City of Westminster Item No. CMfED&T/58/2004 Decision-maker Date Title of Report CABINET MEMBER FOR ECONOMIC DEVELOPMENT AND TRANSPORTATION 27 October 2004 Maintenance Management of Bridges and Other Highway Structures Classification Report of FOR GENERAL RELEASE Director of Environment and Leisure Wards Involved All Policy Context To maintain and improve the quality of the City Councils’ streets and buildings through a planned maintenance and improvement programme. The costs of capital works recommended in this report total £626,000 for which financial approval is sought. Provision exists in the approved capital programme for this expenditure. Financial Summary 1 Summary 1.1 This report provides: 1.2 A review of the strategy adopted in maintaining the City Council’s Bridges and Other Highway Structures. An update of the Assessment and Strengthening Programme, particularly in respect of Bridges and Structures owned by Network Rail and London Underground Limited where slippage in programme have resulted in rephasing of expenditure. And seeks approval to: Implement the 2004/05 programme of Planned Preventative Maintenance to Bridges and Structures owned and maintained by the City Council. Continue with the Administration of the London Package for Bridges and Other Highway Structures. A financial contribution to the Royal Borough of Kensington & Chelsea in respect of essential repainting to Ladbroke Grove Bridge under the terms of an existing legal agreement. 1 2 Recommendations 2.1 That approval be given to capital expenditure of £551,000 in 2004/05 in respect of Planned Preventative Maintenance of the City Council’s Bridges and other Highway Structures necessary to maintain their structural integrity and ensure public safety. 2.2 That approval is given to capital expenditure of £75,000 in 2004/05 for the Administration of the London Package for Bridges and Other Highway Structures. 2.3 That approval is given to contribute £48,000 to the Royal Borough of Kensington and Chelsea for the scheduled repainting of Ladbroke Grove Canal Bridge. 3 Background Information 3.1 Bridges form a key part of the highway system by nature of their strategic location and because of the consequences when they fail or when their capacity is impaired. Inspection is an essential part of bridge maintenance and must be conducted systematically and not just confined to those occasions when there is a breakdown or failure. The emphasis of all bridge inspection and maintenance in Westminster is on public safety and prolonging the economic life of the structure. 3.2 The City of Westminster has a high concentration of structures of varying age, size and strategic importance. Many of these structures date back to before 1922 when the first national loading standard was introduced. A number of these structures are also of significant historical value. 3.3 Within the City there are also a considerable number of structures owned by London Underground Ltd. and many of these are on the earliest lines constructed, namely the Metropolitan, District and Circle lines. In addition there are also structures owned by Network Rail, Transport for London (on the TLRN), British Waterways and the Public Utility Companies. 3.4 Previous reports to the former Traffic Sub-Committee have outlined the Management Strategy adopted in maintaining the City Council’s Bridges and other Highway Structures. (A “highway structure” is a structure either over, under or adjacent to a public highway which may at any time be expected to withstand the effects of vehicular and/or pedestrian loading). 3.5 In 1987 the Department for Transport introduced a “15-year Rehabilitation Programme”, to improve the quality of maintenance and to upgrade substandard features. The Assessment and Strengthening programme to cater for the European Community (EC) requirement to allow 40 tonne vehicles on UK Roads, formed a substantial part of this programme. 3.6 Both the Government’s 10-Year Plan for Transport and the Mayor of London’s Transport Strategy highlight the objective of the “…elimination of the maintenance backlog for local roads, bridges and lighting, as part of a £30 2 billion programme”. The City Council is working closely with other London Borough’s, via the LoBEG (London Bridges Engineering Group) Forum, in producing a Strategy for identifying the backlog in bridge maintenance and producing a forward investment programme to meet this objective. 