DEP05-0322 & DEP05-0323 STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION COMPASS ENVIRONMENTAL, INC., and SHAW ENVIRONMENTAL, INC., ) ) ) Petitioners, ) ) vs. ) ) DEPARTMENT OF ENVIRONMENTAL ) PROTECTION, ) ) Respondent, ) ) and ) ) CDM CONSTRUCTORS, INC., ) ) Intervenor. ) / OGC CASE NOs.: DOAH CASE NOs.: 04-1997 05-0004 05-0007 05-0008 FINAL ORDER On March 21, 2005, an Administrative Law Judge with the Division of Administrative Hearings (“DOAH”) submitted his Recommended Order (“RO”) to the Florida Department of Environmental Protection (“DEP”) in this administrative proceeding. Copies of the RO were served upon counsel for the Petitioners, Compass Environmental, Inc. (“Compass”), Shaw Environmental, Inc. (“Shaw”), and the Intervenor, CDM Constructors, Inc. (“CDM”). A copy of the RO is attached hereto as Exhibit A. Exceptions to the RO were filed on behalf of each of the parties on March 31, 2005. CDM and DEP then filed timely Responses to the Exceptions of Compass and Shaw, and Compass and Shaw filed timely Responses to the Exceptions of CDM and DEP. The matter is now before the Secretary of DEP for final agency action. BACKGROUND This proceeding arose out of actions taken by DEP pursuant to § 403.4154(3), F. S., to abate an imminent hazard. The imminent hazard involved two abandoned phosphogypsum stack systems at the former Piney Point fertilizer plant adjacent to Port Manatee in Manatee County (“Piney Point”). Piney Point is located about one mile inland from Bishops Harbor, a portion of Tampa Bay. “Phosphogypsum” is a by-product of the process of converting raw phosphate rock into phosphoric acid; and “stack systems” are large impoundments containing water, which has been contaminated by coming into contact with the phosphogypsum. Federal and state regulations require that the phosphogypsum be managed in stack systems. This process is accomplished by using process water to “slurry” the phosphogypsum into the stacks. This process water becomes extremely polluted as a result of the manufacturing activities and is typically very acidic. The process water contains heavy metals, such as arsenic, cadmium, chromium, and fluoride, in addition to high levels of nutrients, nitrogen, and total dissolved solids. It is also slightly radioactive. The process water is stored in impoundments surrounded by the phosphogypsum stacks, in cooling ponds, and in surrounding seepage ditches. There are two phosphogypsum stacks at the Piney Point site, and it is estimated that there are currently 500 to 550 million gallons of contaminated process water in and surrounding the two stacks. 2 Until early 2001, the Piney Point fertilizer plant was owned and operated by Piney Point Phosphates, Inc., a subsidiary of Mulberry Phosphate Company (“Mulberry”). In February of 2001, Mulberry filed a petition for protection from creditors in the United States Bankruptcy Court in Tampa, Florida. At the same time, Mulberry notified the Department that it did not have the resources to maintain the Piney Point site. Because of the potential for release of the contaminated waters from Piney Point into Tampa Bay, DEP immediately assumed financial responsibility for Piney Point. In May of 2001, a state court appointed a Receiver for Piney Point to take "all reasonable steps and action to preserve the Property's environmental integrity and its compliance with environmental regulations." To execute these duties, the Receiver entered into a contract with DEP. DEP then retained the services of Ardaman and Associates (“Ardaman”), an international engineering consulting firm in Orlando, Florida, as its engineer of record to design a plan to close Piney Point and to ensure that the plan was properly implemented. At about the same time, the Receiver contracted with IT Corporation, the predecessor to Shaw, to begin some of the site closure work on an emergency basis. Since that time, the Department has spent approximately $63 million at Piney Point, with Shaw receiving a majority of that amount. DEP then issued an Invitation to Negotiate (“ITN”) in July of 2004, entitled “Closure of the Piney Point Phosphogypsum Stack System."1 This ITN called for contractors to submit responses for services at the Piney Point site in three primary areas: continued operation and maintenance of the site; water consumption; and closure of the phosphogypsum stack system. Water consumption consists of treating Subsection 403.4154(3)(e), F.S., authorizes DEP to contract with various entities, including “thirdparty contractors,” to perform all or part of the work in order to “abate or substantially reduce an imminent hazard.” 1 3 the process water and removing it from the site by evaporation, irrigation, discharge, or other methods. Closure of the stacks includes draining water from the stacks, grading the banks, and installing liners, clean soil, and sod. The proposed Piney Point contract is estimated to be worth approximately $51.2 million to the successful vendor. DEP’s ultimate goal is to convert the Piney Point site into a freshwater reservoir for Manatee County residents. DEP then selected a seven-member team to serve as evaluators for the Piney Point ITN, one of whom ultimately did not participate in the evaluation process. CDM, Compass, Coburn Construction, and Shaw submitted responses to the ITN in September of 2004.2 The remaining six members of the evaluation teamed subsequently reviewed the proposals of CDM, Compass, and Shaw, independently. The final average rankings were very close. Shaw was ranked first, followed by Compass and CDM, who were tied. In October of 2004, DEP gave notice of its rankings, and informed CDM, Compass, and Shaw that it intended to exercise its right to conduct oral discussions with all three vendors. The three vendors would then be asked to submit Best and Final Offers (“BAFOs”), which would be scored anew. This process was consistent with the ITN, which provided that DEP "reserves the right to short list respondents deemed to be in the competitive range to conduct oral discussions prior to the final determination of contract award." DEP had determined that oral discussions with representatives of CDM, Compass, and Shaw would be helpful in formulating BAFO Instructions. DEP subsequently determined that Coburn Construction ‘s reply to the ITN was “nonresponsive,” and Coburn did not contest this determination. 