area. Moreover, WCS already operates under a 5-year MoU signed on 13 December 1999 with MAFF and MoE defining a cooperative programme on biodiversity conservation in Cambodia. WCS has now been required to sign individual Project MoUs. The project agreement with MAFF for the Northern Plains was signed in December 2003 and lasts for the duration of the 7 year project (until 2011). WCS is committed to the conservation of the Northern Plains landscape having contributed $475,400 to activities during 2000-2003. During the full project WCS is looking to mobilise co-financing of about $1,600,000. 74.Specific linkages to GEF and IA programs and activities include: • UNDP/GEF/ADB Integrated Resource Management and Development in the Tonle Sap Region There is an important relationship between the Northern Plains and the Tonle Sap that is essential for the existence of a unique assemblage of wildlife. Reflecting this, the project would complement the current UNDP-GEF for Integrated Resource Management and Development in the Tonle Sap Region. Many of the globally threatened species that breed on the Tonle Sap, such as Spot-billed Pelicans Pelecanus philippensis, Painted Storks Mycteria leucocephala, Greater 27 and Lesser Adjutants Leptoptilus dubius and L. javanicus are heavily reliant on being able to disperse across the Northern Plains in the wet season when resources on the lake are scarce. Conversely, Sarus Cranes Grus antigone and White-shouldered Ibis Pseudibis davisoni breed in the Northern Plains and return to the large permanent wetlands on the floodplain at the beginning of the dry season. However, far from being a simple flow of wildlife following the flood line, the regeneration of habitats and the movements of wildlife are complex and little understood. Of the two landscapes, the lake has received nearly all of the recent conservation attention, and has been designated a UNESCO Biosphere Reserve. Whilst warranted, the status of the Northern Plains as, firstly, a unique biome and, secondly, as an integral ecological cornerstone for the Tonle Sap, has been entirely neglected. This bias in conservation resources has long-term dangers, which, if ignored, could result in the loss of a significant proportion of regional biodiversity. • WB/GEF Biodiversity and Protected Areas Management Project (BPAMP) BPAMP’s overall objective is to improve the MOE’s capacity to plan, implement and monitor an effective system of protected areas (PA’s). The immediate objectives focus on developing and testing measures to minimize degradation of the biodiversity of Virachey National Park (VNP) and to use the field experiences for the development of the national PA system. At national level, the project has made important contributions towards improving the capacity of the MOE by strengthening the Geographical Information System (GIS) Unit and drafting a Protected Area Law. The final enactment of this law, possibly in 2004, will be particularly relevant for CALM and activities in Kulen Promtep Wildlife Sanctuary. BPAMP has also achieved significant local successes in developing ‘best practice’ models for some project components, which are suitable for implementation inside and outside of Protected Areas in the Northern Plains. These include the development of community-based NRM planning and its integration with provincial planning, and the on-going implementation of a management information system (MIST) originally designed for use in Ugandan National Parks. CALM has held consultations with BPAMP staff to understand how linkages can be made with these components. A trainer from BPAMP participated in the CALM PLUP training course, including a detailed description of the activities undertaken to setup community NRM committees. The MIST software is particularly relevant for use by enforcement teams, to enable reporting and analysis of patrolling effort and trends in illegal activities, and might suitable to transfer to the Northern Plains as part of Component 3 (Law enforcement) of CALM. BPAMP has also recently developed a management plan for VNP, which, although relatively complicated, might provide a model for plans developed by CALM for Kulen Promtep later in the project. During the full project these linkages will be investigated further. According to BPAMP’s mid-term review the project’s impact has been limited by (i) insufficient technical support (especially from international advisors), (ii) the physical distance between the two project offices; (iii) the weak institutionalisation of the project which limited the scope of project operation and continue to make planning and agreements beyond the project period difficult; and (iv) rapid changes in legislation which made it difficult for the project to pursue a coherent strategy towards the local communities. Two of these (ii and iii) are relevant to CALM, 28 whilst the others are less applicable. CALM has, for example, been developed with strong international assistance from WCS, and this relationship will be maintained through the full project. Further, the legislative framework (with the exception of the new PA law) is now established and further changes in policy are unlikely, although individual components may be strengthened through sub-decrees. However, the physical remoteness of the Northern Plains is likely to have a strong impact on the project, and this should be taken into account when determining where project staff should be stationed. CALM should also take into account the relative weakness of BPAMP to produce institutional arrangements within MOE, or to form linkages with other ministries (especially MAFF) and projects. This has particular relevance to Components 1 and 3 of CALM, although both ministries are implementing agencies and are represented on the project steering committee. Project activities and management structures should be rapidly integrated during the full project with ministerial and provincial departments, if the project is to achieve government ownership and management sustainability. Opportunities for forming cross-linkages between staff working on similar components in MAFF and MOE areas should be pursued, to foster ministerial cooperation at multiple levels. • UNDP/GEF Medium-size Project for the Cardamom Mountains The Management of the Cardamom Mountains Range Project focuses on the consolidation of management activities in the region’s three protected areas: the Central Cardamom Protected Forest (CCPF), the Phnom Aural and Phnom Samkos Wildlife Sanctuary (PSWS). The project aims to build national and local government capacity to manage the three areas, combined with sustainable development interventions designed to reduce pressure on the sites from local populations. The project is being co-implemented by the Forest Administration (FA) of the Ministry of Agriculture, Forestry and Fisheries (MAFF) and the Department of the Nature Conservation and Protection (DNCP) of the Ministry of Environment (MoE) in partnership with Conservation International (CI) and Fauna and Flora International (FFI) respectively. The CI/FA component will last until August 2004; while FFI/MoE component will last until April 2006. The project will improve the planning, management and regulatory framework for these protected areas, for example through management plans and land-use zoning systems, practices that could be shared with the CALM Project. The two projects will be able to exchange information regarding wildlife, monitoring and data management to provide a better understanding of landscape management issues. The Cardamom Project will also provide examples of the engagement of local communities in sustainable natural resource management through the use of agreements and the PLUP process. These initiatives are similar to those proposed by CALM under Component 2. • UNDP Seila/PLG The project activities and plan will be integrated into the Provincial Seila/PLG Program, thus the project will be recognised and will operate within the provincial annual planning framework. The Provincial Rural Development Committee/EXCOM will be used to provide leadership forums to discuss and coordinate to integrated landscape conservation and development into the Provincial 29 Development Plans (PDPs). At the commune level, the CDC will be responsible for drawing commune PLUP maps and producing management plans for natural resource areas. PLG is part of the larger Seila programme. Seila is establishing community-based natural resource and environmental management programmes in other provinces, including Ratanakiri (building on the CARERE initiatives) and Siem Reap (supported by DANIDA). The Siem Reap provincial project will extend to an area including one of the Northern Plains’ key sites for conservation in 2005-7. Experience from these other initiatives will be used to understand how to implement CALM initiatives within the Seila/PLG framework in the Northern Plains. • UNDP-GEF Mekong River Basin Wetlands Biodiversity Conservation and Sustainable Use Programme The Northern Plains covers four provinces including the Ramsar Site of Stung Treng located on the Mekong River, which is the demonstration site of the Mekong Wetland Project. The sustainable use and conservation of the Ramsar site should be seen as part of the landscape management strategy and would significantly contribute to the conservation of habitats for migratory bird species. The Mekong Wetland project aims for conservation and sustainable use of biodiversity in the Lower Mekong Basin through strengthening capacity at regional, national and local level, formulating mechanisms to effectively manage wetlands. The project involves four countries sharing the Mekong wetland river basin: Cambodia, Laos, Thailand and Vietnam. At the regional level, the program will develop and apply technical tools for conservation and management of wetlands, as well as developing systems for all the countries to collaborate in wetland conservation. Given the importance of Mekong wetlands for migratory birds within the Northern Plains region, the two projects will provide direct benefits to each other. At national level, by encouraging a multi-sector approach through building capacities and increasing public involvement, the programme will enhance planning processes. The information base needed to support sound wetlands policy, planning and management decision-making will also be strengthened through the development of specialists network, awareness campaigns, adequate tools, and Wetland Action Plan. At the local level, within the demonstration site of Stung Treng, integrated planning and community-based natural resource management will be implemented. The programme will identify the values of the fresh water ecosystem and work with local people to develop improved management systems and alternative livelihood options. Training will be provided and information will be disseminated as part of a targeted awareness campaign. Sharing lessons learnt from local governance, community based natural resource management and ecotourism, as well as national policy implication from GEF projects will benefit conservation of biodiversity in the respective projects. • WB/Land Management and Administration Project (LMAP) The overall goals of the project are to reduce poverty, promote social stability and stimulate economic development. The specific objectives of the project are to improve land tenure security and promote the development of efficient land markets. The project is planned to run 30 from 2002-2007 and is managed by the Ministry of Land Management, Urban Planning and Construction. LMAP has supported the establishment of the “Council on Land Policy Reform” by the Government. LMAP is developing legislation and policies to strengthen land tenure through implementation of the land law, which is directly relevant to component 2 of CALM. LMAP has set up Provincial Cadastral Commissions to resolve land disputes and conflicts, following the guidance of the recently approved Sub-decree. CALM will help local communities and Government officials to understand and use these commissions to help secure community tenure and title as part of component 2. LMAP is also producing guidelines and case studies to improve land-use mapping and zoning and CALM will be able to learn from these findings and integrate them into the management of the Northern Plains. • MAFF/ICF management of Ang Trapeang Thmor Ang Trapeang Thmor is a large man-made reservoir, constructed during the 1970s. The large wetland and grassland areas provide an essential dry season feeding refuge for the majority population of Eastern Sarus Crane Grus antigone. The site is also important for many stork species, Spot-billed Pelican Pelecanus philippensis, and has probably the largest single herd of Indochinese Eld’s Deer Cervus eldi siamensis. Earlier surveys by WCS, the International Crane Foundation (ICF) and MAFF had identified Ang Trapeang Thmor as a critical landscape feature for biodiversity conservation. This led to the proclamation, by Royal Decree, of the site as a Conservation Area for Sarus Crane. Ang Trapeang Thmor continues to be managed by MAFF with support from ICF. It is therefore not recognised as a key site for CALM due to the existing management assistance. CALM will be able to learn from the experiences of that project, particularly in establishing a site management structure and the importance of land-use planning. Sustainability 75. CALM will build the capacity of the government staff at the national and local levels to maintain project ownership. This will include considerable support to the new local government system, the Commune Councils, which were established by elections in 2003. The commune officials will be primarily responsible for developing community regulations on natural resource management. Further, CALM will build cross-institutional coordination amongst relevant government agencies. Key project outcomes will be endorsed by the appropriate government authorities. Consultation and participatory processes will generate a better understanding of conservation priorities and better cooperation with relevant government agencies. The participatory and consultation processes will also be promoted to generate trust and respect the voices of various national stakeholders. 76.The project will develop leadership of key national staff in planning, decision making and coordination. The implementation process will be led by Cambodian nationals with the 31 minimum of technical assistance from external consultants. This will ensure that there is very little dependency on external resources after completion of the project. The use of participatory land-use planning processes with communities and stakeholders will build local capacity for land management and development planning. Component 1 will develop a landscape conservation plan, which will be mainstreamed into the local, provincial and national planning process. The project will integrate the principles of good governance such as improving accountability and transparency of decision making process. 77.Several factors will help to ensure the sustainability of necessary project activities and benefits beyond the completion of the GEF project. - Conformity of project activities with new RGC legislation and policy development strategy, and specifically by integrating the project into the Provincial Development Plans (PDPs). - High level of commitment from the RGC for integrated forest management in the Northern Plains. Evidence for this includes the recent designation of a major new protected area (Preah Vihear Protected Forest) and the commitment already shown during the PDF-B phase. - Strong level of commitment from NGOs to support continued biodiversity conservation and community natural resource management in the Northern Plains. - Conformity with the RGC’s policy of decentralisation. The project will raise provincial and community capacity to manage biodiversity and natural resources, in order to substitute expensive centralised control. 78.The project will be designed to cover all setup costs, and ensure that any necessary long-term maintenance costs of project initiatives are minimal. Many components will be completed within the timescale of the project: Landscape Conservation Framework (Component 1). Establishment of community land-use tenure and title (Component 2) and resource management plans (Component 2). Environmental Education program (Component 3) For other components or activities initial costs will be high, however necessary maintenance costs will be low: Incentives scheme (Component 2). Law enforcement (Component 3). As security and institutional structures are established the capacity of local communities and provincial government to enforce laws should be strengthened so that available resources are sufficient to cover long-term costs. Monitoring (Component 3). However it is recognised that sufficient financial sustainability must be established to cover these maintenance costs, especially the incentives scheme and monitoring program. An incremental cost matrix will be produced to identify the costs and activities. Opportunities for key-species eco-tourism have been researched during the PDF-B, and there is potential for tourism to fund necessary project activities, especially the village incentive scheme (Component 2). During the full project, activities will create a framework for key species eco-tourism that benefits both 32 biodiversity and local communities. Further activities will investigate the potential for establishing a trust fund, or securing long-term additional government and NGO financial commitment, to fund other necessary project activities (e.g. the monitoring program). 79. WCS/FA/MoE has successfully piloted a model for biological monitoring at a project site in Mondulkiri. The same model will be implemented in the Northern Plains as part of Component 3, and was established at the Preah Vihear Protected Forest during the PDF-B. Although the start-up costs can be quite high, by year 4 the annual cost of this program is about $10,000. 80. Through Component 3, the project will ensure that there is a structure for sound management of long term activities. Site management staff will be members of the appropriate authority (FA or MoE) with jurisdiction over the area including key sites. The project will not therefore create new (non-government) management structures. The only exception is the Site Project Manager; this position will follow a model created by WCS and the FA for another region in Cambodia. In this region, the FA employs a site manager to co-ordinate activities between FA jurisdictional units within a landscape of importance for biodiversity conservation. Component 1 will ensure that the importance of particular sites within the landscape is recognised and provide support for the continued existence of site managers in the long term. Component 3 will ensure that sufficient training is provided to government managers and provincial staff. Activities under this component will also establish the infrastructure and necessary equipment for long-term management of key sites. Implementation Strategy Inter-Agency Cooperation 81.The Ministry of Agriculture, Forestry and Fisheries and the Ministry of Environment the implementing agencies of the PDF-B, will be involved in project execution through the chairing of the Project Executive Group and by implementation of project activities under the technical assistance of WCS. As remarked earlier, one of the current constraints faced by MAFF and MoE is the lack of an inter-sectoral approach. Through this landscape project, strong ties with MAFF and MoE (relatively the Forestry Administration of MAFF and the Department of Nature Conservation and Protection of MoE) will be established by the project. During the progress of the project, senior staff and technical representatives from various relevant departments at both national and provincial levels will be required to interact, serving to promote multi-sectoral collaboration addressing landscape conservation in the Northern Plains. At policy level, a project steering committee will be established to coordinate policy and management issues. At technical level, a project technical advisory committee will be established to coordinate technical issues. Stakeholder Consultation 82.Inclusion of all stakeholders is critical to the formulation of the project relevant outputs. Stakeholder identification and outreach are needed to ensure participation of a wide range of interests and concerns, including marginalized groups. Extensive consultation through the 33 means of interviews, seminars and workshops will assist in improving planning and decisionmaking under the project. Annex 10 gives the stakeholder consultations completed under the PDF-B, and gives the participation plan for the full project. Risks and Risk Management Strategy 83. There are five risks to the project intervention (see Risk Management Strategy table): 1. Provincial support to the implementation of the new legal structure and government initiatives (land management and administrative policy, forestry reform and law development). 2. Failure to engage the armed forces. 3. Inadequate financial resources for long term running of necessary project activities. 4. Land mines. 5. Security. 6. Corruption 1. Ensuring Provincial support 84. The project relies heavily on the assumption that present national government initiatives continue. Although national policy and legislation is advanced, provincial implementation has been slow and therefore this project will be one of the first to apply the framework in a forested region. Success will be dependent on the extent to which provincial governments are interested and required to execute the new initiatives, though experience with the PDF-B suggests that this interest will remain relatively high. Developing provincial capacity and awareness will be particularly important. The high level of support from national government, and the activities of Seila/PLG means that there are be several mechanisms to ensure the engagement of provincial government in project activities. 2. Engagement of Armed Forces 85. Project success will require the engagement of the Royal Cambodian Armed Forces (RCAF) and Police Forces. The military and police are influential bodies in the Northern Plains, particularly in the border regions, and the governor of Preah Vihear province is a military general. The involvement of the military will be especially necessary if border wildlife trade and logging is to be controlled and if community management plans are to be successful. Issues with military in Cambodia and CALM site Although Cambodia has established democratic government with support from the international community, the country is still in the process of strengthening governance, in particular at the local governance. The lack of strong governance, coupled with a high level of poverty, particularly in the provinces, provides a high incentive for officials to be involved in illegal activities. Provincial soldiers, for example, often receive little more than a monthly ration of rice as salary, and therefore require an alternative source of income to maintain their base. Since the 34 military are armed their capacity for corruption and illegal activities is considerably greater than other officials. The Northern Plains is no exception. In the area of CALM project, military threat to biodiversity includes - Illegal logging: Military are the principal proponent of illegal logging in the Northern Plains; local community people sometimes act as guides to show the armed teams the locations of the best trees - Large-scale hunting: Since the gun confiscation programs in the late 1990s firearms are restricted to the Military and Police who use them for hunting, or loan the guns to others. - Wildlife trade in border: wildlife is sold through a series of middlemen either for the national markets, or the international trade, principally across the Thai and Laos PDR border. These border crossings are controlled by the police and military on both sides, and sometimes, the military is involved in such trade. These activities are possible in the Northern Plains because there is little associated ‘cost’. 25 years of conflict has disrupted traditional forms of land management, and encouraged a prevailing attitude of insecurity, promoting a short-term approach to resource extraction based upon competition with other individuals or groups. In addition, the lack of effective law enforcement means that these activities are not penalised. The people who benefit most from this situation tend to be those who are richer and better equiped (generally people from outside or members of the military or police), at the expense of local people. CALM project addresses these threats by the following: 1) Strengthen governance/system of land and natural resource management 86. Engaging the RCAF and Police Forces in conservation will not be a simple matter. Enduring biodiversity results will only come from overall improvements in good governance. The 2003 UNDP Human Development Report considered the issue (Chapter 6: “Public Policies to Ensure Environmental Sustainability”). It suggests two responses to institutional failures and poor governance: strengthened property rights and decentralisation of environmental governance (accompanied by efforts that build community capacity to manage environmental resources and influence planning and policy-making). The CALM project provides these responses. In collaboration with other agencies, the project will establish the first land management system, based upon tenure and title, in the Northern Plains (Components 1 and 2). This will result in the demarcation of land allocated to community management, and clear demarcation of state land. Through the system of community agreements and ‘contracts’ on land-use capacity and understanding of the management of natural resources will be increased, both by communities and by government officials responsible for authorising land management systems. These activities will establish responsibilities for land and natural resources management, consequently the impact and occurrence of illegal activities will become clearly defined. 35 Component 1 will integrate these outputs at higher government levels. Land-use maps and community management plans will require authorisation from Provincial Government, and thus the government will assume some responsibility to ensure that they are not violated by other governmental agencies. The project will support provincial and district-level consultation workshops so that the new land management system is disseminated to stakeholders, including the military. The new Land Law allows for a system of land conflict resolution through provincial Cadastral Commissions. These will be the principal authority used to judge situations where land violations occur. 