INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5310 Date ISDS Prepared/Updated: 10/12/2010 I. BASIC INFORMATION A. Basic Project Data Country: Vietnam Project ID: P118783 Project Name: Vietnam - Managing Natural Hazards Project Task Team Leader: Cuong Hung Pham Estimated Appraisal Date: October 20, Estimated Board Date: March 12, 2012 2011 Managing Unit: EASVS Lending Instrument: Specific Investment Loan Sector: Flood protection (50%);Sub-national government administration (25%);Public administration- Water, sanitation and flood protection (25%) Theme: Natural disaster management (70%);Municipal governance and institution building (15%);Climate change (15%) IBRD Amount (US$m.): 0.00 IDA Amount (US$m.): 150.00 GEF Amount (US$m.): 0.00 PCF Amount (US$m.): 0.00 Other financing amounts by source: BORROWER/RECIPIENT 0.00 0.00 B. Project Objectives [from section 2 of PCN] The overarching objective of the proposed project is to strengthen national, provincial, and local capacities for natural disaster prevention, preparedness, and mitigation. This objective would be achieved through the following; # Strengthening the capacities of national, provincial and local disaster risk management entities to better plan and mitigate against hazard risks, thereby reducing losses of life, damage to property, and interruptions of economic activities. # Improving weather forecasting and early warning systems to more effectively collect, process, and disseminate information to enable various stakeholders to undertake more timely and effective actions to mitigate against disaster risks and respond to weather events more generally; and # Putting in place effective structural measures to reduce typhoon and storm risks in high priority areas. This would be achieved through medium to large scale infrastructure investments carried out by ministries and provinces, and small scale interventions identified and carried out by vulnerable communities. C. Project Description [from section 3 of PCN] Proposed project components, with an estimated total cost of US$150 million, are as follows: Component 1: Institutional Strengthening (US$7 million). This component would strengthen institutional capacities for DRM planning at national and provincial levels. It would help prepare a national DRM database to track the progress of actions taken, strengthen the capacity of the newly formed National DMC, improve/extend provincial level integrated disaster risk management planning, support provincial disaster mapping and zoning, support dam safety database management, support further work on disaster-resilient building code design (based on different geographical regions); and strengthen disaster management communications. Component 2: Strengthening Weather Forecasting and Early Warning Systems (US$30 million). This component would improve national, regional and provincial capacities for weather and disaster forecasting and early warning systems through the provision of modern hydrometeorological observation equipment and communication facilities, development of improved databases, strengthening of systems for the dissemination of forecasts and early warnings to different stakeholders, and the strengthening of human resources in pertinent agencies. Improvements in these systems would be leveraged to also include improved weather forecasting services/products for agricultural, tourism, construction and other industry purposes. Further applications of historical and up to date weather data for insurance purposes would possibly be supported. Component 3: Community-Based Disaster Risk Management (US$20 million). This component would support a significant scaling up of the Government#s CBDRM program, initiated under the NRDMP-I. Provincial level DRM centers would be established (or strengthened where already exist) and would provide support for district- and commune-level DRM activities, including planning and mitigation strategy development. Support would be provided for DRM training at community levels as well as for small-scale priority investments, especially for flood and drought mitigation. It is expected that some 10 provinces and about 100 communes would be supported under this component. Co-financing would be sought. Component 4: Support for Priority Disaster Risk Mitigation Investments (US$90 million). This component would support the Government in implementing significant structural measures proposed in the Implementation plan of the National Strategy for natural Disaster Prevention, Response, and Mitigation to 2020. A river basin approach shall be used to identify and prioritize investment subprojects within the selected basins in the Central Region. The structural measures will mitigate risks posed by floods, landslides, and major storms. Due to especially challenging safeguards considerations, no construction of new reservoirs would be eligible for financing under this component. However, the rehabilitation of selected dams to improve their safety would be eligible. Component 5: Project management (US$3 million). This component would provide support for project management activities including preparation, implementation and monitoring of social and environmental safeguard policies, fiduciary and financial management, etc. It also will support the development of an M&E system for the project. D. Project location (if known) The project area will likely be the provinces in the Central Region of Vietnam. Particular focus will be given to the four major river basins, Vietnam#s most disaster-prone area. These four basins are Ca, Vu Gia-Thu Bon, Tra Khuc-Tra Bong, and Kone, spanning the six (6) provinces of Nghe An, Ha Tinh, Danang, Quang Nam, Quang Ngai and Binh Dinh. An additional four provinces, namely Thanh Hoa, Quang Binh, Quang Tri and Binh Thuan, have also been proposed by MARD to be covered by the project. This issue of additional provinces would be subject to further discussion with the Bank task team. However, the inclusion of new provinces does not affect the requirements regarding the compliance of safeguards policies. E. Borrower’s Institutional Capacity for Safeguard Policies [from PCN] The Borrower possesses some capacity for