2 4 Before drafting the BAFO Instructions, a Department of Revenue attorney and Purchasing Analyst having substantial experience with procurements were added to the evaluation team. As finally formed, the evaluation team consisted of two attorneys, four engineers, and two persons with significant procurement experience. CDM, Compass, and Shaw each made oral presentations on November 3, 2004. All of the evaluators attended the oral presentation. As part of this process, the three vendors were able to ask questions of the evaluators, and the evaluators were able to ask questions of the vendors. Following these oral discussions, another round of discussions was held with each vendor by three members of the evaluation team. These later discussions, referred to as "negotiation sessions," were conducted for the purpose of better understanding the cost elements and facts of each vendor’s initial proposal in order to develop the BAFO Instructions. The BAFO Instructions were ultimately issued by DEP in November of 2004, and responses were timely filed by CDM, Compass, and Shaw on December 1, 2004. The BAFO instructions also notified the three vendors that DEP would begin negotiations with the top-ranked vendor immediately after the BAFO rankings were posted. None of the three vendors have challenged this oral discussion and BAFO Instruction process conducted by DEP in this case. Each of the eight evaluators conducted an individual review of the three responses to the BAFO Instructions, without any discussions with the other evaluators about their respective evaluations. It is undisputed that, other than one phone call from one evaluator to clarify what information the three vendors had received with the Instructions, the evaluators had no contact with one another during the process of 5 evaluation of the BAFOs. After the evaluators submitted their score sheets to DEP, the rankings were totaled, added up and averaged to obtain a final ranking for each vendor in order to determine the “best value” for the state.3 The final rankings were: CDM was ranked first with an average rank of 1.688; Compass was ranked second with an average rank of 1.813; and Shaw was ranked third with an average rank of 2.500. On December 7, 2004, the Department posted a recommended award of the Piney Point contract to CDM. Compass and Shaw then filed timely petitions protesting the proposed contract award to CDM. Compass contended that the Piney Point ITN negotiation process was flawed due to the involvement of a member of DEP's evaluation committee, Dr. Nadim Fuleihan (“Fuleihan”), a senior vice-president and principal engineer of Ardaman. Compass alleged that Dr. Fuleihan had an actual or apparent conflict of interest because one of Ardaman’s clients (Mosaic Company) was a listed subcontractor in CDM's proposal. Shaw raised this same purported conflict of interest issue in its petition. Shaw further contended that the proposals of CDM and Compass were non-responsive, the evaluations were not conducted in the "sunshine" as required by Florida law, and the scoring of the responses was arbitrary, capricious, and contrary to competition. DEP then referred the matter to DOAH for a formal administrative hearing. Compass's petition was assigned DOAH Case No. 05-0007BID, and Shaw's petition was assigned DOAH Case No. 05-0008BID. Administrative Law Judge, Donald R. Alexander (“ALJ”), was assigned to preside over the cases. CDM subsequently filed a 3 The averaging of ranks was utilized by DEP in order to normalize the evaluations so that an especially generous or especially hard grader would not skew the outcome. (RO, para. 30). 6 Petition to Intervene, which was granted by the ALJ. A DOAH final hearing was held in the consolidated cases on February 2, 3, 4 and 7, 2005, in Tallahassee, Florida. Prior to the final hearing, Shaw also filed a Petition for Review of Non-Final Agency Action and Motion to Stay with the First District Court of Appeal seeking to stay DEP’s decision to continue contract negotiations with CDM until this protest is resolved. Shaw’s Motion to Stay was denied, and a decision on the merits of the case remains pending before the court. See Shaw Environmental, Inc. v. State, Department of Environmental Protection, Case No. 1D05-407 (Fla. 1st DCA March 2, 2005). The ALJ issued his RO in this case on March 21, 2005. The only problem identified by the ALJ with the entire Piney Point ITN and BAFO process in his 44-page RO was with the alleged conflict of interest on the part of Dr. Fuleihan. The ALJ found that Fuleihan’s firm, Ardaman, had a contractual relationship with one of CDM’s listed subcontractors, Mosaic. Fuleihan did not consider this relationship to be a conflict of interest and did not therefore disclose it to DEP when asked before both the initial review round and the BAFO round to disclose conflicts of interest. The ALJ also found that Fuleihan learned (during discovery in this case and after the BAFO evaluation process was over) that Ardaman also had a contract valued at $57,000 dollars with CDM’s parent company in St. Louis, Missouri for work done in Idaho. Notwithstanding these contractual relationships between Ardaman and Mosaic and CDM’s parent company, the ALJ concluded that there was no record evidence that Fuelihan would “be enriched in any way,” or “exhibited bias or favoritism during the solicitation process,” or “acted improperly in evaluating the proposals.” (RO, paragraphs 46, 48, 49). Nevertheless, in his summary paragraph 52, the ALJ concluded that: 7 In summary, while there is no evidence that Ardaman’s professional relationship with both a prime contractor and a subcontractor caused the evaluator [Fuleihan] to exhibit bias or favoritism towards any particular vendor, the relationships give rise to an appearance of impropriety so that a reasonable person might question the impartiality of Dr. Fuleihan. By not having those relationships disclosed, the Department’s governing statutes, policies, and instructions were contravened. STANDARD OF REVIEW Subsection 120.57(1)(l), Florida