Cisco TelePresence Experience & Order Assurance (EOA) Program Program Overview The spirit of the EOA program is grounded in delivering a superior TelePresence experience to our customers. Equally paramount, is enabling our partners to achieve success by providing them with the expertise and guidance they need. The EOA program ensures that our customers receive the highest quality Cisco TelePresence experience possible by providing a process in which the field can validate critical assessment data prior to order release and solution deployment. Throughout the process, assessments are completed by the field to identify potential room and network remediation needs before installing the equipment. The assessments are submitted and automatically reviewed with Cisco Subject Matter Experts (SME) available to offer assistance and guidance. Process Overview There are 3 primary steps involved in the process that will help our partners deliver an exceptional TelePresence experience. The 3 steps are: SURVEY & RELEASE SITE ANALYSIS INSTALLATION & ACCEPTANCE Again, the goal is to simplify the process, making it easier to execute, with added assurance for customer satisfaction, while at the same time accelerate the Compliance Hold release on customer orders. SURVEY & RELEASE The overall goal of the survey and release step is to provide a way for the partner to evaluate a customer’s existing room and network infrastructure without anything more than then collecting the information through conversations and interviews. Furthermore, even if the customer is building a new room(s) and/or an overlay network, it is still very important to use this step to ensure that all the necessary areas are evaluated and considered. Additionally, this step provides a mechanism by which product hold can be released. Once the surveys are submitted in the EOA Web Tool, an immediate response is given. Depending on the results, the equipment can be released from Compliance Hold, or further review between the TSBU Engineering team and the partner will be required to help resolve any major issues. There are three or four forms required in this step depending on the Product type being deployed: *Prequalification Network Path Assessment Survey Room Readiness Assessment Survey Product Hold Release Request (PHR) Prequalification The prequalification form is a high level questionnaire, which could be referred to as a ‘survey’. While it does include some questions around network and application, it is far more focused on the room environment. History shows that the prequalification is a proven method of quickly highlighting areas of needed remediation for the customer, giving them more time to respond, plan and begin room and/or network remediation. In fact, many partners have used the prequalification as a way to help the customer select a room that will support TelePresence with the least amount of remediation. Network Path Assessment Survey The Network Path Assessment Survey provides adequate assurance that the partner has reviewed major areas of the network and application environment and communicated results to the customer for review and possible remediation. It is required for all TelePresence endpoint types, including the management components. The major areas covered in the NPA Survey include: TelePresence Versions Compatibility Call Management Call Scheduling Multipoint Interoperability Inter-company Exchange Auto-Collaboration Network Design QoS and Security Hardware/Software Infrastructure Room Readiness Assessment Survey The Room Readiness Assessment Survey provides adequate assurance that the partner has reviewed major areas of the room and environmental characteristics and communicated results to the customer for review and possible remediation. It is required for all Triple Screen Systems. The major areas covered in the RAA Survey include: Remediation Status Environment Overview Power Network Data Ports HVAC Visual Obstructions Illumination (Fixture Type) Drawings Floor Plan Reflected Ceiling Plan Pictures Product Hold Release Request (PHR) Another very important piece of the first step in the process is the actual mechanism to request the release of product hold, or Compliance Hold. Because Cisco does not dictate how the partner places the customer order, many complexities can arise which force the EOA Team to manage orders very precisely. This then makes it imperative to put the ownership in the hands of the partner to initiate the specific request for Compliance Hold, so that all precautions are made to not inadvertently ship equipment that the customer is not prepared to receive, let alone deploy. Process Requirements Again, using the product family categories will make understanding EOA process requirements easier. Single Screen Systems Process (CTS-500, CTS-1000, CTS-1300-65) Because the Single Screen Systems do not typically require the same level of Room Remediation to the degree as the Triple Screen Systems, the EOA program only requires that the Network Path Assessment Survey and Network Path Assessment Site Analysis be completed for single screen systems. This is not to say that Single Screen Systems may not benefit from a Room Readiness Assessment, and that in some cases room remediation would be favorable to increase the overall experience. This process is depicted in the below diagram. TelePresence Component Process The TelePresence Components included in the EOA Program are the CTS-Manager and the CTS-CTMS (Multipoint). The process to release the components from Compliance Hold has been simplified with the new NPA. Both require the NPA Survey to be completed and the subsequent release request. However, only the multipoint switch requires the follow-on NPA Site Analysis to