4 Inspection 4.1 To ensure that these structures are maintained to the highest standards it is essential that their condition is reviewed and monitored on a regular basis. The City Council has adopted the standards set by the Department for Transport (DfT) and carries out regular inspections and reporting of structures with the following frequency: Principal Inspections General Inspection Superficial Inspections Special Inspections - 6 yearly - 2 yearly - Yearly - Ad-hoc Appendix 2 explains the inspection regime in more detail. 4.2 The regular inspection process gathers information on a highway structure in respect of defects and can record deterioration over time (defects are recorded in terms of extent, severity and priority). 4.3 It is vital that the right information is collected, stored and used in the correct way. To this end the City Council operates a Bridge Management System (BMS) that enables prioritised programmes of work to be produced. This ensures that the best use of financial resources is achieved. 4.4 The Maintenance of Bridges and other Highway Structures is carried out under the following headings: Routine and Ad-hoc Maintenance Planned Preventative Maintenance Other Structural Maintenance & Improvements - Revenue expenditure Capital expenditure Capital expenditure 5. Routine and Ad-hoc Maintenance 5.1 Routine Maintenance comprises those items of work, such as cleaning of drains and expansion joints to Bridges, walls and ceilings to Subways and Underpasses, and the maintenance of services, lighting etc. 5.2 Ad-hoc maintenance comprises ‘reactive’ maintenance work following damage caused by vandalism and vehicle damage. Also included is the removal of graffiti and urgent repairs to ensure that public safety is maintained. 5.3 The opening of the Golden Jubilee Bridges to the public in 2002 has resulted in these structures being added to the City Council’s Routine and Ad-hoc Maintenance programme. 5.4 Routine and Ad-hoc Maintenance are both funded from Revenue. 3 6. Planned Preventative Maintenance 6.1 All structures deteriorate over time and any work aimed at maintaining the durability of the bridge or other highway structure is classed as Planned Preventative Maintenance. Such work can be divided into two broad headings: Structural - This is essential to ensure the integrity and load carrying capacity of the Bridge/Structure is maintained. Non-Structural - Such work includes: Renewal of Mechanical and Electrical equipment Renewal of Lighting Major Repainting / Corrosion Protection Renewal / Replacement of drainage systems etc. 6.2 The programme of Planned Preventative Maintenance in 2004/05 for which financial approval is sought is as follows: Structural Strand Underpass Strand Underpass Waterloo Bridge Link Subway Strand/Aldwich Tunnel £ Structural Repair and partial re-waterproofing Replacement of defective expansion joints Replacement of defective expansion joint and minor repairs Replacement of access gantry and minor repairs 42,000 30,000 Replacement of Emergency (SOS) Telephones Electrical Upgrades (Identified from Electrical Integrity Testing) Upgrade Fire Panel (Fire Safety) Electrical Upgrades (Identified from Electrical Integrity Testing) Upgrade to Emergency (SOS) Telephones Drainage Pump replacement (end of useful life) Electrical Upgrades (Identified from Electrical Integrity Testing) 14,000 12,000 38,000 Non-Structural Piccadilly Underpass Piccadilly Underpass Piccadilly Underpass Strand Underpass Strand Underpass Piccadilly Underpass / Wellington Arch Various Structures 65,000 5,000 60,000 20,000 40,000 70,000 Asbestos Study (Control of Asbestos at Work Regulations 2002) Vehicle Incursion Study and Risk Assessments Development of Bridge Management Database 35,000 8,000 10,000 Provider’s Management Fee Client Costs 38,000 16,000 Overall Total £503,000 4 6.3 The work detailed above has been identified as being high priority and is essential to prevent any serious safety or structural consequences. 6.4 The new Contracts for Transportation Services commence on 1 October 2004 and advantage will be taken of the reduced prices provided by the new Provider, West One Infrastructure Services (A Joint Venture comprising J.Murphy & Sons Ltd, F.M Conway Ltd and WSP Consultants supported by Hyder Consulting) to deliver these essential works. 6.5 The estimated costs quoted above are based upon the rates and prices contained in the new contracts. 7. Ladbroke Grove Canal Bridge 7.1 Ladbroke Grove Canal Bridge is owned and maintained by the Royal Borough of Kensington and Chelsea (RBKC). The bridge spans the Grand Union Canal at the boundary between the two councils. 7.2 In 1994 the bridge was strengthened with the costs being shared equally between Westminster and RBKC. At the time a legal agreement was entered into with RBKC for the strengthening work and future maintenance costs on the bridge. This agreement requires the City Council to contribute 50% towards these costs. 