Statutes (“F. S.”), provides that an agency final order “may reject or modify an administrative law judge’s conclusions of law and interpretations of administrative rules over which it has substantive jurisdiction.” Subsection 120.57(1)(l) also prescribes that an agency reviewing a DOAH recommended order may not reject or modify the findings of fact of an administrative law judge, “unless the agency first determines from a review of the entire record, and states with particularity in the order, that the findings of fact were not based upon competent substantial evidence or that the proceedings on which the findings were based did not comply with essential requirements of law.” There is no contention in any of the Exceptions filed in this case that the DOAH proceeding did not comply with essential requirements of law. Thus, the ALJ’s findings of fact cannot be rejected unless it is demonstrated that they were not based on competent substantial evidence of record. Also, I have no authority to reweigh the evidence presented at the final hearing, attempt to resolve conflicts therein, or judge the credibility of witnesses. These evidentiary matters are within the province of the ALJ, as the trier of the facts in this administrative proceeding. Heifetz v. Dept. of Business Regulation, 475 So.2d 1277, 1281 (Fla. 1st DCA 1985). 8 The standard of review in this proceeding where a DEP procurement decision is being contested is also governed by established case law of Florida. The appellate courts have repeatedly held that public agencies have wide discretion in soliciting and accepting proposals through the competitive procurement process; and such decisions, when based on honest exercises of discretion, will not be overturned by the courts even if they may appear to be erroneous and even if reasonable persons may disagree. Dept. of Transportation v. Groves-Watkins Constructors, 530 So.2d 912, 913 (Fla. 1988); Liberty County v. Baxter’s Asphalt and Concrete, 421 So.2d 505, 507 (Fla. 1982); Engineering Contractors v. Broward County, 789 So.2d 445, 450 (Fla. 4th DCA 2001); Scientific Games v. Dittler Brothers, 586 So.2d 1128, 1131 (Fla. 1st DCA 1991). In addition, the 1996 revisions to the Administrative Procedure Act (“APA”) included an amendment substantially rewriting subsection 120.57(3), F. S., now entitled “ADDITIONAL PROCEDURES APPLICABLE TO PROTESTS TO CONTRACT SOLICITATION OR AWARD.” Current subsection 120.57(3) reads, in pertinent part, as follows: (f) . . . Unless otherwise provided by statute, the burden of proof shall rest with the party protesting the proposed agency action. In a competitiveprocurement protest, other than a rejection of all bids, proposals, or replies, the administrative law judge shall conduct a de novo proceeding to determine whether the agency's proposed action is contrary to the agency's governing statutes, the agency's rules or policies, or the solicitation specifications. The standard of proof for such proceedings shall be whether the proposed agency action was clearly erroneous, contrary to competition, arbitrary, or capricious. If there are disputed issues of material fact, the de novo hearing under § 120.57(3)(f) is subject to the same procedural requirements as other formal hearings held pursuant to § 120.57(1), F.S. See subsection 120.57(3)(d)3, F.S. It is the 9 responsibility of the administrative law judge under § 120.57(3)(f), to “determine whether the agency's proposed [procurement] action is contrary to the agency's governing statutes, the agency's rules or policies, or the solicitation specifications,” and the burden of proof is on “the party protesting the proposed agency action.” The Florida case law construing § 120.57(3)(f) concludes, however, that the phrase “de novo proceeding” set forth therein is used to describe a somewhat different administrative proceeding from that normally conducted pursuant to § 120.57(1), Florida Statutes. See State Contracting v. Dept. of Transportation, 709 So.2d. 607 (Fla. 1st DCA 1998). In a typical § 120.57(1) hearing, the administrative law judge essentially sits in the place of the agency being challenged; and this de novo proceeding is designed, not to review prior agency action, but to actually formulate final agency action on the matter being contested. See, e.g., Hamilton County Commissioners v. Dept. of Environmental Regulation, 587 So.2d. 1378, 1387 (Fla. 1st DCA 1991). In contrast, the de novo proceeding described in § 120.57(3)(f) has been construed by the First District Court of Appeal of Florida to be a “form of intra-agency review” where the object of the proceeding is to “evaluate the [prior] action taken by the agency,” rather than to formulate final agency action. State Contracting, 709 So.2d at 609. The State Contracting opinion cites with approval to Intercontinental Properties, Inc. v. Dept. of Health & Rehab. Services, 606 So.2d. 380 (Fla. 3d DCA 1992), interpreting the phrase “de novo hearing” as used in bid protest proceedings before the 1996 revision of the Administrative Procedure Act. State Contracting, 709 So.2d at 609. On page 386 of its Intercontinental Properties opinion, the court concluded as follows: Although the hearing before the hearing officer was a de novo proceeding, that simply means that there was an evidentiary hearing during which 10 each party had a full opportunity to develop an evidentiary record for administrative review purposes. It does not mean, as the hearing officer apparently thought, that the hearing officer sits as a substitute for the Department and makes a determination whether to award the bid de novo. DOAH Administrative Law Judge (“ALJ”), John G. Van Laningham, has observed that the State Contracting “intra-agency review” interpretation of a § 120.57(3)(f) de novo proceeding actually results in a proceeding having a “hybrid nature of an appellate trial.” See Syslogic Technology Services v. South Forida Water Management District, 26 FALR 1368, 1382 (Fla. SFWMD 2002), appeal dismissed without a published opinion, 819 So.2d 771, Fla. App. LEXIS 8828 (Fla. 2d DCA 2002). The Syslogic Technology Services Final Order adopts a detailed analysis by ALJ Van Laningham of the “standard of review” issue under § 120.57(3)(f). ALJ Van Laningham noted that, although designated as a “standard of proof” in § 120.57(3)(f), the terms “clearly erroneous”, “arbitrary,” or “capricious” are actually recognized review standards, rather than standards of proof normally applicable in evidentiary hearings. 