assessing the project#s environmental and social impacts, and proposing mitigation programs to address potential negative impacts and risks. Such capacity will be further strengthened through capacity building efforts that will be implemented during project the preparation and implementation. F. Environmental and Social Safeguards Specialists Ms Ly Thi Dieu Vu (EASVS) Mr Tuan Anh Le (EASVS) II. SAFEGUARD POLICIES THAT MIGHT APPLY Safeguard Policies Triggered Yes No TBD Environmental Assessment (OP/BP 4.01) X The project area is located in the central coastal region of Vietnam, which is frequently subject to natural disasters such as flood and storms, landslides, erosion etc. These hazards cause losses to human lives and assets. The four rivers systems are mostly short but with high bed slopes. The proposed project applies an integrated river basin approach to mitigate the impacts of natural hazards in these vulnerable areas, and therefore it is expected that the project will bring about net positive environmental impacts. At the project level, an Environmental Management Framework (EMF) will be prepared. The contents of the EMF will include: (i) descriptions of baseline conditions by project river basins or geographical regions as appropriate to provide the basis for identifying the environmental restrictions to be applied to each type of project investment, for the assessment of the natural hazard risks in project area, and for predicting the project#s potential environmental impacts; (ii) identification of policies and any other macro issues which contribute to the underlying issues of natural hazard risks in the project areas using a river basin approach; (iii) standard mitigation measures for the identified impacts; (iv) a framework for EA preparation requirements, review and clearance of future Components 4 sub-projects; and (v) Standard Codes of Practice (COP) for all stages of sub-project preparation and implementation including site selection, design, construction and operation. At the sub-project level under component 4, where structural measures are proposed for Safeguard Policies Triggered Yes No TBD mitigating the risks posed by floods, landslides and major storms, some negative environmental impacts would be predicted for the construction phase. These are: (a) increased dust and noise level during construction phase, (b) reduced water and soil quality due to waste and waste water from construction sites, and workers# camps, (c) disturbance of local traffic and daily life activities of local communities, (d) increased safety risks for local communities at construction sites and materials transportation routes; and (e) impacts on existing infrastructure such as irrigation channels, power lines, telephone lines etc. As the project area experienced extensive bombing during the war a few decades ago, there are potential risks related to unexploded landmines (UXO) during excavation works. Environmental Assessments (EA) to cover both construction and operation phases will be carried out to predict sub-project potential impacts and risks. Corresponding environmental management plans, which include engineering design solutions and plans for implementation of mine clearance by authorized workers before the site is handed over to construction contractor. Construction practices to mitigate potential negative impacts shall be prepared for component 4 sub-projects. In addition, de-mining certificates will be obtained prior to commissioning excavation works in sites with a potential UXO presence. For Component 3, where small-scale investments would be provided for about 100 communes of some ten provinces for commune-level disaster mitigation measures, the potential environmental impacts would be localized, at small scale, temporary, and can be minimized by standard mitigation measures incorporated into sub-project design or practiced during the construction phase. The mitigation measures will be documented in the Project#s EMF. The project EMF, subproject EAs and EMPs prepared for first year investments will be ready and disclosed for public access before project appraisal. Natural Habitats (OP/BP 4.04) X Screening to identify the existence of natural habitats and any critical natural habitats in the proposed project areas will be included as part of the EMF. If there are any natural habitats potentially affected by the proposed project, OP 4.04 will be triggered. Alternative analysis will be considered to avoid potential impacts on natural habitat and if necessary, appropriate mitigation measures and an implementation plan will be developed. Forests (OP/BP 4.36) X If there are any forests potentially affected by the proposed project, OP 4.36 will be triggered. Alternative analysis will be considered to avoid potential impacts on forests and if necessary, appropriate mitigation measures and an implementation plan will be developed. Pest Management (OP 4.09) X There will neither any procurement of pesticides or fertilizers, nor will there be any irrigation works within the project which would lead to the increased use of pesticides and fertilizers. Physical Cultural Resources (OP/BP 4.11) X Screening and assessments of the project#s potential impacts on physical cultural heritage, such as pagodas, temples, churches, graveyards, sacred trees, monuments, historical sites, and archaeological objects etc, will be included as part of the project EMF. OP 4.11 will be triggered if the sub-project EA identifies that the sub-project would affect any areas or sites of physical cultural heritage, and appropriate mitigation measures and implementation arrangements would be developed. Chance find procedures will also be included in the Project EMF and sub-project EMPs. Safeguard Policies Triggered Yes No TBD Indigenous Peoples (OP/BP 4.10) X Because various ethnic minority groups are present in the project areas, a social assessment consistent with the Bank OP 4.10 will be done during the preparation stage to evaluate project#s potential positive and adverse effects on ethnic minority communities. The scope and level of details of the social assessment (SA), taking into account the nature of project, review of ethnic minority