also be completed. Triple Screen System Process For the Triple Screen Systems, however, the process is a cross-over between the original serial process and the new parallel process. These larger and more complex systems require that Room Readiness also be evaluated prior to deployment. The Room Readiness Assessment (RRA) will be redesigned into a two part process, similar to the new NPA, within the coming months. Until that time we will continue to leverage the existing serial process for the Room Readiness requirements. The diagram below depicts what is required by the EOA process before the order ships. The Prequal, NPA survey, and the full RRA are required before Compliance Hold can be released. Notice that the parallel process is in place for the Network Path Assessment as explained previously. SITE ANALYSIS The purpose of this step is to guarantee that the room(s) and network paths are within the required specifications for Cisco TelePresence. Using measurements tools, raw data is extrapolated from the room and network environment. It is important to note that as the EOA process transitions fully to this new model, the release of the equipment is occurring ahead of the final assessment step. This means that the ownership of ensuring it is performed and evaluated prior to installation and deployment is put on the partner. There are 2 assessments as part of this step: Room Readiness Assessment Site Analysis Network Path Assessment Site Analysis Room Readiness Assessment Site Analysis The Room Readiness Assessment is a comprehensive test that includes many room environment variables. A special RRA Kit is used to gather this information and contains things like light and sound metering tools. Each partner is required to procure an RRA Kit either from the dealer that Cisco recommends, or can purchase similar devices to capture the needed data. The following lists the general areas that are covered under the RRA. Environment Detail STC NRC IIC Ambient Noise Floor Reverberation Illumination Details Illumination Measurements Network Path Assessment Site Analysis As mentioned earlier, the Network Path Assessment Site Analysis collects path statistics such as latency, jitter, and loss and can only be captured once circuits and/or paths are fully provisioned and functional. It can be completed in parallel with the shipment in order to meet project timelines, customer expectations and accelerate the overall process. This is the full list of the major areas currently covered in the NPA site analysis. Link Utilization Device Utilization BW, Latency, Jitter, Loss INSTALLATION & ACCEPTANCE This final step in the process can best be understood as the installation and final validation. Needless to say, installation is self explanatory. Other than mentioning that only a skilled technician should be performing the installation, it is important to note that installation should not occur until the room and network remediation is complete. Once the units are installed, any further remediation work may become much more difficult and costly to implement. So what does Installation & Acceptance mean? It is best explained through use of the categories of the product family. It is expected that the partner will ensure that all room and network remediation has been completed prior to installation, or at the very least prior to the time the customer has accepted the solution and began to use it. The EOA process can be leveraged to determine an exact measurement that needs to be reached before being considered ready for production deployment. Let’s examine this. Single Screen Systems With Single Screen Systems, the EOA Process can be leverage so that Production Deployment should not occur until that particular ‘site’ has a Network Path Assessment Survey and Site Analysis with a GREEN condition. This means that all aspects of the Network Readiness have been addressed. Triple Screen Systems With Triple Screen Systems, Cisco goes one step further. While it is left to the partner to ensure that all room and network remediation is complete, the Cisco TSBU engineering group requires an additional assessment be performed, thereby certifying the room for production. The validation is known as Cisco TelePresence Experience Validation, or CTX. The CTX historically was performed only by the Cisco engineering team and was performed by a Cisco TSBU engineer onsite. It was done using the same RRA Kit that a partner would use during the RRA Site Analysis step, but also went further to perform a quasi Customer Acceptance Test. However, with the most active and proven partners, a new process has been implemented to accelerate the validation process. This new process is called Post Installation Assessment, or PIA. This process enables the partner to perform the assessment immediately following the installation and deployment of TelePresence. Using the RRA Kit, performing the same customer acceptance tests, and submitting the information and additional pictures to Cisco engineering, a ‘remote CTX’ can be delivered. This is the preferred method for partners and Cisco alike, as it puts more ownership on the partner and accelerates the time to signoff with the customer. Three Steps to Success To understand the steps to success, it is essential to answer the most basic questions. The table below outlines the “What, Why, Who, When, Where, and How” for each step in the EOA Program. Survey & Release What The first step in the EOA process. It is designed to assist the field in evaluating a customer’s Room and Network Readiness at a high level and provide the mechanism to request Compliance Hold release. Specifically, the online forms that need to be completed in this step include: Prequalification: A series