Standard IMA Updates

advertisement
BLUE PLAINS REGIONAL COMMITTEE (BPRC)
Standard IMA Updates for August 23, 2007
Note: ‘Actual Flow’ - Each jurisdiction is asked to include their current ‘IMA Actual Flow’ figure as
of the end of July (if available) in their jurisdictional reports.
TABLE 1 – May-June-July
JURISDICTION (May) / Values
District
WSSC
(May)
(May)
FLOW PARAMETERS
Blue Plains Total
(May)
Monthly Average [MA]
Rolling 12-month Average
Flow [RAA]
298 MGD
134.208 MGD
120.379 MGD
28.182 MGD
313 MGD
143.212 MGD
145.416 MGD
(July 06)
125.049 MGD
126.279 MGD
(July 06)
29.346 MGD
28.199 MGD
(Feb 07)
IMA ‘Actual Flow’
n/a
Additional Information
Fairfax
(May)
1.75 inches rain (National Airport)
JURISDICTION (June) / Values
District
WSSC
(June)
(June)
FLOW PARAMETERS
Blue Plains Total
(June)
Monthly Average [MA]
Rolling 12-month Average
Flow [RAA]
297 MGD
140.045 MGD
113.586 MGD
27.671 MGD
310 MGD
141.985 MGD
145.416 MGD
(July 06)
123.083 MGD
29.312 MGD
126.279 MGD
29.312 MGD
IMA ‘Actual Flow’
n/a
Additional Information
Fairfax
(June)
1.38 inches rain (National Airport)
JURISDICTION (July) / Values
District
WSSC
(July)
(July)
FLOW PARAMETERS
Blue Plains Total
(July)
Monthly Average [MA]
Rolling 12-month Average
Flow [RAA]
288 MGD
142.738 MGD
105.344 MGD
25.593 MGD
306 MGD
140.489 MGD
143.295 MGD
(August 2006)
121.326 MGD
125.759 MGD
(August 2006)
29.013 MGD
29.312 MGD
(June 2007)
IMA ‘Actual Flow’
Additional Information
n/a
Fairfax
(July)
2.40 inches rain (National Airport)
Notes:
‘Actual Flow’ - Each jurisdiction includes their current IMA ‘Actual Flow’ figures as of the end of the previous
month (when available) in their jurisdictional reports.
District – Availability of flow information for the District is subject to reporting by ALL users to DC-WASA no
later than 20 days after the end of each month, at which time DC-WASA compiles and distributes the BPSA
report within 5 days.
BPRC Standard IMA Updates
August 23, 2007
Page 2 of 2
TABLE 2 – May-June-July
BLUE PLAINS
OPERATIONS/PROGRAMS
BNR Operations
Total Nitrogen (mg/l)
Biosolids Management
Program
(wet tons per day)
Overall Plant Operations
CSO LTCP Implementation
Egg-shaped Digesters
Water
Conservation/Wastewater
Reduction Efforts
(Quarterly)
PI Odor Control Project
(Periodic)
COMMENTS
Performance was impacted
because three of the twelve
nitrification-denitrification reactors
were out of service due to pipeline
leaks. Repairs are underway.
VALUES
May data:
Monthly –
6.6 mg/L
RAA –
6.3 mg/l
Monthly –
1284 wt/d
Normal operations; normal
RAA –
production.
1261 wt/d
Normal operations; All permit conditions met.
VALUES
June data:
Monthly –
6.8 mg/L
VALUES
July data:
Monthly –
6.6 mg/L
RAA –
6.4 mg/l
Monthly –
1061 wt/d
RAA –
1239 wt/d
RAA –
6.4 mg/l
Monthly –
1133 wt/d
RAA –
1240 wt/d
Nothing new to report.
The DC-WASA Board of Directors rejected the single bid received and placed
the project on hold until a more favorable bidding environment is experienced
(possibly two to three years). In the interim, WASA will monitor the
construction bidding environment, regulatory initiatives affecting land
application, and monitor evolving wastewater treatment technologies.
Nothing new to report.
Design on the three sites in Maryland was essentially complete by late
November, 2006. When final plans were submitted to NPS (both C&O Canal
and GWMP Parks), despite having seen the designs numerous times during
the last several years, NPS staff identified major design issues that would
necessitate major redesign and additional costs. DC-WASA management
intends to escalate the issues to higher levels of NPS management.
Concurrently, WASA is conducting a review of the basis of design for the odor
control process in light of numerous cost escalations and schedule delays.
MM#4-BPRC Standard IMA Updates - May-June-July for 082307
Download