CONTINUING PROFESSIONAL DEVELOPMENT Maximum Period 3 Hours VARIATIONS AND ADDITIONAL WORK NOT PLAIN SAILING By Roger Knowles VARIATIONS AND ADDITIONAL WORK NOT PLAIN SAILING Variation Clauses The variations clause which appears in most standard forms of contract is extremely important from the employer’s point of view where the contract provides for the contractor to construct the works described in the contract for a lump sum. In the absence of a variations clause the contractor’s obligation will be limited to completing the work described in the contract and there will be no obligation to undertake any variations or additional work. It has been argued that if the work is necessary to complete what is described in the contract then the contractor in relation to a lump sum contract will be obliged to undertake the work even though it may not have been referred to in the specifications or shown on the drawings. For example door furniture may not have been specifically referred to in the contract documents but where a contractor enters into a lump sum contract for the construction of say a house it would be implied that the price includes for door furniture. In the case of Williams v Fitzmaurice (1858) it was held that the contractor had an obligation to provide the flooring even though it was not mentioned in the specification. Power to order variations is usually bestowed on the employer by way of a variations clause. Standard Contract Variations Clauses Most of the commonly used standard forms of contract include an extensive variations clause. The normal variations clause will provide power for the employer to call for varied or additional work including additions, omissions, substitutions, alterations, changes in the quality, form, character, kind, position, dimension, level or line. Some of the contracts go even further. In the JCT 1998 contracts provision is made for the addition, alteration or omission of any restriction imposed in the contract such as access to the works, limitation of working space, limitation of working hours and the execution of work in any order. The powers of the employer are usually exercised by somebody on his behalf. Under JCT contacts where the employer is responsible for the design of the works it is the Architect or Contract Administrator whose duty it is to issue instructions regarding variations. Under the ICE conditions it is the Engineer who undertakes the task. Where the contact provides for the contractor to undertake the design it is usually the Employers Agent of Representative who will issue the instructions. Instructions given to the contactor to vary the works should be in writing but some contacts provide for the giving of oral instruction. The clauses which specifically allow for oral instructions to be given need to be fully understood to avoid disputes from arising. It is a requirement of the JCT 1998 contracts that if an instruction to vary the works is given otherwise than in writing, which seems another way of saying if given orally, then the contractor will be obliged to confirm the instruction within 7 days. Hopefully the wording in the confirmation is in keeping with that given orally otherwise the Architect has a further 7 days to dissent. If no dissent is forthcoming the variations as confirmed will take effect. If no confirmation is made by the contractor the Architect can issue his own confirmation at any time up to the issue of the final certificate. Evaluation of Variations and Additional Work To ensure that the contract leaves little to be the subject of negotiations nearly all of the standard forms of contract provide a mechanism for evaluating variations and changes. Wherever possible rates are included in the contract documents which are used for the evaluation of variations and additional works. They are sometimes included in a Bill of Quantities as per JCT 1998 With Quantities and ICE 6th and 7th Editions. Where there is no Bill of Quantities for example JCT 1998 Without Quantities there is often a schedule of rates provided as one of the contract documents which is used for the evaluation of variations and extra works. Difficulties can often occur with contracts where the contractor is required to undertake the design of the works. There is usually no Bill of Quantities or schedule of rates, merely a contract sum analysis which is usually insufficiently detailed to proved specific rates for use in the evaluation of variations and additional work. It is therefore advisable for employers who use contracts of this nature to avoid where possible the giving of instructions for variations and extra works. It is usually the duty of the Architect, Contract Administrator or Engineer to undertake the task of evaluating variations and additional works. The contract rates however will only apply where specifically required by the contract. For example the contract rates only apply where a JCT 1998 or ICE contract is used if the varied or additional work is of a similar character and executed under similar conditions to that described in the contract. If work is of a similar character but is not executed under similar conditions then it will be a matter of applying a PR to the contract rate. Where the character of the work carried out differs from that described in the contract them a fair valuation will be