MULTIPLE PACKAGES CM AT RISK CONTRACTING PROCEDURE This process is used for CM at Risk contracts where the CM has been selected to perform Document Review Phase, Procurement Phase and Construction Phase Services and the Construction Phase Services will be contracted and performed in additional phases. For example the initial phase may be site work and utilities, followed by excavation and shoring, foundations, core and shell, and interiors. The end result will be that the CM holds two contracts; one for Document Review and Procurement Services and one for all of the Construction Phase Services. The intent is to minimize the administrative burden placed on the project team that would result from a separate contract being issued for each construction phase of the project. Change Orders to the Document Review and Procurement Phases Contract, and the Construction Phase Contract, would be kept separate to the appropriate contract and be sequentially numbered. One submittal and RFI log would also be kept for each of the contracts. This procedure as described below should be followed as additional Construction Phase packages are to be awarded beyond the initial contract: The process is initiated by a Memorandum of Negotiation (MoN). The approval routing of the MoN is similar to the routing required for Board on Changes approval (FP&C Project Manager, FP&C Division Manager, Contract Administration Manager, FP&C Director, and Chief Facilities Officer). Accompanying documents would be the CM’s Proposal and any additional negotiation documents. HECO-8s should be issued sequentially 001, 002, 003, etc. with each package for approval. HECO-8 construction values for previous packages should be listed individually, but should be rolled up to reflect a cumulative construction value as each is issued. As additional packages are to be awarded, the CO-9 will be revised to list the additions and reflect the cumulative contract amount. As revised CO-9s are issued, the “Original Contract” line item in the Schedule of Values will be revised accordingly to reflect the cumulative construction value. Bonding will be secured for the design-to construction amount at the time of the award of the second contract (the Construction Phase contract award). If the final buy-out exceeds the design-to construction cost, the CM fee for increased bonding will be adjusted accordingly by Change Order. The CM Purchase Order will be adjusted by a “Purchase Order Change” procedure with each contract revision based on the phased award amounts. Change Orders will be processed as they occur and will be numbered sequentially during the life of the project. The value of approved Change Orders will not be incorporated into Contract revisions as additional packages are awarded. The value of approved change orders from work performed under previous versions of the CO-9 will be carried forward on the Schedule of Values (HECO-12) under the “Approved Change Orders” line items. Example: Project 207-XXXXX-001 207-XXXXX-002 207-XXXXX-003 207-XXXXX-004 207-XXXXX-005 Package Pkg Award Description Amount Site Utilities $5,000,000 Excavation & Shoring $1,000,000 Foundations $2,000,000 Core & Shell $10,000,000 Interiors $10,000,000 CO-9 (Revised) Total Value of Amount Approved Changes $5,000,000 $200,000 $6,000,000 $300,000 $8,000,000 $340,000 $18,000,000 $450,000 $28,000,000 $750,000 “Adjusted Contract Total” HECO-12 $5,200,000 $6,300,000 $8,340,000 $18,450,000 $28,750,000