7.3 The RBKC have advised of the need to undertake re-painting work of the bridge during the summer 2004 at a cost of £96,000. In accordance with the legal agreement City Council’s contribution to those works will therefore be £48,000. 7.4 Approval is therefore sought to contribute to the cost of the Project. 8. Assessment & Strengthening Programme - Update Assessment 8.1 The City Council commenced a programme of Bridge Assessment Studies in April 1991 for those Bridges and other Highway Structures that they own and maintain. This was completed in March 1996. 8.2 The necessary structural assessments were carried out in association with the regular 6-yearly Principal Inspections. This ensured that maintenance needs and any sub-standard features, in line with the Department for Transport’s 15year rehabilitation programme, were identified. This also enabled the service life of the structure to be assessed, before determining the extent of any necessary strengthening and/or repair. 8.3 The assessment process is split into four stages: Stage 1 – Inspection and simple assessment Stage 2 – Detailed assessment Stage 3 – Risk Analysis and Feasibility Study for Interim Measures Stage 4 – Feasibility Study for Strengthening 5 Interim Measures 8.4 Interim Measures are an essential and integral part of the assessment and strengthening programme. Any structure that is found to be sub-standard needs to be kept in a safe condition pending permanent strengthening or replacement. It is however not possible to predict in advance of an assessment (Stage 3) the need for such measures. A contingency allowance is therefore made in the capital programme to allow for such measures. 8.5 In December 2003 Interim Measures in the form of barriers in the central reserve were introduced on Lord Hills Bridge spanning the railway in Paddington. The bridge carries public highway but is owned by Network Rail. 8.6 The need for Interim Measures was identified after a structural assessment carried out by consultants employed by Network Rail found the bridge to be sub-standard. Strengthening 8.7 The final strengthening scheme in the City Council’s bridge strengthening programme was the Strengthening and Structural Repairs to the Elevated Harrow Road. 8.8 The aim throughout the City Council’s strengthening programme has been to carry out all the necessary work, where possible, to a structure in one visit thereby keeping traffic disruption to a minimum. 8.9 All City Council owned and maintained structures have been subject to a detailed structural assessment. Those structures found not to meet the requirements of the new loading standards have been strengthened and all structures have been returned to the routine inspection and maintenance programme. 8.10 Although all structures owned and maintained by the City Council have been assessed and strengthened, there are a number of structures owned by the Transport Undertakers, and others, which have yet to be dealt with. An update in respect of these structures within the City is provided below. 9. Structures Owned by the Transport Undertakers 9.1 Previous reports to both the former Planning and Transportation Committee and the former Traffic & Works Sub-Committee advised members of the limitations of responsibility of the Transport Undertakers (British Rail/Network Rail, London Underground Limited and British Waterways Board) for maintaining the load-bearing capacity of their bridges. 9.2 The responsibility for assessing and upgrading bridges owned by them, to the new standard, falls to the City Council. London Underground Limited (LUL) 6 9.3 London Underground Limited (LUL) had previously advised that they had completed the necessary assessments to bridges and other highway structures owned by them that support the public highway in Westminster. 9.4 LUL further advised that they had examined 21 additional structures supporting station concourses within the City. Of these 20 have failed to meet the new loading standards. 9.5 LUL’s approach has been to carry out a Stage 1 assessment followed by an Assessment to determine their legal liability as defined in the Transport Act 1968. 