applied. There may be circumstances where work which has not been varied but has been affected by work which has been the subject of a variation. For example additional work may have been instructed which needs to be urgently completed and involves transferring operatives from other parts of the works. This could well affect the productivity or the work from which operatives were transferred. Both the JCT and ICE conditions allow for new rates to be applied to the work so affected in order to compensate the contractor for the additional cost which has resulted from the transfer of the operatives. Daywork Most standard forms of contract provide for the payment of contractors and subcontractors on a daywork basis under certain specified circumstances. Examples are varied work which involves altering work already completed. This usually involves the contractor or subcontractor keeping accurate records of the time spent by the on site labour in carrying out a section of the works together with the materials and plant employed. The contract usually requires the contractor to submit these records to the Architect/Contract Administrator or Engineer at specified times. In the case of JCT contracts the records must be submitted at the end of the week following the week in which the work has been carried out. By way of contrast the ICE conditions require the contractor to submit records on a daily basis. The JCT contracts indicate that it is appropriate for contractors to be paid on a daywork basis if it is not possible to properly measure and value the work. This differs from the ICE conditions which provide for payment on a daywork basis where the Engineer considers it appropriate. Pricing Errors It is not uncommon for contractors to make pricing errors in putting together their tenders. On a lump sum contract the result may be that the price which is submitted is less than would have been the case if the error had not been present. This may be due to say an error in extending a unit price into the total price column. If the error is discovered before the contract is entered into the contractor will normally be given the option of standing by the tender amount which includes the error or withdrawing the tender. It is not usual to allow the contractor to correct the error even if the net result would still leave the contractor with the lowest price. If all the work is subject to remeasure as in the case of ICE 6th and 7th Editions then the extending error whilst affecting the tender sum will due to the work all being remeasured and priced at the unit rates not affect the final account sum. In other words the contractor will not suffer from the extending error. Pricing Errors Affected by Variations The contractor may include in his tender an incorrect unit rate which may have been priced too high or too low. If the error is not identified during the tender vetting stage and the contractor’s tender price included in the contract along with the error then the contractor will either suffer the loss or derive a benefit. The contractor’s loss or gain can be further affected if the item of work is subject to a variation in quantity. Contractors often argue where the contract includes a pricing error which fixes the rate at too low a level that the low rate only applies to the quantity of work included in the contract and that any excess quantity should be priced at a fair rate. This argument was proved to be unsound by the decision in the case of Dudley Corporation v Parsons and Morrin Ltd (1959). The contract terms were RIBA 1939 form where the evaluation of variations was dealt with in a manner similar to JCT 1998. In this case the contractor priced an item for excavating 750 cubic yards of rock for a lump sum of £75 i.e. two shillings per cubic yard. Unfortunately this was a gross undervaluation. More rock was encountered during the excavation process than was anticipated and the final total came to 2230 cubic yards. The architect valued 750 cubic yards at the two shillings rate in the contract and the balance at £2 per cubic yard. It was held by the Court of Appeal that this was incorrect and that the contract rate of two shillings per cubic yard should apply to the full 2230 cubic yards. A similar situation occurred in the case of Henry Boot Construction v Alstom Combined Cycle (2000) but in this case the rate included in the contract due to an error in the pricing of sheet piling was too high. Alstom was the employer for the construction of a combined cycle gas turbine power station at Connahs Quay. Boot carried out the civils work employing the ICE 5th edition conditions. In post tender negotiations Boot submitted a price of £250,880 for additional and different temporary work in connection with the lowering of cold water pipework. This extra work formed part of the contract. In calculating this figure Boot had made an error when pricing the sheet piling, the result of which produced a sum much higher than it should have been. This error remained undetected during post tender negotiations pre-contract negotiation. A variation was issued during the course of the work which involved more sheet piling. Boot extrapolated the rate from the £250,880 lump sum for the sheet piling work at the inflated rate. This would if accepted provide a windfall for Boot. The Court of Appeal found in