STUDY OF THE STORM DRAIN SEWER OF THE URBAN CATCHMENT OF LA RIERETA, SAN BOI DE LLOBREGAT, SPAIN Team 3: Aline Veról José Rivero Pedro Ramos Ramiro Pighini 1. Introduction The traditional canalisation approach for flood control has been complemented or replaced by new concepts that consider a systemic approach, with distributed interventions over the catchment intending to recreate flow patterns prior to the urbanisation. LID measures have been proposed to fulfil this aim. However, the spatio-temporal variability of the phenomenon gives particular characteristics to each catchment. In this context, a systemic evaluation of flood control projects is needed, providing adequate spatial coverage without superimposing effects in time. Mathematical modelling emerges as a useful tool to represent the integrated behaviour of urban drainage and landscape. This paper presents the proposition of LID measures on the urban catchment of "La Riereta", at Sant Boi de Llobregat, in Spain, with the aid of EPA Storm Water Management Model (SWMM). 2. Objective The general objective of this project is to perform an analysis on the model of the storm drain sewer of “La Riereta”, an urban catchment located in Spain, and propose a sewer rehabilitation process. To carry out this process, a hydrological and hydraulic model will be developed using the EPA Storm Water Management Model (EPA SWMM 5.0). 3. LID – Low Impact Development Low impact development (LID), developed by Coffman et al. (1998), is a relatively new concept in stormwater management. LID design adopts a set of procedures that try to understand and reproduce hydrological behaviour prior to urbanisation. In this context, the use of functional landscapes appear as useful elements in the urban mesh, in order to allow the recovering of infiltration and detention characteristics of the natural watershed. It is a change in the traditional design concepts, moving towards a site design that mimics natural watershed hydrological functions, involving volume, discharge, recharge and frequency. The main principles of this approach may be briefly described by the following points: minimise runoff, acting on impervious rates reduction and maintaining green areas; preserve concentration times of pre-development, by increasing flow paths and surfasse roughness; use of retention reservoir for peak discharge control and improve water quality; use of additional detention reservoirs to prevent flooding, if necessary. In Brazil, the concept was developed and formalised by Baptista et al. (2005) and is well known as ¨compensatory techniques¨. Veról, Rivero, Ramos & Pighini, 2012 Some basic LID principles include conservation of natural features, minimisation of impervious surfaces, hydraulic disconnects, disbursement of runoff and phytoremediation. In this context, permeable pavements, bioretention facilities, vegetated roof covers, grass swales, dry wells, filter strips, vegetated buffers, rain barrels, cisterns, infiltration trenches, on-lot detention reservoirs, temporary storage reservoirs, reforestation, among others, may be good solutions for achieving these goals and can also integrate harmoniously into the urban environment as they can be designed as recreational areas in dry weather and, then, assume the characteristics of multifunctional landscapes (Miguez et al. ,2011). The figures below show some examples of LID measures. Figure 1. Bioretention Figure 2. Infiltration trenches Figure 3. Vegetated roof covers Veról, Rivero, Ramos & Pighini, 2012 Figure 4. Permeable pavements Figure 5. Rain Barrels 4. Methodology To develop the proposed case study, the group followed the methodology suggested by the organisers and detailed below: Basin discretisation; Determination of the input data (for sub-catchments, conducts and manholes); Calibration and validation of the model using three different rain events and hydrographs registered at the outlet of the urban basin; Determination of the design rainfall for TR 10; Simulation of the drainage network diagnosis; Analysis of the catchment to evaluate and propose the use of LID measures; Simulation of the drainage network considering the implementation of the proposed LID measures; Analysis and discussion of results. Veról, Rivero, Ramos & Pighini, 2012 5. Case Study 5.1. Description