87. The 2003 Human Development Report goes on to state: “In many developing countries natural resources are plundered by corruption, benefiting powerful elites at the expense of poor people who depend on such resources. Countering corruption requires strengthening governance, with better enforcement, stiffer penalties and increased community involvement. In several countries citizens are assessing how well governments provide access to environmental decision-making and regularly monitor environmental governance. Both efforts will likely spur further progress.” CALM fully supports this approach. The project alternative is to strengthen local community ownership of what are essentially “open-access” resources; by assisting with the application of new Land and Forestry Laws to provide land tenure or usufructual rights and also to develop Community Management Plans for these reousrces (Component 2). Importantly, by supporting an improvement in site-based management there will be much greater disincentive for armed forces to engage in illegal activities (Component 3). This improvement is an essential part of the intervention. A general increase in governance of the Northern Plains is hoped to “squeeze” the illegal activities out. 88. To achieve this “squeeze”, careful attention needs to be paid to making the link between biodiversity management and human development. CALM integrates biodiversity issues into the national development frameworks, by building on the new legislative framework. The project will also strengthen decentralisation for environmental management by supporting the new laws and working through the Seila/PLG programme. It aims to empower civil society through an environmental awareness program and by demonstrating mechanisms to strengthen civil management of biodiversity resources. It also seeks to reduce environment-related conflict by working at four sites specifically chosen to minimize the potential for conflict. 2) Awareness raising Component 3b of the project will increase the awareness of military personnel towards natural resources, management issues, and the role that the military should adopt. The boundaries of community resource areas and state areas will be clearly defined and their significance explained. It is important for military personnel who are involved in illegal activities or who are unsustainably exploiting natural resources to be aware of their actions. 36 The project is piloting an education and awareness program for military personnel, which, if successful, could be extended across the Northern Plains through Component 3b. The new Military Commander, Key Nonn, has assisted project staff in visiting remote army bases to conducted education awareness. Such activities provide a useful example of both increasing awareness of military and engaging them in the project. Since the authority of the Commander must be sought, and he accompanies the project team, this provides an opportunity for him to learn about CALM and its objectives. The project will develop and disseminate a code of environmental conduct for military and police that will be approved by Ministry of Defence, with MoE and MAFF. The process should involve extensive consultations with both military, MAFF and MoE. The Ministry of Defence has a Department of Training, which has been involved in the prodcution of similar codes in other areas, and whose input will be sought. 3) Support from high government officials It is also important that high officials from military, understand the importance of conservation and natural resource management. If key personnel do not understand issues associated with natural resources management, regulations, and management responsibilities, it would be difficult to make all the military personnel to follow the rules. CALM will negotiate with military and senior government officer to obtain evidence of afirm and substantive commitment from RCAF and the Provincial Military, MAFF, and MoE before the project starts. This will include formal discussions and minutes of these meetings, In addition, the project will support greater dialogue between these agencies. Conflicts will be resolved through higher bodies inside the MoE and MAFF. In other areas of Cambodia conflicts have been successfully resolved through high level discussions between MAFF and the Ministry of Interior or Ministry of Defence. Frequent reporting to national government will be necessary so that the relevant Government agency (MAFF or MoE) is aware of those situations where local initiatives are failing. Experience with other projects suggests that national government is driven and able to intervene in those situations where conflicts arise. The most important of the project’s key sites, the Preah Vihear Protected Forest, was declared by Government sub-decree in 2002, and its borders determined by the same government staff who have worked on developing CALM. National government has also shown considerable interest in the threats to biodiversity, such as those the project aims to reduce. Recently there has been positive commitment from the Prime Minister himself in addressing illegal forest related activities through (1) The Prime Minister’s Public Announcement on 31 May 2004 on a government-wide campaign against deforestation; (2) The Prime Minister’s Decision of 06 June 2004 on the establishment of a national committee to prevent, eliminate and suppress the acts of clearance, burning, earth working and encroaching forest lands to claim ownership; and (3) the Prime Minister’s Order of 09 June 2004 on the prevention, suppression, burning, earth working and encroaching forestland to claim ownership. 37 All government agencies are charged with developing their own procedures to implement these orders. 4) Military and Police engagement in conservation Projects in other areas of Cambodia have shown that it is difficult to achieve conservation goals if the Military and Police are not engaged in project activities (e.g. through Component 3c). Approval for joint enforcement teams will be sought from military and police commanders, MoE and MAFF. This model has been adopted in other areas, where it has successfully involved military staff and their officers in conservation activities and goals. In later years, the project will work with provincial and national authorities to request the relocation of military checkpoints and camps away from key sites for conservation (except in those cases where there is a clear National Defence objective). 5) Monitoring Through the site monitoring program (Component 3d) illegal activities performed by the military will be recorded and used to produce yearly reports on the success of the project at reducing this threat. 3. Financial Sustainability 89. The project is assuming that it will be possible to ensure financial sustainability of necessary activities, particularly the incentives scheme. This will be essential if the project is to create structures for long-term biodiversity conservation. The section on sustainability (above) has already considered this issue. 4. Land Mines. Land mines are prevalent in a few sites inside project areas, however the project will mitigate their impact through continuing consultations started during the PDF-B with de-mining agencies, local authorities charged with identifying and prioritising mined areas (e.g. LUPU) and with local communities, so that mined areas are understood and cleared. The project will not develop land-use regulations (e.g. community forestry) for mined areas. Safety and security protocols developed by the project office will make sure that activities are not undertaken in or across mined areas. 5. Security Since 1998 there has been a steady increase in security in the project area, and it is hoped that this trend will continue as governance and access improves. Nevertheless bandits remain a problem in one project site, and security in this area was particularly poor during the PDF-B. The project took this problem extremely seriously and worked to mitigate its impact through 38 consultations with provincial and district police authorities and direct communication with the Provincial Governor. As a consequence several arrests were made and the situation has since improved. During the full project all staff will operate within Safety and Security Protocols developed by the project office, and continuing the policy of advising police authorities on local staff movements. In addition, it is anticipated that project activities will contribute to a continued increase in security. Support to site management authorities and law enforcement teams should lead to a general improvement in the local security situation (Components 3a and 3c). Increases in governance through Component 1 should create awareness of local problems and stimulate higher authorities into taking action (as happened during the PDF-B). 6. Corruption Corruption could be a problem for project implementation. A strong monitoring and evaluation framework has been incorporated into the project design: by maintaining an open and transparent implementation process, with independent review, oversight by the project management staff and auditing of expenses it is hoped that this risk will be minimised. The PDF-B was audited and it was concluded that no funds had been misappropriated during project formulation. It is hoped that this initial foundation will be continued. Addressing fundamental governance issues (low government pay, etc…) is not an outcome of this project, however by linking with Seila/PLG it is anticipated that the project will assist general on-going efforts to improve governance, and, indeed, serve as a model for future projects. 39 Risk Management Strategy 1. Risks 1. Provincial support to the implementation of the new legal structure and government initiatives (land management and administrative policy, forestry reform and law development) continues. 2. Current status of risk on-going 3. Risk rating medium 4. Mitigation activities 5. Relevant project activities Mitigation activities at the provincial level will include improving local governance (mainly through existing Seila/PLG mechanisms) and awareness of sound environmental and natural resource management. The National Project Steering Committee will have an oversight role, and could intervene if required. All Activities under Component 1: Incorporating biodiversity into the implementation of new laws. Particularly including training and awareness-raising (1.1 and 1.2), Seila/PLG integration workshops (1.4 – 1.8), Provincial Steering Committee integrated into PRDC (1.6). Awareness raising 1. Consultations during PDF-B have suggested that provincial authorities’ interest is high, and central government is willing to support project initiatives if required (Annex 10). 2. Raising awareness of provincial authorities. Improving local governance 3. Development of provincial capacity 4. Integration of project activities into Seila/PLG supported provincial planning processes (Annex 9). Seila/PLG’s aim is to support local governance, through decentralised planning, accountability and transparency. 5. Provincial Steering Committee to 40 Development of community land-use plans and their approval by authorities (Component 2, particularly Activities 2a.4 – 2a.6). Environmental Education program (Component 3), particularly Activities 3b.3 – 3b.4. Agreements made with local authorities and military and police commanders (Activity 3c.1) National-level Project Steering review project progress and resolve conflicts, integrated into PRDC. 6. Involvement of additional implementing agencies and projects during the 7-year period of CALM. Example – DANIDA will support an NRM component to Seila in Siem Reap province in 2005. National level – 7. Project Steering Committee, involving national ministries, can identify barriers to implementation and mobilise centrallevel support if necessary. 41 Committee (Activity 4.2) 2. Failure to engage the armed forces. on-going high 3. Financial Sustainability of Activities long term low Activities include – 1. Community land-use plans, tenure and title (Component 2)) supported and recognised by provincial government (Component 1). Site-based management systems (Component 3a) and law enforcement teams (Component 3c). 2. Education (Component 3b) 3. Meetings and workshops conducted with high-ranking provincial and government officials during Component 1 and the Project Steering Committee. 4. Involvement of armed forces in law enforcement teams (Component 3c). 5. Site-based monitoring (Component 3d). See Sustainability section of Project Component 3a will specifically Document. identify necessary long-term The project includes a large number of costs and create a funding plan activities that aim to build the capacity of so that these activities can communities and provincial authorities to continue. manage land and natural resources. These activities will be completed within the timescale of the project (see Para. 77 of Project Document). For others the start-up costs will be high, but maintenance costs will be low. See description in of Project Document 1. Strengthen governance/system of land and natural resource management 2. Awareness raising 3. Support from high government officials 4. Military and Police engagement in conservation 5. Monitoring 42 4. Land-mines 5. Security short to medium term short to medium term low medium to low Land mines are prevalent in a few sites inside project areas, however the project will mitigate their impact by: 1. Continuing consultations with demining agencies, local authorities charged with identifying and prioritising mined areas (e.g. LUPU) and with local communities, so that mined areas are understood and cleared. 2. Land-use regulations (e.g. community forestry) will not be developed for mined areas. 3. Facilitating visits by de-mining agencies and provincial authorities to communities with adjacent mined areas. Promoting clearing of areas important for local livelihoods. 4. Ensuring that no project personnel work in mined areas. Considerable progress has been made in de-mining the project areas during the past few years and if these efforts continue hopefully the risk of land mines will be much reduced in the longer term. The security situation at one project site was poor in 2003, although with the formation of a new government it has subsequently improved. The project takes local security problems, and their threat to communities and staff, extremely seriously and has worked to mitigate this problem during the PDF-B by: 43 Liaison with communities, LUPU and de-mining agencies will occur during the preparation of community land-use plans (Component 2) and their approval (Components 1 and 2). Participation by project representatives in district and provincial integration workshops (Activities 1.4 - 1.6 and 1.8) will ensure that local priorities for de-mining can be promoted at higher levels. Project safety and security protocols will be developed by the Project Office (Activity 4.1), including the risk of land mines. Project safety and security protocols will be developed by the Project Office (Activity 4.1). Project will improve site-based management through Component 3, in particular 1. Extensive consultations with provincial police authorities, PLG and the Provincial Governor. These consultations led to several arrests in 2004 and the establishment of new police posts. 2. Development of project security protocols. 3. Advising provincial police on staff movements. These activities will continue during the full project. In addition, by supporting site-based management and agreements with local authorities the project aims to achieve a general improvement in governance in these areas. 6. Corruption short to long term low Overall since 1998 there has been a steady increase in security in the project site and it is hoped that this trend will continue as governance and access improves. Strong Monitoring and Evaluation framework Independent project technical advisors Annual Adaptive Management reviews and Independent Evaluations Partnership with Seila/PLG Annual Auditing 44 support to management authorities (3a) and law enforcement (3c). Improvements in governance will be achieved through agreements with local commanders and authorities (Activity 3c.1) and Component 1 (see Risk 1). Project Management Component 4. International Project Advisor, TPR and steering committee meetings (Component 1). Result Frameworks 90.The CALM project will deliver the GEF alternative through four components over the seven year project duration (see Logical Framework [Annex 5], Incremental Cost Matrix [Annex 6], Budget and Workplan [Section II]). The overall project goal is “the effective conservation of key components of Cambodia’s Northern Plains Landscape’. Component 1: Incorporating biodiversity into landscape-level planning processes Outcome 1 - Integrated conservation and development planning at the landscape-level 91.Cambodia is currently developing and implementing new land management legislation, of which the Land Law is the most significant at the national level, but within this, biodiversity conservation values are not yet fully recognised. Provincial implementation of this policy is weak, and an opportunity exists to integrate conservation management objectives at the landscape scale, working both inside and outside the current protected areas network. To do this, the project will work in cooperation with the UNDP-funded Seila/PLG programme to build the capacity of provincial planners and land management decision-makers to consider and apply biodiversity values. The project will also integrate the results of Components 2 and 3 into commune plans, district integration workshops and provincial planning processes. Through the project steering committee and Provincial Rural Development Committee a framework will be established for integrated conservation planning at the landscape scale. The framework will include dialogue and agreements made with all relevant stakeholders on activities. Component 2: Applying Mainstreaming Measures Outcome 2a - Establishment of appropriate community land tenure and resource-right use 92.Current land and resource-use patterns reveal an ‘open-access’ system that results in general over-exploitation with no incentives for sustainable or co-ordinated management. The Royal Government of Cambodia’s new Land Law permits the process of Participatory Land-use Planning (PLUP) for all land estate, including forest estate and protected areas. Elements of the PLUP process will be used to determine rights, title and demarcate village land-use areas. This process of planning will subsequently highlight where and how tenure may be sought and, using additional PLUP elements, how appropriate tenure systems should be established over particular resources and resource areas. These activities are essential in order that more complex resourceuse issues can be addressed in Component 3. Since two of the project key sites lies within concession forests, the land use planning process will enable biodiversity to be mainstreamed into the forestry sector. Outcome 2b - Community engagement in natural resource management 93.A participatory process will work with villages to produce management plans for the land areas and resources for which tenure and title were negotiated as part of Component 2. Initially management plans will cover simple issues where there is considerable agreement between authorities and villages. For more complicated issues where agreement cannot be reached, such as forest fires or hunting with dogs, an incentive scheme will be introduced to reward improved management. The scheme will provide benefits in return for improved management and maintenance of wildlife populations (measured by Component 3d) to encourage the concept of ‘ownership’ and the value of the wildlife resource. An on-going evaluation of the incentive 45 scheme will be conducted for adaptive management. This evaluation will include collection of data on community livelihoods, which will be used to monitor the impact of the project on local people. Through the use of incentive schemes and land use planning at potential eco-tourism sites, the project aims to mainstream biodiversity into this sector. Component 3: Strengthening capacity for biodiversity management Outcome 3a - Establishment of long-term financial and management sustainability 94. The project will be designed to cover all setup costs, and ensure that any necessary long-term maintenance costs of project initiatives are minimal. Many components will be completed within the timescale of the project: Landscape Conservation Framework (Component 1). Establishment of community land-use tenure and title (Component 2a) and resource management plans (Component 2b). Environmental Education program (Component 3b). For other components or activities initial costs will be high, however necessary maintenance costs will be low: Incentives scheme (Component 2b). Law enforcement (Component 3c). As security and institutional structures are established the capacity of local communities and provincial government to enforce laws should be strengthened so that available resources are sufficient to cover long-term costs. Monitoring (Component 3d). 95. However it is recognised that sufficient financial sustainability must be established to cover these maintenance costs, especially the incentives scheme and monitoring program. An incremental cost matrix will be produced to identify the costs and activities. Further, the project will establish a structure for sound management of these activities. Site management staff will be members of the appropriate authority (FA or MoE) with jurisdiction over the area including key sites. This will provide the necessary sustainability of project management. Opportunities for key-species eco-tourism have been researched during the PDF-B, and there is potential for tourism to fund necessary project activities, especially the village incentive scheme (Component 3). During the full project, activities will create a framework for key species eco-tourism that benefits both biodiversity and local communities. Further activities will investigate the potential for establishing a trust fund, or securing long-term additional government and NGO financial commitment, to fund other necessary project activities (e.g. the monitoring program). Outcome 3b - Increased public awareness of the key project sites for conservation and the need for sustainable use of natural resources 96.While environmental awareness will be an important theme throughout the work of Components 1, 2a and 2b, additional supplementary activities will be needed to target specific groups and specific issues (e.g. those with communities living in close proximity to breeding bird colonies). This work needs to be both specialised and to have its achievements measurable if it is not to avoid conventional pitfalls of education/awareness activities. This Component will run concurrently with the PLUP process, with which it is closely linked, and seek to identify specific activity needs that the process will highlight. 46 97.A mobile education unit will be formed to increase awareness levels in and around key sites for conservation and a school support program will target local education efforts. The program will aim to build awareness and pride in key species conservation. Particular focus will be placed upon education and awareness activities for armed forces and at military bases to encourage their participation in conservation. An on-going evaluation scheme will assess and adapt the education activities to improve their impact. The setup costs (teacher training, production of materials and so on) will be covered by this component. However, by training provincial teachers and provincial department staff it is anticipated that activities will continue with minimal funding beyond the 7 year project. Outcome 3c - Reduction in illegal commercial exploitation of biological resources and their components 98.Effective law enforcement will be necessary for successful biodiversity conservation, particularly with respect to reducing commercial hunting and wildlife trade. This will require improvements in the technical training, equipment and available infrastructure (e.g. offices for FA Sangkats) for government staff. Law enforcement teams will include representatives from relevant provincial authorities and the armed forces and work within guidelines determined by authorities and village natural resource management agreements. Additionally, once community organisations are established and tenure issues have been resolved, then local representation on these enforcement teams will begin in order to better involve locals, increase community responsibility for NRM management, and to build local methods of dealing with forest crime. The timing and nature of this participation will be linked to the achievements of Component 2. 99.A data management system will be designed to collect and collate information gathered during patrols and enforcement activities, and a reporting system established to monitor these activities and their impacts. This data system will probably be modelled on that already implemented by BPAMP project in north-eastern Cambodia. Outcome 3d - Adequate data for conservation management and project evaluation purposes 100. The results framework will use five indicators to measure the project’s impact: Biological populations Habitat extent Level of human activities identified as threats Community livelihood indicators Extent of Government support 101. The first three determine the immediate success of the project in achieving the objective, the the fourth monitors the project’s impact on local people and the last will be crucial if activities are to be sustained. Site monitoring programs will collect standardised data to allow rigorous conclusions to be made about the levels of the first three indicators; activities during Component 2 will measure the fourth and government plans, reports and proclamations will measure progress on the final indicator. This will require the development of a database management system for input of field data and analysis of results. Training in data collection and analysis techniques will ensure that there is sufficient capacity for provincial staff and communities to understand the results of the monitoring program and the implications of these results for project activities. A pilot database was developed during the PDF-B phase and staff trained in its use. 47 Under this component, one activity will use the vulture restaurant program, also developed during the PDF-B, to monitor the population of Gyps vultures in the Northern Plains. The Cambodian population will represent only one of two existent populations following the dramatic declines in the Indian Subcontinent. 