favour of Boot. Its reasoning was that the parties had agreed the rate and were as a result stuck with it; the mistake was irrelevant. A third case Aldi Stores v Galliford (2000) involved an argument concerning varied quantities but was unconnected with a pricing error but more related to tactical pricing The price for the work included disposing of contaminated material to a licensed tip at a rate of £44.50 and the disposal of clean material at a rate of £8.50. During negotiations Galliford agreed to absorb the rates for the disposal of both clean and contaminated material in the overall price for the work. The rate for the disposal of both clean and contaminate material was thus nil. When the work got underway it transpired that all the excavated materials were contaminated and had to be disposed at the licensed tip. The contractor claimed that there had been a variation and with it an entitlement to revisit the rates for the disposal of the excavated material. It was held by the court that as there was no change in the conditions under which the work had been carried out the contractor was held to the price in the contract for disposing of the contaminated material which was nil. Loss of Profit on Work Omitted Contractors often argue that where work is omitted from the contract they lose an opportunity of earning the profit element which was built into the value of work omitted. This being the case they claim from the employer the loss they allege they have suffered. Whether they are entitled to this loss of profit will to a large extent depend upon the wording of the contract and whether the work has truly been omitted or merely omitted from the contract with arrangements made for it to be undertaken by others. Many years ago when JCT 63 was extensively used it was a relatively simple task to recover loss of profit when work was omitted. Clause 11(6) includes an entitlement for the contractor to be paid any direct loss and or expense which results from the issue of a variation. Loss of profit would certainly fall within the ambit of direct loss and expense. JCT 1998 however does not include this clause or anything like it. The wording of the variations clause indicates that where work is omitted the omission will be valued at contract rates where work is of a similar character executed under similar conditions and does not significantly change the quantities. If as a result of the omission there is a significant change in quantities then the contractor is entitled to be paid a fair allowance for the change in quantities. It may therefore be successfully argued that the omission of work significantly changes the quantities and as a result the loss of profit on the omitted work would form part of the fair allowance. A similar case can be made out where ICE 5th and 6th editions are employed. In these contracts the engineer has power to change rates or prices for any items of work in the contract which are rendered inapplicable due to the varied work. The argument would run that the rates may be rendered inapplicable for the remainder of the work due to the omission and therefore a re-rating would be appropriate which would include loss of profit on omitted work. This is probably the best argument which contractors could use albeit somewhat tenuous, in the absence of a JCT 63 type clause. The situation however is very different when work is omitted and given to other to undertake. This often occurs where the employer is looking to save cost and takes bite size chunks out of the contract to enable others to carry out the work at cheaper prices. The matter came before the courts in Australia, where the construction industry is run on similar lines to the UK, in the case of Carr v J A Berriman (1953). In this case the court held that if work is omitted from the contract and given to others to carry out the contractor is entitled to be paid loss of profit. The reasoning being that the contractor is entitled to undertake all the work in the contract unless the terms state otherwise. In transferring work to others the employer is in breach of contract and loss of profit would form part of the damages which would become payable. In Amec Building Ltd v Cadmus Investments Co Ltd (1996) the contractor claimed for loss of profit in relation to a provisional sum which was omitted from the contract and the work given to others to undertake. Amec claimed for loss of profit and referred the matter to arbitration. The arbitrator found in favour of Amec and the matter was then referred to the court by Cadmus. In finding in favour of Amec the judge stated: It seems to me that the arbitrator was perfectly correct in deciding that such an arbitrary withdrawal of work from the provisional sums and the giving of it to the third party was something for which Amec were entitled to be compensated and the compensation that he arrived at namely the loss of the profit having accepted figures put forward to him in evidence is one which is not open to be impugned on appeal as a matter of law. When Does a Variation Become a Separate Contract? Contractors who find themselves with contracts which have been the subject of extensive change and where they are consistently losing money often look for a quick way out of the dilemma. One route which has found limited success is to argue that due to extensive