26 FALR at 1380. The ALJ also concluded that it is highly unlikely that the Legislature intended to change the standard of proof in bid protest cases from the recognized preponderance of evidence standard applicable to all other administrative proceedings. Id. at 1380. The ALJ further concluded that it is thus a reasonable interpretation of the term “standard of proof” in § 120.57(3)(f) to mean “standard of review.” Id. at 1380. ALJ Van Laningham’s “standard of review” interpretation of § 120.57(3)(f) was adopted without any modifications by the South Florida Water Management District in its Final Order. Id. at 1368. I view this interpretation of § 120.57(3)(f) in the Syslogic Technology Services case to be reasonable and persuasive. Accordingly, in preparing 11 this Final Order, the standard of review applied in determining the propriety of DEP’s proposed award of the Piney Point contract to CDM was whether this action was “clearly erroneous, contrary to competition, arbitrary, or capricious.” (emphasis added). RULINGS ON EXCEPTIONS OF DEP AND CDM Preface Upon review of the Exceptions to the RO filed on behalf of DEP and CDM, I conclude they raise many similar issues and objections to the ALJ’s findings, conclusions, and ultimate recommendation. These Exceptions will thus be consolidated for purposes of this Final Order, except for CDM’s request for an award of attorney’s fees, which will be addressed separately. DEP’s Exception No. 1 and CDM’s Exception E These Exceptions both contend that the DEP Final Order should contain a ruling that Shaw lacks standing in this administrative proceeding because of its position as the third-ranked vendor in the BAFOs evaluation process. Cf. Preston Carroll Co. v. Florida Keys Aqueduct Authority, 400 So.2d 524 (Fla. 3d DCA 1981). Both DEP and CDM correctly note that the ALJ did not make any ruling on this standing issue. DEP and CDM assert that DEP’s final order should find that Shaw failed to establish standing. I decline, however, to supplement the ALJ’s conclusions of law by making a de novo ruling in this Final Order on the issue of Shaw’s standing, which was not addressed in the RO on review. Even if this Final Order contained a ruling dismissing Shaw’s petition for lack of standing due to its third-ranked vendor position, I am not convinced that I would have authority to reject the ALJ’s findings and conclusions addressing the merits of Shaw’s 12 claims. Cf. Hamilton County v. Dept. of Environmental Regulation, 587 So.2d 1378, 1383 (Fla. 1st DCA 1991) (concluding that the issue of Hamilton County’s standing was “moot,” since the [remaining] issues had been fully litigated in the administrative proceeding). And, of course, in an ITN procurement, any vendor could receive the contract if negotiations with competing vendors did not result in an award. DEP Exception No. 1 and CDM Exception E are denied. DEP Exception No. 10 and CDM Exception C.14 These two Exceptions both object to the third sentence of paragraph 33 of the RO where the ALJ finds: “if Dr. Fuleihan’s scores were removed from the final tabulation, as requested by Compass, then Compass would be the highest ranked vendor.” (emphasis added). CDM and DEP contend that this crucial finding is not supported by competent substantial evidence of record, but is based solely on a pure mathematical miscalculation by the ALJ. The uncontested findings of the ALJ concerning the scores and rankings of the BAFO submittals of CDM, Compass, and Shaw by each of the eight evaluators are set forth in paragraphs 32 and 33 of the RO, which read in pertinent part as follows: 32. Mr. Alden ranked CDM first with a score of 177, Compass second with a score of 174, and Shaw third with a score of 172. Mr. Black ranked CDM first with a score of 140, Compass second with a score of 137 and Shaw third with a score of 106. Mr. Brown ranked CDM first with a score of 205, Compass second with a score of 183 and Shaw third with a score of 182. Mr. Coram ranked Compass first with a score of 180, Shaw second with a score of 175 and CDM third with a score of 170. Dr. Fuleihan ranked CDM first with a score of 192, while Compass and Shaw tied with scores of 189. Ms. Phillips originally submitted her evaluations with Compass ranked first with a score of 144, and Shaw and CDM tied with a score of 141. Due to an error when she transposed her scores from her notes to her score sheet, she corrected her evaluations at the hearing. With the corrected scores Compass was still ranked first [by Ms. Phillips] 4 Because these exceptions are dispositive, I address them out of sequence. 13 with a score of 144, but CDM was now second with a score of 143, and Shaw third with a score of 139. However, this correction did not change the final results of the evaluation process. Mr. Wright ranked Shaw first with a score of 183, Compass second with a score of 181, and CDM third with a score of 166. Mr. Zamani ranked CDM first with a score of 218, Compass second with a score of 210, and Shaw third with a score of 191. (emphasis added). 