9.6 Consultants have been appointed to review the work carried out by LUL, and to undertake Stage 2, 3 and 4 Assessments as necessary to determine the City Council’s liability. However, LUL have agreed to carry out Stage 2 assessments at their own expense although there has been very little progress on this. 9.7 It was anticipated that the assessment work would have been completed by now. However, LUL have been undergoing significant organisational changes recently with the creation of the following Infraco’s (Infrastructure Companies) which has significantly affected their programme: JNP (Jubilee, Northern, Piccadilly) BCV (Bakerloo, Central, Victoria) SSL (Sub-Surface Lines) 9.8 Recent meetings between LUL have advised that at present there is no need to install any Interim Protection Measures to any of their structures. During their assessment studies they have been endeavouring to minimise the need to carry out strengthening works by further rigorous analysis and testing. 9.9 Progress has been made this year with the JNP Infraco. There are three structures that have been determined as under-strength. However, further work is underway which is likely to show that they may not require any strengthening. Network Rail (NR) 9.10 A detailed update on Network Rail owned bridge structures was given to the Transport and Infrastructure Overview and Scrutiny Committee in February 2004. Further reports will be presented when details of required strengthening and their programme for implementation has been agreed with Network Rail. Cost for Assessment of Network Rail and LUL Bridges 9.11 The current delay in progressing the assessment programme has not resulted in any increases in expenditure. However there is a need to reschedule the expenditure over a longer period. 9.12 Expenditure for the Assessment of both Network Rail and LUL Structures is met by 100% Grant from TfL. 7 9.13 The required re-phasing of expenditure for this work is shown in Section 16 of this report. 10. Structures Owned by Statutory Undertakers 10.1 The responsibility for the assessment and strengthening of structures owned by the Statutory Undertakers is considered to rest solely with the undertakers themselves. However, the Statutory Undertakers are seeking legal opinion on this issue. 11. Privately Owned Structures 11.1 There are a substantial number of privately owned structures, which support the public highway within Westminster. The responsibility for the assessment and upgrading such structures, to meet the new loading standards, has yet to be determined by the Department for Transport (DfT). 11.2 Privately owned structures include vaults lying beneath the highway and highway authorities have a duty to ensure that they can support highway loading. Many of these vaults are poorly maintained by the owner and consequently collapse. A protocol is currently being developed to manage the vault collapses in Westminster. This protocol will be the subject of a separate Cabinet Report in the near future. 12. Package Approach for London 12.1 A report to the former Traffic Sub-Committee in March 1997 set out the ‘Package Approach’ for the Assessment, Strengthening and Other Structural Maintenance of Bridges and Other Highway Structures which was introduced in London from the 1997/98 financial year. This was set up to provide a more co-ordinated and prioritised approach to Assessment and Strengthening to ensure maximum use of available Government funding. 12.2 Since April 2001, the Annual Transport Capital Expenditure Settlement for Bridge Assessment, Strengthening and other Structural Maintenance in London, has been provided from Transport for London (TfL) in the form of direct Grant. 12.3 Allocations of funding between the Boroughs is based upon an agreed Prioritisation Strategy which provides a fair basis for the allocation and ensures that those structures most at risk and on the most important routes are dealt with first. 12.4 Throughout the year actual expenditure against allocation is monitored and under-spends can be re-allocated to those Boroughs with over-spends and new schemes that can be progressed. 8 12.5 The City Council has taken a leading role in the setting up of the London Package for Bridges and Structures and acts as lead advisor to ‘Transport for London – Borough Partnerships’ on behalf of the 33 London Boroughs. 12.6 For 2003/2004 the City Council received grant in respect of the following: 12.7 Administration of the London Package Assessment of Network Rail LUL/Structures Interim Measures Lords Hill Bridge Elevated Harrow Road (Retention) £ 75,000 £ 115,000 £ 150,000 £ 40,000 For 2004/2005 the initial grant allocation to the City Council is as follows: Administration of the London Package Assessments (Network Rail) £ 75,000 £ 60,000 12.8 Approval is sought to continue with the Administration of the London Package for Bridges and Other Highway Structures and for capital expenditure of £75,000 in 2004/05. 13. Vehicular Incursions onto the Railway 13.1 In February 2001 the Selby Train Disaster occurred in which 10 people were killed after a vehicle left the M62 motorway, ran down the railway embankment and onto the East Coast Mainline where it was subsequently struck by a passenger train. 