The present case study is an urban catchment located in Sant Boi de Llobregat, a town near Barcelona, Spain (Figure 6). This catchment has a surface area of approximately 17 ha and it presents high indexes of impermeability. Its slope varies from high to medium values. Roof drainage discharges directly to the streets through downspouts. Additionally, a group of inlets distributed in the streets ensure the collection of the generated runoff after the occurrence of rainfall. The drainage system of “La Riereta” is a combined sewer network and it is mainly composed by circular cross-section pipes with different diameters and made by concrete. Figure 6. Sant Boi de Llobregat Veról, Rivero, Ramos & Pighini, 2012 6. Results The obtained results are presented in the following items. a) Discretisation The first step of all the work was to divide the studied area into sub-catchments, each one with an approximate area of 1ha (Figures 7 and 8). Also, the hydrologic and hydraulic parameters which SWMM incorporates were defined. Figure 7. Definition of the working catchment Figure 8. Definition of the working catchment in SWMM Veról, Rivero, Ramos & Pighini, 2012 b) Rainfall Three different rainfall events, with their corresponding flows – measured at the catchment outfall – were assigned for each group. Each of these events is identified by the name of the saint of the day in which the registration started. Table 1 presents the rainfall events assigned for team 3 and figures 9 to 11 show these events. Table 1. Rainfall events assigned for Team 3 Rainfall event – Team 3 Efrén Santa Cecilia Susana Figure 9. Rainfall event – Santa Cecilia Veról, Rivero, Ramos & Pighini, 2012 Figure 10. Rainfall event – Efren Figure 11. Rainfall event – Susana Veról, Rivero, Ramos & Pighini, 2012 c) Calibration / Validation The chosen rainfall events for calibration of the model were: Susana and Efrén. The resulting hydrographs are showed in Figures 12 and 13. Susana Rainfall Event 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 0 10 20 30 Measured flow(m3/s) 40 50 Calculated flow (m3/s) Figure 12. Calibration of the model with Susana rainfall event Efrén Rainfall Event 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 0 20 40 60 80 100 120 140 Measured flow (m3/s)Time [min]Calculated flow (m3/s) Figure 13. Calibration of the model with Efrén rainfall event Veról, Rivero, Ramos & Pighini, 2012 Santa Cecilia rainfall event was used to validate the model. The corresponding hydrograph is showed on Figure 14. Santa Cecilia Rainfall Event 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 0 10 20 30 40 Measured flow (m3/s) 50 60 70 80 90 100 Calculated flow (m3/s) Figure 14. Validation of the model with Santa Cecilia rainfall event After the calibration and validation of the model, the adopted parameters for sub catchments, conducts and junctions were, respectively: Veról, Rivero, Ramos & Pighini, 2012 Table 2. Parameters adopted for sub catchments Name S06 S12 S13 S01 S02 S03 S05 S07 S08 S09 S4A S4B S4C S10A S10B S11B S11A S14A Raingage Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Pluv1 Outlet N12 N9 N2 N13 N14 2 N12 N11 N11 N6 N10 N10 N10 N7 N15 N16 N9 N4 Total Area 0.5 0.66 2.06 0.77 0.44 1 0.66 0.55 0.9 0.69 0.6 0.09 0.5 0.87 0.57 1.1 0.95 0.2 Pcnt. Imperv 81.16 94.87 90.73 87.8 92.23 71.73 84.08 98.06 88.5 92.64 89.3 89.3 89.3 96.37 96.37 95.97 95.97 95.3 Width 500 660 2060 770 440 1000 660 550 900 690 600 90 500 870 570 1100 950 200 Pcnt. Slope 2.28 1.52 4.09 6.63 3.16 4.65 1.9 4.09 4.39 6.46 2.34 2.34 2.34 4.72 4.72 4.01 4.01 5.49 Curb N-Imperv N-Perv S-Imperv Length 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 0 0.04 0.15 0.65 S-Perv 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 PctZero RouteTo 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET OUTLET Veról, Rivero, Ramos & Pighini, 2012 Table 3. Parameters adopted for conduits Name C2 C4 C6 C7 C9 C10 C11 C12 C13 C14 C5 C8 C15 C16 C12A Inlet Node N2 N4 N6 N7 N9 N10 N11 N12 N13 N14 N5 N8 N15 N16 2 Outlet Node N4 N5 N7 N8 N11 N11 N12 2 N14 1 N9 N9 N7 N9 N14 Length 70.86 50.56 80.59 59.12 123.33 61.14 108.06 36 120.34 45.52 64.88 10.73 105 145 50 Manning N 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 Inlet Offset 30.89 23.33 26.46 24.57 21.46 21.73 15.46 15.7 16.22 13.13 