city and county of denver - Rocky Mountain e

advertisement
Addendum No. 1
Request for Proposal No. 7061
CITY AND COUNTY OF DENVER
DEPARTMENT OF GENERAL SERVICES
PURCHASING DIVISION
www.denvergov.org/purchasing
WELLINGTON E. WEBB
MUNICIPAL OFFICE BUILDING
201 WEST COLFAX AVE., DEPT. 304
DENVER, CO 80202
PHONE: (720) 913-8100
FAX: (720) 913-8101
Date: April 12, 2013
ADDENDUM NO. 1
REQUEST FOR PROPOSAL NO. 7061
INTERNET PORT ACCESS
The following questions and their answers are hereby incorporated into and made part of the
above referenced Proposal:
(Q) QUESTIONS and (A) ANSWERS
Q1.
Would the City of Denver be interested in a solution that proposes providing a port at the
following Points-of-Presence (PoP)? This solution could potentially result in significant
costs savings and give the City the ability to scale bandwidth to as high as 10 Gb. (The
City would procure transport ‘last mile service’ from the PoP to their facilities at 201
Colfax and 10 Galapagos.)




1500 Champa St.
910 15th St. - Comfluent
639 E 18th Ave - Comfluent
1850 Pearl St. – Level 3
A1. The routing through the above locations would not be an issue but the City's
expectation is that the handoff to the City will be at 201 W. Colfax and 10
Galapagos.
Q2.
Will the City and awarded vendor be able to merge the City's contract document with
awarded vendor's Master Services Agreement?
A2. Yes, the City will work with the awarded vendor on a mutually agreed upon
contract and /or service agreement.
Addendum No. 1
Request for Proposal No. 7061
Q3.
The SOW requests scalability and pricing in 500 Mb increments up to 10Gb but the
pricing form (Section C5) only indicates increments up to 2Gb. How should we indicate
pricing for the increments between 2Gb and 10Gb?
A3. Please add pricing from 2Gb through 10Gb in 500Mb increments to the table
provided.
Q4.
Could you provide the projected award date and installation/implementation timeline for
the project?
A4. The estimated award date will be two weeks from the due date making it May 2.
The contracting process will take an estimated eight to twelve weeks.
Implementation will start after the contracting process is complete.
Q5.
What is the term of the contract?
A5.
The initial term will be three years with two one-year renewal options.
Proposer shall initial here
and attach to their Proposal. Failure to do so may be cause
to consider your proposal non-responsive and cause for rejection.