33. After the evaluators submitted their score sheets, the ranks were added up and averaged to obtain a final ranking for each vendor. The final ranking was as follows: CDM was ranked first with an average rank of 1.688, Compass second with an average rank of 1.813, and Shaw third with an average rank of 2.500. The ALJ’s related uncontested findings in paragraphs 29 and 30 of the RO concerning DEP’s vendor-ranking process after receiving all the evaluators’ scores are: 29. . . .Each vendor was then assigned a ranking based on its weighted total score. The vendor with the highest score received a rank of one, the second highest score received a rank of two, and the third highest score received a rank of three. If two or more vendors had identical scores, the ranks were added together and divided by two. 30. After all the scores had been submitted, the ranks of each vendor were averaged to determine the best proposal for the state. Average ranks were used in order to normalize the evaluations so that an especially generous or especially hard grader would not skew the outcome. CDM and DEP assert that, based on the ALJ’s above-quoted findings, if Fuleihan’s scores are removed and the average rankings of the three vendors are recalculated based on the scores of the remaining seven evaluators utilizing Ms. Phillips’ corrected scores then, as a matter of pure mathematics, CDM and Compass have an identical “highest-ranking” of 1.714 and Shaw is third at 2.571, as reflected by the following chart based on uncontested numerical data extracted from paragraphs 29, 30, and 32 of the RO: 14 TABLE 1: Scores and Ranking using corrected scores for Barbara Phillips Evaluator Alden Black Brown Coram Phillips Wright Zamani Total Average CDM 177 140 205 170 143 166 218 1219 174.14 1.0 1.0 1.0 3.0 2.0 3.0 1.0 12 1.714 Compass 174 2.0 137 2.0 183 2.0 180 1.0 144 1.0 181 2.0 210 2.0 1209 12 172.71 1.714 Shaw 172 106 182 175 139 183 191 1148 164.00 3.0 3.0 3.0 2.0 3.0 1.0 3.0 18 2.571 I agree with this contention of CDM and DEP and conclude that, utilizing only the uncontested data found in paragraphs 29-30 and 32 of the RO, a correct mathematical re-calculation of the scores and rankings of the remaining seven evaluators after Fuleihan’s scores are removed inevitably results in CDM and Compass being tied as the “highest-ranked” vendor. I find after a review of the entire record, that there is no competent substantial evidence supporting the ALJ’s challenged finding in paragraph 33 that Compass would be the sole highest-ranked vendor if Dr. Fuleihan’s scores are removed from the final BAFOs tabulations. In its Responses to Exceptions, Shaw does not contest any portion of these Exceptions of DEP and CDM. In addition, neither Compass nor Shaw filed an Exception to paragraph 32 of the RO pertaining to the ALJ’s findings concerning Ms. Phillips’ original and corrected evaluation scores. I also deem it significant that the subsequent Responses to Exceptions filed by Compass did not dispute the basic fact that, as a matter of pure mathematical calculation, CDM and Compass are tied as the highest-ranked vendor when Ms. Phillips’ corrected scores are utilized and Fuleihan’s scores are removed. Compass only contends in its Responses to Exceptions that Ms. 15 Phillips “cannot change her scores at the Final Hearing.” I reject this contention of Compass for several reasons. First, the DOAH record does not reflect that Compass made a timely objection at the final hearing to this testimony of Ms. Phillips concerning the error in her original BAFOs evaluation scores and her subsequent corrections. Thus, Compass has waived its right to now object to this testimony of Ms. Phillips. See Tri-State Systems v. Dept. of Transportation, 500 So.2d 212, 215 (Fla. 1st DCA 1986), rev. den., 506 So.2d 1041 (Fla. 1987) (concluding that hearsay testimony admitted into evidence without objection at a DOAH final hearing becomes “usable as proof just as any other evidence”). Second, the failure of Compass and Shaw to object to the ALJ’s Finding of Fact 32 in their Exceptions to the RO constitutes a waiver of any purported errors in these factual findings. See Couch v. Commission on Ethics, 617 So.2d 1119, 1124 (Fla. 5th DCA 1993) (concluding that Couch waived his right to challenge a DOAH hearing officer’s findings of fact on appeal because of his failure to file exceptions to the findings). To reject a crucial finding of the ALJ based on an objection first raised by Compass in its Responses to Exceptions would also unfairly deny CDM the opportunity to file a reply in opposition. Third, even if Compass or Shaw had made a timely objection to this testimony of Ms. Phillips and had also filed Exceptions to the ALJ’s Finding of Fact 32, I would not have “substantive jurisdiction” under § 120.57(1)(l), F.S., to reject an evidentiary ruling by the ALJ as to the admissibility of such testimony. See, Barfield v. Dept. of Health, 805 So.2d 1008, 1011-12 (Fla. 1st DCA 2001) (concluding that the Board of Dentistry 16 lacked substantive jurisdiction on review of a DOAH RO to reject an evidentiary ruling by the ALJ that certain documents were inadmissible hearsay). Finally, even if I set these concerns aside, I would be compelled to reject the argument because it appears to suggest that Ms. Phillips should not have testified about the error in her scoring after she noticed her mistake. I cannot accept a legal argument that would require less than full candor from a witness. Based on this mathematical correction that CDM and Compass are “co-highest ranked” vendors, if Fuleihan’s scores are removed from the BAFOs evaluation process, I conclude that DEP staff would have had the sound discretion to begin negotiations with either CDM or Compass under the ITN process. See Baxter’s Asphalt, 421 So.2d at 507 (stating that a governmental agency awarding a bid has “wide discretion” and is not to be overturned “even if reasonable persons may disagree” about the proper recipient of the award). Because DEP has wide discretion and may exercise that discretion even in a manner with which reasonable people might disagree, it cannot be “clearly erroneous, contrary to competition, arbitrary, or capricious” to award the contract to one of the “co-highest ranked” vendors, namely, CDM. In view of the above rulings, DEP’s Exception No. 10 and CDM’s Exception C.1 are granted. DEP Exception Nos. 2 through 9 and CDM Exception C.2 and D1 through D.5. These related Exceptions all object to portions of the RO where the ALJ addresses the allegations of Compass and Shaw that Fuleihan’s role in the Piney Point BAFO evaluation process created a conflict of interest warranting a determination that DEP’s proposed award of the contract to CDM was arbitrary, capricious, and contrary to 17 competition. Having decided in the previous section of this Order that commencing ITN discussions with CDM was permissible (even without Fuleihan’s scores) it is unnecessary to decide whether including Fuleihan’s scores in the evaluation process would have created an appearance of impropriety. Like courts, I am