F. DETAILED ENGINEERING DESIGN SERVICES FOR THE

advertisement
F. DETAILED ENGINEERING DESIGN SERVICES FOR THE
UPGRADING OF THE SWIP WORKSHOP
TERMS OF REFERENCE
Background
1.
The Government has identified solid waste in [] as a
priority problem and has requested the World Bank to assist
in the implementation of the Proposed [] Solid Waste
Management Project ([]). The objectives of the [] are: (1)
to improve the efficiency of collection and disposal of solid
waste and (2) to improve the environmental conditions in [],
through the utilization of waste transfer stations in
collecting solid waste, the adoption of the sanitary landfill
method of disposal, and the eventual closure of all open
dumps in [].
2.
One
of
the
problems
inherent
in
the
collection/transport, transfer and disposal system is the
lack of facilities or depots for major repair and maintenance
works
for
government-owned
compactor
trucks,
storage
containers/trailers and other types of collection vehicles,
as well as transfer station and sanitary landfill vehicles
and equipment that require such services.
3.
In light of the lack of facilities and, more
importantly, in order to protect its capital investments, the
Government has decided to include in the proposed [] a
component for the rehabilitation and upgrading of the
existing Solid Waste Improvement Project (SWIP) Workshop to
serve as a repair and maintenance facility primarily for
those vehicles and equipment acquired with World Bank
financial assistance and secondarily, for certain qualified
government-owned vehicles and equipment that would require
regular and periodic servicing and maintenance as part of an
approved preventive maintenance program.
4.
The SWIP Workshop/Depot is located at a _____ square
meter site located at [] in []. It was a component of the
World Bank- assisted SWIP Program which was implemented in
19__ and was intended to be a repair and maintenance depot
for 10 compactor trucks, 6 arm roll trucks and the containers
that were acquired with the vehicles during that time.
It
was then projected that the depot had been able to service 50
units (including container vans) under the SWIP Program.
5.
At present, the depot is additionally being used as a
garage workshop for 116 units of various collection/storage
equipment under a JICA grant. Repair and maintenance works
are performed on these equipments when needed.
6.
It is anticipated that in the future additional units
of vehicles/equipment under other grants/loans will be
serviced by the SWIP Workshop. There is therefore a need to
re-assess the utilization of the workshop considering space
limitations as dictated upon by the size of the property.
7.
With the projected volume of servicing required, it is
anticipated that the SWIP Workshop will have inadequate
repair and maintenance facilities and personnel to operate
the facility when it is utilized at its maximum capacity.
8.
It is to fill this need that the upgrading of the SWIP
workshop was conceived to become a part of the [] for which
World Bank-assistance is being sought.
Objectives
9.
The Consultant shall adequately address the following
objectives
in
performing
investigations
and
surveys,
engineering analysis and design work:
a. The workshop shall have the capability to service, repair
and maintain collection vehicles, transfer station and
sanitary landfill vehicles and equipment acquired with
World Bank financial-assistance.
b. Solution of the surface drainage problem in the facility.
Elimination of ponding of rainwater on the central
pavement and the management of spillage from lubricants,
oils and fuel.
c. Repair of the pavement cracks and damage throughout the
facility including regrading and repaving and other
remedial works as required.
d. Provide a ramp for under chassis repair and maintenance
for all trucks and other vehicles being serviced in the
facility.
e. Provide
for
adequate
workshop
office
considering projected increase in activities.
facilities
f. Provide for driver/mechanic quarters, adequate working and
washing bays and storage areas. Upgrade or improve these
facilities as required.
g. Ensure that work bays have adequate vertical clearance in
order to accommodate larger compactor trucks and container
vans for servicing.
h. Provide for adequate infrastructure support facilities
such as for domestic water supply and sanitary sewage,
stormwater drainage, lighting, power and communication
systems.
i. Provide for adequate parking space for the fleet of
vehicles and equipment that will be serviced in the
facility.
j. Design the facilities so that they will have a minimum
life of 25 years and be able to withstand seismic events.
k. Ensure that all demolition, rehabilitation and reconstruction plans and phasing are clearly specified,
details clearly drawn, and safety and quality control
measures fully identified.
Scope of Services
10.
Pre-design Services
10.1
Review of Available and Site-specific information.
Review all available documents and plans of the
existing
facility
to
obtain
a
thorough
understanding of the existing functions, space
allocation, and physical infrastructure provided
at the site. The review shall be complemented by
a detailed survey of topographic characteristics,
drainage and sanitation conditions, water supply,
fire protection, electrical supply, road and
traffic conditions, and communications facilities.
10.2
Develop Site-specific Data.
Establish from the
survey
the
extent
of
repair
work
or
rehabilitation/reconstruction
of
basic
infrastructure
needed
for
the
upgrade;
and
perform, as needed, topographic surveys, soil
borings, geophysical tests, non-destructive and
destructive structural tests and identification of
all underground utilities (i.e. water lines, storm
drains, sewer lines, gas lines, electric and
telephone lines) and existing structures that have
a bearing on the upgrade design.
Special attention shall be given to the structural
evaluation
of
existing
buildings'/structures'
capacity for expansion and additional loads as the
case may be.
10.3
Analysis of Pre-design Data. Analyze
information gathered and data generated
in
the
the
above
tasks
and
evaluate design conditions.