102. This component will monitor and quantify the ecological impacts and requirements of the innovative sustainable natural resource management being trialled at the four key sites. These will be used to generate knowledge on the application of sustainable natural resource management techniques in the Northern Plains. The results will be used to provide adequate data to inform conservation management decisions by site authorities. Protocols for data collection and monitoring will be developed and improved as part of the adaptive management process. To the extent possible, community-based monitoring techniques will be developed and used. Component 4: Project Management and Evaluation Outcome 4: Adequate reporting on project outcomes and indicators. 103. A Project Management Office will be required for the duration of the project only, to coordinate administration and reporting on GEF activities. This component will include required activities to evaluate progress towards achieving impact and outcome indicators. Baseline information on indicator levels has already been collected during the PDF-B, and will be augmented by data collected in year 1 of CALM. It will also include the annual project reviews, adaptive management missions and planning meetings, adaptive management technical expertise, mid-term evaluation ($30,000) and final evaluation ($30,000). 104. Each year there will be a major, participatory adaptive management review of each of the four key sites. The missions will be timed so that they benefit from as up to date monitoring results as possible, but more importantly, can provide timely input to the annual project review. The adaptive management reviews will also include a focus on knowledge management (through formal lessons learned preparation etc and informal consultations and feedback loops), as well as dissemination to practitioners across the Northern Plains. Tools will be developed for adaptive management both for the improvement of outcomes at the key sites and to contribute to the broader application of biodiversity considerations in land management processes at the provincial levels. 105. The project is adopting a ‘landscape’ conservation strategy, with targeted interventions at particular sites. These sites have been selected because together they are necessary and sufficient for successful conservation of all species found in the landscape. An annual evaluation process, informed by data collected during the monitoring program, will be necessary to set intervention priorities for the following year. The objective should be the maintenance of key species at all the identified sites. This annual evaluation will be necessary if the project is to avoid a ‘site by site’ implementation strategy that will not result in successful landscape-level conservation. 48 PART III: MANAGEMENT ARRANGEMENTS Execution 106.Given the leading role taken in project design and implementation of the PDF-B by WCS, UNDP and the Royal Government of Cambodia have decided that the most appropriate implementation modality for CALM is NGO implementation. The selection of WCS was approved on 5 May 2005, based upon the results of a UNDP-authored capacity assessment, and extensive government consultations. The capacity assessment clearly indicated the suitability of WCS, highlighting the NGO’s technical, managerial, administrative and financial expertise both globally and in Cambodia at delivering conservation projects. WCS already operates under a 5year MoU with MAFF and MoE defining a co-operative programme on biodiversity conservation in Cambodia. In addition, WCS has an agreement with MAFF covering the relevant components of CALM that was signed in December 2003 and lasts for the duration of the CALM. WCS’s involvement in the project will be a major asset to the Government. The two Government ministries, MAFF and MoE, will enter into agreements with WCS for the implementation of individual project components with the technical assistance of WCS. 107.As per the UNDP Programming for Results Management Guide, and as Implementing Partner, WCS will be responsible and accountable for overall management of the project and the attainment of all project objectives, including such tasks as the planning of project activities, financial accountability, the assessment of progress and technical quality, reporting to the stakeholders of the project (UNDP, Royal Government of Cambodia and beneficiaries), project monitoring and evaluation. Implementation (see Annex 7 for Terms of Reference) 108. WCS will enter in agreements for the implementation of the project with both the Department of Nature Conservation and Protection (DNCP) of the Ministry of Environment and the Forest Administration (FA) of MAFF. DNCP has a mandate over the management of Kulen Promtep Wildlife Sanctuary while FA has a mandate over the management of the Preah Vihear Protected Forest, Phnom Tbeng and the concession forest that includes the O’Scach River. Thus, the DNCP will play a leading role in implementing project activities in the Kulen Promtep Wildlife Sanctuary and the FA will lead project implementation of project activities in remaining areas. The Ministry of Land Management (MLMUPC) is the Government body responsible for the implementation of the Land Law and will be an essential partner in the Participatory LandUse Planning (PLUP) process across the landscape, within both the Wildlife Sanctuary and the rest of the Forest Estate. The provincial departments of MLMUPC will be crucial implementing partners, and the project will enter into agreements for these activities with these departments. 109.To facilitate the implementation of the project, and at the request of the implementing partner, the UNDP Cambodia Country office will provide support services to the project in accordance with the UNDP procedures. UNDP will assist WCS with access to information, services and support, provide WCS with all relevant documents on UNDP rules and procedures, and assist with liason with stakeholders. UNDP will be responsible for monitoring the progress of the project and reporting to GEF and for disbursement of GEF funds. Monitoring activities will include the project reviews (TPR meeting, mid-term and final evaluation). 49 110.The practical and technical implementation of the project will be led at all steps by the Wildlife Conservation Society (WCS). 111.To enhance national ownership and leadership a Project Executive Group (PEG) will be established and chaired by the Minister of Agriculture, Forestry and Fisheries, will be established to provide overall guidance for the implementation of the project. The PEG will consist of representatives of the relevant parties including the Council for Development of Cambodia, the Ministry of Environment (deputy chair), the Ministry of Agriculture, Forestry and Fisheries, Ministry of Land Management Urban Planning and Construction, Ministry of Defense, Regional Representatives from Military, Police and Border Police, UNDP, WCS, Seila/PLG and Provincial Governors of 5 provinces, which share boundaries and territories with the Northern Plains landscape. Representatives of other ministries and organizations will be invited to attend as appropriate. The PSC will advise on project implementation, provide a mechanism for resolving implementation problems that go beyond single department mandates, and review progress. Meetings will take place at least yearly during the life of the Project. The existing Provincial Rural Development Committee (PRDC) will function as a Sub-Executive Group (SEG) in those provinces where the project has significant activities. The SEG will be chaired by the Governor, or their representative, and will consist of representatives from Provincial Departments, Seila/PLG, WCS, Military, Police and Border Police. The SEG will advise on project activities and provide a forum to integrate initiatives across the landscape. Members of the SEG (such as the Governor’s office) will be responsible for approving site management plans produced by project components. 112.The National Project Director (NPD) appointed by MAFF will serve as the government director of the project. The same modality worked efficiently during the phase and is therefore recommended to continue in the full project. A Deputy National Director (DNPD) appointed by MoE will be responsible for overall management of activities in Kulen Promtep Wildlife Sanctuary. overall PDF-B Project project WCS, in consultation with UNDP, will appoint/recruit an International Project Advisor (IPA) who act as the overall project manager and will be responsible for day-to-day management and decision-making for the project. A Project Support (UNDP program officer) will be appointed or recruited to provide project administration and management support from UNDP to WCS as required by the needs of the project or WCS. To ensure appropriate management milestones are managed and completed, UNDP will designate a Project Assurance Officer. The Project Assurance will support the Project Executive Group by carrying out objective and independent oversight and monitoring functions. A Project Implementation Office (PIO) has been established in Tbeng Meanchey (Preah Vihear province), since this region will be the focus of implementation activities and is in the centre of the landscape. 50 Two National Site Managers (NSMs) will be recruited by CALM and will serve as the principal liaison between the project and the NPD and PSC. The NSMs will be responsible for reporting to the NPD, PSC, UNDP/GEF and WCS on the project’s progress. Individual Project Implementation Units (PIU) will be responsible for project activities. Some activities relate to site-based management, and these will be coordinated through existing Government management authorities, such as the Kulen Promtep Wildlife Sanctuary. Other activities provide support to decentralized government processes, implementation of new laws and support to the formation of site-based plans by local authorities, and these will be coordinated by new PIUs that will be required only for the duration of the project. Adaptive management 113. UNDP is intent on implementing a monitoring process that serves as an effective support tool to the project implementation team, allowing them to incorporate new scientific knowledge, and the results of lessons learned in similar projects elsewhere. This approach is particularly important for a project, which seeks to integrate conservation into a productive landscape. 114. Adaptive management will be promoted in order to create conditions that ensure greater success in project implementation. The term “adaptive management” is used in the context of experience developed by “Foundation for Success”, under the Biodiversity Conservation Network. They defined the concept as3: “Adaptive management is a process of defining actions, decision-making, and learning in which a group responsible for the conservation of a particular area is responsive to biophysical and social changes and is able to respond quickly and appropriately to these changes. In order to make sound management decisions under complex and evolving conditions, a group must be able to: Continuously test assumptions and hypotheses; Experiment with alternative approaches to resolve problems and address pertinent issues; Generate, analyze and use relevant and reliable data and information; Determine the impacts of its chosen course of action; and Learn from failure as well as success and apply these lessons to future program decisions. “An organization's ability to understand and react to the complex and dynamic ecological and social environments at a given project site is a major determinant of its success. Adaptive management is a useful tool in helping organizations deal with the complexity of managing conservation and development projects.” 115.The objectives of the adaptive management reviews in the context of the CALM project will be: From: “Adaptive Management of Conservation and Development Projects: Transforming Theory into Practice”. Biodiversity Support Program Reference No.: 39, 1999 3 51 To strengthen the existing annual project review process (APR). The reviews will provide support to the project implementation team in preparation for the APR and will improve the basis for recommendations made by the PEG. To apply adaptive, learning-based approaches to project implementation. Adaptive, learningbased implementation requires a clear understanding of the project logic and periodic well structured events in which the project’s experience (successes and failures) and changes in its operating context (opportunities and threats) can be examined in an objective manner by those involved. To promote exchange and learning across UNDP/GEF’s portfolio of similar projects in the Asia/Pacific region. Progress in individual projects and across the UNDP/GEF portfolio will be enhanced by reciprocal visits that permit peer managers to examine and contribute to addressing issues raised by the execution of one another’s projects. To improve the documentation and dissemination of project learning’s and project accomplishments. This will ensure that the outcomes and lessons learned from each project are widely disseminated. Adaptive management reviews will be undertaken yearly by the IPA, NSMs, MAFF, MoE, the project team and may include representatives from the UNDP Country Office. Individual project components will undertake their own adaptive management reviews prior to this. The review process will be used to: Generate the workplan for the coming year Update the risk assessment and risk management strategy Upadate the project logical framework Quantify progress towards meeting indicators in the results measurement framework (Annex 4) and logical framework (Annex 5). Identify Lessons learned Identify key project achievements that should be publicized (e.g. reports for publication, etc..). Audit 116.As per UNDP/GEF Administration and Financial Guidelines, projects exceeding expenditures of $20,000 per year should be audited annually. The audit will be conducted in conformity with generally accepted international standards, by UNDP internal auditors hired directly by UNDP Cambodia. Funds to finance the audit are included in the project budget. The audit report will be an integral part of the monitoring and evaluation process and its contents shall be taken into account in the annual progress review and evaluations of the project. 52 CALM Project Structure Project Executive Group Chairman: MAFF (CDC, MAFF, MoE, MLMUPC, MoD, Governors, UNDP, Seila, WCS) Ministry of Agriculture, Forestry and Fisheries Forestry Administration UNDP/GEF Project Assurance Ministry of Environment Department of Nature Conservation and Protection National Project Director Deputy NPD WCS (Implementing Partner) WCS Cambodia Director Intl Project Advisor Project Implementation Office (Tbeng Meanchey) National Site Managers WCS Technical Advisors Administration Director Sub-Executive Group (Governor, Seila/PLG, ExCom, Provincial Departments, FA Cantonment) Preah Vihear Protected Forest Director Kulen Promtep Wildlife Sanctuary Director Phnom Tbeng and O’Scach Key Sites Environmental Education Unit Communities and Natural Resource Management Unit 53 Monitoring and Evaluation Unit PART IV: MONITORING AND EVALUTION PLAN AND BUDGET Project monitoring and evaluation will be conducted in accordance with established UNDP and GEF procedures and will be provided by the project team and the UNDP Country Office (UNDP-CO) with support from UNDP/GEF. The Results Measurement Framework in Annex 4 and the Logical Framework Matrix in Annex 5 provide performance and impact indicators for project implementation along with their corresponding means of verification. These will form the basis on which the project's Monitoring and Evaluation system will be built. WCS and UNDPCambodia shall be responsible that the overall monitoring and evaluation framework for the CALM project will effectively assess the quality and appropriateness of the various outputs/results of the project activities, and contribute to the national development goals of the country. The following sections outline the principle components of the Monitoring and Evaluation Plan and indicative cost estimates related to M&E activities. Specific funds have been allocated in the CALM budget. Conservation Impact Monitoring 117.The conservation impact of the project will be evaluated using 4 key indicators (see Annex 4): a) Populations of key wildlife species (see Annex 1 for definitions) b) Habitat Extent c) Level of human activities identified as threats (see Annex 3) d) Government support, indicated by recognition for key sites 118.A monitoring and evaluation program will also be essential for: a) To provide the objective, quantifiable, measures of change required to determine reward rates for the community-based incentive scheme b) Inform law enforcement teams c) Provide information for internal project adaptive management at key sites 119.In the project logframe, the monitoring program is designated a separate component in recognition of its importance, and the necessity of maintaining independence between project activities and their evaluation. This is particularly relevant given that the results of the monitoring program will be used to set reward rates for the incentive scheme. The project recognises the critical need for quantifiable indicators, not just for management to adapt activities, but to provide a public and transparent process to evaluate project success. Both communities and government need to understand and accept monitoring results for there to be genuine stakeholder buy-in to the project. 120.A model for monitoring of biological populations has been developed by WCS/MAFF/MoE in another area of Cambodia and will be applied to the project site. Key species have been identified (see Annex 1), and will be the principal target of population monitoring. The necessary baseline data for the biological monitoring program was collected during the PDF-B phase, and this will be used to analyse future trends in populations during the full project. Key members of government and communities have received appropriate training in applying the methodologies. 54 121.Monitoring of habitat extent and quality will require the analysis of time-series remote sensing data, with field data collection for ground-truthing. Suitable baseline datasets already exist, both from aerial photography and satellite imagery. 122.Trends in human activities, where they impact on land-use, will also be monitored through the results of remote sensing data analysis. Data on other human activities, including illegal activities and other types of hunting, fishing and NTFP collection will be collected by field teams. The details of the data required will depend upon the threats analysis (see Annex 3) and those activities prohibited under agreed village management regulations. For the latter reason, monitoring systems may require different forms for particular villages. Baseline data needs will be determined early in the project, and data recorded before the implementation of management agreements and incentive schemes, in order that their impact can be evaluated. The Site-based monitoring systems (Component 3d) will measure the conservation impact indicators and will provide the results to site managers for their adaptive management review process (Component 3a) Project Inception Phase An Inception Workshop will be conducted with CALM, MAFF, MoE, Seila/PLG, Provincial Government, UNDP-Cambodia and other representatives as appropriate. Prior to the inception workshop the first Annual Workplan will be produced by the CALM team. This will include precise and measurable performance indicators (baselines and targets) for the first year in a manner consistent with the expected outcomes for the project. The indicators will be used to assess whether implementation is proceeding at the intended pace and in the right direction. A fundamental objective of this Inception Workshop will be to assist all stakeholders to understand and take ownership of the CALM’s goals and objectives, as well as to review the first annual workplan on the basis of the project's logframe matrix. Additionally, the purpose and objective of the Inception Workshop will be to: (i) introduce project staff with the UNDP-GEF expanded team which will support the project during its implementation, namely UNDP-Cambodia and responsible Regional Coordinating Unit staff; (ii) detail the roles, support services and complementary responsibilities of UNDP-Cambodia and Regional Coordinating Unit staff vis a vis the project team; (iii) provide a detailed overview of UNDP-GEF reporting and monitoring and evaluation (M&E) requirements, with particular emphasis on the Annual Project Implementation Reviews (PIRs) and related documentation, the Annual Project Report (APR), Tripartite Review Meetings, as well as mid-term and final evaluations. Equally, the Inception Workshop will provide an opportunity to inform the project team on UNDP project related budgetary planning, budget reviews, and mandatory budget rephasings. The Inception Workshop will also provide an opportunity for all parties to understand their roles, functions, and responsibilities within the project's decision-making structures, including reporting and communication lines, and conflict resolution mechanisms. Linkages with other projects, including those supported by UNDP and GEF will be discussed. 55 Monitoring responsibilities and events A detailed schedule of project reviews meetings will be developed by CALM, in consultation with project implementation partners and stakeholder representatives and incorporated in the Project Inception Report. Such a schedule will include: (i) tentative time frames for Tripartite Reviews, and (ii) project related Monitoring and Evaluation activities. Day to day monitoring of implementation progress will be the responsibility of the NSMs and IPA based on the project's Annual Workplan and its indicators. CALM will inform UNDPCambodia of any delays or difficulties faced during implementation so that the appropriate support or corrective measures can be adopted in a timely and remedial fashion. The NSMs and the IPA will fine-tune the progress and performance/impact indicators of the project in consultation with the full project team at the Inception Workshop with support from UNDP-Cambodia and assisted by the UNDP-GEF Regional Coordinating Unit. Specific targets for the first year implementation progress indicators together with their means of verification will be developed at this Workshop. These will be used to assess whether implementation is proceeding at the intended pace and in the right direction and will form part of the Annual Workplan. The local implementing agencies will also take part in the Inception Workshop in which a common vision of overall project goals will be established. Targets and indicators for subsequent years would be defined annually as part of the internal evaluation and planning processes undertaken by the project team. Impact indicators, and their measurement, has been clearly described in the section about (Conservation Impact Monitoring) and Annex 4. Periodic monitoring of implementation progress will be undertaken by UNDP-Cambodia through quarterly meetings with CALM, or more frequently as deemed necessary. This will allow parties to take stock and to troubleshoot any problems pertaining to the project in a timely fashion to ensure smooth implementation of project activities. UNDP-Cambodia and UNDP-GEF Regional Coordinating Unit as appropriate, will conduct yearly visits to the Northern Plains, if required, to assess project progress. Visits will be scheduled in the CALM Annual Workplan. Any other member of the Steering Committee can also accompany, as decided by the PSC. A Field Visit Report will be prepared by UNDPCambodia and circulated no less than one month after the visit to CALM, all PSC members, and UNDP-GEF. Annual Monitoring will occur through the Tripartite Review (TPR), undertaken by the Project Steering Committee (PSC). This is the highest policy-level meeting of the parties directly involved in the implementation of a project. CALM will be subject to Tripartite Review (TPR) at least once every year. The first such meeting will be held within the first twelve months of the start of full implementation. CALM will prepare an Annual Project Report (APR) and submit it to UNDP-Cambodia and the UNDP-GEF regional office at least two weeks prior to the TPR for review and comments. 