extra work or all of the work carried out being so fundamentally different from what the contractor contracted to undertake then either the extra work or all of the work represents a new contract. This being the situation the contactor, if the argument succeeds, will be entitled to payment on a quantum meruit basis and not be tied to the rates referred to in the variation clause. Standard Forms of Contract The standard forms of contract try to circumvent this argument before it is raised. The ICE conditions state that no variation shall vitiate or invalidate the contract. Similar wording exists in the JCT Forms which state that no variation required by or subsequently sanctioned by the Architect shall vitiate the contract. The intention behind the wording is that no variation will have the effect of creating a separate contract. Whilst this may be the intention, in the final analysis it will be the court or tribunal who decides whether or not a separate contract arises out of the varied work Legal Precedence There have been a number of cases where this matter has been placed before the court for a decision. Thorn v London Corporation (1876) In this case the judge said “if the additional or varied work is so peculiar so unexpected and so different from what any person reckoned or calculated on, it may not be within the contract at all” A mere increase in the quantities of the work will not invalidate the original contract even though substantial. The work ordered must be totally different from that contracted for and this being the case the contractor will be entitled to payment on a quantum meruit basis and not the contract rates. Bush v Whitehaven Trustees (1888) In this case a contractor undertook to lay a water main and divert certain streams on the understanding that the work would be carried out in the month of June, Due to delays on the part of the employer the contractor was unable to proceed before the winter when wages were higher and the works more difficult due to the weather conditions. The court held that these changed circumstances were such that the contractor became entitled to payment on a quantum meruit basis. Blue Circle v Holland Dredging (1987) A contract was let under the ICE 5th Edition for dredging work in Lough Larne. The dumping of the dredged material was to be in areas agreed with the local authority. A variation was issued to facilitate the dumping of the dredged material to form a bird island. It was held that as the island construction was completely outside the original dredging Holland was not obliged to accept the work as a variation. Hence the island became the subject of a separate agreement. McAlpine Humberoak v McDermott International (1996) In this case a contract was let for the construction of four huge pallets in connection with the construction of an oil rig. The number of drawings used increased from 22 which were available at tender stage to 161 for the construction of the work. In addition the contractor raised many TQs (technical queries) in relation to the drawings. The lower court held that the changes were so extensive that the old contract had been replaced. When the dispute was referred to the Court of Appeal a different view was taken when it was decided that the changes fell within the variations clause. Costain Civil Engineering Ltd v Zanen Dredging and Contracting Co Ltd (1996). This case arose out of a subcontract in connection with the construction of a tunnel under the River Conway. The subcontract employed was the ICE Blue Form of Subcontract and the work comprised site preparation and dredging operations. A part of the work was the backfilling of a casting bay which had been used for the construction of the concrete units which formed the tunnel. It was decided that rather than backfilling the casting bays the void would be used to construct a marina. It was argued that the work relating to the marina should be valued at contract rates with an uplift of around 10%. The judged ruled that the marina was not a variation but a separate contract and that this method of valuing the works was not appropriate. Cautious Approach It would appear that it is only in the most exceptional circumstances that an argument that the work as carried out represents a separate contract will succeed. In any event if a contractor is to be successful with this type of claim it is essential that he takes some form of stand at the earliest moment. The continued execution of the work, without protest, on the terms of the contract, for example the payment provisions and applications for extensions of time, may render it difficult for the contractor to subsequently argue that the contract has no application. Quantum Meruit Where it is decided that work does not fall within the original contract or where all of the work is so radically different that none of the work is covered by the original contract then payment will be due on a quantum meruit basis. Where this occurs it would not be appropriate to regard the work as though it had been performed to any extent under the contract. Keating on Building Contracts 7th Edition as at 4-26 makes it clear that payment should be made at fair commercial rates. Standard Questions and Model Answers Standard Questions 1. How does a variations clause benefit an employer where the contract is a lump sum contract? 