13.2 The crash raised general concerns about the issue of accidental incursion of road vehicles onto the railway. In February 2003 the Department for Transport published the document “Managing the accidental obstruction of the railway by road vehicles”. This document set out the steps that should be taken jointly by railway infrastructure authorities and highway authorities to manage the risk of the accidental incursion of road vehicles onto the railway. 13.3 Included in the document are the protocol for apportioning responsibility and costs of improvements at locations where roads maintainable at public expense meet, cross or run close to railways, and also the risk ranking exercise used to prioritise the comparative risk at each site. 13.4 Under the Health and Safety at Work Act 1974 (HSWA), railway companies have a legal obligation to assess risk not only to its employees but also to anyone else potentially affected by its activities and implement actions identified through the risk assessment process. 13.5 Highway authorities, under the Highways Act 1980, have a duty to maintain the highway to ensure the safe passage of road users. They also have a duty under the Road Traffic Act 1988 to study road traffic accidents and to take such measures, as they consider appropriate to prevent them. 9 13.6 It is recognised that it may be difficult for a railway infrastructure authority to fulfil its duties under the HSWA if the actions it identifies from its risk assessment need to be taken on land outside the railway boundaries, where it has no authority to take action. The agreed protocol therefore sets out the responsibilities between the rail and highway authorities at the various stages in the risk mitigation process. 13.7 The first stage in the risk mitigation process is to carry out risk ranking and assessments at vulnerable sites. City Council Officers have undertaken risk rankings at a number of sites in the City of Westminster (mainly bridge sites) using the guidance developed by Network Rail the County Surveyors Society (CSS) and the Health and Safety Executive (HSE). 13.8 The results of the risk ranking exercise on Network Rail infrastructure concluded that the probability of vehicles leaving the public road and reaching the railway line is very low. The built up nature of the City combined with relatively low vehicle speeds and line speeds of trains are dominating factors in the result. The conclusion of the exercise is that no additional protection measures will be required on the City’s roads to cater for the possibility of errant vehicles reaching the Railway. 13.9 A similar exercise needs to be undertaken for London Underground infrastructure where the public highway crosses over or meets any “at surface” lines belonging to London Underground and it is proposed to carry out this work during this financial year at an estimated cost of £8,000. 13.10 At this stage it is not anticipated that the risk-ranking exercise will result in the need to provide additional protective measures on the highway in mitigation against the possibility of errant vehicles reaching LUL’s railway tracks. However, any exceptions to this will be reported to the Cabinet Member. 14. The Control of Asbestos at Work Regulations 2002 14.1 A new duty to manage asbestos in ‘non-domestic premise’ has been included in the Control of Asbestos Regulations 2002. This requires duty holders to: Assess whether premises contain asbestos Assess the risk from asbestos; and Take action to manage the risk from asbestos 14.2 Although the supply and use of asbestos was almost entirely banned in the 1980’s and it’s use in construction and refurbishment is now illegal there were many asbestos-containing materials used in construction in the past. Where in place asbestos-containing materials still pose a danger to Health and Safety if disturbed. 14.3 The new regulations impose a new duty to carry out an assessment to establish whether asbestos is likely to be present. 10 14.4 Many of the City Council’s Bridges & Structures are old and may contain asbestos-containing materials. (It is noted that blue asbestos was discovered in the Strand/Kingsway Underpass which led to it’s closure and refurbishment in the early 1990’s.) It is therefore proposed to carry out a study to: Assess whether asbestos-containing materials are present Assess the risk Prepare a detailed action plan to manage the risk from any asbestoscontaining materials identified. This work will involve a desk study of available information (record drawings, files etc..) together with an inspection of each structure. 