reluctant to decide issues that have no practical significance. See, e.g., New Mexico Env’t Dep’t v. Foulson (In re L.F. Jennings Oil Co.), 4 F.3d 887, 889 (10th Cir. 1993) (declining to address an issue because resolution would have “no practical significance”). I therefore decline to rule on these exceptions. If an appellate court disagrees with my ruling on DEP Exception No. 10 and CDM Exception C.1, and it becomes necessary to rule on the merits of DEP Exception Nos. 2 through 9 and CDM’s Exception C.2 and D1 through D.5, DEP requests that the matter be remanded to this agency for substantive review and final disposition. Accordingly, DEP Exception Nos. 2 through 9 and CDM’s Exception C.2 and D.1 through D.5 are deemed to be nonessential to the final disposition of this case and are denied at this time on that procedural basis alone. RULING ON CDM’S REQUEST FOR ATTORNEYS’ FEES CDM concludes its Exceptions with a request that DEP issue a final order “awarding attorney’s fees to CDM in an amount to be determined by separate order.” However, a state agency has limited jurisdiction over the subject matter of allowable attorney’s fees and costs in formal administrative proceedings. Under § 120.595(1), F. S., an agency is only authorized to award attorney’s fees and costs to a prevailing party where the ALJ has entered a RO determining that a nonprevailing adverse party 18 has “participated in the proceeding for an improper purpose,” and the suggested amount of the attorney’s fees and costs is designated in the RO. The RO now on review does not address the issue of whether any party has participated in this proceeding for an improper purpose. The RO also does not designate the amount of attorney’s fees and costs to be awarded by DEP in its Final Order as required by § 120.595(1). Unlike trial judges, agency heads do not have authority to enter separate orders awarding or denying attorney’s fees and costs after final orders have been entered in administrative cases. The award of attorney’s fees and costs by an agency pursuant to § 120.595(1) must be made in “the final order in a [s. 120.57(1)] proceeding.” See subsection 120.595(1)(b). Sections 57.105(1) and 57.105(5), F.S., also require that the ALJ make a determination that the losing party or the losing party’s attorney knew or should have known that a claim or defense would not be supported by the material facts or by the application of the existing law to the material facts. These determinations and any related award of attorney’s fees must be made by the ALJ in a separate order, which is directly reviewable by the appropriate district court of appeal. CDM’s request for an award of attorney’s fees in a separate DEP order is denied. RULINGS ON COMPASS’S EXCEPTIONS TO THE RECOMMENDED ORDER Exceptions 1 through 4 to Findings of Fact These related Exceptions object to portions of the ALJ’s Finding of Facts 43, 44, 45, and 47 dealing with an alleged conflict of interest on the part of Dr. Fuleihan. Having decided earlier that commencing ITN discussions with CDM was permissible, and for reasons discussed when denying DEP Exceptions Nos. 2 through 9 and CDM 19 Exception C.2 and D.1 through D.5, these Exceptions are deemed to be moot and nonessential to the final disposition of this case and are therefore denied on procedural grounds. Nevertheless, in the event an appellate court were to reverse the dispositive ruling granting DEP Exception No. 10 and CDM Exception C.1, I also conclude that these Exceptions of Compass are insufficient on their merits. Paragraphs 43-45 and 47 of the RO contain significant findings by the ALJ that: all three vendors knew of Fuleihan’s participation in the ITN and BAFO process; Ardaman would not gain anything due to Mosaic serving as a subcontractor to CDM; Mosaic would only have a limited role on CDM’s team; and Fuleihan did not attempt to influence the BAFO process to the advantage of any particular vendor. The challenged factual findings appear to be reasonable interpretations of and/or inferences drawn by the ALJ from competent substantial evidence of record which I cannot reweigh here. See Heifitz v. Dept. of Business Regulation, 475 So.2d 1277, 1281-82 (Fla. 1st DCA 1985). This competent substantial evidence includes the final hearing testimony of Dr. Fuleihan; DEP Contract Administrator, Gwenn Godfrey; Chief of DEP’s Bureau of Mine Reclamation, Phil Coram; and CDM official, Michael Edgar. (See, e.g., Tr. Vol. 2, pp. 214-16, 257-63; Tr. Vol. 3, pp. 257-63; Tr. Vol. 5, pp. 621-28, 631-49, 666-68; Tr. Vol. 7, pp. 827-31, 848-52; and Tr. Vol. 8, pp. 885-90 ). Compass’s Exceptions to Findings of Fact 43, 44, 45, and 47 are thus denied on both procedural and substantive grounds. 20 EXCEPTIONS TO CONCLUSIONS OF LAW A. Preliminary Statement This portion of Compass’s Exceptions, consisting entirely of argument of counsel, does not take Exception to any page or paragraph of the RO as required by subsection 120.57(1)(k), F.S. Consequently, no ruling on counsel’s Preliminary Statement is required. B. Exceptions 1. Conclusion of Law 77 This Exception of Compass does not find fault with the existing language of the ALJ’s Conclusion of Law 77. Instead, Compass requests that the Secretary of DEP supplement Conclusion of Law 77 with additional language. The suggested additional language would consist of a statutory interpretation by the Secretary of DEP that the role of Fuleihan in the evaluation process contravened the provisions of Sections 112.311, 112.312, and 112.313, Florida Statutes. These cited statutes are a part of the statutory “Code of Ethics for Public Officers and Employees.” For reasons discussed when denying DEP Exceptions Nos. 2 through 9 and CDM Exceptions C.2 and D.1 through D.5, I decline, as unnecessary, Compass’s request to supplement the ALJ’s Conclusion of Law 77. In view of the above, Compass’s Exception to Conclusion of Law 77 is denied. 