March 3, 2009
Mr. Jon Parker, E.I.T.
Phelps Engineering, Inc.
1270 North Winchester
Olathe, KS 66061
ELITE SQUAD TENNIS FACILITY – LIONSGATE MARKETPLACE
PRELIMINARY STORMWATER MANAGEMENT STUDY
14501 METCALF AVENUE
ESR 2009-00005
Dear Jon:
We have reviewed the Preliminary Stormwater Management Study dated
February 25, 2009 for the proposed project. The study is acceptable for Planning
Commission consideration of the Revised Preliminary Plan approval on April 13, 2009.
If you have questions on this approval, please contact me at (913) 895-6009 or by email
at alysen.abel@opkansas.org.
Alysen M. Abel, P.E.
Civil Engineer II
mb
c: Peggy Sneegas, P.E. - Assistant Director, Planning and Development Services
Tony Meyers, P.E. - Supervisory Civil Engineer
David Miller, P.E. - Supervisory Civil Engineer
Michael D. Ackerley, P.E. - Senior Civil Engineer
Pam Fortun, P.E. - Senior Stormwater Treatment Engineer
Dave Dalecky - Planner
Pre-Application File: 54-2008-22 - Tennis Facility at Lionsgate Marketplace