14.5 The ‘Action Plan’ will form an integral part of an individual Maintenance and Health & Safety File required under the Construction Design & Management Regulations (CDM Regulations) for each structure. 15. National Initiatives – Update 15.1 The DfT has set up a National Roads Liaison Group (RLG) together with a number of National Boards to provide an overall co-ordinated approach to the identification and implementation of National Policy. There are three ‘Boards’ covering Highways, Lighting and Bridges. 15.2 The National Bridges Board has identified a number of key areas for development where the industry is lacking in clear policy and standards. These are: Code of Practice for the Inspection & Maintenance Management of Bridges & Other Highway Structures Bridge Management Systems Best Value Performance Indicators and other Performance Monitoring Tools 15.3 The City Council is represented on the National Bridges Board and is taking the lead in the development of both the Code of Practice and the Best Value Key Performance Indicators. 15.4 Development of Best Value Key Performance Indicators (kpi’s) is underway. A ‘Bridge Condition Indicator’ has been produced for use from 2003/04 and further indicators will be available sometime during 2004/05. 15.5 Development of the “Code of Practice for the Maintenance Management of Bridges & Other Highway Structures” commenced in January 2004 and will be available by January 2005. The City Council’s Policies and Standards will be reviewed when the Code of Practice is available. 15.6 In respect of the Best Value kpi’s, these will be applied when they are issued by either the DfT or Audit Commission. However, data collection for production of Bridge Condition Indicators commenced during 2002/03. 11 16. Financial Implications Inspection and Maintenance Management 16.1 Approval is sought to expenditure of £503,000 in 2004/05 in respect of Planned Preventative Maintenance to the City Council’s Bridges and other Highway Structures as detailed in 6.2 above. 16.2 Approval is also sought to expenditure of £48,000 in respect of a contribution to the Royal Borough of Kensington & Chelsea in respect of essential repainting to the Ladbroke Grove Bridge under the terms of a legal agreement. 16.2 The proposed expenditure in respect of both the Planned Preventative Maintenance and the contribution to the Royal Borough of Kensington & Chelsea will be met from the provision of £551,000 that exists in the approved capital programme for 2004/05 in respect of Structural Repairs & Refurbishment of Bridges and Highway Structures, funded from the Parking Places Reserve Account. Some of this expenditure may be entitled to direct grant from TfL and officers will continue to press for funding from this source. 16.3 The revenue implications of the capital expenditure of £551,000 assuming an asset life of 10 years, over the next four years would be as follows: Capital Charges 2005/06 2006/07 2007/08 2008/09 £80,584 £78,035 £75,487 £72,939 Administration of the London Package 16.4 Approval is sought to expenditure of £75,000 in 2004/05 for the Administration of the London Package for which provision of exists within the approved capital programme. This expenditure will be met by way of direct grant from TfL. 16.5 The revenue implications of the capital expenditure of £75,000 assuming an asset life of 10 years over the next four years would be as follows: Capital Charges 2005/06 2006/07 2007/08 2008/09 £10,969 £10,622 £10,275 £9,928 Bridge Assessment Studies to Network Rail and LUL Bridges 16.6 As stated above, in paragraph 9.11, the delayed Bridge Assessment Studies to Railtrack and LUL Structures within the City has resulted in the need to revise the current expenditure profile. 12 The revised expenditure Profile is as follows: £000’s Previous 2002/03 Years Capital Programme 526 Provision Revised 526 Expenditure Profile 2003/04 2004/05 TOTAL 100 229 - 865 100 60 169 865 16.7 Up to and including 2000/01 this expenditure was met from the General Fund and received grant support in the form of SCA. From 2001/02 onwards this has been fully funded by Transport Grant from TfL. 17. Legal Implications 17.1 Section 13 of this report identifies a responsibility for dealing with potential risks at vulnerable sites where Railways (Network Rail and London Underground) and Roads interact. Agreed ‘protocols’ have been issued by the Department for Transport setting out the responsibilities between rail and highway authorities and the need to carry out risk assessments. These ‘risk assessments’ are to be undertaken jointly by the rail authority and the City Council and will determine whether any risk mitigation is necessary. 