56 The APR will be used as one of the basic documents for discussions in the TPR meeting. CALM will present the APR to the TPR, highlighting policy issues and recommendations for the decision of the TPR participants. CALM will also inform the participants of any agreement reached by stakeholders during the APR preparation on how to resolve operational issues. Terminal Tripartite Review The terminal tripartite review is held in the last month of project operations. CALM is responsible for preparing the Terminal Report and submitting it to UNDP-Cambodia and the UNDP/GEF Regional Coordinating Unit. It shall be prepared in draft at least two months in advance of the terminal TPR in order to allow review, and will serve as the basis for discussions during the review. The terminal tripartite review considers the implementation of the project as a whole, paying particular attention to whether the project has achieved its stated objectives and contributed to the broader environmental objective. It decides whether any actions are still necessary, particularly in relation to sustainability of project results, and acts as a vehicle through which lessons learnt can be captured to feed into other projects under implementation of formulation. The TPR has the authority to suspend disbursement if project performance indicators are not met. Indicators are provided in Annexes 4 and 5 and will be developed further at the Inception Workshop. Work plan and Reporting requirements The IPA and NSMs in conjunction with the UNDP-GEF extended team will be responsible for the preparation and submission of the following reports that form part of the monitoring process. (a) Inception Report (IR) A Project Inception Report will be prepared immediately following the Inception Workshop. It will include a detailed First Year Work Plan divided in quarterly time-frames detailing the activities and progress indicators that will guide implementation during the first year of the project. This Work Plan will include the time-frames for meetings of the project's decision making structures. The Report will also include the detailed project budget for the first full year of implementation, and including any monitoring and evaluation requirements to effectively measure project performance during the targeted 12 months time-frame. A section will be included on progress to date on project establishment and start-up activities and an update of any changed external conditions that may effect project implementation. When finalized the report will be circulated to project counterparts who will be given a period of one calendar month in which to respond with comments or queries. Prior to this circulation of the IR, the UNDP-Cambodia and UNDP-GEF’s Regional Coordinating Unit will review the document. (b) Annual Project Report (APR) The APR is a UNDP requirement and part of UNDP-Cambodia’s central oversight, monitoring and project management. It is a self-assessment report submitted by the Executing Agency 57 (WCS) to UNDP-Cambodia and provides input to the country office reporting process, as well as forming a key input to the Tripartite Review (TPR). An APR will be prepared on an annual basis two weeks prior to the TPR, to reflect progress achieved in meeting the project's Annual Work Plan and assess performance of the project in contributing to intended outcomes through outputs and partnership work. The format of the APR is flexible but should include the following: An analysis of project performance over the reporting period, including outputs produced and, where possible, information on the status of the outcome The constraints experienced in the progress towards results and the reasons for these The three (at most) major constraints to achievement of results Annual Work Plan and other expenditure reports Lessons learned Clear recommendations for future orientation in addressing key problems in lack of progress (c) Project Implementation Review (PIR) The PIR is an annual monitoring process mandated by the GEF. It has become an essential management and monitoring tool for project managers and offers the main vehicle for extracting lessons from ongoing projects. Once the project has been under implementation for a year, a Project Implementation Report must be completed by UNDP-Cambodia together with the Executing Agency (WCS). The PIR can be prepared any time during the year and ideally two weeks prior to the TPR. The PIR should then be discussed in the TPR so that the result would be a PIR that has been agreed upon by the project, the executing agency and UNDP-Cambodia. The individual PIRs are collected, reviewed and analysed by the Regional Coordinating Office of UNDP/GEF prior to sending them to UNDP/GEF headquarters. The PIR and APR follow a standard harmonized format in recognition of their similarity. (d) Quarterly Progress Reports One week after the end of each quarter, the Executing Agency (WCS) is required to prepare a summary report (maximum one page) of the project's substantive and technical progress towards achieving its objective as described in the annual work plan. These quarterly reports will include financial statements. The summaries are reviewed and cleared by UNDP-Cambodia one week before being sent to the UNDP/GEF Regional Coordinator. (e) Periodic Thematic Reports As and when called for by UNDP-Cambodia, UNDP-GEF or the Implementing Partner, the project team will prepare Specific Thematic Reports, focusing on specific issues or areas of activity. The request for a Thematic Report will be provided to the project team in written form by UNDP and will clearly state the issue or activities that need to be reported on. These reports can be used as a form of lessons learnt exercise, specific oversight in key areas, or as troubleshooting exercises to evaluate and overcome obstacles and difficulties encountered. UNDP is requested to minimize its requests for Thematic Reports, and when such are necessary will allow reasonable timeframes for their preparation by the project team. 58 (f) Project Terminal Report During the last three months of the project the project team will prepare the Project Terminal Report. This comprehensive report will summarize all activities, achievements and outputs of the Project, lessons learnt, objectives met, or not achieved, structures and systems implemented, etc. and will be the definitive statement of the Project’s activities during its lifetime. It will also lay out recommendations for any further steps that may need to be taken to ensure sustainability and replicability of the Project’s activities. Evaluation The project will be subjected to at least two independent external evaluations as follows:(i) Mid-term Evaluation An independent Mid-Term Evaluation will be undertaken at the middle of the fourth year of implementation. The Mid-Term Evaluation will determine progress being made towards the achievement of outcomes and will identify course correction if needed. It will focus on the effectiveness, efficiency and timeliness of project implementation; will highlight issues requiring decisions and actions; and will present initial lessons learned about project design, implementation and management. Findings of this review will be incorporated as recommendations for enhanced implementation during the final half of the project’s term. The organization, terms of reference and timing of the mid-term evaluation will be decided after consultation between the parties to the project document. The Terms of Reference for this Midterm evaluation will be prepared by the UNDP Country Office based on guidance from the Regional Coordinating Unit and UNDP-GEF. (ii) Final Evaluation An independent Final Evaluation will take place three months prior to the terminal tripartite review meeting, and will focus on the same issues as the mid-term evaluation. The final evaluation will also look at impact and sustainability of results, including the contribution to capacity development and the achievement of global environmental goals. The Final Evaluation should also provide recommendations for follow-up activities. The Terms of Reference for this evaluation will be prepared by UNDP-Cambodia based on guidance from the Regional Coordinating Unit and UNDP-GEF. Learning and Knowledge Sharing Results from the project will be disseminated within and beyond the project intervention zone through a number of existing information sharing networks and forums. In addition: The project will participate, as relevant and appropriate, in UNDP/GEF sponsored networks, organized for Senior Personnel working on projects that share common characteristics. UNDP/GEF shall establish a number of networks, such as Integrated Ecosystem Management, eco-tourism, co-management, etc, that will largely function on the basis of an electronic platform. 59 The project will identify and participate, as relevant and appropriate, in scientific, policybased and/or any other networks, which may be of benefit to project implementation though lessons learned. The project will identify, analyze, and share lessons learned that might be beneficial in the design and implementation of similar future projects. Identify and analyzing lessons learned is an on-going process. UNDP/GEF shall provide a format and assist the project team in categorizing, documenting and reporting on lessons learned every 2 years. Monitoring and Evaluation Work plan and corresponding Budget Type of M&E activity Responsible Parties Budget US$ Excluding project team Staff time Time frame Inception Workshop (UNDP staff travel costs to be charged to IA fees) IPA and NSMs CALM staff UNDP Cambodia UNDP GEF $2000 Inception Report CALM staff UNDP Cambodia None Measurement of Means of Verification for Project Impact Indicators Image analysis and interpretation: $25,000 Site-based Monitoring teams: approximately $10,000/year. Community teams: approximately 5,000 in years 3 and 6. Measurement of Means of Verification for Project Progress and Performance (on an annual basis ) APR and PIR See Annex 4. IPA will oversee the hiring of the contract for image analysis and interpretation, all other indicators will be measured by site monitoring teams (Component 3d) and community teams (Component 2b) IPA and NSMs Measurements by individual activity coordinators None: incorporated into annual reports by activity coordinators Annually for the adaptive management review prior to APR/PIR None Annually $14,000 ($2000/year) Every year, upon receipt of APR As required, $8,000 included in budget. As required, $8,000 included in budget. To be determined by CALM and UNDP Cambodia To be determined by CALM and UNDPCambodia TPR (UNDP staff travel costs to be charged to IA fees) Periodic status reports NSMs and IPA UNDP-Cambodia UNDP-GEF MAFF, MoE UNDP Cambodia NSMs and IPA CALM staff Seila/PLG Provincial Government UNDP-GEF Regional Coordinating Unit CALM Technical reports CALM 60 Within first two months of project start up Immediately following Inception Workshop Habitat extent: start and end of project, Site-based monitoring teams: annual reports. Mid-term External Evaluation Final External Evaluation Terminal Report Audit Visits to field sites (UNDP staff travel costs to be charged to IA fees) NSMs and IPA CALM staff UNDP-Cambodia UNDP-GEF Regional Coordinating Unit External Consultants (i.e. evaluation team) NSMs and IPA CALM staff UNDP-Cambodia UNDP-GEF Regional Coordinating Unit External Consultants (i.e. evaluation team) NSMs and IPA CALM staff UNDP-Cambodia UNDP-CO Project team UNDP Cambodia UNDP-GEF Regional Coordinating Unit (as appropriate) Government representatives TOTAL INDICATIVE COST Excluding project team staff time and UNDP staff and travel expenses 61 $30,000 In Year 4. $30,000 In Year 7. None $21,000 (average $3000 per year) At least one month before the end of the project Yearly As required. US$ 235,000 PART V: LEGAL CONTEXT 123.This Project Document shall be the instrument referred to as such in Article I of the Standard Basic Assistance Agreement between the Royal Government of Cambodia and the United Nations Development Programme, signed by the parties on 19 December 1994. The host country implementing agency shall, for the purpose of the Standard Basic Assistance Agreement, refer to the government co-operating agency described in that Agreement. 124.UNDP acts in this Project as Implementing Agency of the Global Environment Facility (GEF), and all rights and privileges pertaining to UNDP as per the terms of the SBAA shall be extended mutatis mutandis to GEF. 125.The UNDP Resident Representative in Cambodia is authorized to effect in writing the following types of revision to this Project Document, provided that he/she has verified the agreement thereto with the Executive Coordinator, GEF Unit, UNDP (or designated Officer-inCharge/Representative) and is assured that the other signatories to the Project Document have no objection to the proposed changes: Revision of, or addition to, any of the annexes to the Project Document; Revisions which do not involve significant changes in the immediate objectives, outputs or activities of the project, but are caused by the rearrangement of the inputs already agreed to or by cost increases due to inflation; Mandatory annual revisions which re-phase the delivery of agreed project inputs or increased expert or other costs due to inflation or take into account agency expenditure flexibility; and Inclusion of additional annexes and attachments only as set out here in this Project Document. SECTION II : STRATEGIC RESULTS FRAMEWORK AND GEF INCREMENT 63 PART I: Incremental Cost Analysis Component Component 1. Incorporating biodiversity into landscape-level planning processes Component 2. Applying Mainstreaming Measures 2a. Community landuse tenure and title 2b. Village agreements on natural resource management linked to direct incentives scheme Category Baseline US $ $68,000 Seila/PLG and MoE, MAFF annual provincial budgets Alternative Increment $1,256,920 $1,148,920 Of which: GEF: $442,350 WCS: $333,050 Seila/PLG: $350,000 RGC: $23,520 Baseline $120,000 LUPU (land Use Planning Unit) $60,000 Seila/PLG Domestic Benefit UNDP support to Seila/PLG and Provincial Rural Development Committee (PRDC). However, the PRDC currently has does not consider conservation values. Sectoral management by Provincial MoE and MAFF considers some aspects of the landscape, but is uncoordinated and unfocused. Technical management capacity and infrastructure (including equipment) are poor. Global Benefit No consideration of the global importance of biodiversity and key sites in planning decisions. Establishment, through PRDC and Project Steering Committee of integrated provincial and national conservation and development planning. Management between agencies is co-ordinated. Planning decisions by government and agencies reference and take into account conservation priorities. Community Land-use tenure and title Isolated projects supported by LUPU, but without consideration of conservation priorities. General absence of implementation of mechanisms to regulate ownership of natural resources. Continuing over-exploitation by communities, especially in competition with increasing numbers of immigrants and temporary migrants from other areas. Unregulated new settlements impacting on resource-use patterns of established communities. Eventual loss of wood, fish and wildlife resources. No community benefit from tourism. Global conservation values included in national and provincial planning strategies. PRDCs reflect global conservation priorities. 64 No clear ownership of key sites for conservation and associated management responsibilities. 2 key sites afforded govt. recognition. Alternative Increment Component 3: Strengthening capacity for biodiversity management Baseline $843,182 $663,182 Of which: GEF: $362,700 WCS: $214,200 Seila/PLG: $78,407 RGC: $7,875 $30,000 (MAFF and MoE law enforcement budgets) Village agreements on natural resource management linked to direct incentives scheme Commune Development Plans assisted by Seila/PLG, but these do not explicitly include natural resource management. Poor local government capacity to manage natural resources. No incentives for improved natural resource management, or conservation-orientated activities. Continued unregulated over-exploitation. Local government planning process does not include conservation values. Community Land-use tenure and title Implementation of new laws governing the ownership of natural resources. Community understanding of rights and responsibilities. Reduction in unauthorised immigration, and resource exploitation by temporary migrants. Ownership (state/private) established for key sites for conservation, producing a framework upon which subsequent activities are developed. Recognition of key sites by govt. Reduction in threats to global biodiversity conservation values. Village agreements on natural resource management linked to direct incentives scheme Implementation of new laws governing the management of natural resources. Community understanding and regulation of improved management practices, and defence of resource-use rights. Incentive scheme provides direct rewards in return for reduction of threats to wildlife. Crucially, the scheme establishes a link between wildlife and rewards given, creating a clear foundation for community conservation management. Financial and management sustainability of activities No financial management planning by Provincial MoE/MAFF. Wildlife tourism occurs, but is unregulated and gives no benefits to local communities or protected area/forest management. Reduction in activities by communities that threaten global wildlife conservation values. Creation of link between biodiversity and incentives results in community support against immigrants that seek to exploit local wildlife. 3a. Financial and 65 Conservation management remains weak and under-funded. management sustainability of activities 3b. Environmental awareness program targeted at communities and armed forces. Environmental awareness program targeted at communities and armed forces Poor understanding of threats to biodiversity conservation and the importance of maintaining environmental services. No understanding of the location and boundaries of key sites for conservation, or new protected forest. No focusing of efforts on these key sites. No understanding of the global importance of species. Law enforcement Weak implementation of protected area laws, new forestry law and wildlife sub-decrees by MoE and MAFF. Untargeted and unplanned enforcement does not recognise key sites for conservation or the major threats to conservation. Global importance of biodiversity, or the necessity of maintaining critical ecosystem services not recognised in enforcement activities. Monitoring and adaptive site management No collection of standardised data. No analysis of trends in populations, habitat, or human activities. No monitoring of species of global importance. Financial and management sustainability of activities Plan for long-term financing of activities. Management structure, including transparent financial system, established. Eco-tourism guidelines and regulations, so that communities understand the link between conservation and tourist income. Long-term funding and management structure for an area of global significance for conservation. 3c. Law enforcement 3d. Monitoring and site adaptive management Alternative Increment $1,934,075 $1,904,075 Of which: GEF: $939,200 WCS: $861,100 Seila/PLG: $35,000 RGC: $68,775 66 Component 4. Project Management and Evaluation Baseline $nil Alternative Increment $752,440 $752,440 Of which: GEF: $555,750 WCS: $191,650 RGC: $5,040 Environmental awareness program targeted at communities and armed forces Co-ordinated education program targeted at all stakeholders, including communities, armed forces and authorities, especially around key sites. Increased understanding of the threats to biodiversity conservation and the necessary services provided by the environment (e.g. maintenance of watersheds). Understanding of the location and boundaries of key sites for conservation, and the project and its objectives. Clear understanding by stakeholders of the global importance of species found on the Northern Plains. Law enforcement Clear understanding of laws and requirements for implementation. Co-ordinated, planned enforcement activities focused around key sites and address key threats. Teams are well trained, equipped and have sufficient infrastructure. Global importance of biodiversity and critical ecosystem services recognised in enforcement activities. Reduction in illegal activities, especially at key sites. Monitoring and adaptive site management Established monitoring programs at all key sites. Training of staff in methodologies, data analysis and interpretation of results. Sufficient data for long-term monitoring of populations, habitats and human activities to determine project impact. Provision of simple reports to advise site adaptive management. No capacity to report on overall project activities or expenditure. Little adaptive management or evaluation of management activities. Ongoing monitoring of the impact of project outcomes in achieving global environmental benefits. Project office to administer expenditure and coordinate activities. Adaptive management framework to improve effectiveness of project implementation. Mid-term and final evaluations. 67 Part II: Logical framework analysis Project Objective The effective conservation of the key components of biodiversity of Cambodia’s Northern Plains Landscape Key Outcome Indicators Biological Populations Percentage of Km squares where key species recorded (patch occupancy) Survey records from monitoring transects and points, e.g. encounter-rates from camera-traps Maintenance of Habitat Number of hectares of forest within key sites Number of hectares of grassland Reduction in human activities causing excessive resource usePercentage of water bodies with poison/electric fishing activity within key sites Number of hunting incidences (traps/dogs/guns) recorded at monitoring points within key sites Baseline Target Baseline data exists for 3 key sites, and will be collected for site 4 in year 1. 25% increase in total key species records at two sites by year 5, remaining by year 7 Results of monitoring transects and points established at all sites in year 1. Maintained presence of each key species at respective sites Protected Forest 135,396 Wildlife Sanctuary - 76,884 O’Scach-O’Dar 57,998 Phnom Tbeng 27,858 No decreases in forest area compared with baseline in years 3 and 7. Analysis of remote-sensing data in year 1 No net loss of grassland area compared with baseline in years 2-7. 90% of dry season water bodies poisoned or electric fished 50% reduction in Protected Forest site by year 2, achieved at remaining sites by year 4. 75% reduction at all sites by year 5. Baseline will be established in year 1 for all sites 20% reduction in Protected Forest site by year 2, achieved at 68 remaining sites by year 4. 75% reduction at all sites by year 5. Verification Means Site Monitoring programs (Component 3d) - standardized transect data - point counts - fixed camera-traps Assumptions Maintenance of government, military, police and community interest and support for biodiversity conservation Conservation areas are of sufficient size to support biological populations Populations are able to recover from past overexploitation Site Monitoring programs (Component 3d) - analysis of timeseries remote sensing data Site Monitoring programs (Component 3d) - data collection within key sites, including core areas and village management areas - enforcement team reports Number of Km squares with logging activity recorded by teams in key sites Baseline data exists for 3 key sites, and will be collected for site 4 in year 1. 30% reduction in Protected Forest site by year 2, achieved at remaining sites by year 4. 75% reduction at all sites by year 5. > 40% of families in 2003. 20% reduction at two sites by year 4, 50% reduction at three sites by year 7. Community surveys in years 3 and 6 (Component 2d). Percentage of families that experience an annual rice shortage of more than 100kg > 40% of families in 2003. 20% reduction at two sites by year 4, 50% reduction at three sites by year 7. Community surveys in years 3 and 6 (Component 2d). Percentage of families with more than 2 cows or buffalos >70% of families in 2003. 20% increase at two sites by year 4, 50% increase at three sites by year 7. Community surveys in years 4 and 7 (Component 2d). 236,886ha (72%) 2 sites recognised 4 sites recognised by year 5. Government maps Protected Forest - 2 Wildlife Sanctuary 2 Phnom Tbeng – 1 1 at each site by year 5. Government records Community Livelihoods – Number of families doing shifting cultivation Government Support Number of hectares of key sites with formal recognition Number of military bases in key sites Shifting cultivation is an unpopular form of agriculture with local people, that produces low yields. Shortage of livestock is the major reason people chose this livelihood. Livestock shortage is a major barrier to improvements in agriculture Key Species: Asian Elephant (evergreen forests), Giant/White-shouldered Ibis (water bodies), Eld’s Deer (dry forests and water bodies), Large Cats, Oriental Darter, Sarus Crane (grasslands), Vultures, Wild Cattle (evergreen and dry forests), White-shouldered Ibis, White-winged Duck (river forests) 69 Project Components 1. Incorporating biodiversity into landscape-level planning processes Key Outcome Indicators Number of Seila/PLG Commune Development Plans including conservation planning Level of capacity in key provincial ministries and government for conservation planning and co-ordination. Provincial Development Plans, Sectoral Agency Plans (e.g. Concessionaires) include conservation priorities Conservation landscape incorporated within national planning strategies 2. Applying Mainstreaming Measures 2a. Community land-use tenure and title Level of Provincial capacity for participatory land-use planning Baseline Target Verification Means Assumptions Currently no CDPs include conservation plans 5 by year 3, 8 by year 5 - Revised Commune Development Plans No staff trained. Candidate staff from each ministry, authority and agency trained by year 3. At least 100 staff trained. Plans and EIAs reference conservation plans by year 3 - Reports of training courses. Number of staff trained. Authorities’ interest in being involved in coordinated landuse planning continues. PDP, Ministry, Agency plans and Environmental Impact Assessments do not account for conservation priorities Currently only mentioned within Biodiversity Action Plan 1 training course for provincial government staff completed during PDF-B Included within MAFF annual plans by year 3. Endorsement of key site management plans by year 3 (MAFF, MOE, MLMUPC). 2 further training courses for 20 government staff each. Training courses for 12 villages by year 3. - Conservation guidelines for landscape, including maps of priorities and management objectives - Minutes of Provincial Development committees Sectoral Plans (Ministries and NGOs) and EIAs - Revised plans by central level agencies Seila/PLG’s interest in NRM continues. Provincial capacity can be increased or is sufficient for coordinated planning. Community and district plans are supported by higher authorities. Key developments are made in Cambodia’s land law legal framework Seila/PLG accepted as main provincial planning framework - Number of trained PLUP facilitators. Provincial governments support PLUP process Trained provincial 70 Government approved landuse maps No villages have tenure or title maps 6 villages by year 3, 12 by year 5 to have established land and resource tenure - Government recognized PLUP maps staff remain in provincial government. Number of village committees No villages have land-use planning committees 6 villages by year 3, 12 by year 5 to have established committees - Number of committees and records of activities Local governance structures (Commune Councils) remain. Authorities endorse community plans. 