issues in the project area, and scale of the proposed project#s potential effects on ethnic minority groups, will be determined after more information become available from the Client regarding the proposed subprojects, detailed project activities and project locations. A consultant will be recruited (with the support from the Bank) to help Client with the SA exercise. The SA report will be disclosed prior to appraisal. An Indigenous Peoples Planning Framework (IPPF) will be prepared by the Borrower in compliance with OP 4.10 and in consultation with ethnic minority communities in the selected project areas. Indigenous Peoples Plans (IPP) will also be developed for subprojects (where determined necessary) to set forth measures for ensuring that ethnic minority people receive social and economic benefits that are culturally appropriate to them, and that an action plan is in place to avoid, minimize, mitigate, or compensate for adverse effects, if any. For all the subprojects that are carried out in the first year and that affect ethnic minority people, IPP will be prepared prior to appraisal. The IPPF will be used to guide the preparation of IPPs and will be disclosed before appraisal. It will also explain why no specific IPP can be prepared. Involuntary Resettlement (OP/BP 4.12) X The project may involve acquisition of land and involuntary resettlement due to proposed construction of medium to large scale infrastructure (as subprojects) within four major river basins in the Central Vietnam. Construction of these subprojects will be screened during preparation stage of the project. In cases where the zone of impact of subprojects cannot be determined, or the zone of impact is known but the precise location of construction works cannot be determined during the preparation stage, a resettlement policy framework (RPF), consistent with OP 4.12, will be prepared prior to appraisal of the project. For subprojects that are to be carried out in the first year of the project implementation, if land acquisition is required to allow construction of these subprojects, resettlement action plans (RAPs), conforming to OP 4.12, will be prepared as a condition to project appraisal. It is noted that RPF will specify steps to be taken for preparation, review, and clearance of RAPs for subsequent sub-projects for which the impacts only become known during project implementation. In addition, if there is a need for infrastructure projects that are to be in rural areas and this involves restriction of access to protected area or designated park, resulting in adverse impact of livelihoods of displaced persons, a draft process framework, conforming to relevant provisions of this policy, will be required as a condition of appraisal. The need for preparation of process framework will be determined following first field visits during project preparation. A review of PMU#s experience with Bank projects will be included in project document to assess the need for capacity building. Projects considered linked to the project would be further clarified following upcoming preparation missions. If appropriate, qualifying linked project will be described in the PAD, including due diligence report confirming that these projects are Safeguard Policies Triggered Yes No TBD currently in compliance with domestic laws and regulations, as well as the nature of the applicability of OP 4.12. Safety of Dams (OP/BP 4.37) X The proposed project may finance the rehabilitation of some existing dams to improve their safety. Where dam rehabilitation is proposed, the borrower will arrange for dam specialists to (a) inspect and evaluate the safety status of the existing dam, its appurtenances, and its performance history; (b) review and evaluate the owner's operation and maintenance procedures; and (c) provide a written report of findings and recommendations for remedial work or safetyrelated measures necessary to upgrade the existing dam to an acceptable standard of safety. A Dam Safety Framework will be developed for the Project. The Bank may accept previous assessments of dam safety or recommendations of improvements needed in the existing dam if the borrower provides evidence that (a) an effective dam safety program is already in operation, and (b) full-level inspections and dam safety assessments of the existing dam, which are satisfactory to the Bank, have already been conducted and documented. Projects on International Waterways (OP/BP 7.50) X Among the four river basins proposed, three have catchments located entirely within Vietnam. Parts of the Ca river upstream run within Lao PDR before entering Vietnam. Of the Ca river#s 513km length and 27.200 km² catchment area, 361 km of its length and 17.730 km² of the river catchment (downstream) is in Vietnam. Whether or not OP 7.50 is triggered will be determined by project appraisal. Projects in Disputed Areas (OP/BP 7.60) X None of the project provinces are located within disputed areas. Environmental Category: B - Partial Assessment III. SAFEGUARD PREPARATION PLAN A. Target date for the Quality Enhancement Review (QER), at which time the PAD-stage ISDS would be prepared: 08/08/2011 B. For simple projects that will not require a QER, the target date for preparing the PAD-stage ISDS: N/A C. Time frame for launching and completing the safeguard-related studies that may be needed. The specific studies and their timing1 should be specified in the PAD-stage ISDS. Finalization of TOR for EMF: 30 July 2010 Mobilization of Environmental consultant: November 2010 Draft EMF and EAs of Component 4 first year investments, if required: August 2011 Final EMF and sub-project EAs (if required): appraisal 1 Reminder: The Bank's Disclosure Policy requires that safeguard-related documents be disclosed before appraisal (i) at the InfoShop and (ii) in-country, at publicly accessible locations and in a form and language that are accessible to potentially affected persons. IV. APPROVALS Signed and submitted by: Task Team Leader: Mr Cuong Hung Pham Approved by: Regional Safeguards Coordinator: Mr John R. Butler Comments: Acting Regional Safeguards Adviser Sector Manager: Mr Paul Vallely Comments: 09/01/2010 10/12/2010 09/08/2010