E2022 Supplemental Environmental Assessment1 Extension of Dennery River Flood Mitigation Works Disaster Management Project II, Additional Financing July 31, 2008 Introduction and Background The Second Disaster Management Project (DMP II) was made effective in October 27, 2004. Under that project, flood mitigation works located along the Dennery River were rehabilitated to improve flood protection against hurricane related storm surge for the village of Dennery. The works consisted of the restoration of approximately 150 meters of an existing flood mitigation levee located along the northern margin of the Dennery River extending east to Dennery Bay. These works consisted of the rehabilitation of the earthen berm restoring it to its design height and the installation of rock armor along the levee’s river side exposure. During the construction of this earthwork, an engineering assessment was performed to evaluate the adequacy of the existing system and concluded that that, while helpful, these works did not provide adequate flood protection from foreseeable extreme storm events. The assessment recommended the construction of an additional 100 meters of levee completing the system from the bay to the Dennery River Bridge. The completion of this system will close the remaining flood protection gap and greatly improve the operation and security of the flood protection system. Existing Situation Dennery is a fishing village located on the east coast of St. Lucia. It is characterized as an agricultural community of low to moderate income. The community is highly vulnerable to storm surge and hurricane forces and, in the past, has suffered severe damages from flooding and storm related forces. During the initial World Bank financed Disaster Management program (Emergency Recovery and Disaster Management Project), a study was undertaken which recommended that a sea defense system be constructed to protect the village from future storm related events. The system was also designed to reclaim eroded beach area along the Dennery bay, an area where past hurricanes had removed some 20 meters of beach front over a 40 year period. Under DMP II, the sea defense works were completed and included the construction of a 415 meter long buried revetment and the construction of three offshore breakwaters. In addition, river flood defenses were rehabilitated to mitigate storm surge flood exposures along the southern end of the village. This has been a source of flooding which had historically resulted major damages to the village. These defenses consist of a levee system extending from the bay for 1 The original EA is dated Feb. 26, 2004. some 150 meters along the northern bank of the Dennery River. The works are approximately 4 meters high and approximately 6 meters wide. The levee is of earth construction and is covered with rock armor protecting the river exposure of the structure. An additional 100 meters of river bank remain unprotected, extending from the western end of the existing structure to the Dennery river bridge. According to engineering calculations performed during the rehabilitation work, this gap still allows for the potential of catastrophic flooding under foreseeable major storm event conditions. With the availability of funding provided under the Additional Financing agreement, the Government of Saint Lucia elected to take the opportunity to complete the flood control works in order to maximize protection for the community. Description of the Project Under this project, approximately 100 meters of levee will be constructed along the northern bank of the Dennery River. The works will extend the existing levee closing the final gap in the flood protection system along that river. The levee will be of the same design as the existing system consisting of an earthen berm with rock armor on the river exposure approximately 4 meters high and 6 meters wide. Construction will involve the placement of fill material along the river bank using a combination of heavy equipment and hand labor. Work is expected to take some six (6) months. Construction material will be transported from Government approved quarry facilities and trucked to the construction site. The work is confined to the river embankment and no changes to the flow dynamics of the river system will be made. Once levee construction is completed, the contractor will stabilize the works with erosion control vegetation as approved by the Ministry of Communications, Works, Transport and Public Utilities (MCWT&PU). Project supervision will be under the direction of MCWT&PU as was the case with the initial rehabilitation works. Description of the Environment The construction area on the north bank passes through several parcels of private land which are characterized as idle agricultural lands or old-field environment. These lands have not been in active production for several years and are overgrown with grasses and shrubs as well as pioneer coconut palms. The south bank of the river is the principal flood plain and is composed of mangrove wetlands. This area will not be disturbed during construction. No structures are located in the construction area and lands surrounding the works are privately owned. Social Issues During the design of the works planned under this project, initial surveys identified that the works would be constructed on private lands. This triggered Bank safeguard Involuntary Resettlement OP/BP 4.12. During preparation, the PCU, with the assistance of the team’s social development specialist, designed a compliance program to be implemented by the Government of St. Lucia for the execution of a land acquisition program. The government has complied in all respects with this plan and all lands required for the project are now owned by the Government. During the execution of the plan, the government took several meetings with the community and the landowners to explain the project and its goals and impacts. The plan was well received by the community and the community is looking forward to the completion of the works. Anticipated Environmental Impacts The impacts resulting from the project are wholly beneficial to the community as the works will serve to mitigate the impacts from potential flooding during storm events. Negative impacts such as noise, dust generation, erosion are typical of those associated with small construction works. A framework is already in place with the project to manage such impacts through the addition of environmental performance clauses to the works contract. Negative impacts associated with the project will be confined to the construction phase and are temporary in nature. No non-mitigatible negative impacts have been identified in association with these works. Environmental Management Consistent with the requirements of DMP II as presented in the project operations manual, environmental management will be accomplished through the use of contract environmental compliance clauses and a plan for periodic inspection on the part of the Government of Saint Lucia to ensure compliance. This system has been used throughout the Disaster Management Project and has worked well with previous construction works. In addition to the implementation of good practices during the construction phase, the contractor will be required to hold periodic meetings with the community to apprise them of activities to be expected. An inception meeting will be held prior to the start of construction to present the construction program plan. The PCU will take advantage of this meeting to coordinate with the Ministry of Physical Development in reinforcing the need to maintain vigilance over public lands and prohibit illegal occupation of reclaimed lands created with the construction of the sea defenses under DMP II. Specifically, the following environmental activities will be undertaken to ensure the project proceeds as planned: The Contractor together with the Government of Saint Lucia will hold an initial meeting with the Dennery community to present the construction plan. The contractor shall schedule periodic meetings with the community to apprise them of progress and any changes to the program that may occur once construction has begun. MCWT&PU together with the PCU shall develop a maintenance plan for the river defense works to include community responsibilities and present this plan to the community representatives. This plan shall assign specific responsibilities for system maintenance and shall be developed as a formal agreement between the community and National Government. During the construction phase, MCWT&PU shall supervise and report on work progress and environmental compliance. Inspections will be made biweekly as construction progresses. Copies of field reports shall be provided to the PCU. The Ministry of Physical Development (MOPD) shall maintain vigilance over the completed works to ensure that future illegal encroachment does not occur to damage or affect the performance of the levee system. MCWT&PU will provide the contractor with approved specifications for slope stabilization and re-vegetation so as to ensure erosion is properly controlled. Reporting and Bank Supervision Progress reports shall be filed with the PCU during the execution of the works. Bank supervision and surveillance will be conducted during the regular supervision missions planned for the execution of the Additional Financing phase of the DMP II project.