Provide a report on the engineering analysis,
complete with the identification of design issues
and needs. Meet with client to discuss analysis.
10.4
Develop Alternative Design Concepts.
Develop a
minimum of three layouts and process design
schemes for the upgrade design. Consider volume,
condition and qualifications of serviced vehicles
and
equipment
based
on
developed
criteria.
Consider also the limitations of the site.
The
alternative layout and process design schemes
shall be prepared in sufficient detail to provide
preliminary
engineering
estimates
for
each
alternative scheme.
Meet with the client to
discuss
alternative
schemes
and
select
a
recommended scheme.
10.5
Conduct Environmental Impact Assessment.
Prepare
an environmental impact assessment to meet DENR
and
other
relevant
authority's
requirements.
Include impacts on traffic, noise, odor, dust,
aesthetics, drainage and human settlements.
10.6
Finalize Design Concepts.
Based upon the review
comments from associated agencies and the client,
finalize design concepts as appropriate.
11.
Detailed Engineering Design Services.
11.1
Process Design.
Develop the workshop's detailed
process design considering all design parameters,
criteria and requirements stipulated by the client
and
incorporate
findings,
conclusions
and
decisions
developed
during
the
Pre-design
Services.
11.2
Site
Development
Works
Design.
Perform
engineering analysis and designs for upgrading
and/or reconstruction of civil works to include
the following:
a. demolition plan which involves those sections of the
workshop which have to be taken down or removed to allow
new structures or members to be constructed.
b. site preparation such as clearing, earthwork excavation
and filling, removal of demolition debris, grading and
compaction, as needed.
c. all-weather onsite driveway, working pavements and parking
areas
to
meet
design
loads
and
standards
of
vehicles/equipment being serviced.
d. an efficient and safe on-site traffic circulation and
parking system for vehicles/ equipment being received,
documented, serviced and released, and those required to
be garaged at the facility for a prescribed number of
days.
Include appropriate pavement markings, control
signs and other traffic control devices.
e. main
office
building,
storage
and
workshop
bays,
fueling/lube stations, hydraulic lifts, workers' quarters,
canteen and other amenities.
f. drainage system.
g. water
supply,
sanitary
sewerage
system
including
facilities for treatment of wash-water as may be required.
h. fire
protection
system
including
extinguishers to put out fire.
water
supply
and
i. washing facilities.
11.3
Electro-Mechanical
Works
Design.
Perform
engineering analysis and undertake upgrade and/or
reconstruction
design
for
the
following
electro-mechanical works:
a. all electro-mechanical works for the workshop bays
including air and lube equipment, hydraulic lifts, tire
equipment, power and mechanical tools, fuel storage tanks,
fuel equipment, etc.
b. electrical power and distribution system.
c. heating, ventilation and air-conditioning (HVAC) system.
d. traffic management controls.
e. wash bays/enclosures.
f. communication system.
g. fire alarm/protection system.
h. workshop overhead cranes.
Provide an operations and maintenance manual for the
functional use of the electro-mechanical works other than
those that are normally provided by the manufacturers/
suppliers for specific machinery/ equipment.
11.4
Architectural Design. Design the facilities to be
compatible
with
the
existing
and
planned
structures within the immediate vicinity of the
site.
Design the facilities to be functionally
effective, simple and economical to operate, and
which require only minimum maintenance.
11.5
Quantity and Cost Estimates. Prepare the bill of
quantities for all works and cost estimates of pay
items for each component of the design.
Define
the methods of payment per item (lump sum, unit
cost) which would be most appropriate to effect a
system for cost and quality control.
11.6
Tender and Contract Documents.
Prepare the
following
documents
for
civil
and
electro-mechanical works included within the scope
of services, including:
a. instruction to tenderers
b. complete set of final construction drawings
c. technical specifications
d. bill of quantities
e. conditions of contract
f. form of contract
g. bidding form
Reports and Plans
12. Monthly progress reports, not exceeding five pages, in
twenty copies, describing the progress made on the services,
are required and shall be submitted not later than 7 days
after the reported month.
The reports shall include the
problems encountered, if any, and major findings and
recommendations
as
well
as
the
basis
for
such
recommendations.
13. Ten copies of the comparative evaluation report of
alternative schemes for the design concepts and ten copies of
the environmental impact report shall be submitted for review
and approval of the Government before proceeding to the
detailed engineering design works.
14. Ten copies of the preliminary plans and drawings with
their
corresponding
design
analysis,
quantity
and
construction cost estimates.
This submittal shall be made
ahead of the target date of completion of the detailed
engineering design services and shall be accompanied by all
calculations and procedures used in the design and analysis.
15. Fifty copies of all plans, drawings, specifications,
the necessary bidding and tender documents; ten confidential
copies of cost estimates and one set of reproducible plans
and drawings on stable-based materials shall be provided upon
completion of final design engineering efforts.
Schedule
16. The detailed engineering design and other services
included in these terms of reference shall be completed
within a period of six (6) months.
Cooperation and Organizational and Contractual Arrangements
17. The Metro Manila Authority will be responsible for the
successful execution of this project, being the lead
implementing agency for solid waste improvements for the
metropolis. To this end a full-time Project Manager will be
assigned.
Coordination with the other concerned government
agencies will also be his responsibility.
18. Funding for the implementation of the project has been
obtained by the Government through a loan with the World
Bank.
Download