2b. Village agreements on natural resource management linked to direct incentives scheme Level of Provincial and local capacity for Sustainable Natural Resource Management Provincial staff and villages have no capacity to support villages in developing sustainable natural resource management plans 3 training courses for 20 government staff each. Training courses for 8 villages by year 5. Number of villages successfully implementing natural resource management plans No villages have natural resource management plans 5 villages by year 3, 8 by year 5 Number of villages with successfully implemented incentive scheme contracts Contract established with 1 village for initiation of ecotourism, in exchange for reduction of hunting and wildlife trade 71 5 villages by year 3, 8 by year 5 - Number of trained natural resource management facilitators. - Number of communities trained. - Existence of natural resource management committees - Commune development plans in years 3-7. Community Forestry Agreements. - Village contracts No drastic change in legislative framework. Communities agree to act together with the support of the project to manage key wildlife and natural resources. Communities recognize/agree to enforcement teams as a support and monitoring. 3. Strengthening capacity for biodiversity management 3a. Financial and management sustainability of activities 3b. Environmental awareness program targeted at communities and armed forces. Established project management structures for key sites Although 50% of project staff are full government employees, only 1 key site has a government management structure that includes relevant project staff. Project staff at two key sites are included in government management structures by year 2, remainder by year 4. - Government management structures. Key site management plans None exist Plans for 2 areas by year 2, remaining 2 areas by year 4. - Management Plans exist and are reviewed annually Sufficient interest exist in key species eco-tourism. Sustainable financing of project activities 95% funding from WCS and UNDP-GEF 30% funding from WCS by year 7, remainder from government, tourism or other sources. - Financial statements. The targeted ecotourism market requires minimal infrastructure investment. Number of villages around key sites with increased awareness of project, species and the importance of natural resource management. Pre-testing will be conducted in year 1. 6 Villages recognize project and its objective, state key species and threats by year 3, further 6 villages by year 5. - Comparison of pretesting results with questionnaires completed in years 3, 5 and 7. Senior military support continues. Number of provincial sectoral staff and agencies with increased awareness of project, sites, and issues for conservation management Existing provincial and agency plans Staff and agencies can identify key sites by year 2, and identify issues for conservation management by year 5 - Provincial, Ministry and Sectoral Agency plans in years 3-7. 72 Government support for project management and activities continues Security threats remain limited. 3c Law enforcement Number of army personnel and commanders with increased awareness of project, sites, and threats to conservation No baseline exists, pretesting will be conducted in year 1 Personnel at 5 bases can identify key sites by year 2 and threats to conservation by year 4. 12 military personnel have participated in enforcement team activity by year 2. - Comparison of pretesting results with questionnaires completed in years 27 - Agreements produced with military commanders (Component 3) - Enforcement team composition Number of incidences of commercial logging within key sites Enforcement team reports in year 1 Less than 5 incidences of commercial logging annually in Protected Forest site by year 3, achieved at remaining sites by year 4. Less than 20 incidences of wildlife trade annually in Protected Forest site by year 3, achieved at remaining sites by year 4. Monitoring program (Component 3) - data collection within key sites - enforcement team reports Number of incidences of wildlife trade Enforcement team reports in year 1 Security threats remain limited Approval of enforcement teams Relevant authorities agree to the establishment of enforcement teams. Patrol teams have sufficient authority to effect law enforcement. Illegal activities of armed forces can be brought under control. 3d. Monitoring and site adaptive management Number of key sites with monitoring programs designed to collect sufficient data for evaluating project impact indicators. Biological Monitoring program established at the Preah Vihear Protected Forest during the PDF-B. 73 Monitoring program established at all sites by year 2. - Annual monitoring report for key sites - Database Staff trained in monitoring methodologies remain in provincial govt. 4. Project Management and Evaluation. Increased provincial capacity for biological monitoring. 1 provincial team trained in biological monitoring during PDF-B. 4 provincial teams trained by year 2. - Number of people trained. Adaptive management to inform intervention priorities at key sites No adaptive management Management plans for key sites take into account the results of monitoring programs when determining annual priorities. - Revised management plans Adaptive management by Project Implementation Units No adaptive management Rolling and annual workplans by project implementation units take into account activities’ progress and problems encountered. - Revised Workplans No project evaluation Mid-term and final reviews - Review reports Evaluation 74 Project Logical Framework Components Component 1. Incorporating biodiversity into the implementation of new laws Outcome 1. Integrated conservation and development planning at the landscapelevel Outcome Indicators (20042011) Number of Seila/PLG Commune Development Plans including conservation planning Level of capacity in key provincial ministries and government for conservation planning and coordination. Provincial Development Plans, Sectoral Agency Plans (e.g. Concessionaires) include conservation priorities Activities Indicators Assumptions 1.1 Training completed during years 1-4. Authorities’ interest 1.1 Training of provincial staff from MoE, Number of people trained. MAFF, MLMUPC in planning and project in being involved in management. These staff will be responsible coordinated land-use for implementation of new laws and planning continues. conservation priorities. Seila/PLG’s interest 1.2 Training and awareness (through 1.2 Number of people trained during in NRM continues. Component 3) in conservation priorities and years 1-4. Provincial capacity planning for relevant staff in all provincial can be increased or is governments in the Northern Plains. sufficient for coordinated 1.3 Incorporate village PLUP land-use plans 1.3 Commune Development Plans planning. into commune development plans from the villages where PLUP is (supported by Seila/PLG). completed (Component 2). Community and district plans are 1.4 Incorporation of commune development 1.4 District integration workshops, plans into district integration workshops and and provincial plans shown to include supported by higher authorities. provincial planning processes, supported by village PLUP plans. Seila/PLG. 1.5 Holding of integration workshops and 1.5 Number of people consulted or Key developments stakeholder consultations to disseminate attending workshops, agencies are made in Cambodia’s land law project plans and receive input from other involved. legal framework planning agencies. 75 Components Outcome Indicators (20042011) Conservation landscape incorporated within national planning strategies Component 2. Applying Mainstreaming Measures Level of Provincial capacity for participatory landuse planning Component 2a Community land-use tenure and title Government approved land-use maps Activities Indicators Assumptions 1.6 Establish a framework through the Provincial Rural Development committee and Provincial Steering Committee to integrate conservation priorities into development planning. 1.6 Planning recognizes conservation Seila/PLG accepted priorities and adapts development as main provincial plans as a result. planning framework 1.7 Co-ordinate conservation activities with Military, Concessionaires and development agencies. Formation of agreements. 1.7 Meetings and resultant agreements. Monitoring reports of agreements. 1.8 Integration of project conservation plans into sectoral planning processes, including provincial government (PLG), MoE, MAFF and Ministry of tourism. 1.8 Endorsement of plans in land-use by Seila/PLG committees, MoE committees, PLG committees, MAFF committees, Ministry of tourism. Government support for key sites for conservation. 2a.1 Training courses in years 1-2 in new laws and PLUP process. Visits to other relevant national projects. 2a.1 Number of people attending training courses and visiting other projects. Trained provincial staff remain in provincial govt. 2a.2 Preparation of PLUP maps and formation of village natural resource management committees. 2a.2 Natural resource management committees created in 5 priority villages4 around two key sites in year 1. Extension to villages in remaining key sites by year 3. Local governance structures (Commune Councils) remain Authorities endorse community plans. Number of village 4 Priority villages have already been identified during the PDF-B, defined as villages particularly close to keystone resources for wildlife, where establishment of land management systems is an urgently required intervention. 76 Components Outcome 2a. Establishment of appropriate community land tenure and resourceright use Component 2b Village agreements on natural resource management linked to direct incentives scheme Outcome 2b. Outcome Indicators (20042011) committees Activities Indicators Assumptions 2a.3 Conflict resolution in villages. 2a.3 Conflict resolution completed in priority villages in year 2, with extension to remaining areas in year 3. No drastic change in legislative framework. 2a.4 Cooperation with authorities to formally recognize PLUP maps. Workshops to disseminate results. 2a.4 PLUP maps receive formal recognition in year 2 for priority villages, extension to remaining areas by year 5. Number of people attending workshops. Provincial government support for PLUP process continues. 2a.5 Demarcation of village land-use areas and development of local agreements on land-use maps. 2a.5 Demarcations completed for priority villages by year 2, remaining villages by year 4. 2a.6 Consolidate outputs into GIS system for national registration. 2a.6 All project data stored in database and linked to a provincial-level GIS system 2b.1 Number of people attending Communities agree training courses. Set of village to act together with regulations. the support of the project to manage key wildlife and natural resources. 2b.2 Report. Communities recognize/agree to enforcement teams as Level of Provincial and local capacity for Sustainable Natural Resource Management 2b.1 Training and awareness workshops on Sustainable Natural Resource and Environmental Management, agreements and regulations for government staff and communities. Number of villages successfully implementing natural resource 2b.2 Design of appropriate mechanism for an incentive scheme: how the scheme will function and be monitored. 77 Components Community engagement in natural resource management Component 3a. Financial and management sustainability of Outcome Indicators (20042011) management plans Number of villages with successfully implemented incentive scheme contracts Established project management structures for key sites Activities Indicators 2b.3 Development of village agreements (including Community Forestry Agreements) for management of natural resources, including agreements on the situations when enforcement activities will be used. Initiation of agreement monitoring system. 2b.3 Agreements completed and a support and signed by priority villages by year 2. monitoring presence. 2b.4 On-going evaluation of village agreements produced in priority villages. 2b.4 Adapted village agreements resulting from evaluations. 2b.5 Negotiations with villages regarding key conservation issues. Implementation of incentive scheme to cover the results of these negotiations. 2b.5 Contracts between the project and priority villages governing incentive structures. Revised village regulations. 2b.6 Regular auditing of incentive scheme activities for adaptive management, including community surveys in years 3 and 6 to measure impact on livelihoods (for contribution to impact indicator). 2b.6 Adapted management plans. Reports on community livelihood impact indicator levels in years 3 and 6. 2b.7 Extension of activities to further villages. 3a.1 Establish management structures within existing FA and MoE systems for key sites. Provide training to staff in management and financing. , 2b.7 Village agreements and contracts. 78 3a.1 Government management structures. Number of staff trained Assumptions Government support for project and activities continue. Components Outcome Indicators (20042011) activities Outcome 3a. Establishment of long-term financial and management sustainability Key site management plans Sustainable financing of project activities Activities Indicators 3a.2 Provide equipment and adequate infrastructure for key sites. 3a.3 Establish an accountable financial system, for the long-term running of the project. 3a.4 Annual and long-term management plans for key sites. 3a.2 Equipment purchased buildings funded. 3a.3 Project financial system. 3a.5 Determine long-term running costs to maintain necessary project initiatives (especially Component 2 and Component 3) in the long-term at each key site. 3a.5 Incremental cost matrix Assumptions and Security threats remain limited. 3a.4 Written management plans for each key site produced annually and every 5 years, from year 2. Management plans are adapted based upon results of monitoring program (Component 3d). 3a.6 Establish a framework for key species 3a.6 Eco-tourism guidelines, payment eco-tourism that benefits biodiversity and system and management system. local villages, through incentive schemes and agreements created under Component 2. 3a.7 Evaluate feasibility of establishing a trust fund, partnerships and capacity development to mobilize resources to cover costs identified under Activity 3s.5. 79 3a.7 Recommendations of feasibility report acted upon. Sufficient interest exists in key species eco-tourism. The targeted ecotourism market requires minimal infrastructure investment. Components Outcome Indicators (20042011) Component 3b. Environmental awareness program targeted at communities and armed forces. Number of villages around key sites with increased awareness of project, species and the importance of natural resource management. Outcome 3b. Increased public awareness of the key project sites for conservation and the need for sustainable use of natural Number of provincial sectoral staff and agencies with increased awareness of project, sites, and issues for conservation management Activities Indicators 3a.8 Secure additional long-term government and NGO commitment to cover costs identified under Activity 3a.5 and management costs under Activity 3a.1. 3a.8 Necessary funding commitment from NGOs and Government. 3b.1 Identification of education requirements and methods. Consideration of strategies required for different groups (military vs. communities). 3b.1 Plan of environmental education Senior military project. support continues. 3b.2 Preparation of environmental education materials, training of staff. 3b.2 Pre-testing assessment. Number of staff trained. 3b.3 Education activities in all villages surrounding key sites and with armed forces across the landscape. 3b.3 Priority villages and armed forces bases completed by year 2, remaining areas by year 4. 3b.4 Building local/provincial support for key species conservation, based upon plan developed in 3b.1 and 3b,2, Includes mobile education unit, capacity-building for provincial and local authorities and study tours. 3b.4 Component plan developed in year 2 based on outcomes of 3b.1 and 3b.2. Activity reports from education teams. 80 Assumptions Components resources Component 3c. Law enforcement Outcome 3c. Reduction in illegal commercial exploitation of biological resources and their components Outcome Indicators (20042011) Number of army personnel and commanders with increased awareness of project, sites, and threats to conservation Number of incidences of commercial logging within key sites Number of incidences of wildlife trade Activities Indicators 3b.5 On-going evaluation of education activities and their impact. 3b.5 Evaluation shows increased awareness of target audience. 3c.1 Production of agreements with local authorities, communities and security forces. 3c.1 Agreements produced by the end Security threats of year 1. remain limited 3c.2 Assemble staff and define law enforcement protocol, target areas and activities. Develop a strategy for curtailing border wildlife trade. 3c.2 Team structures and staffing. Written plan of proposed enforcement activities. Assumptions Approval of enforcement teams 3c.4 Demarcation of protected sites within the landscape. Relevant authorities agree to the establishment of 3c.3 Number of people trained and enforcement teams. equipped. Patrol teams have sufficient authority to effect law 3c.4 Boundaries established and enforcement. marked on the ground. 3c.5 Development of a database to monitor effectiveness of enforcement activities, with a reporting system. Illegal activities of 3c.5 Evidence of use of the data armed forces can be management system, including brought under control. generated reports. 3c.3 Training, equipment and infrastructure provided for provincial government enforcement staff. 81 Components Component 3d. Monitoring and site adaptive management Outcome 3d. Adequate data for conservation management purposes Outcome Indicators (20042011) Number of key sites with monitoring programs designed to collect sufficient data for evaluating project impact indicators. Increased provincial capacity for biological monitoring. Adaptive management to inform intervention priorities at key sites. Activities Indicators 3c.6 Evaluation of enforcement activities. 3c.6 Reduced wildlife trade and illegal logging demonstrated by reports and data collected by enforcement teams. 3d.1 Planning of monitoring program, including methodology, monitoring sites and protocols. 3d.1 Report on the proposed Staff trained in monitoring program in year 1. monitoring methodologies remain in provincial 3d.2 Staff training materials; number govt. of people trained. 3d.2 Training of staff in monitoring methodologies in years 1-2. Assumptions 3d.3 Trial of monitoring program. 3d.3 Monitoring program established in one key site during year 1. First year report. 3d.4 Development of a data management system for the monitoring program, with training of provincial staff in its use. 3d.4 Data management system and documentation. Number of staff trained. 3d.5 On-going evaluation of trial monitoring program. 3d.5 Adaptation of monitoring program following from the results of evaluations. 3d.6 Extension of program to other key sites 3d.6 Implementation by year 2. reports. 3d.7 Monitoring of Vulture Populations 82 and 3d.7 Annual reports of vulture numbers yearly Components Component 4. Project Management and Evaluation Outcome 4. Adequate reporting on project outcomes and indicators Outcome Indicators (20042011) Adaptive management by project implementation units Mid-term and final reviews Activities Indicators 3d.8 Annual evaluation of site activities based on results of monitoring program to identify problems and priority interventions for following year. 3d.8 Adaptation of site management plans resulting from problems analysis. Priorities established for each site intervention. 4.1 Establishment of project office and administrative staff 4.1 Office and staff exist 4.2 Regular meetings of Project Steering Committee to monitor and advise on implementation, ensuring initiatives are integrated into government strategy and approved. 4.2 Minutes of meetings. 4.3 Rolling and Annual evaluation of project activities based upon results of monitoring program and progress made towards outcome indicators. 4.3 Adaptation of rolling and annual workplans for project implementation units resulting from analysis. 4.4 Reports from reviews. 4.4 Mid-term and final reviews 83 Assumptions SECTION III: TOTAL WORKPLAN AND BUDGET 84 FINANCING PLAN Summary The total financial package of the intervention (excluding preparatory funds) is estimated to be US$ 4,468,618. Of this, the GEF is requested to support incremental costs through a grant of US$ 2,300,000, in addition to the US$ 210,000 dispersed during the PDF-B. All co-financing sources, WCS, Seila/PLG and the RGC, are parallel funding with a total value of US$ 2,665,518 including monies dispersed during the PDF-B. The table below summarises the co-financing sources. An incremental cost analysis has been provided as Annex 6 in Section 1. Name of Cofinancier (source) WCS (preparatory phase) WCS (preparatory phase) WCS WCS Co-financing Sources Status Classification Type Amount (US$) NGO Grant 260,000 Dispersed during PDF-B NGO NGO NGO Seila/PLG (Year 1) Multilateral donor project Seila/PLG Multilateral donor project RGC (preparatory phase) RGC EA EA Committed in-kind Grant 215,400 Dispersed during PDF-B 1,100,000 Confirmed. See letter attached. Confirmed. See letter attached. Confirmed. See letter attached. Confirmed. See description below and letter attached. Dispersed during PDF-B Committed in-kind Grant 500,000 Committed in-kind 331,005 Committed in-kind Committed in-kind 21,500 132,402 105,210 RGC has endorsed the project. 2,665,518 Sub-Total Co-financing WCS WCS dispersed US$ 475,400 during the PDF-B phase and has committed co-financing of US$ 1,600,000 (US$ 500,000 in-kind, US$ 1,100,000 grant) to the full project. This has been calculated on the basis of US$ 200,000 per annum, including the 1-year preparatory phase to the full project following the end of the PDF-B. Seila/PLG Seila/PLG is committing various financial resources to the five provinces (Preah Vihear, Banteay Meanchey Odor Meanchey, Stung Treng and Siem Reap) of the Northern Plains project. Some of these resources are for unrelated activities or for activities which can be considered baseline to the GEF proposed project. However, considerable resources are being directed to specific 85 activities that are crucial for the success of the CALM project and which are recognised in the project logistical framework. The current phase of Seila/PLG is due to last until 2005, however UNDP funding to PLG is expected to be renewed for the 2006-2010 phase. The annual PLG planning process is particularly relevant for CALM and activities leading to Outcome 1: Integrated conservation and development planning at the landscape-level. Without PLG activities there would be no forum to integrate project achievements at key sites into district, provincial or landscape plans. In 2004 and 2005 the annual UNDP financing for these processes will be approximately $50,000 per province. If biodiversity values are integrated into only 20% of planning activities, the total in 2004-5 would be $100,000, with a further $250,000 anticipated for 2006-2010 if the current contribution is maintained at this level. PLG also provides funding to Provincial Departments, through the Provincial Rural Development Committee (PRDC). In 2004 and 2005 $32,402 will be allocated to activities that directly contribute to natural resources management and are within the CALM logistical framework (such as establishing community forests). Even if the Seila/PLG contribution remains the same, at a minimum level, over 2006-2010 the contribution is expected to be $81,005. In reality, the CALM project is expected to motivate a greater contribution than this from Seila/PLG through influencing the ability of the relevant Government agencies to apply for resources, though this cannot now be estimated. From the committed budgets of Seila/PLG and the operational plans for coming years, it is expected that a total of US$463,407 will be provided for activities directly related to the CALM project. 