22.31 23.18 28.518 26.193 14 Outlet Offset 24.18 22.51 24.57 23.28 15.46 18.06 15.9 14.2 13.73 12.51 21.46 22.87 24.574 22.87 13.13 Init. Flow 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Max. Flow 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Link C2 C4 C6 C7 C9 C10 C11 C12 C13 C14 C5 C8 C15 C16 C12A Shape Geom1 CIRCULAR 0.5 CIRCULAR 0.4 CIRCULAR 0.4 CIRCULAR 0.4 CIRCULAR 1 CIRCULAR 0.3 CIRCULAR 1 CIRCULAR 1 CIRCULAR 0.6 CIRCULAR 1.2 CIRCULAR 0.6 CIRCULAR 0.5 CIRCULAR 0.5 CIRCULAR 0.6 CIRCULAR 1.2 Geom2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Geom3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Geom4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Barrels 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Veról, Rivero, Ramos & Pighini, 2012 Table 4. Parameters adopted for junctions Name N2 N4 N6 N7 N9 N10 N11 N12 N13 N14 N5 N8 N15 N16 2 Invert Elev. 30.696 23.33 26.263 24.57 21.46 21.725 15.46 15.7 16.22 13.13 22.31 23.17 28.518 26.193 14 Max. Depth 0 0 0 0 0 0 4 0 0 0 0 0 0 0 0 Init. Surcharge Ponded Depth Depth Area 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Veról, Rivero, Ramos & Pighini, 2012 d) Diagnosis of drainage network Once the model was calibrated and validated, the team modelled the diagnosis of the drainage network for a design rainfall. A design rainfall of 10 years of recurrence time is used not only in the city of Barcelona, but also in some municipalities around it, like Sant Boi de Llobregat. In this case, the design rainfall should be obtained from the IDF curve Barcelona-Fabra, based on precipitation series registered between the years of 1927-1993. This IDF curves are described by the following expressions: Where: I: (mm/h) T: (years) D: (minutes) The duration of the design rainfall is 1 hour. Figure 15 shows it. 250.00 200.00 150.00 100.00 50.00 0.00 5 10 15 20 25 30 35 40 45 50 55 60 Figure 15. Design rainfall obtained for TR 10 Veról, Rivero, Ramos & Pighini, 2012 1 N14 2 N12 N11 N8 N9 N7 N6 Water Elevation Profile: Node N6 - 1 28 27 26 25 24 23 Elevation (m) 22 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 Distance (m) 300 350 400 450 500 07/24/2012 00:24:00 N14 450 500 1 2 N12 N11 N9 N5 N4 N2 Water Elevation Profile: Node N2 - 1 33 32 31 30 29 28 27 26 Elevation (m) 25 24 23 22 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 300 Distance (m) 350 400 550 07/24/2012 00:24:00 Veról, Rivero, Ramos & Pighini, 2012 1 N14 N13 Water Elevation Profile: Node N13 - 1 17 Elevation (m) 16 15 14 13 0 10 20 30 40 50 60 70 80 90 Distance (m) 100 110 120 130 140 150 160 07/24/2012 00:24:00 1 N14 2 N12 N11 N10 Water Elevation Profile: Node N10 - 1 22 21 20 Elevation (m) 19 18 17 16 15 14 13 0 20 40 60 80 100 120 140 160 Distance (m) 180 200 220 240 260 280 300 07/24/2012 00:24:00 Veról, Rivero, Ramos & Pighini, 2012 1 N14 2 N12 N11 N9 N16 Water Elevation Profile: Node N16 - 1 28 27 26 25 24 23 Elevation (m) 22 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 Distance (m) 300 350 400 450 500 07/24/2012 00:24:00 1 N14 2 N12 N11 N8 N7 N15 Water Elevation Profile: Node N15 - 1 30 29 28 27 26 25 Elevation (m) 24 23 22 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 300 Distance (m) 350 400 450 500 07/24/2012 00:24:00 Veról, Rivero, Ramos & Pighini, 2012 e) Intervention Proposal Once the diagnosis for the drainage network of “La Riereta” was made, the team made a particular study for the current catchment, considering the implementation of LID measures and the aid of SWMM. The chosen LID measures were: Porous pavements, Bioretention cells, and Rain barrels. The obtained results are showed above. PP1 PP1 PP1 PP1 PP1 Type/Layer Parameters PP SURFACE 2 PAVEMENT 120 STORAGE 250 DRAIN 0 0 0.18 0.75 0.5 0.018 0 10 0 2 100 0 6 5 0 PP2 PP2 PP2 PP2 PP2 PP SURFACE PAVEMENT STORAGE DRAIN 2 120 250 0 0 0.18 0.75 0.5 0.018 0 10 0 3 100 0 6 5 0 RB1 RB1 RB1 RB STORAGE DRAIN 1500 2 0.75 0.5 10 0 0 2 BR1 BR1 BR1 BR1 BR1 BC SURFACE SOIL STORAGE DRAIN 4 500 500 0 0.5 0.3 0.75 0.5 0.2 0.2 100 0 0.5 0.1 0.5 0 6 5 10.0 3.5 Veról, Rivero, Ramos & Pighini, 2012 SubcatchmentLID Process Number S06 S12 S12 S13 S13 S13 S01 S01 S02 S02 S03 S03 S05 S05 S07 S07 S08 S08 S09 S09 S4A S4A S4B S4B S4C S4C S10A S10A S10B S10B S11B S11B S11A S11A S14A S14A RB1 RB1 PP1 PP1 RB1 BR1 RB1 PP1 RB1 PP1 PP1 