of high-level questions generally related to room environment. Once submitted, an immediate evaluation and response is generated indicating areas and level of remediation needed. Network Path Assessment Survey: A range of broad and more specific questions related to network, application and infrastructure design and implementation. It covers Network Readiness holistically. Room Readiness Assessment Survey: A range of broad and more specific questions related to room & environmental characteristics. It covers Room Readiness holistically. Product Hold Release Request (PHR): A short form used to initiate a formal request to release Compliance Hold. It captures the Sales Order Number, Line Item, Ship Set Number, etc. and automates the release workflow between the partner, EOA Team, and Cisco manufacturing. Why This step is the initial assurance that appropriate discussions and predeployment reviews have occurred between the partner and the end customer. Additionally, controlling the release of equipment assists the partners in managing the delivery at the end customer site. Because all TelePresence orders are owned by partners, it is very important that they control the release and management of them. Who The people involved range from Cisco Account Teams, Partners, and Cisco AS. Prequalification: Cisco Account Team, Partner, or Cisco AS. Network Path Assessment Survey: Partner or Cisco AS Room Readiness Assessment Survey: Partner or Cisco AS Product Hold Release Request: Partner or Cisco AS When Some elements can be completed prior to an order being placed, while other elements occur after the order is booked. Prequalification: Before or after an order is booked Network Path Assessment Survey: Before or after an order is booked Room Readiness Assessment Survey: Before or after an order is booked Product Hold Release Request: After an order is booked Where Collecting the information required to complete the forms can be done via onsite or remote meeting with customer. Completing the submission of the data for EOA Process is done via the EOA Web Tool online. https://tools.cisco.com/tsbu/oa/index.html How First, data is collected by communicating with the end customer. Next, that data is transferred into the EOA Web Tool. This simple online tool provides an immediate response which can then be shared with the customer. The Product Hold Release request is completed directly on the EOA Web Tool. The EOA team reviews and approvals are automatically sent to Cisco manufacturing. Site Analysis What The second step in the EOA Process. The 2 types are: Room Readiness Assessment Site Analysis: An in-depth series of tests performed using an RRA Kit which includes an acoustics and light meter. Network Path Assessment Site Analysis: An in-depth ‘path’ test performed using one of several tools available to capture latency, jitter, and packet loss. Why To ensure room and network remediation needs, and/or confirmation that remediation or build-to-spec rooms and networks have been done correctly. Who Room Readiness Assessment Site Analysis: Partner or Cisco AS Network Path Assessment Site Analysis: Partner or Cisco AS. When Room Readiness Assessment Site Analysis: Before and/or after room remediation or build-to-spec has occurred, and before endpoint installation. The Network Path Assessment Site Analysis: After circuits are installed and before deployment. Where Room Readiness Assessment Site Analysis: Onsite in proposed endpoint installation location. Network Path Assessment Site Analysis: Onsite, central location, or one side of a path. How Room Readiness Assessment Site Analysis: Data capture is done using the RRA Tool Kit. Results are uploaded into the EOA Web Tool. Network Path Assessment Site Analysis: Data capture is done by using one of the following tools. IPSLA, VSAA, CTS Codec, or other. Results are transferred into the EOA Web tool. Installation & Acceptance What The final step in the EOA Process. Single Screen Systems require a ‘GREEN’ status on the NPA Survey and NPA Site Analysis, before meeting the guideline of a product ready ‘room’. Triple Screen Systems require a Validation status of ‘PASS’ before being considered production ready. They are validated for their acoustics, lighting, continuity, and network design and system performance. Why This ensures customer satisfaction and eliminates potential issues after the end customer is using the system. Logistically, it is far easier to address any issues before the customer begins using them. Who Installation: Partners or Cisco AS. Validation: A combination of the partner or Cisco AS, and Cisco engineering. When Installation: After the rooms and network are in optimal condition. Validation – Onsite: 1-2 weeks after installation. Validation – Remote: Within 24 hrs. Where Installation: Occurs on customer premises Validation: Onsite or remote. How Installation occurs by skilled technicians following the specific Assembly Guides provided by Cisco. Validation is performed using the RRA Kit and a series of ‘user acceptance’ test scenarios. Cisco Engineer will transfer data to EOA Web tool and produce a response that is generated and emailed to partner for delivery to the customer. If done by remotely, partner sends a collection of pictures and test results to Cisco Engineer for validation. Related Support Information EOA Web Page https://tools.cisco.com/tsbu/oa/index.html Partner Resource Central http://www.ciscoet.com/solutionfrontpage.asp?sid=7 Cisco Technical Support (TAC) Cisco TAC Website Customer Service Cisco Customer Service Website Contacts | Feedback | Help | Site Map © 1992-2008 Cisco Systems, Inc. All rights reserved. Terms & Conditions | Privacy Statement | Cookie Policy | Trademarks of Cisco Systems, Inc.