86 DETAILED BUDGETS A. GEF (annual ATLAS budget) Award ID: tbd Award Title: PIMS 2177 BD FSP:Cambodia Northern Plains Project ID: tbd Project Title: GEF OUTCOME/ Atlas Activity 1. Integrated conservation and development planning at the landscapelevel FSP Establishing Conservation Areas through Landscape Management (CALM) in the Northern Plains of Cambodia Responsible Atlas Party Source Budgetary (Implementing of Account Agent) Funds Code ERP/ATLAS Budget Description/Input YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 TOTALS WCS GEF 71200 Intl Project Advisor 52,000 54,600 57,300 60,200 31,600 WCS GEF 71300 Natl Management Advisor 19,600 10,300 0 0 0 WCS GEF 12,000 12,000 12,000 8,000 4,000 WCS GEF 71600 Study Tours. Workshops. Provincial 74200 Steering Committee Meetings 4,000 4,000 4,000 4,000 4,000 WCS GEF 72500 1,000 1,000 1,000 1,000 1,000 33,200 34,800 323,700 0 0 29,900 4,000 2,000 54,000 4,000 4,000 28,000 1,000 750 Sub-total 2. Establishment of Community Engagement in conservation management WCS GEF 71200 Intl Specialists (NRM and Communities) WCS GEF 71300 Natl Communities Specialists WCS GEF WCS 442,350 67,200 14,950 70,600 9,000 52,900 9,450 0 3,800 0 0 0 0 0 0 190,700 71400 Communities Officers 7,150 11,150 11,650 4,800 3,500 3,650 3,800 45,700 GEF 72500 Expendable Equipment and Supplies and Imagery 3,000 2,500 2,250 1,250 500 500 500 10,500 WCS GEF 72300 Boundary Demarcation 2,500 2,500 2,500 1,250 0 0 0 8,750 WCS GEF 74500 Incentive Scheme Payments 5,000 5,000 5,000 5,000 5,000 3,500 2,500 31,000 WCS GEF 71600 Travel and Workshops 6,000 6,000 6,000 2,500 500 500 500 22,000 WCS GEF 72200 Non-Expendable Equipment 8,800 0 0 0 0 0 0 8,800 WCS GEF 73400 Equipment Maintenance & Fuel 1,600 1,600 1,600 1,600 550 550 550 Sub-total 3. Strengthened capacity for biodiversity management 6,750 $ WCS GEF 71200 Intl Monitoring and GIS Specialist WCS GEF 71300 GIS Specialist WCS GEF WCS GEF 37,200 8,050 $ 362,700 18,000 18,900 0 0 0 0 0 3,300 3,450 3,600 3,800 2,000 0 0 16,150 71400 National Officers 59,900 63,450 66,400 55,850 47,800 38,200 30,700 362,300 74200 Audio/Visual Production and Posters 10,000 10,000 10,000 10,000 0 0 0 40,000 87 36,900 WCS GEF 72100 Contracts : Database Programming, Infrastructure Development and Imagery Interpretation 120,000 70,000 10,000 0 0 5,000 0 205,000 WCS GEF 71600 Travel and Workshops WCS GEF 72500 Supplies 15,000 15,000 15,000 10,000 10,000 7,500 5,850 78,350 3,250 3,250 3,250 3,250 3,250 2,250 1,250 19,750 WCS GEF 72300 Expendable Equipment and Boundary Demarcation 5,250 6,500 3,250 3,250 1,850 1,300 1,100 22,500 WCS GEF 74500 Vulture Restaurants 2,500 2,500 2,500 2,500 0 0 0 10,000 WCS GEF 72200 Non-Expendable Equipment 71,600 0 0 0 0 0 0 71,600 WCS GEF 72400 Non-Expendable Equipment 4,000 0 0 0 0 0 0 4,000 WCS GEF 73400 Equipment Maintenance & Fuel 10,850 10,850 10,850 10,800 10,800 10,800 7,700 72,650 GEF 71400 Project Administrators and Officers 19,750 20,450 21,150 21,950 18,850 18,700 19,400 140,250 GEF 72400 Communication Costs 2,400 2,400 2,400 2,400 2,400 2,400 2,400 16,800 GEF 72400 Communication Costs 1,000 1,000 1,000 1,000 1,000 1,000 1,000 7,000 WCS GEF 73100 Office Rental 3,600 3,600 3,600 3,600 3,000 3,000 2,400 22,800 WCS GEF 72500 Office Equipment and Supplies WCS GEF 71600 International and National Travel, Field Visits, DSAs, Project Executive Group UNDP GEF 74100 Audit UNDP GEF 74500 Independent Evaluations WCS GEF 75100 Indirect Costs WCS GEF 72800 Non-Expendable Equipment 2,000 WCS GEF 73400 Equipment Maintenance & Fuel 1,400 Sub-total 4. Learning, WCS evaluation and adaptive management WCS UNDP increased $ 4,500 4,500 4,500 4,500 2,700 2,700 2,700 26,100 11,000 11,000 11,000 11,000 7,000 7,000 6,000 64,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000 21,000 0 0 0 30,000 0 0 30,000 60,000 45,000 35,000 30,000 25,000 17,000 16,000 16,000 184,000 0 0 2,000 0 0 0 4,000 1,400 1,400 1,400 1,400 1,400 1,400 9,800 Sub-total $ 555,750 TOTAL $ 2,300,000 B. WCS (7-year budget) ITEM 939,200 DETAILS 1. Incorporating biodiversity into landscape-level planning processes Staff Intl Technical Advisors 88 ATLAS CODE TOTAL COST 71200 244,300 TOTALS $1,600,000 Activities Study Tours. Site-level training. Site workshops and national workshops. Provincial Steering Committee Meetings Travel 71600 54,000 Reports/Publications 74200 28,000 Supplies 72500 6,750 $ 333,050 2. Applying Mainstreaming Measures Staff Intl NRM Specialist Natl Communities Specialists Communities Officers Activities 71200 71300 71400 60,000 28,200 45,700 72500 2,750 Boundary Demarcation 72300 8,750 Incentive Scheme Payments 74500 31,000 71600 22,000 72500 7,750 73400 8,050 Buying Imagery Travel Aerial Photos Travel Equipment Expendable Equipment and Supplies Equipment Maintenance & Fuel Motorbikes (6) $ 214,200 3. Strengthening capacity for biodiversity management Staff Intl PA Advisors Intl Monitoring and GIS Intl Eco-tourism Specialist GIS Specialist Natl Site Managers Eco-tourism Specialist Eco-tourism Officers Law Enforcement Officers Rangers Education Officers Monitoring Officers 71200 71200 71200 71300 71400 71300 71400 71400 71400 71400 71400 89 163,900 36,900 26,500 16,150 85,350 15,700 8,800 104,850 89,300 9,600 23,900 Local Staff Support Staff Activities Contract : Infrastructure development Boundary Demarcation / Signboards Teacher Supplements Drivers, Cooks Travel Equipment Expendable Equipment Expendable Equipment Supplies Annual ranger/patrol team equipment Expendable Equipment Vulture Restaurant Cows Non-Expendable Equipment Vulture Trap Hi-lux (2), Motorbikes (20), Generators (12), Radios (20) Equipment Maintenance & Fuel 71400 71400 7,200 14,700 72100 50,000 72300 10,250 71600 78,350 72500 19,750 72300 12,250 74500 10,000 72200 5,000 73400 72,650 $ 861,100 4. Project Management and Evaluation Staff WCS Administrator Local Staff Activities 71400 71400 68,900 4,250 Communication Costs 72400 16,800 Office Rental 73100 22,800 Office Equipment and Supplies 72500 11,600 National Travel, Field Visits, DSAs 71600 22,000 71600 21,000 Batteries, Medical Kits etc.. 72500 14,500 Hi-lux (1) 73400 9,800 International Travel Equipment Expendable Equipment Equipment Maintenance & Fuel $ 191,650 90 C. Seila/PLG (7-year budget) ITEM DETAILS 1. Incorporating biodiversity into landscape-level planning processes Support to ExCom, Training and Capacity-building Salary support to staff Travel, DSAs, etc.. Training Costs to Commune Councils Motorcycle Maintenance & Fuel Office Supplies Communications Materials/handouts Snacks Seila T-shirts and caps Provincial Planning Process DSA for staff Materials/handouts Snacks Office Supplies Camera and motorbike Computer training course Contingency cost 2. Applying Mainstreaming Measures Support to Provincial Departments - Preah Vihear Contract to Prov Dept Environ Community Forestry Contract to Prov Dept Land Mgmt Education on Land-use policy Support to Provincial Departments - Oddar Meanchey Contract to Prov Dept Land Mgmt Land-use plan Contract to Prov Dept Environ Community Forestry 91 ATLAS CODE TOTAL COST 71300 71600 71600 73400 72500 72400 72500 72500 72300 126,000 21,000 55,937 56,700 4,200 1,680 20,195 10,808 3,500 71600 72500 72500 72500 72200 20,146 11,514 5,660 1,680 9,240 469 1,271 72100 72100 35,000 14,000 72100 72100 18,697 10,710 TOTALS $ 463,407 $ 350,000 $ 78,407 3. Strengthening capacity for biodiversity management Support to Provincial Departments - Preah Vihear Contract to Prov Dept Environ Environmental Education Support to Provincial Departments - Stung Treng Contract to Prov Dept Environ Environmental Education 72100 7,000 72100 28,000 $ 35,000 D. RGC (7-year budget) ITEM TOTAL COST 1. Incorporating biodiversity into landscape-level planning processes National Programme Office National Programme Director NPD support staff (two counterparts) Attendance of personnel at meetings Provincial Steering Committee Contributions from other government staff Attendance at meetings, workshops, training etc Contributions to documents etc Government decision making process leading to approving key project outputs 2. Applying Mainstreaming Measures Contributions from other government staff Attendance at meetings, workshops, training etc Contributions to documents etc Government decision making process leading to approving key project outputs 3. Strengthening capacity for biodiversity management Provincial Office and Management Provincial project co-manager (2 people) Provincial Support staff Office space rent Utilities/building maintenance etc 6,300 6,300 2,520 5,250 1,050 2,100 $ 23,520 $ 7,875 5,250 525 2,100 12,600 8,400 33,600 8,400 92 TOTALS $ 105,210 Contributions from other government staff Attendance at meetings, workshops, training etc Contributions to documents etc Government decision making process leading to approving key project outputs 4. Project Management and Evaluation Attendance of personnel at meetings National Steering Committee Technical Working Group Meetings 2,625 1,050 2,100 $ 68,775 $ 5,040 2,520 2,520 93 WORKPLAN (see Detailed Budgets [above] for a breakdown of costs under each outcome) Outcomes Output Indicators 1. Incorporating biodiversity into landscape-level planning processes Outcome 1. 1.1 Training of provincial staff from MoE, MAFF, 1.1 Training completed during years 1-4. Integrated MLMUPC in planning and project management. Number of people trained. conservation These staff will be responsible for and implementation of new laws and conservation development priorities. planning at 1.2 Training and awareness (through 1.2 Number of people trained during years the Component 3) in conservation priorities and 1-4. landscapeplanning for relevant staff in all provincial level governments in the Northern Plains. 1.3 Incorporate village PLUP land-use plans into 1.3 Commune Development Plans from commune development plans (supported by the villages where PLUP is completed Seila/PLG). (Component 2). 1.4 Incorporation of commune development plans into district integration workshops and provincial planning processes, supported by Seila/PLG. 1.5 Holding of integration workshops and stakeholder consultations to disseminate project plans and receive input from other planning agencies. 1.6 Establish a framework through the Provincial Rural Development committee and Provincial Steering Committee to integrate conservation priorities into development planning. 1.4 District integration workshops, and provincial plans shown to include village PLUP plans. 1.7 Co-ordinate conservation activities with Military, Concessionaires and development agencies. Formation of agreements. 1.7 Meetings and resultant agreements. Monitoring reports of agreements. 1.8 Integration of project conservation plans into sectoral planning processes, including provincial government (PLG), MoE, MAFF and Ministry of tourism. 1.8 Endorsement of plans in land-use by Seila/PLG committees, MoE committees, PLG committees, MAFF committees, Ministry of tourism. Government support for key sites for conservation. Yr1 Yr2 TIMEFRAME (Years) Yr3 Yr4 Yr5 Yr6 Yr7 Responsible Party WCS WCS WCS and Seila/PLG WCS and Seila/PLG 1.5 Number of people consulted or attending workshops, agencies involved. WCS and Seila/PLG 1.6 Planning recognizes conservation priorities and adapts development plans as a result. WCS and Seila/PLG 2. Applying Mainstreaming Measures 94 BUDGET Source and Amount WCS, MAFF and MoE WCS, MAFF, MoE and Seila/PLG GEF: $442,350 WCS: $333,050 Seila/PLG: $350,000 RGC: $23,520 Outcomes Outcome 2a. Establishment of appropriate community land tenure and resourceright use Output 2a.1 Training courses in years 1-2 in new laws and PLUP process. Visits to other relevant national projects. 2a.1 Number of people attending training courses and visiting other projects. 2a.2 Preparation of PLUP maps and formation of village natural resource management committees. 2a.2 Natural resource management committees created in 5 priority villages around two key sites in year 1. Extension to villages in remaining key sites by year 3. 2a.3 Conflict resolution completed in priority villages in year 2, with extension to remaining areas in year 3. 2a.3 Conflict resolution in villages. Outcome 2b. Community engagement in natural resource management Indicators Yr1 Yr2 TIMEFRAME (Years) Yr3 Yr4 Yr5 Yr6 Yr7 Responsible Party BUDGET Source and Amount WCS 2a.4 Cooperation with authorities to formally recognize PLUP maps. Workshops to disseminate results. 2a.4 PLUP maps receive formal recognition in year 2 for priority villages, extension to remaining areas by year 5. Number of people attending workshops. 2a.5 Demarcation of village land-use areas and development of local agreements on land-use maps. 2a.5 Demarcations completed for priority villages by year 2, remaining villages by year 4. 2a.6 Consolidate outputs into GIS system for national registration. 2a.6 All project data stored in database and linked to a provincial-level GIS system 2b.1 Training and awareness workshops on Sustainable Natural Resource and Environmental Management, agreements and regulations for government staff and communities. 2b.2 Design of appropriate mechanism for an incentive scheme: how the scheme will function and be monitored. 2b.1 Number of people attending training courses. Set of village regulations. 2b.3 Development of village agreements (including Community Forestry Agreements) for management of natural resources, including agreements on the situations when enforcement activities will be used. Initiation of agreement monitoring system. 2b.4 On-going evaluation of village agreements produced in priority villages. 2b.3 Agreements completed and signed by priority villages by year 2. WCS WCS WCS, MAFF, MoE and Seila/PLG WCS WCS WCS 2b.2 Report. WCS WCS, MAFF, MoE and Seila/PLG 2b.4 Adapted village agreements resulting from evaluations. WCS 95 GEF: $362,700 WCS: $214,200 Seila/PLG: $78,407 RGC: $7,875 Outcomes Output 2b.5 Negotiations with villages regarding key conservation issues. Implementation of incentive scheme to cover the results of these negotiations. 2b.6 Regular auditing of incentive scheme activities for adaptive management, including community surveys in years 3 and 6 to measure impact on livelihoods (for contribution to impact indicator). 2b.7 Extension of activities to further villages. Indicators Yr1 Yr2 TIMEFRAME (Years) Yr3 Yr4 Yr5 Yr6 Yr7 Responsible Party BUDGET Source and Amount 2b.5 Contracts between the project and priority villages governing incentive structures. Revised village regulations. WCS 2b.6 Adapted management plans. Reports on community livelihood impact indicator levels in years 3 and 6. WCS 2b.7 Village agreements and contracts. WCS 3. Strengthening capacity for biodiversity management Outcome 3a. 3a.1 Establish management structures within Establishment existing FA and MoE systems for key sites. of long-term Provide training to staff in management and financial and financing. , management 3a.2 Provide equipment and adequate sustainability infrastructure for key sites. 3a.1 Government management structures. Number of staff trained. MAFF, MoE and WCS 3a.2 Equipment purchased and buildings funded. 3a.3 Establish an accountable financial system, for the long-term running of the project. 3a.3 Project financial system. 3a.4 Annual and long-term management plans for key sites. 3a.4 Written management plans for each key site produced annually and every 5 years, from year 2. Management plans are adapted based upon results of monitoring program (Component 3d). MAFF, MoE and WCS WCS 3a.5 Determine long-term running costs to maintain necessary project initiatives (especially Component 2 and Component 3) in the longterm at each key site. 3a.6 Establish a framework for key species ecotourism that benefits biodiversity and local villages, through incentive schemes and agreements created under Component 2. 3a.5 Incremental cost matrix 3a.7 Evaluate feasibility of establishing a trust fund, partnerships and capacity development to mobilize resources to cover costs identified under Activity 3s.5. 3a.7 Recommendations of feasibility report acted upon. MAFF, MoE and WCS WCS 3a.6 Eco-tourism guidelines, payment system and management system. WCS WCS 96 GEF: $939,200 WCS: $861,100 Seila/PLG: $35,000 RGC: $68,775 Outcomes Outcome 3b. Increased public awareness of the key project sites for conservation and the need for sustainable use of natural resources Output Indicators 3a.8 Secure additional long-term government and NGO commitment to cover costs identified under Activity 3a.5 and management costs under Activity 3a.1. 3b.1 Identification of education requirements and methods. Consideration of strategies required for different groups (military vs. communities). 3a.8 Necessary funding commitment from NGOs and Government. 3b.2 Preparation of environmental education materials, training of staff. 3b.2 Pre-testing assessment. Number of staff trained. 3b.3 Education activities in all villages surrounding key sites and with armed forces across the landscape. 3b.3 Priority villages and armed forces bases completed by year 2, remaining areas by year 4. 3b.4 Building local/provincial support for key species conservation, based upon plan developed in 3b.1 and 3b,2, Includes mobile education unit, capacity-building for provincial and local authorities and study tours. 3b.5 On-going evaluation of education activities and their impact. 3b.4 Component plan developed in year 2 based on outcomes of 3b.1 and 3b.2. Activity reports from education teams. 3c.1 Production of agreements with local authorities, communities and security forces. 3c.1 Agreements produced by the end of year 1. 3c.2 Assemble staff and define law enforcement protocol, target areas and activities. Develop a strategy for curtailing border wildlife trade. 3c.2 Team structures and staffing. Written plan of proposed enforcement activities. 3c.3 Training, equipment and infrastructure provided for provincial government enforcement staff. 3c.3 Number of people trained and equipped. 3c.4 Demarcation of protected sites within the landscape. 3c.4 Boundaries established and marked on the ground. 3c.5 Development of a database to monitor effectiveness of enforcement activities, with a reporting system. 3c.5 Evidence of use of the data management system, including generated reports. Yr1 Yr2 TIMEFRAME (Years) Yr3 Yr4 Yr5 Yr6 Yr7 Responsible Party WCS 3b.1 Plan of environmental education project. WCS WCS WCS WCS 3b.5 Evaluation shows increased awareness of target audience. WCS Outcome 3c. Reduction in illegal commercial exploitation of biological resources and their components WCS 97 MAFF, MoE and WCS MAFF, MoE and WCS MAFF, MoE and WCS WCS BUDGET Source and Amount Outcomes Outcome 3d. Adequate data for conservation management purposes Output Indicators 3c.6 Evaluation of enforcement activities. 3c.6 Reduced wildlife trade and illegal logging demonstrated by reports and data collected by enforcement teams. 3d.1 Planning of monitoring program, including methodology, monitoring sites and protocols. 3d.1 Report on the proposed monitoring program in year 1. 3d.2 Training of staff in monitoring methodologies in years 1-2. 3d.2 Staff training materials; number of people trained. 3d.3 Trial of monitoring program. 3d.3 Monitoring program established in one key site during year 1. First year report. 3d.4 Development of a data management system for the monitoring program, with training of provincial staff in its use. 3d.4 Data management system and documentation. Number of staff trained. 3d.5 On-going evaluation of trial monitoring program. 3d.5 Adaptation of monitoring program following from the results of evaluations. 3d.6 Extension of program to other key sites by year 2. 3d.6 Implementation and yearly reports. 3d.7 Monitoring of Vulture Populations 3d.7 Annual reports of vulture numbers Yr1 Yr2 TIMEFRAME (Years) Yr3 Yr4 Yr5 Yr6 Yr7 Responsible Party BUDGET Source and Amount WCS WCS WCS WCS WCS WCS WCS WCS 3d.8 Annual evaluation of site activities based on results of monitoring program to identify problems and priority interventions for following year. 4. Project Management and Evaluation. 3d.8 Adaptation of site management plans resulting from problems analysis. Priorities established for each site intervention. Outcome 4. Adequate reporting on project outcomes and indicators 4.1 Office and staff exist 4.1 Establishment of project office and administrative staff WCS WCS 4.2 Regular meetings of Project Steering Committee to monitor and advise on implementation, ensuring initiatives are integrated into government strategy and approved. 4.2 Minutes of meetings. WCS, MAFF, MoE and Seila/PLG 98 GEF: $555,750 WCS: $191,650 RGC: $5,040 Outcomes Output 4.3 Rolling and Annual evaluation of project activities based upon results of monitoring program and progress made towards outcome indicators. 4.4 Mid-term and final reviews Indicators Yr1 Yr2 TIMEFRAME (Years) Yr3 Yr4 Yr5 Yr6 Yr7 Responsible Party 4.3 Adaptation of rolling and annual workplans for project implementation units resulting from analysis. WCS 4.4 Reports from reviews. WCS 99 BUDGET Source and Amount SECTION IV : ADDITIONAL INFORMATION 100 PART I: Other Agreements Co-financing letters (see attached) - UNDP for Seila/PLG - WCS - RGC (from MoE GEF focal point) Support letters (see attached) - Preah Vihear Military - Preah Vihear Police - Preah Vihear Governor PART II: Terms of References for key project staffs and main sub-contracts Annex 1.7: Terms of Reference (ToR) 1. Project Executive Group ToR The Project Executive Group (PEG) will provide guidance and direction to the CALM Project, funded by UNDP/GEF. Although the PEG will have decision-making powers as well as an advisory function, it may not unilaterally alter project objectives or outputs. The PEG may alter project activities and/or implementation arrangements, including arrangements for the sub-contracts, only if there is clear and consistent evidence, based on progress reports against project output indicators that the project activities are failing to deliver project outputs, or the sub-contracts are failing to meet their obligations under their Terms of Reference. Changes to project activities and/or implementation arrangements funded by the GEF will require the consent of the UNDP/GEF Executive Coordinator or his representative. The Minister of MAFF will be the Chairman of the PEG. The committee will meet at least annually, or more often if required. The annual meeting will be the TPR. The Chairman, Deputy Chairman, UNDP or WCS may request committee meetings. The PEG will be responsible for the following: Advise project management on implementation; Review project progress; Approve the annual work plan and budget; Monitor project expenditures; Review the project APR/PIR during the annual Tripartite Review (TPR) Foster coordination and synergy between the different components and actors involved in CALM; and Provide a framework for conflict resolution in case of any problem arising during the implementation of CALM. The PEG membership will comprise of: 101 Minister of MAFF as the PEG Chairman; Minister of MoE as the PEG Deputy Chairman Representatives of MAFF, MoE, MLMUPC, MoD and CDC; Governors, or Representative of the five Project Provinces; Representatives of Regional Police, Military and Border Police units; Representative of UNDP-Cambodia and UNDP-GEF Regional Coordinating Unit if required for TPR. Representative of Seila/PLG; and Representative of WCS Representatives of other government bodies and other international organizations as relevant will be invited to participate in meetings of the PEG to offer policy and technical advice. 2. Sub-Executive Group ToR The Sub-Executive Group (SEG) will provide guidance and direction to the provincial implementation of CALM Project, funded by UNDP/GEF. There will be one SEG for each province with on-going activities. The SEGs will assist with achieving of Outcome 1 of CALM: Integrated conservation and development planning at the landscape-level. The SEGs will have a primarily integration role, to advise on project implementation, resolve conflicts, and involve relevant provincial authorities in decision-making processes. The SEGs may alter project activities within the province, only if there is clear and consistent evidence, based on progress reports against project output indicators that the project activities are failing to deliver project outputs. Changes to project activities and/or implementation arrangements funded by the GEF will require the consent of the UNDP/GEF Executive Coordinator or his representative. The Provincial Governor will be the Chairman of the SEG. The committee will meet at least annually, or more often if required. The Chairman, Deputy Chairman, UNDP or WCS may request committee meetings. The SEG will be responsible for the following: Advise project management on implementation; Review project progress, particularly Community and Site Management Plans; Review the project APR/PIR; Foster coordination and synergy between the different components and actors involved in CALM; and Provide a framework for conflict resolution in case of any problem arising during the implementation of CALM. The SEG membership will comprise of: Provincial Governor as the SEG Chairman; 102 Representatives of FA Cantonment, Provincial Departments (including Environment and Land Management); Representatives of Provincial Police, Military and Border Police units; Representative of Seila/PLG; and Representative of WCS Representatives of other government bodies and other international organizations as relevant will be invited to participate in meetings of the SEG to offer policy and technical advice. 103 3. International Project Advisor (IPA) Position: International Project Advisor (IPA) Duty Station: CALM Project Office, Tbeng Meanchey Duration: 4 years full-time, 3 years half-time. The IPA will be appointed by WCS. Background Under the overall supervision of the WCS Cambodia Director, and in close collaboration with the National Site Managers (NSMs) and the Project Office based in Tbeng Meanchey, the IPA will be responsible for establishment of the project activities as per the project document. In particular he/she will be responsible for for planning and implementing two protected area management systems described in Component 3. The position is based in the Project Office in Tbeng Meanchey, with time in Phnom Penh Duties and Responsibilities The IPA will: (i) Establish all project activities and ensure that activities are in accordance with the project document, particularly relating to Components 1 and 3 of CALM; (ii) Establish a Project Office, including a system of control of project expenditures and reporting on activities and results to the GEF; (iii) together with the NSMs design a management structure and regulations for the protected areas; (iv) with the NSMs recruit and train protected area staff; (v) oversee the construction of required infrastructure and purchasing of equipment; (vi) with the NSMs produce management plans for each site, including zonation maps; (vii) implement a database system to monitor and report to protected area managers on management activities; (viii) establish an adaptive management protocol; (ix) Respond to queries raised by UNDP Cambodia, WCS Cambodia, the Project Steering Committee and the National Project Director; (x) With the NSMs prepare and update quarterly and annual work plans and review the budget accordingly through a participatory process, and in close collaboration with the Project Office, the executing agency, the implementing agencies and Seila/PLG; (xi) Liaise with the relevant ministries, national and international research institutes, NGOs, Seila/PLG and other relevant institutions in order to involve their staff and coordinate their efforts in project activities. Cooperation and coordination with relevant provincial government agencies will be particularly crucial in regard to law enforcement within the core areas; (xii) Coordinate the required reporting duties with the assistance of the National and International Consultants, and as per the UNDP Guidelines and the Project Document; (xiii) Participate in the PEG and SEG meetings; (xiv) Carry out the functions of GEF Clearing House Mechanism Focal Point; (xv) Ensure that the Cambodia GEF Focal Point is kept advised of Project progress; (xvi) Organise project evaluations; (xvii) With the NSMs prepare the terminal report; and (xviii) Initiate and mobilize resources for the potential follow-up activities. Outputs to be produced In collaboration with the NSMs, the IPA will provide the following outputs: 104 1. A successful establishment of the project activities, including activities sub-contracted by the project; 2. Reviewed and updated quarterly and annual work plans and budgets through a participatory process involving the Project Office, WCS, the Government agencies and Seila/PLG; 3. Assistance to the NSMs in preparation of quarterly progress reports, annual progress reports, and the final report; 4. Provide technical support and facilitate consultants, project staff, and sub-contracts; 5. Communicate effectively with all levels of government to ensure the integration of project activities and outputs into planning processes and national initiatives (e.g. land management). In particular through the PEG and SEG, and other relevant committees, facilitate the recognition of project outputs at higher government levels. 