2. Give examples of some of the undertakings required by variation clauses which appear in standard forms of contract. 3. How do the JCT contracts deal with variations where the instruction is given other than in writing? 4. What are the basic rules for valuing variations on a JCT contract? 5. How do standard forms of contract usually deal with the matter of payment of the contractor on a daywork basis? 6. What is the effect on the contractors financial position if the contractor when preparing his tender makes an arithmetical error and as a result the tender is lower than otherwise would be the case 7. A contractor includes in a tender where a Bill of Quantities is uses a rate which due to an error is either much higher or lower than it should be. If the quantities of the item substantially increase should the incorrect rate still be used? 8. Where work is omitted from the contract will the contractor be entitled to recover loss of profit? 9. Under what circumstance may a variation be dealt with as a separate contract Model Answers 1. Where a contract is let which has no variations clause to carry out work for a lump sum, the contractor will be obliged to construct the work described in the contract for the lump sum and will be under no obligation to carry out variations to the works as instructed by the employer or agent acting on his behalf. If the contractor agrees to carry out additional work he will be able to successfully argue that the work constitutes a separate contract and therefore will not be held to the rates and prices in the original contract. Where the contract contains a variations clause the employer has a right to have instructions issued whereby the contractor is obliged to undertake extra or varied work at the rates referred to in the variations clause. 2. Examples of obligations conferred on the contractor in some of the variation clauses which appear in standard forms of contract: Varied or additional work including additions, omissions, substitutions and alterations Changes in the form, quality, character, kind, position, dimension, line or level Alteration, addition or omission of any restriction imposed in the contract, such as access to the works, limitation of working space and hours and the execution of work in any order. 3. If an instruction is given otherwise than in writing such as a verbal instruction then the contractor must confirm the instruction in writing within 7 days. Once the instruction has been confirmed then the Architect/Contract Administrator has a further 7 days to dissent from what has been confirmed. If no dissent is forthcoming the variation as confirmed will take effect. 4. Where ever possible rates included in contract documents are intended for use when evaluating variations. The contract rates may be set out in a Bill of Quantities or a schedule of rates. These rates are used for evaluating variations where the work is of a similar character and executed under similar conditions as those described in the contract. If work is of a similar character but is not executed under similar conditions then it will be a matter of applying a PR to the contract rate. Where the character of the work carried out differs from that described in the contract them a fair valuation will be applied. 5. Most standard forms of contract provide for the payment of contractors and subcontractors on a daywork basis. This usually involves the contractor or subcontractor keeping accurate records of the time spent by the on site labour in carrying out a section of the works together with the materials and plant employed. The contract usually requires the contractor to submit these records to the Architect/Contract Administrator or Engineer at specified times. In the case of JCT contracts the records must be submitted at the end of the week following the week in which the work has been carried out. By way of contrast the ICE conditions require the contractor to submit records on a daily basis. The JCT contract indicates that it is appropriate for contractors to be paid on a daywork basis if it is not possible to properly measure and value the work. This differs from the ICE conditions which provide for payment on a daywork basis where the Engineer considers it appropriate. 6. It is not uncommon for contractors to make pricing errors in putting together their tenders. On a lump sum contract the result may be that the price which is submitted is less than would have been the case if the error had not been present. This may be due to say an error in extending a unit price into the total price column. If the error is discovered before the contract is entered into the contractor will normally be given the option of standing by the tender amount which includes the error or withdrawing the tender. It is not usual to allow the contractor to correct the error even if the net result would still leave the contractor with the lowest price. If all the work is subject to remeasure as in the case of ICE 6th and 7th Editions then the extending error whilst affecting the tender sum will, due to the work all being remeasured and priced at the unit rates, not affect the final account sum. In other words the contractor will not suffer from the extending error. 