17.2 Section 14 of this report identifies a new duty to manage asbestos in ‘nondomestic premise’ under the Control of Asbestos Regulations 2002. These new regulations impose a new duty to carry out an assessment to establish whether asbestos is likely to be present and to prepare a detailed action plan to manage the risk from any asbestos-containing materials identified. 17.3 Previous reports to both the former Planning and Transportation Committee and the former Traffic & Works Sub-Committee advised members of the limitations of responsibility of the Transport Undertakers (British Rail/Network Rail, London Underground Limited and British Waterways Board) for maintaining the load-bearing capacity of their bridges. The responsibility for assessing and upgrading bridges owned by them, to the new standard, falls to the City Council. 18. Staffing Implications 18.1 There are no staffing implications arising from this report. 19. Outstanding Issues 19.1 There are no outstanding issues. 13 20. Performance Plan Implications 20.1 There is no specific reference contained within the Performance Plan. 21. Consultation 21.1 This report was considered at the Transport & Infrastructure Overview and Scrutiny Committee on 12 October 2004. The Committee agreed that this was a significant issue with widespread financial, safety and traffic disruption implications in the short and long term and recommended that the relevant Cabinet Members note the implications. 22. Crime and Disorder Act 22.1 There are no Crime and Disorder Act implications arising from this report. 23. Health and Safety Issues 23.1 All works undertaken will be closely monitored and carried out to the requirements of the Health & Safety at Work Act and the Construction Design and Management Regulations. 23.2 A new duty to manage asbestos in ‘non-domestic premise’ has been included in the Control of Asbestos Regulations 2002. These new regulations impose a new duty to carry out an assessment to establish whether asbestos is likely to be present. It is proposed to carry out a study to leading to the preparation of a detailed action plan to manage the risk from any asbestos-containing materials identified. 24. Co-operation with Health Authorities 24.1 There are no implications arising from this report requiring co-operation or coordination with the Health Authorities. 25. Human Rights Act 1998 25.1 There are no Human Rights Act implications arising from this report. 26. Conclusion 26.1 Planned Preventative Maintenance is required to maintain the structural integrity of the structures in Westminster and to ensure public safety. If this work is not carried out, there may be serious public safety implications in addition to potential financial consequences to the City Council. 14 26.2 Under a legal agreement between Westminster City Council and the Royal Borough of Kensington and Chelsea, Westminster are required to contribute £48,000 in 2004/05 towards the maintenance painting of Ladbroke Grove Canal Bridge. It is proposed to fund this work out of the 2004/05 Planned Preventative Maintenance Budget. 26.3 The City Council is taking a leading role in managing the London Package for Bridges and Structures and acts as lead advisor to ‘Transport for London – Borough Partnerships’ on behalf of the 33 London Boroughs. 26.4 The results of the risk analysis into vehicular incursions onto the railway line concluded that all the potential sites identified in Westminster were very low and that there is no need to provide additional protective measures on the highway in mitigation against errant vehicles reaching the railway. 26.5 A new duty to manage asbestos in ‘non-domestic premise’ has been included in the Control of Asbestos Regulations 2002. These new regulations impose a new duty to carry out an assessment to establish whether asbestos is likely to be present. It is therefore proposed to carry out a study to leading to the preparation of a detailed action plan to manage the risk from any asbestoscontaining materials identified. IF YOU HAVE ANY QUERIES ABOUT THIS REPORT OR WISH TO INSPECT ANY OF THE BACKGROUND PAPERS, PLEASE CONTACT David.A.Yeoell on 020 7641 2622 EMAIL ADDRESS: dyeoell@westminster.gov.uk FAX NUMBER: 020 7641 2658 BACKGROUND PAPERS The documents used or referred to in compiling the report were: 1. 2. 3. 4. 5. 6. 7. 