6. Establish a procedure for adaptive management, and an annual adaptive management review process. 7. With the NSMs produce development plans for the two protected areas in the Northern Plains. These development plans should include (i) a management structure, (ii) management regulations and responsibilities, (iii) establish a process to produce a zonation of each area, and (iv) establish a staff training and recruitment schedule. 8. A ranger manual for protected area staff, which should include (i) staff code of conduct, (ii) staff responsibilities, (iii) management rules and regulations, (iv) data collection protocols, (v) data entry forms. 9. A database manual for protected area management units, which should include the functioning of the database, reporting features and data-entry protocols. 10. A completed set of management rules, protocols, structure, zonation for each protected area. 11. With the NSMs, in the second year, produce management plans for each protected area. 12. Review, edit and disseminate the reports to relevant government, NGO and UN bodies, and foster cooperation with them regarding implementation of the different strategies. Qualifications The successful candidate should be have the following attributes: 1. Strong technical background in a relevant discipline: biodiversity conservation, protected area management, environment training; 105 2. Minimum of three years working experience in Project Management; 3. Minimum of three years working experience in areas relevant for the project; 4. Demonstrated ability to work with government and to foster cooperation between governmental agencies, NGOs, etc; 5. Extensive experience in Asia, and ideally in Cambodia; 6. Previous experience with the UN and more specifically UNDP and the GEF would be an important asset; 7. Computer literate; and 8. Perfect written and verbal command of English, and ideally good spoken Khmer. NB: Gender and cultural diversity is preferred 4. International Communities and Education Specialist (ICES) Position: International Education Specialist (ICES) Duty Station: CALM Project Office, Tbeng Meanchey Duration: 3 Years The ICES will be appointed by WCS. Background The Northern Plains is currently characterized by an ‘open-access’ management system, with no recognized land tenure or title assigned to any parties. Establishing an effective land management, including the natural resources found, is essential if conservation priorities are to be integrated into the landscape and the needs of communities recognized in protected area plans. Current awareness of the environment, biodiversity conservation, the law, and land and natural resource management by provincial authorities, armed forces and local communities in the Northern Plains is also weak. Under the overall supervision of WCS and together with the national communities specialists, the ICES will be responsible for planning and implementing all activites described in Component 2 of the CALM project document, in addition to the education program described in Component 3b and eco-tourism initiatives (Component 3a). The position is based in the Project Office in Tbeng Meanchey, but part of the time will be spent in Phnom Penh and other provinces where CALM has activities. Duties and Responsibilities In collaboration with the national communities and education specialists and the IPA, the ICES will: (i) design an environmental education program for the Northern Plains, targeted at local communities and armed forces around the key sites and at provincial departments and 106 authorities; (ii) hold training and awareness workshops for provincial staff and target audiences; (iii) establish a mobile education unit and other units required to implement the education plan; (iv) organize study tours, as required; (v) review and adapt education activities, based upon results of evaluations; (vi) with the INRMS to work with local communities to establish land-use plans for each target village; (vii) facilitate preparation of community regulations for land and natural resource management; (viii) facilitate the official recognition of these regulations; (ix) design the incentive scheme (direct payments for conservation); (x) advise on the implementation the incentive scheme in target villages; (xi) review and audit the incentive scheme; (xii) design an eco-tourism programme for suitable key sites in the Northern Plains; (xiii) facilitate the production of community eco-tourism regulations for key sites; and (xiv) review the effectiveness of eco-tourism initiatives. Outputs to be produced In collaboration with the national communities specialists the IECS will produce: 1. Training needs report based upon capacity of provincial staff and target audiences. 2. Design of the education programme. 3. Reports on training and awareness workshops and study tours. 4. Report on the education programme and its impact. 5. Review education activities as required by evaluations. 6. Reports on the PLUP process completed in target villages (with INRMS). 7. Produce land and natural resource management maps once the PLUP process is completed. 8. A set of community land and natural resource management regulations (with INRMS), incorporating the incentive scheme. 9. A framework for key species eco-tourism. 10. A set of community eco-tourism regulations. 11. A report on the design and implementation of the incentive scheme system. 12. A methodology to assess community livelihoods in years 3 and 6, to measure progress against baseline levels Qualifications The successful candidate should be have the following attributes: 107 1. Strong technical background in natural resource mamagement, education and communication; 2. Minimum of four years working experience in areas relevant for the project; 3. Demonstrated ability to communicate, and foster cooperation with governmental agencies, NGOs, etc; 4. Extensive experience in Asia, and ideally in Cambodia; 5. Ability to travel and spend extended periods undertaking consultation and fieldwork; 6. Computer literate; and 7. Perfect written and verbal command of English, and ideally good spoken Khmer. NB: Gender and cultural diversity is preferred 5. International Natural Resource Management Specialist (INRMS) Position: International Natural Resource Management Specialist (INRMS) Duty Station: CALM Project Office, Tbeng Meanchey Duration: 12 months. The INRMS will be appointed by WCS. Background The Northern Plains is currently characterized by an ‘open-access’ management system, with no recognized land tenure or title assigned to any parties. Establishing an effective land management, including the natural resources found, is essential if conservation priorities are to be integrated into the landscape and the needs of communities recognized in protected area plans. Under the overall supervision of WCS, the INRMS will be responsible for conducting natural resource management research to inform the progress of activities described in Component 2 of the CALM project document, and the implementation of legal policies. The position is based in the Project Office in Tbeng Meanchey, but part of the time will be spent in Phnom Penh and other provinces where CALM has activities. Duties and Responsibilities In collaboration with the national communities specialists, the INRMS will: (i) conduct a training needs assessment for national communities facilitators and local communities on PLUP and NRM; (ii) organize training and awareness workshops based upon these recommendations, with the assistance of the International Communities/Education Specialist (ICES) if required; (iii) assist the ICES to work with local communities to establish land-use plans for each target 108 village; (iv) advise on the preparation of community regulations for land and natural resource management; (v) facilitate the official recognition of these regulations; (vi) design the incentive scheme (direct payments for conservation); (vii) advise on the implementation the incentive scheme in target villages; (vii) review and audit the incentive scheme; and (viii) initiate natural resource management research as required to inform project decisions. Outputs to be produced In collaboration with the national communities specialists the INRMS will produce: 1. Training needs report based upon capacity of national community specialists and local communities for land and natural resource management. 2. Reports on the PLUP process completed in target villages (with ICES). 3. With the ICES produce land and natural resource management maps once the PLUP process is completed. 4. A set of community land and natural resource management regulations (with ICES). 5. A report on the design and implementation of the incentive scheme system. 6. Natural resource management research reports, as required. Qualifications The successful candidate should be have the following attributes: 1. Strong technical background in natural resource management, facilitating community development and community participation in NRM or conservation (Master’s degree or higher); 2. Minimum of four years working experience in areas relevant for the project: natural resource management, facilitating community development and community participation in NRM or conservation in rural areas; 3. Demonstrated ability to communicate, work in a team, and liaise with governmental agencies, NGOs, etc; 4. Extensive experience in Asia, and ideally in Cambodia; 5. Ability to travel and spend extended periods undertaking consultation and fieldwork. 6. Computer literate; and 7. Perfect written and verbal command of English, and ideally good spoken Khmer. 109 NB: Gender and cultural diversity is preferred 6. International GIS Specialist (IGS) Position: International Monitoring and GIS Specialist (IMGS) Duty Station: CALM Project Office, Tbeng Meanchey Duration: 12 months The IMGS will be appointed by WCS. Background Mapping of protected area zones and management systems, and community land and natural resource management systems, will be key outputs of Components 2 and 3 of CALM. Together with the National GIS Specialist the IMGS will be responsible for providing GIS and mapping support, at the direction of the IPA, ICES and NSMs. The position is based in the Project Office in Tbeng Meanchey. Duties and responsibilities With the National GIS Specialist the IMGS will provide GIS support to the project, in particular: (i) community land-use (PLUP) maps for approval; (ii) protected area maps and zonations; (iii) analysis of land-use patterns and changes; (iv) mapping of key habitat features; (v) analyzing the spatial impact of management decisions and human threats to biodiversity; (vi) supervising the production of accurate remote-sensing maps of the land-use of the Northern Plains in years 1 and 2. Outputs to be produced 1. Community land-use (PLUP) maps 2. Protected Area zonations 3. Supervise a contract in Years 1 and 2 to produce an accurate land-use map of the Northern Plains’ key sites, derived from remote sensing data. 4. Detailed maps for each key site, giving land-use, wildlife habitat features and their distribution, and management systems. 5. Supervise a contract in Years 1 and 2 to produce data management systems for key sites in the Northern Plains. The systems should include monitoring and reporting on enforcement activities (with the IPA). Qualifications The successful candidate should be have the following attributes: 110 1. Strong technical background in research, statistical analysis and GIS; 2. Minimum of four years working experience in areas relevant for the project: ecological research and GIS; 3. Demonstrated ability to communicate, work in a team, and liaise with governmental agencies, NGOs, etc; 4. Extensive experience in Asia, and ideally in Cambodia; 5. Ability to travel and spend extended periods undertaking consultation and fieldwork. 6. Computer literate; and 7. Perfect written and verbal command of English, and ideally good spoken Khmer. 7. National Site Managers (NSMs) Position: National Site Managers (NSMs) (2 positions) Duty Station: CALM Project Office, Tbeng Meanchey Duration: 7 Years The NSMs will be appointed by WCS. Background Under the overall supervision of the WCS Cambodia Director, and in close consultation with the IPA the NSMs are responsible for day-to-day management, coordination and supervision of the implementation of project activities. The positions are based in the Project Office in Tbeng Meanchey, but part of the time will be spent in other provinces where CALM has activities. Duties and Responsibilities The NSMs will: (i) Coordinate and supervise all project activities and ensure that activities are in accordance with the project document; (ii) Respond to queries raised by UNDP Cambodia, WCS Cambodia, the Project Steering Committee, the IPA and ICES; (iii) Prepare and update quarterly and annual work plans and review the budget accordingly through a participatory process, and in close collaboration with the Project Office, WCS and International Advisors; (iv) With the IPA identify and recruit the project staff in close consultation; (v) Liaise with the relevant ministries, national and international research institutes, NGOs, Seila/PLG and other relevant institutions in order to involve their staff and coordinate their efforts in project activities. Cooperation and coordination with relevant provincial government agencies will be particularly crucial in regard to law enforcement within the core areas; (vi) Coordinate the required reporting duties with the assistance of the National and International Consultants; (vii) Participate in the PEG and SEG 111 meetings; (viii) With the IPA, carry out the functions of GEF Clearing House Mechanism Focal Point; (ix) With the IPA, ensure that the Cambodia GEF Focal Point is kept advised of Project progress;; and (x) Specifically assist the IPA with all activities relating to Component 3 (Strengthening capacity for biodiversity management) of CALM, including establishing appropriate adaptive management and review procedures. Outputs to be produced 1. A successful implementation of the project's activities, including the activities subcontracted by the project at project sites; 2. Reviewed work plans and budget through a participatory process involving the IPA, the Project Office, WCS and the Government agencies; 3. Quarterly progress reports, annual progress report, and final report in collaboration with the IPA; 4. Communicate effectively with all levels of government to ensure the integration of project activities and outputs into planning processes and national initiatives (e.g. land management). In particular through the PEG and SEG, and other relevant committees, facilitate the recognition of project outputs at higher government levels. 5. Together with the National and International Consultants ensure the completion of the following report-based deliverables to a sufficient level of rigour: site management plans; training needs assessment report for law enforcement officers, education staff; biodiversity monitoring reports; annual reports on output indicators and conservation impact indicators. 6. Review, edit and disseminate the reports to relevant government, NGO and UN bodies, and foster cooperation with them regarding implementation of the different strategies. Qualifications 1. Advanced degree (Master’s or higher) in the area relevant to protected area management, biodiversity conservation and monitoring; 2. Good knowledge of the nature of biodiversity; 3. Minimum two years working experience as a Project Manager and a demonstrated ability in managing donor-funded projects, especially UNDP projects; 4. Minimum of five years of working experience in the area relevant to the project; protected area management, biodiversity conservation; 5. Demonstrated ability in liaison and fostering cooperation between agencies, including governmental, academic, NGOs, etc.; 112 6. Computer literate; and 7. Perfect written and verbal command of English. 8. National Administration Director (NAD) Position: National Administration Director (NAD) Duty Station: WCS Office, Phnom Penh Duration: 7 years. The NAD will be appointed by WCS., Background The project will require a strong administration office to manage the various needs of project components and site managers, and to organize effective reporting to GEF on activities and expenditure. Under the supervision of the IPA, the NAD will be responsible for establishing and maintaining an administration system, ensuring that activity reports are completed and reporting to GEF on activities and expenditure. Outputs to be produced 1. Project administration policy manual 2. Project financial system 3. Quarterly, annual and final financial reports 4. Organise activity reports. Qualifications 1. Degree in business or financial management 2. Minimum five years experience in financial administration of large projects, ideally for UN or UN agencies. 3. Demonstrated ability in liaison and fostering cooperation between agencies, including governmental, academic, NGOs, etc.; 4. Computer literate; and 5. Perfect written and verbal command of English. NB: Gender diversity is preferred 113 PART III: Stakeholder Involvement Plan Stakeholder consultations and participation plan Stakeholder Consultations during PDF-B Date Purpose Key Stakeholders Key findings and Conclusions 2 January 2004 Brief on the progress of the PDF-B project GEF Government Operational Focal Point - Director General of MoE UNDP and WCS representatives 2 January 2004 Review project stakeholder meetings and discuss project progress Deputy Resident Representative of UNDP Cambodia UNDP and WCS representatives 18 December 2003 Brief on the progress of the PDF-B project Project Advisory Committee - MAFF, MoE, DNCP, FA, Provincial authorities and departments - His Excellency was pleased with the activities of the CALM project and the efforts made to consult stakeholders within Government and local communities. - Need for clear modality arrangements for the project’s implementation, especially in regard to the Kulen Promtep Wildlife Sanctuary. - Agreed to new endorsement letter for CALM project. - The project PDF-B phase has achieved all major objectives. - Preparation of Project Document is progressing well and feedback from Government agencies has been positive and productive. - Importance of co-financing for full CALM project, and the potential role of Seila/PLG programme (also funded by UNDP). Agreed that Seila/PLG should be included as a crucial cofinancing partner. - See Appendix 1. - Appreciated the progress of the project development phase - Understood the threats and the proposed interventions in the logframe - Suggested to have individual institutional consultations with MAFF, MoE and provincial authorities over the draft logframe, then followed by a national workshop - Suggested that the logframe should strongly address the supports in infrastructure development, capacity building, community forestry and livelihood development, boundary demarcation, wildlife trade control and resettlement and immigration control. (See attached minutes). - Save Cambodia’s Wildlife have developed a curriculum and trained non-formal teachers in the Northern Plains provinces, and would be able to do so again - Mlup Baitong have a radio unit that is planning to visit Preah Vihear to produce programs with the local radio station - Mlup Baitong have some experience of training military personnel in environmental education - Handicap International will be withdrawing in November 2003, but Seila/PLG will continue to support LUPU - LUPU have an annual provincial planning process that determines priorities for demining and subsequent land-use options. There are 7 trained staff in each province. - The procedures for facilitating LUPU to visit new areas (within key sites) that are mined were discussed. - LUPU will also be working with Austcare and World Vision in other districts in the Northern Plains - Seila/PLG provided information about the provincial planning process and copies of commune development plans for 2003 Seek initial comments on the logframe 27 participants 28 and 29 November 2003 Investigate options for cooperating on environmental education projects 21 October and 19 November 2003 Explain CALM project, learn about LUPU in the Northern Plains 23 October and 22 Explain CALM Save Cambodia’s Wildlife Mlup Baitong WCS technical staff 5 participants Handicap International staff LUPU provincial staff WCS project staff 5 participants Seila/PLG staff WCS technical 114 Date Purpose Key Stakeholders Key findings and Conclusions November 2003 project, learn about Seila/PLG in Northern Plains and discuss future cooperation Discuss PLUP and holding a training workshop in Preah Vihear Discuss the importance of learning from PLUP/NREM in Ratanakiri Discuss cooperation on activities to improve livelihoods of communities around key sites and project management staff (MAFF) - WCS project staff were invited to provincial meetings, scheduled for December 2003 - Seila/PLG were invited to attend PLUP training course in January 2004 to learn about the land law and PLUP process - Arrangements to incorporate project plans into the Seila/PLG process was discussed Produce problem and threat analysis for the Northern Plains and proposed interventions Discussion on integration and cooperation between the provincial departments of environment WCS/MAFF/MoE project staff and Provincial technical staff 11 participants Discussion with Colonel Ghnem Sok Heng on border wildlife trade Participatory problems analysis and consultations with 8 WCS/MAFF project staff and technical advisors Colonel Ghnem Sok Heng 6 participants WCS/MAFF/MOE project staff, technical advisors and communities More than 600 8 October 2003 Subsequent meetings October December 2003 29 September - 10 October 2003 11-14 May 2003 March 2003 January June 2003 5 participants PLUP focal point MLMUPC LMAP 10 participants Action Against Hunger WCS Staff 5 participants Directors of the Provincial Departments of the three provinces and WCS staff 6 participants - Enthusiastic about assisting with the implementation of the new land law in the Northern Plains - Agreed to support a training workshop in Preah Vihear for 1931 January 2004 - Training workshop will include a description of the new Land Law by a legal expert from MLMUPC - Kim Sovann from Ratanakiri will attend the training to provide advice on land-use planning in forested areas. - AAH is interested to continue work on improving village food security in districts containing key sites for conservation. - AAH has funding for continuing village garden scheme and animal health workers - WCS is able to provide technical veterinary support to assist with the identification and treatment schedules for domestic cattle - Joint proposals written and submitted to obtain funding for a 3year project - Key species and key sites identified - Draft threats and problems analysis was completed (see Annex 3) - Interventions for different threats proposed and discussed - Sharing information about illegal activities related to logging and wildlife trade - Cooperation was sought on law enforcement - Assessed basic needs of the provincial environmental departments in assisting the management of Kulen Promtep Wildlife Sanctuary. - Assessed key stakeholders in the three provinces and threats to the wildlife sanctuary - Colonel Ghnem Sok Heng agreed that reduction of border wildlife trade was necessary and gave his support - Participatory maps were drawn of resource use areas - Discussions on environmental and natural resource management problems and threats. Prioritization. - Recommendations produced for future natural resource management by communities. 115 Date January 2003 and 8 - 11 April 2003 December 2002 and 12-15 March 2003 Purpose Key Stakeholders Key findings and Conclusions communities Capacity assessment of provincial department of forestry, and consultations on training needs. participants Provincial department of forestry, Preah Vihear, staff WCS/MAFF project staff and technical advisor Capacity assessment of provincial department of environment, and consultations on training needs. Provincial department of environment, Preah Vihear, staff WCS/MoE project staff and technical advisor - Assessment of village livelihoods. - See Appendix 2. - DAFF have 70 staff, but few with a high level of education or formal training - Equipment, infrastructure are insufficient for management needs - A training course was requested, and provided by WCS trainers from 8-11 April 2003. - Opportunities for building capacity during the full project were discussed. - See Appendix 3. - PDoE have 17 staff and 25 rangers in Kulen Promtep Wildlife Sanctuary - Few staff are educated or have received any training - Equipment, infrastructure are insufficient for management needs - Seila/PLG have provided funds to PDoE to undertake activities, however it is unclear if PDoE has the capacity to achieve these activities - PDoE has particular problems prosecuting the perpetrators of illegal activities in wildlife sanctuaries, due to problems completing official documentation - A training course was requested, and provided by WCS trainers from 12-15 March 2003, in collaboration with the Seila/PLG funded training course for Kulen Promtep Wildlife Sanctuary rangers - Opportunities for building capacity during the full project were discussed. Local Consultations In each village (except for those around Phnom Tbeng) PRA techniques were used to: Map village resource use areas Discuss trends in wildlife populations and the causes of any changes Discuss livelihood problems relating to environmental problems experienced by communities, and prioritise them. Meetings included group discussions with up to 100 people (in one village including representatives of all families), smaller group consultations with village elders and commune officials, and key informant interviews with school teachers and village workers. Preah Vihear Protected Forest and O’Scach Key Sites. Project staff visited all 4 Communes directly surrounding the area, or 7 of 10 villages. 2 further communes (5 villages) at a greater distance but known to use forest in the O’Scach area were also visited. Kulen Promtep Wildlife Sanctuary. Detailed consultations were undertaken in all 4 villages in, or nearby, to key sites. 