RB1 PP1 RB1 RB1 PP1 PP1 RB1 PP1 RB1 PP1 RB1 RB1 PP1 PP1 RB1 PP1 RB1 PP1 RB1 RB1 PP2 RB1 PP1 PP1 RB1 Area 15 15 1 1 22 1 28 1 32 1 1 30 1 15 23 1 1 24 2 30 1 23 2 1 1 25 1 15 2 21 20 2 30 1 1 6 Width 0.8 0.8 700 2150 0.8 1200 0.8 800 0.8 500 500 0.8 700 0.8 0.8 868 812 0.8 900 0.8 500 0.8 0.8 280 500 0.8 942 0.8 1040 0.8 0.8 700 0.8 840 400 0.8 InitSatur 0 0 7 7 0 40 0 7 0 5 7 0 7 0 0 7 7 0 7 0 5 0 0 7 5 0 6 0 7 0 0 7 0 7 7 0 FromImprv 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 70 70 12 12 40 48 75 12 80 13 8 30 13 80 80 17 11 85 30 70 11 85 65 35 12 85 12 80 19 80 75 10 70 10 21 60 ToPerv Report File 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Veról, Rivero, Ramos & Pighini, 2012 Design Rainfall Tr=10 and Flow Discharge 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 165 170 175 180 185 190 195 200 205 210 215 220 225 230 235 240 Time [min] 0 6.00 Desing Rainfall Tr=10 5.00 50 4.00 100 3.00 150 2.00 Flow Discharge [m3/s] Flow Discharge with LID measures 200 1.00 0.00 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 165 170 175 180 185 190 195 200 205 210 215 220 225 230 235 240 250 Time [min] 1 N14 2 N12 N11 N8 N9 N7 N6 Water Elevation Profile: Node N6 - 1 28 27 26 25 24 23 22 Elevation (m) Intensity [mm/h] Flow Discharge 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 Distance (m) 300 350 400 450 500 07/24/2012 00:24:00 Veról, Rivero, Ramos & Pighini, 2012 1 N14 2 N12 N11 N9 N5 N4 N2 Water Elevation Profile: Node N2 - 1 33 32 31 30 29 28 27 26 Elevation (m) 25 24 23 22 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 300 Distance (m) 350 400 450 500 550 07/24/2012 00:24:00 Veról, Rivero, Ramos & Pighini, 2012 1 N14 2 N12 N11 N10 Water Elevation Profile: Node N10 - 1 22 21 20 Elevation (m) 19 18 17 16 15 14 13 0 20 40 60 80 100 120 140 160 Distance (m) 180 200 220 240 260 280 300 07/24/2012 00:24:00 1 N14 2 N12 N11 N9 N16 Water Elevation Profile: Node N16 - 1 28 27 26 25 24 23 Elevation (m) 22 21 20 19 18 17 16 15 14 13 0 50 100 150 200 250 Distance (m) 300 350 400 450 500 07/24/2012 00:24:00 Veról, Rivero, Ramos & Pighini, 2012 Veról, Rivero, Ramos & Pighini, 2012 7. Conclusion The calibration of the model showed a reasonable result, but the validation showed an exaggerated over estimation in the total volume. Considering the design rainfall, the nodes N4, N7 and N10 surcharged. The main purpose of this work was to treat this flooding problem using the LID concept. The use of LID, such as permeable pavements, rain barrels and bioretention cells, showed a good result on the main drainage line, where the actions in the catchment context are more sensible. The nodes that were flooded in the borders of the catchment were less sensible to LID measures because the surfaces related to these nodes were small and the distributed measures could not be as effective as they were in the catchment context. Another problem was that in the borders of the catchment there may occur, in reality, a diversion to the neighbouring catchments. As it has not been considered in the modelling, possibly the discharge in these nodes may be overestimated. This problem may also be the explanation for the calibration/validation results. In a real situation, a good result could be achieved by the use of LID combined with other flooding control measures. As an example, detention catchments or drainage net rehabilitation could be jointly considered. Veról, Rivero, Ramos & Pighini, 2012 8. References EPA. Low Impact Development: A Literature Review. 2000. Batista, M.; Nascimento, N. & Barraud, S. Compensatory Techniques on Urban Drainage. ABRH: Porto Alegre, Brazil, 2005. (in Portuguese). Miguez, M.G.; Verol, A. P. Carneiro, P. R. F. Sustainable Drainage Systems: An Integrated Approach, Combining Hydraulic Engineering Design, Urban Land Control and River Revitalisation Aspects. In: Drainage Systems. Intech, 2012. Miguez, M.G.; Mascarenhas, F.C.B.; Magalhães, L. P. C. Multifunctional landscapes for urban flood control: the case of Rio de Janeiro (Chapter 2). Flood Prevention and Remediation, ed. Mascarenhas, F.C.B., WIT Press: Southampton, Boston, pp. 33-52, 2011. PRINCE GEORGE’S COUNTY, Department of Environment Resources. Low Impact Development Design Strategies: An Integrated Design Approach. 1999. Veról, Rivero, Ramos & Pighini, 2012