8. Report to Traffic & Works Sub-Committee March 1996 Report to Traffic Sub-Committee March 1997 Report to Traffic Sub-Committee March 1998 Report to P&T Operational Sub-Committee March 1999 Report to T&H Operational Sub-Committee March 2001 Report To Cabinet Member for T&I March 2003 Report to the Transport & Infrastructure Overview and Scrutiny Committee - February 2004. Report to Transport & Infrastructure Overview and Scrutiny Committee - October 2004 15 For completion by Cabinet Member Declaration of Interest I have no interest to declare in respect of this report Signed ……………………………. Date ……………………………… NAME: I have to declare an interest State nature of interest ……..…………………………………………… ……………………………………………………………………………….. Signed ……………………………. Date ………………………………… NAME: (N.B: If you have an interest you should seek advice as to whether it is appropriate to make a decision in relation to this matter.) For the reasons set out above, I agree the recommendation(s) in the report entitled Maintenance Management of Bridges and Other Highway Structures and reject any alternative options which are referred to but not recommended. Signed ……………………………………………… Cabinet Member for ………………………………. Date ………………………………………………… If you have any additional comment which you would want actioned in connection with your decision you should discuss this with the report author and then set out your comment below before the report and this pro-forma is returned to the Secretariat for processing. Additional comment: ………………………………………………………………… …………………………………………………………………………………………. …………………………………………………………………………………………. 16 NOTE: If you do not wish to approve the recommendations, or wish to make an alternative decision, it is important that you consult the report author, the Director of Legal and Administrative Services, the Chief Financial Officer and, if there are staffing implications, the Head of Personnel (or their representatives) so that (1) you can be made aware of any further relevant considerations that you should take into account before making the decision and (2) your reasons for the decision can be properly identified and recorded, as required by law. Note to Cabinet Member: Your decision will now be published and copied to the Members of the relevant Overview & Scrutiny Committee. If the decision falls within the criteria for call-in, it will not be implemented until five working days have elapsed from publication to allow the Overview and Scrutiny Committee to decide whether it wishes to call the matter in. 17 APPENDIX 1 Bridges and Structures owned and maintained by Westminster Structure Name Ward THAMES BRIDGES Waterloo Bridge Golden Jubilee Footbridges St.James’s St.James’s OTHER BRIDGES Elevated Harrow Road (Westbound) Lancaster Place Vaults Bishops Bridge Road Westbourne Terrace Bridge Harrow Road Gyratory Warwick Avenue Carlton Bridge Wedlake Street Footbridge Formosa Street Footbridge Hyde Park/ Westbourne/Bayswater St.James’s Hyde Park Little Venice Little Venice Little Venice Westbourne Westbourne Westbourne ROAD UNDERPASSES Piccadilly/Hyde Park Corner Strand/Kingsway Harrow Road (Westbound) West End St.James’s Little Venice/Hyde Park/Westbourne PEDESTRIAN SUBWAYS Charing Cross/Strand Complex Harrow Road/Porteus Road Lord Hills Trafalgar Square/Cockspur Street Parliament Street Bridge Street Bessborough Street (Pimlico Station) Waterloo Bridge Link Subway St.James’s Hyde Park/Little Venice Westbourne St.James’s St.James’s St James’s Tachbrook St.James’s PIPE SUBWAYS Strand/Aldwich Complex Kingsway Charing Cross Road Shaftsbury Avenue Northumberland Avenue Piccadilly Circus Cranbourne Street Marble Arch Marylebone St.James’s St.James’s St.James’s/West End St.James’s/West End St.James’s St.James’s/West End St.James’s Knightsbridge and Belgravia Bryanston and Dorset Square Victoria Embankment Garrick Street St.James’s St.James’s RETAINING WALLS 18 Various Various 19 APPENDIX 2 Maintenance Management of Bridges and other Highway Structures Routine Inspection Programme Principal Inspections - 6 yearly This level of inspection requires a close examination (within touching distance) of all inspectable parts of the structure, including access equipment and both destructible and non-destructible testing. General Inspection - 2 yearly This consists of a visual inspection of all external parts of the structure. Access equipment may be required in some cases. Superficial Inspection - 1 yearly This type of inspection consists of a cursory check for obvious deficiencies, which might lead to traffic accidents or high maintenance costs. Special Inspections A special inspection may be required for the following reasons: (i) (ii) (iii) To investigate a specific problem that has been found; Structures that are either weight restricted, cast iron or have been subject to impact or fire damage; Before and after the passage of abnormally heavy loads on a structure that has been proved sub-standard by calculation. 20