2. Omitted Conclusion of Law - Standing In this Exception, Compass does not object to any existing finding of fact or conclusion of law in the ALJ’s Recommended Order. Instead, Compass correctly notes that the ALJ did not make a ruling in his RO dealing with Shaw’s standing to file its 21 petition protesting the subject contract award to CDM. Compass requests that this agency Final Order supplement the RO on review by making a legal ruling dismissing Shaw’s petition for lack of standing because it is undisputed that Shaw is the “thirdranked” responder to DEP’s BAFO solicitation. The same Shaw lack of standing claim was raised in DEP’s Exception No. 1 and CDM’s Exception E. Compass’s request that this Final Order dismiss Shaw’s petition for lack of standing is denied for the reasons set forth in my above ruling denying DEP’s Exception No. 1 and CDM’s Exception E, which are incorporated by reference herein. 3. Omitted Conclusions of Law - Disposition Compass’s final Exception deals with the ALJ’s ultimate recommendation that DEP enter a final order determining that its proposed award of the contract to CDM, “which was based upon a review, grading, and ranking of the vendors by an evaluation team that included Dr. Fuleihan, is contrary to its governing statutes, policies, and specifications.” Compass suggests that the Secretary of DEP should supplement the ALJ’s existing recommendation by adding the following language: The Department shall award the contract to Compass and enter into negotiations with Compass without delay. Compass’s request that DEP supplement the ALJ’s recommendation as quoted above is deemed to be moot because this Final Order does not adopt the ALJ’s existing recommendation that DEP’s final order determine that the proposed award of the contract to CDM is “contrary to its governing statutes, policies, and specifications.” Even if the appellate courts were to subsequently agree with the ALJ’s recommendation, I am of the view that the ALJ was correct in not recommending a specific action to be taken by DEP. As note above, it is established case law that the 22 remedy for a violation of contract procurement procedures is “within the sound discretion of the agency.” GTECH Corporation, 737 So.2d at 619; Moore, 596 So.2d at 761. In this contested procurement case, the ALJ did not act as a substitute for DEP and did not have the authority to make a determination to award or reject the bids or proposals de novo. Intercontinental Properties, 606 So.2d at 386; Moore, 596 So.2d at 761. Instead, the ALJ functioned in a review capacity only, and his responsibility did not include a recommendation on how DEP should proceed. Id. at 761; § 120.57(3)(f). I also reject Compass’s attempt to characterize the ALJ’s recommendation as an “omitted Conclusion of Law.” Compass’s final Exception is thus denied. RULINGS ON SHAW’S EXCEPTIONS TO THE RECOMMENDED ORDER Exception Nos. 1 and 2 These Exceptions, dealing with factual findings of the ALJ on the Fuleihan conflict of interest issue unfavorable to both Compass and Shaw, are deemed to be moot for the reasons set forth in my above rulings denying Compass’s Exceptions to Finding of Facts 43, 44, 45, and 47. However, in the event an appellate court were to reverse the ruling granting DEP Exception 10 and CDM Exception C.1, I also conclude these Exceptions of Shaw are insufficient on their merits. The challenged findings in paragraphs 43, 47, and 52 appear to be reasonable interpretations and/or inferences drawn by the ALJ from substantial competent evidence of record, including the testimony of Dr. Fuleihan, Gwenn Godfrey, and Phil Coram Shaw’s Exceptions Nos. 1 and 2 are thus denied on both procedural and substantive grounds. 23 Exception No. 3 Shaw’s third Exception objects to the ALJ’s Findings of Fact 55, 56, part of 72, and part of related Conclusion of Law 78. In these portions of the RO, the ALJ rejects Shaw’s claims that Compass’s proposed water consumption and treatment methods in its BAFO submittal were not responsive to DEP’s Instructions. The ALJ found there was no credible evidence that Compass’s proposed water treatment method would not work. (RO. para. 56) The ALJ also concluded that the BAFOs submittals of CDM and Compass conformed in all [material] respects to the solicitations; and to the extent there were any minor deviations, they were immaterial and did not give Compass or CDM any advantage over Shaw and could be waived by DEP. (RO, para. 72). I conclude that the challenged factual findings and legal conclusions are reasonable interpretations and/or inferences drawn by the ALJ from competent substantial evidence of record. This competent substantial evidence includes the cumulative expert testimony at the final hearing of Phil Coram, Dr. Vaughn Astley, and Craig Kovach. See also Joint Exhibit 4, Attachments 2 and 3; and Joint Exhibit 26. Shaw cites to certain documentary evidence and the testimony of one of its witnesses and employees, John Nance, in support of its contention that the challenged findings and conclusions of the ALJ are erroneous. However, if there is competent substantial evidence to support the ALJ’s challenged findings of fact, it is irrelevant that there may also be competent substantial evidence to support contrary findings. Arand Construction Co. v. Dyer, 592 So.2d 276, 280 (Fla. 1st DCA 1991); Conshor, Inc. v. Roberts, 498 So.2d 622, 623 (Fla. 1st DCA 1986). Accordingly, Shaw’s Exception No. 3 is denied. 24 Exception No. 4 Shaw’s fourth and final Exception objects to the ALJ’s Findings of Fact 67 and part of Finding of Fact 72, and a part of his related Conclusion of Law 78. In these portions of the RO, the ALJ addressed and rejected Shaw’s allegations that the BAFO submittal of CDM was “non-responsive” because it purportedly failed to comply with the portion of the BAFO Instructions pertaining to certain “milestones” in the closure schedule at the Piney Point site. The ALJ found that any omissions or deviations by CDM from the BAFO Instructions dealing with its proposed closure schedule were minor and immaterial and did not give CDM any advantage. (RO, paragraphs 67-72). The ALJ thus concluded that “the evidence does not support a conclusion that the BAFOs submitted by Compass and CDM were non-responsive.” (RO, para. 78). I find these challenged facts and related legal conclusions of the ALJ to be based on competent substantial evidence of record, including the testimony of Phil Coram and Michael Edgar. (See, e.g., Tr. Vol. 1, p. 173; Vol. 8, pp. 