7 There have been two high profile cases which involve a situation where the contractor includes in his tender a pricing error. In the case of Dudley Corporation v Parsons and Morrin Ltd (1959) the rate for excavating in rock was too low whilst in the case of Henry Boot Construction v Alstom Combined Cycle (2000) the rate for sheet piling was too high. In both cases tenders had been prepared using a Bill of Quantities. When the final quantities were measured due to variations they showed a substantial increase compared with the quantities in the Bill of Quantities. As a result Parsons and Morrin sustained a substantial loss whilst Henry Boot enjoyed a windfall profit. It was argued that all quantities in excess of those in the Bill of Quantities should be priced on a fair valuation. The court held in both cases that the wording of the contracts were such that the parties had agreed that variations would be valued at rates in the Bill of Quantities and this would remain the case even if the rates contained substantial errors. This principal will apply if the contract used is one of those commonly employed on construction contracts such as JCT and ICE. 8. Where work is omitted from the contract it is not uncommon for contractors to claim for loss of profit. For contractors to show an entitlement it is necessary for them to identify a clause in the contract under which they are entitled to be paid. Many years ago when JCT 63 was extensively used it was a relatively simple matter to recover loss of profit when work was omitted. Clause 11(6) includes an entitlement for the contractor to be paid any direct loss or expense which results from the issue of a variation. Loss of profit would certainly fall within the ambit of direct loss and expense. JCT 98 and 05 do not include this clause or anything like it and the same applies to the ICE conditions. It would therefore be difficult where these conditions apply for contractors to successfully claim for loss of profit. A case on a tenuous basis can however be made out under JCT 98 and 05 and the ICE conditions for loss of profit. These contracts allow for the rates for work to be altered if there is a significant change in quantities (JCT) or the rates rendered inapplicable (ICE) due to omissions. The argument would run that omissions should trigger off the use of these entitlements and lend weight to a case for loss of profit. It has been decided by the courts, that where work is omitted from the contract and arrangements made to have it carried out by others, then the contractor is entitled to be paid for loss of profit. This applies even if the work omitted is the subject of a provisional sum. The decisions in Carr v JA Berriman (1953) and Amec Building v Cadmus (1996) dealt with the point of legal principal that to take out work which is included in the contract and give it to others to carry out amounts to a breach of contract. 9. Contractors who find themselves with contracts which have been the subject of extensive change and where they are consistently losing money often look for a quick way out of the dilemma. One route which has found limited success is to argue that due to extensive extra work, or all of the work which has been carried out being so fundamentally different from what the contractor contracted to undertake, then either the extra work or all of the work represents a new contract. This being the situation the contactor, if the argument succeeds, will be entitled to payment on a quantum meruit basis and not be tied to the rates referred to in the variation clause. Examples of variations which the courts have held to be separate contracts include: A contract was let on the basis that the laying of a water main and diverting streams would be carried out in June. Due to delays on the part of the employer the work could not be carried out until later in the year. As a result of the delay the contractor experienced losses due to higher wages and more difficult working conditions. It was held by the court that the changes rendered the work to be the subject of a new contract. Bush v Whitehaven Trustees (1888). In the case of Blue Circle v Holland Dredging (1987) a contract was let for dredging work in Lough Larne. The dumping of the dredged material was to be in areas agreed with the local authority. A variation was issued to facilitate the dumping of the dredged material to form a bird island. It was held that as the island construction was completely outside the original dredging Holland was not obliged to accept the work as a variation. Hence the island became the subject of a separate agreement. The case of Costain Civil Engineering Ltd v Zanen Dredging and Contracting Co Ltd (1996) arose out of a subcontract in connection with the construction of a tunnel under the River Conway. The subcontract employed was the ICE Blue Form of Subcontract and the work comprised site preparation and dredging operations. A part of the work was the backfilling of a casting bay which had been used for the construction of the concrete units forming the tunnel. It was decided that rather than backfilling the casting bays the void would be used to construct a marina. It was argued that the work relating to the marina should be valued at contract rates with an uplift of around 10%. The judged ruled that the marina was not a variation but a separate contract and that this method of valuing the works was not appropriate.