116 Phnom Tbeng. Project Staff visited most villages surrounding the hill and had discussions with village representatives. In addition, a socio-economic assessment of local livelihoods was undertaken in 7 off the villages surrounding the protected forest and 2 off the villages in the wildlife sanctuary. Further, the project interacted strongly with a development NGO (Action Against Hunger) who had 10 years experience working in the area. AAH had conducted their own livelihood consultations with the same villages. The projects were able to share results, conclusions and recommendations. AAH has supported the project approach and has suggested collaboration over future activities, so that short-term improvements in food security by AAH might contribute to longer-term activities by CALM. This proposal is currently awaiting approval. Stakeholder Participation Plan Stakeholder Mandate Role in Project Interest in the Project WCS International Conservation NGO. Works under MoUs signed in 1999 with MAFF and MoE Government Ministry responsible for Agriculture, Forestry and Fisheries Executing Agency and project initiator WCS will provide technical and financial assistance to CALM. Member of project steering committee. WCS first worked in the Northern Plains in the 1950s and returned in 2000-2003, investing $300,000 in the area. WCS has been responsible for development of the CALM project. Implementing Agency. MAFF will provide the management and staff for 3 of the key sites. Chairs project steering committee. MAFF will be involved in resolving land conflicts between communities, logging concessions and the provincial departments Government Ministry responsible for management of protected areas Government Ministry responsible for land management and administration Implementing Agency MoE will provide the management and staff for 1 key site. Member of project steering committee. MAFF has had a long interest in the Northern Plains, including the Community Tiger Project since 1998 and proposing the sub-decree that led to the establishment of the Preah Vihear Protected Forest. The new forestry law and wildlife sub-decrees provide the ministry with the necessary legal framework to manage forest areas and protect wildlife. MoE manages Kulen Promtep Wildlife Sanctuary, which has been selected as one of the key sites for conservation MLMUPC, through LMAP and the PLUP focal point, has shown interest in implementing the new land law and procedures in the Northern Plains. Ministry staff have been involved in training The cadastral commission is located in the provincial department and will be responsible for resolving land disputes MAFF MoE, DNCP MLMUPC and Provincial departments Provide official support to the PLUP facilitators during land-use planning and demarcation. Resolve disputes over land. 117 Potential Conflicts MoE will be involved in negotiating land conflicts with communities inside the wildlife sanctuary Stakeholder Mandate MRD Government Ministry responsible for rural development. Provincial Government Responsible for administration and management of province. Seila/PLGUNDP Provides technical and financial assistance to provincial and commune planning process and line ministry activities. Manages forestry and fishery resources at the provincial level. Provincial Department of Agriculture, Forestry and Fisheries Provincial Department of Environment. Responsible for environmental issues at the provincial Role in Project Interest in the Project Responsible for maintaining database of registered land. Member of project steering committee. Collaboration on activities to improve food security in Member of project steering committee. CALM project staff and opened the awareness course in Preah Vihear. Key role in integrated conservation values into provincial planning, approving community management plans and facilitating establishment of law enforcement teams. Provincial government support for activities is essential. Member of project steering committee. Key role in incorporating natural resource management into community development plans, and integrating these at provincial level. The Provincial Governor has attended in several project activities, including training courses, and is known to have a strong interest in wildlife. The first deputy Governor issued a ban on hunting in support of WCS. Management of forested areas, including key sites, and enforcement of wildlife laws. Capacity building of provincial staff will be necessary if project activities are to be sustainable. CALM has worked in close collaboration with DAFF during the PDF-B phase. Three DAFF staff have been employed by CALM and have participated in most provincial activities. DAFF has frequently requested assistance, particularly in controlling border wildlife trade. CALM has worked in close collaboration with DoE during the PDF-B phase. Two provincial counterparts have been employed and they have Actively works with other NGOs on development work in the Northern Plains. Management and patrolling of Kulen Promtep Wildlife Sanctuary. Capacity building of 118 Potential Conflicts The incentive scheme (Component 2) requires that rewards are provided to communities based upon improved management practices, this may conflict with development needs. Occasions may arise where the provincial government must chose between conservation needs and development goals. The Seila/PLG project advisor in the province has demonstrated considerable interest in the CALM project, and is enthusiastic about integrating outputs at commune and provincial levels. DAFF will also be involved in the regulation of forest concessionaires. Stakeholder Mandate Role in Project Interest in the Project level and management of protected areas. provincial staff will be necessary if project activities are to be sustainable. Royal Cambodian Armed Forces and Police forces Responsible for maintenance of defense and security. Involvement in law enforcement activities. The cooperation of military and police commanders around key conservation sites will be crucial if illegal activities are to be controlled. participated in all project activities inside the wildlife sanctuary. WCS supported a training course for wildlife sanctuary rangers, and DoE has frequently asked for further assistance. The Provincial Police Department has shown considerable interest in CALM, and its staff have frequently cooperated with the project. WCS has had consultations with some military commanders, who have indicated their support for reduction in wildlife trade. WCS also has good links with the regional commander in Siem Reap. The provincial governor is also a military general. Communities in Chhep, Chaom Ksan and Kulen Districts Commune councils are responsible for writing management plans and regulating community areas. CALM will encourage and facilitate communities around key sites to complete land-use maps for approval and develop management plans. Incentive schemes will provide rewards in return for improved management and reduction in illegal activities. Communities will benefit from ecotourism projects initiated in their areas. WCS has established close links with at least 5 communities during the PDFB, and employs rangers in these villages. Village consultations during PDF-B established the problems and threats local people face, both to livelihoods and specifically to natural resources. Villages indicated their enthusiasm to be involved in the project, especially for assistance with improving livelihoods and education. Villages will encounter conflicts with livelihoods, although it is hoped that the incentives scheme will mitigate this. Land Use Planning Unit LUPU is a multidepartment provincial body that identifies priority areas for demining and determines subsequent land-use. Two key sites contain mines and CALM will work with LUPU to determine when demining will occur and how the land will be used afterwards. Preah Vihear LUPU were interested in visiting project sites known to contain mines to discuss with communities for their removal. Land allocation conflicts between conservation and communities may arise, however these should be covered by existing community agreements. 119 Potential Conflicts Conflicts may arise if components of the military continue logging and hunting activities. Stakeholder Mandate Role in Project Interest in the Project ITTO Transboundary project ITTO-funded project for conservation of Phatam, Thailand, and transboundary cooperation The ITTO project has established a consultation framework that could be used by CALM to address border issues. WCS has held consultations with Thai and Cambodian project members, and with the Thai border police, all of whom are interested in stopping wildlife trade. The Cambodian project member is provincial DAFF. Chendar Plywood Forest Concession Responsible for management of the forest concession The forest concession lies on the border with the Preah Vihear Protected Forest, and partly overlaps with the O’Skach key site. Action Against Hunger International Development NGO, working in Preah Vihear since 2000 Joint proposals with WCS for improvements in food security in villages surrounding key sites. The head of the logging company has indicated his support for biodiversity conservation efforts and has facilitated project staff working within the concession. Has consistently provided provincial level support for WCS in developing the project plan. Staff have collaborated on animal health issues, and on the writing of proposals for joint activities. 120 Potential Conflicts If the concessionaire follows its management plans and environmental impact assessment no problems should occur. Appendix 1. Project Advisory Committee: Establishing CALM in the Northern Plains of Cambodia Ministry of Agriculture, Forestry and Fisheries (MAFF) 18th Dec 2003 Background On 18 December 2003 at 200pm, a presentation and discussion on the CALM project was held. The meeting was led by H.E Uk Sokhunn, Under Secretary of MAFF, the National Project Director. The meeting served as both a project advisory session as well as an opportunity for additional stakeholders to view, and comment on, the draft plans for the full project. List of participants Ministry of Agriculture, Forestry and Fisheries (MAFF) H.E Uk Sokhunn Under Secretary of State for MAFF and the National Project Director Ministry of Environment (MoE) Mr. Chay Sameth Director, Department of Nature Conservation and Protection (DNCP) Forestry Administration Mr. Ong Sam Art Deputy Director, Forestry Administration Mr. Men Phymean Director, Wildlife Protection Office (WPO) Mr. Lic Vuthy Deputy, Forest and Wildlife Research Institute (FWRI) United Nations Development Program (UNDP) Mr. Lay Khim Department of Environment Preah Vihear (DoE PVH) Mr. Khoy Khunchanrath Director, Provincial Department of Environment Preah Vihear Provincial Authorities Mr. Long Sovann Deputy Governor Preah Vihear Mr. Yem Chan Deputy Director Department of Agriculture in Preah Vihear Mr. Lim Mao Director Forestry office in Preah Vihear Military Soldier No. 122 Soldier No. 4 CALM Project Mr. Tan Setha, Project Coordinator (CALM) and DFRI/MAFF Mr. Kong Kim Sreng, Component Manager, DNCP/MoE Wildlife Conservation Society (WCS) Mr. Joe Walston, Acting Director, WCS Cambodia 121 Mr. Tom Clements, Technical Advisor, CALM Presentations H.E Uk Sokhunn - welcomed all the stakeholders present from MAFF, MoE, WCS, Preah Vihear authorities, UNDP representative and other institution involved in the CALM project. Mr. Tan Setha - presentation on the CALM Project in Preah Vihear Province. The CALM Project employs 26 people. In Preah Vihear Protected Forest: 11 people, 3 from Forestry Administration, 1 from Preah Vihear and 7 Rangers. In Kulen Promtep Wildlife Sanctuary: 15 people, 5 from MoE and 10 Rangers. The main activities during the year: wildlife research in conservation areas - all WCS staff and rangers; to identify the populations of keys species of wildlife such as G. Ibis, W.Ibis, W.W. Duck, S. Crane and mammals, such as Eld’s Deer, Gaur, Banteng and Elephant; Progress has also been made on piloting conservation interventions and with developing strong relationships with communities and other stakeholders. Mr. Kong Kim Sreng - presentation on survey and conservation activities in Kulen Promtep Wildlife Sanctuary. Comments from Participants H.E Uk Sokhunn stated that: He supports the project activities, and is pleased with the skill of the staff. He would like to see even more qualified and intelligent people to come and work on the project. More research should be done in Northern Plain areas not only on wildlife, because for the future these areas will become a potential place for eco-tourism. H.E compared these areas to other developing countries that have built viewing towers in protected areas for looking at wildlife. Infrastructure should be provided for staff and communities working in these areas. Training courses for project staff in communities for appropriates. Do more law enforcements on wildlife trade and other illegal activities. Mr. Chay Samith: He welcomes the work CALM has been doing with MoE and DoE. He would welcome information about the present project infrastructure. The project will need more infrastructure: station, equipment (for office supplements, motorbike, boat…) if it is to be effective. He requests that the project work very closely with communities. He welcomes WCS’s technical support Requests that the project prepares good documents before the next meeting. He asked for the national seminar to be held on 29 Dec, 03. Mr. Khoy Khunchanrath DoE, PVH He welcomes the work that CALM has been doing in Preah Vihear with MoE and DoE. The main objective of the project in Kulen Promtep Wildlife Sanctuary should be community management and education awareness. 122 He asks the project works with and trains MoE rangers, to contribute to the sustainability of activities. He requests to close the Chendar Playwood concession company because this place is the crossing point between Prey Preahroka and Prey Saak for animal migration. Kulen Promtep Wildlife Sanctuary needs large improvements in infrastructure. Soldier No. 122: Live inside the wildlife sanctuary. He requests that they be moved, because they always disturb the wildlife. Further, the government provides only rice to the soldiers, so they are reliant on the forest (especially wildlife) for food and trade. Soldier No. 4: Based on the border with Thailand, near Trapangprasat. They are currently making new settlements within the wildlife sanctuary in areas that have good hard woods like: Beng tree, Nieng Nourn tree… Additonally they are hunting the wildlife. It is possible to discuss problems with the Soldier of No. 122, but it is very difficult to talk to Soldier No. 4. Mr. Long Sovann, Deputy Governor, PVH He welcomes the project’s activities in Preah Vihear He would like the project to help local people create community forests, and provide incentives. He would like the project to provide an education awareness component and especially targeted at the local community, e.g. by using video show about the importance of wildlife and forest for livelihoods and national pride. Mr.Ong Sam Art: Deputy director Forestry Administration. He supports the project activities, but commented that the logframe format was difficult to understand. Mr.Men Phymean, Director of Wildlife Protection Office. Although the PDF-B has completed lots of wildlife research, it is necessary to also look at the forest and plants. Should place controls on the border with Thailand between Sesaket and Uboun province, the principal points for wildlife and orchid trade. Mr.Lic Vuthy, Deputy of Forest and Wildlife Research Institute. Stated that there are many wildlife-protection areas along the border to stop wildlife hunting and illegal logging, but outsiders still cause problems. Mr.Yem Chan, Deputy director Department of Agriculture in PVH. Should continue conservation activities. CALM should link with local communities because they are reliant on natural resources. Should continue efforts to protect forested areas. However strong law enforcement activities may have negative impacts for the local community. Mr.Lim Mao, Director Forestry office in PVH. Welcomes CALM project activities in Preah Vihear over the past year. 123 He mentions that the population of wildlife has increased following the cessation of logging in the Chendar Plywood concession. Wildlife research should include important areas for migration. At the end of the meeting H.E Uk Sokhunn stated that in the future the project should. Report should more clearly. Inform about the meeting more than one week before, and attach all relevant documents Work harder to achieve lasting results The meeting finished at 18:00pm at the same day, all agreed to meet again separately to discuss their comment with WCS before the national workshop. Appendix 2. Consultations and Capacity Assessment of Provincial Department of Agriculture, Forestry and Fisheries, Preah Vihear Province By Tan Setha, MAFF. 1. Structure of DAFF and Provincial Forestry Office DAFF in total have 70 people working in the whole of Preah Vihear Province, composed of: - 65 men - 5 women Education: - 2 Master degrees - 12 Bachelor degrees - 6 Diploma level II - 4 Under diploma level II - 46 Non graduate Transportation and Equipment: - 1 Car - 4 Motorcycle - 1 Computer DAFF is currently working with the following NGOs: - Rural Aid Development (RAD) - Action Against Hunger (AAH) - Seila/PLG program Director of Department of Agriculture, Forestry and Fisheries. 124 DAFF is divided into 7 Offices: Administration Office (Ad.O), Forestry Office (F.O), Agriculture Office (A.O), Fishery Office (Fis.O), Veterinary Office (V.O), Planning Office (P.O), Accounting Office (Ac.O). The Forestry Office is divided into 5 district offices with a total of 16 staff: Tbengmeanchey Forestry Office, Rovieng District Forestry Office, Chamkhsan District Forestry Office, Kulen and Sangkomthmey District Office, Chhep and Cheysen District Office. Director of Preah Vihear Forestry Office Ad.O - Administration office, P.O -Planning office, FM.O - Forest management office, Af.O Afforestation office, L.O. - Legislation office and WP.O - Wildlife protection office. 2. DAFF Activities - Working with NGOs on agriculture education programs to help local people improve vegetable growing. Working with NGOs to build roads, schools and wells. Seila/PLG program has provided assistance to: - Establish a community forestry area - Provide training on the new Forestry Law 125 - Establish a tree nursery - Create fish ponds - Establish an agronomy research station, with additional support from AusAid. 3. Problems faced by DAFF - Insufficient human resources Lack of infrastructure and equipment, including vehicles and radios Poor quality roads make transportation difficult Problems with drought Considerable forest clearance by people 4. Recommendations - Require office in the province and district buildings Provide training to provincial staff Require additional staff that have experience in other regions 5. Phnom Tbeng The Provincial forestry office has proposed to the Ministry that Phnom Tbeng should be removed from the TPP forest concession. Phnom Tbeng is a large (500 metres above sea-level) hill above the provincial town. Logging and land clearance around the base and slopes of the hill is frequent, and if continued might cause erosion. 126 Appendix 3. Consultations and Capacity Assessment of Provincial Department of Environment and Kulen Promtep Wildlife Sanctuary, Preah Vihear Province By Kong Kim Sreng, MoE I. Department of Environment of Preah Vihear. 1. PDoE Responsibilities The Provincial Department of the Environment (PDoE) is responsible for pollution, waste management, natural resources management and the protected areas including Kulen Promtep Wildlife Sanctuary, Beng Per Wildlife Sanctuary and Preah Vihear temple. 2. PDoE Structure PDoE in total have 17 people working in the whole of Preah Vihear Province, composed of: - 15 men - 2 women Education: - 1 Diploma level I - 2 Graduate from High school - 13 Non-graduates All staff were recently nominated from other institutions when PDoE started in the province. 127 Mr. Khoy Khun Chan Rath Director of Department of Environment Acting director of Kulen Promtep WS Mr. Pheung Phang Sub director. -Responsible for PVH temple landscape protected area. Wildlife conservation and environment data management office. - Meung Sam Phon (SD). - Pen Yaok (SD), and also sub director of Beng Per. Mr. Oum Soborin, Sub director - Working with Seila/PLG project Administration office. - Tlang Kim Sy (D). - Chan Bun tha (SD). - 2 staffs Environment Impact Assessment office - Yem Montha (SD). Sang Kum Thmey district. -Mr. Saom Kim Orn (D). Kulen district. -Mr. Hong Hoeung (D). Pollution Monitoring and Education office. - Kong Sambat (D) Roveang district. - Dourng Sunly (D). Cham Ksan district. -Mr. Chum Marong (D). - One staff. Cheb district. -Mr. Reth Leng (D). *Remark: (D)= Director; (SD)= Sub director. PDoE have 2 buildings - one is made of brick and other one is wood. Both are located in Tbeng Meanchey town, where there is a generator. The department has no cars or motorbikes, no fax machine and no telephone. They do have a single computer and 5 radio sets that are used in Tbeng Meanchey, the Wildlife Sanctuaries and Preah Vihear Temple. PDoE is currently working the Seila/PLG program and with LUPU. One staff from the department works with each. 3. Seila/PLG Program 128 In 2003, Seila/PLG approved $14,200 for PDoE, to fund 5 activities, mostly inside the Wildlife Sanctuaries 1. Training course about Protected Area Management for 25 rangers. 2. Education awareness and Understanding about Environment. Includes a training course for 30 staff for 14 days, a training course for 147 members of commune councils, environmental awareness courses for 59 villages. 3. Produce a reservoir for water. 4. Support Eco-tourism and natural resource community management, through data collection, capacity-building to the community, community management, boundary demarcation and project assessment. 5. Operational Support to PDoE. 4. Workplan The PDoE workplan for 2003 aims to: 1. Establish natural resource management in one community in Kulen Promtep wildlife sanctuary. 2. Continue patrolling to control illegal activities in protected areas. 3. Short training course for staff about the environment 4. Short training course for the rangers of Kulen Prumtep wildlife sanctuary. 5. Education awareness program for the villages and communes inside and along the border of the protected areas. 5. Problems faced by PDoE - Lack of human resources and education Lack of training courses Insufficient funding, vehicles and equipment for activities Problems with military and land mines in protected areas Land clearances 6. Recommendations - Require increased national government support Training courses from MoE regarding ministry procedures and enforcement Training courses on management and ranger patrolling Funding for building ranger stations in wildlife sanctuaries Equipment, vehicles and communications devices New, experienced staff to assist with provincial work Require technical advice in order to assist communities with natural resource management 129 II. Kulen Promtep wildlife sanctuary Kulen Prumtep Wildlife Sanctuary is located in three provinces, Preah Vihear, Siem Reap and Odor Meanchey. It currently has no overall director, with each provincial department taking responsibility for their section. The Wildlife Sanctuary contains a total of has eight communes, 35 villages, 3626 houses, 4496 families and 22070 people. Five ranger stations exist within the wildlife sanctuary: 1 Tukhung 2 Yearng 3 Kantourt 4 Krolar Pears 5 Poure UTM: 0481541E, 1532640N. UTM: 0465000E, 1554800N. UTM: 0460200E, 1570200N. UTM: 0498000E, 1545000N. UTM: 0502064E, 1531936N. There are 25 rangers working in the wildlife sanctuary, recruited from villages inside. They have never been trained. Rangers usually patrol one or sometimes two weeks per month, mainly during the dry season when more people are doing illegal activities. They work without using GPS, map or compass but know about their local area. The salary range is 42,500 - 152,000 riel. Their targets are to reduce illegal activities such as hunting, forest clearance, electric fishing or poison fishing. No formal workplan or management plan exists. However, in 2003 PDoE plans to create two more ranger stations: 1 Kulen either at: a Koh Ke b Prey Veng 2 Anteul UTM: 0450200E, 1524200N or UTM: 0451800E, 1539700N. UTM: 0455500E, 1558500N. Particular threats include: - The soldier base near Tukhung station - Wildlife hunting, electro fishing, logging and forest clearance - The road from Thbeng Meanchey to Preah Vihear temple was recently constructed through the wildlife sanctuary, so the land along the road will be the target for encroachment. 130 SIGNATURE PAGE Country: _Cambodia UNDAF Outcome(s)/Indicator(s): Increased and equitable access to and utilization of land, natural resources, markets and related services to enhance livelihoods. UNDAF outputs: Enhanced management capacity of government and empowerment of local communities in sustainable use of natural resources and in environmental protection. Expected Outcome(s)/Indicator (s): Conservation and sustainable use of biodiversity (MYFF,SL3.5) Expected Output(s)/Indicator(s):The Effective Conservation of Key Components of Cambodia’s Northern Plains Landscape Implementing partner: Wildlife Conservation Society Other Partners: The Ministry of Agriculture, Forestry and Fisheries, Ministry of Environment and Provincial Authority of Preh Vihear Province Total budget: $4,468,617 General Management Support Fee: Grant total budget: Allocated resources: Government Regular : Other: GEF: $2,300,000 - WCS: $1,600,000 - UNDP/Seila/PLG: $463,407 In kind contributions (government): $105,210 Programme Period:2006-2020 Project Title: : Establishing Conservation Areas Landscape Management (CALM) in the Northern Plains Project ID: PIMS 2177 Project Duration: 7 years Management Arrangement: NGO Execution Agreed by (Government): _______________________________________________________ (H.E. Mr. Keat Chhon, Senior Minister, Minister of Economy and Finance) Agreed by (Implementing partner/Executing agency):________________________________ (Mr. Joe Walston, WCS Country Program Director) Agreed by (UNDP):______________________________________________________________ (Mr. Douglas Gardner, Resident Representative) 131