902-04); see also CDM’s closure schedule in its BAFO submittal admitted into evidence at the final hearing as the parties’ Joint Exhibit 26. In view of the above, Shaw’s Exception No. 4 is denied. CONCLUSION As noted in the Standard of Review, the Florida courts have historically given special deference to decisions of public agencies involving the solicitation and acceptance of proposals through the competitive procurement process. See, e.g., Culpepper v. Moore, 40 So.2d 366, 370 (Fla. 1949); Baxter’s Asphalt, 421 So.2d at 507; 25 Scientific Games, 586 So.2d at 1131. Thus, the Florida Supreme Court observed over 50 years ago that: So long as a public agency acts in good faith, even though they may reach a conclusion on facts upon which reasonable men may differ, the courts will not generally interfere with their judgment, even though the decision reached may appear to some persons to be erroneous. Culpepper, 40 So.2d at 370. This special deference accorded to public agency decisions should be even greater in this case involving DEP actions arising out of its phosphogypsum “ABATEMENT OF IMMINENT HAZARD” powers under § 403.4154(3), F. S. Under § 403.4154(3), if DEP determines that the physical condition or maintenance of a phosphogypsum stack system “poses an immediate hazard” to the public and/or the environment, DEP is authorized to take prompt action to abate or substantially reduce the imminent hazard, including assuming financial responsibility for remedial action. DEP determined in 2001 that the two Piney Point phosphogypsum stacks posed an imminent hazard under § 403.4154(3) due to the bankruptcy of the owner of the Piney Point fertilizer plant and the bankrupt owner’s notification that it did not have the resources to maintain the site. (RO, paragraphs 6-7). It is undisputed that there are 500 to 550 million gallons of contaminated “process water” estimated to be at the Piney Point site, located only one mile inland from Tampa Bay. (RO, para. 4). It is also undisputed that this process water is very acidic (containing various heavy metals and high levels of nutrients and total dissolved solids), and is even slightly radioactive. (RO, para. 3). Thus, even further deference should be accorded to DEP’s decision to recommend the award of the Piney Point 26 contract to CDM because time is of the essence in this “ABATEMENT OF IMMINENT HAZARD” matter under § 403.4154(3). It is therefore ORDERED: A. The ALJ’s finding in paragraph 33 of the RO that, “if Dr. Fuleihan’s scores were removed from the final tabulation, as requested by Compass, then Compass would be the highest ranked vendor,” is rejected for lack of any supporting competent substantial evidence of record. When Barbara Phillips’ undisputed corrected scores are utilized without including Dr. Fuleihan’s scores, and the ALJ’s unchallenged Findings of Fact 29-32 are applied, CDM and Compass are tied as the highest-ranked vendor and Shaw is third. B. Because it is unnecessary to consider Dr. Fuleihan’s scores to reach the holding of this Final Order, the portions of paragraphs 16-18, 48 through 51, 76-77 of the RO, and endnote 3, construing DEP Directives 202 and 315, a written opinion of DEP attorney, Teresa Mussetto, DEP’s BAFO Instructions, and §§ 287.001 and 287.057(30), F.S., are not adopted in this Final Order. C. The ALJ’s related recommendation that DEP’s final order determine that its proposed award of the contract to CDM, based upon the review, grading, and ranking of the vendors by an evaluation team including Dr. Fuleihan, is “contrary to its governing statutes, policies, and specifications” is also deemed to be dictum and is not adopted. D. As modified and limited in paragraphs A, B, and C above, the Recommended Order (Ex. A) is otherwise adopted by reference herein. E. The petitions of Compass and Shaw are denied. 27 F. The action of DEP staff recommending the award of the Piney Point Phosphogypsum Stack System Management and Closure Contract to CDM, the cohighest ranked vendor, is not “clearly erroneous, contrary to competition, arbitrary, or capricious,” and is hereby AFFIRMED. Any party to this proceeding has the right to seek judicial review of the Final Order pursuant to Section 120.68, Florida Statutes, by the filing of a Notice of Appeal pursuant to Rule 9.110, Florida Rules of Appellate Procedure, with the clerk of the Department in the Office of General Counsel, 3900 Commonwealth Boulevard, M.S. 35, Tallahassee, Florida 32399-3000; and by filing a copy of the Notice of Appeal accompanied by the applicable filing fees with the appropriate District Court of Appeal. The Notice of Appeal must be filed within 30 days from the date this Final Order is filed with the clerk of the Department. DONE AND ORDERED this day of April, 2005, in Tallahassee, Florida. STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION COLLEEN M. CASTILLE Secretary Marjory Stoneman Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 FILED ON THIS DATE PURSUANT TO § 120.52, FLORIDA STATUTES, WITH THE DESIGNATED DEPARTMENT CLERK, RECEIPT OF WHICH IS HEREBY ACKNOWLEDGED. CLERK DATE 28 CERTIFICATE OF SERVICE I HEREBY CERTIFY that a copy of the foregoing Final Order has been sent by United States Postal Service to: Jere Earlywine, Esquire Tew Cardenas LLP 215 South Monroe Street, Suite 702 Tallahassee, FL 32301-1839 J. Andrew Bertron, Jr., Esquire Huey Guilday, Tucker, Schwartz & Williams, P.A. Post Office Box 12500 Tallahassee, FL 32317-2500 Seann M. Frazier, Esquire Greenberg Traurig, P.A. Post Office Drawer 1838 Tallahassee, FL 32302-1838 Dorn C. McGrath, III, Esquire Greenberg, Traurig, P.A. 1750 Tysons Boulevard, Suite 1200 McLean, VA 22102-4208 Ann Cole, Clerk and Donald R. Alexander, Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 and by hand delivery to: Thomas M. Beason, Esquire Marshall G. Wiseheart, Esquire Francine M. Ffolkes, Esquire Brian J. Cross, Esquire Department of Environmental Protection 3900 Commonwealth Blvd., M.S. 35 Tallahassee, FL 32399-3000 this day of April, 2005. STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION J. TERRELL WILLIAMS Assistant General Counsel 3900 Commonwealth Blvd., M.S. 35 Tallahassee, FL 32399-3000 Telephone 850/245-2242 29