Medium-Voltage AC (MVAC) Power Generating System Author: Yucheng Zhang Advisor: Roger A. Dougal Date: 09/23/2009 1. Introduction MVAC power generating system produces AC electric power to the loads (AC, DC). It is composed of turbine-generator (gas turbine, synchronous generator with excitation system), circuit breakers, AC cables and lumped loads. The generators are synchronized together by the automatic synchronizer. All of the models are based on dynamic models to present the dynamic performance during transient status. This MVAC power generating system could be used to analyse: protection, machine characteristics’ analysis, grounding, stability, etc. 2. MVAC Power Generating System The MVAC power generating system has four units of turbine-generators (two 36MW, two 4MW), consisting of a ring bus. The loads are connected to the bus ties and the power can be shared among the turbine-generators, as shown in Fig. 1. With the structure of the ring bus, the reliability of power delivery is enhanced within the microgrid, regardless of which power source is producing at any time. Bus1 TG_36MW DC_Load DC_Load AC / DC AC / DC Bus2 TG_4MW Cable_1_2 Cable_1_3 TG_4MW Bus3 DC_Load DC_Load AC / DC AC / DC Cable2_4 AC_Load AC_Load Bus4 TG_36MW Cable_3_4 AC_Load AC_Load CB Fig. 1 Schematic of the ring bus power system The model of one turbine-generator unit and some details of its associated controls are shown in Fig. 2. The three phases of the turbine generator are connected to the load through bus-ties. A synchronization controller measures terminal voltages, active and reactive powers, and monitors the control signal from the supervisory controller. When activated, it sends bias values to control the frequency (turbine speed) and terminal voltage (rotor current) set-points of the turbine-generator and then closes the bus ties at the moment when the line up of all generator variables is within tolerances. Fig. 2 One unit of automatic synchronizing subsystem For a “dark start”, the supervisory controller detects the zero-voltage condition and commands the first power-generating unit to be the master. The supervisory controller is modeled for deciding the sequence of power-generating units in networks. The first power generating unit then starts up and the frequency and terminal voltages are built up while the unit is still disconnected from the distribution grid. Once the turbine-generator achieves a stable operating point, the synchronization controller issues commands to close the three-phase bus-ties so that any connected load receives power from the first turbine-generator. Before the second generator is started, the supervisory controller detects that the network is already “alive” and commands the second power-generating unit to be a slave. The synchronization controller then monitors the differences between the phases, voltages, and frequencies and slightly adjusts the set points for frequency and terminal voltage to bring the two generators into synchronism. When the second generator achieves stable operation and the differences in voltage, phase, and frequency are within tolerances, the three-phase breaker is closed to connect the second generator to the grid. 2.1. Gas Turbine Model The turbine model is based on the heavy-duty turbine model [1]. It is suitable for the analysis of dynamic power system studies. The structure of the gas turbine and its speed-governor is shown in Fig. 3. With proper parameters in governor, the gas turbine can easily works in either droop mode or isochronous mode. A droop governor is a straight proportional speed controller in which the output is a proportional to the speed error [1]. An isochronous governor is a proportional-plus-reset speed controller in which the rate of change of the output is proportional to the speed error [1]. The coefficients for these two modes are listed in Table. 1. KD = 1 / Droop; K = 25 typically for 4 percent droop setting. Droop setting is adjustable from 2 to 10 percent. 0.23 + Set Point - W ( Xs 1) Ys Z Governor Low Value Select X + 1 a bs c Fs 1 Valve Positioner Fuel System + 0.77 Saturation - 1 Is Acceleration Limiter 1 Is Inertia s + 0.1 Rotor Speed p.u. Wf - f Turbine Electromagnetic Torque Fig.3 Structure of Gas Turbine with Speed-governor Table.1 Speed governor transfer function coefficients Type w Droop KD 0 Isochronous 30 x y z 0.05 1 2.5 0.10 0 N 1 CD s 1 In the schematic the turbine block implements the following Eq. (1): Ttpu f Mpu ,WF 1.3(WF 0.23) 0.5(1 Mpu ) (1) Where WF is the unit fuel flow in per unit (p.u.) calculated from the preceding block and ωMpu is the mechanical speed in p.u. The created model captures the following dynamics of the prime mover: • Turbine rotational inertia • Delay associated with the fuel valve • Delay associated with the combustion chamber • Speed governor 2.2. Synchronous Generator Model with AVR Synchronous generators form the principal source of electric energy in power systems. As the main type of generators widely used in utility grid, distributed generation and isolated power system, the mathematical model of synchronous machine is modeled in detail to review its steady-state and transient performance characteristic. The synchronous generator model is formulated in d-q-0 frame with two q-axis amortisseur circuits as described in [2]. The positive q-axis is defined as leading the positive d-axis by π/2. The transformation equations from the abc reference frame to the dq0 reference frame are given by: cos id i 2 sin q 3 i0 1 2 2 2 ) cos( ) 3 3 ia 2 2 sin( ) sin( ) ib 3 3 ic 1 1 2 2 cos( And the inverse transformation is given by: (2) sin cos ia i 2 cos( 2 ) sin( 2 ) b 3 3 3 ic cos( 2 ) sin( 2 ) 3 3 1 2 i d 1 iq 2 1 i0 2 (3) For voltage and flux, the transformation is in the same format. The complete set of electrical equations is expressed as below. And the definitions of parameters are listed in Table.2. In the following equations, two q-axis amortisseur circuits and one d-axis amortisseur circuit are considered. Stator voltage equations: ed p d qr Ra id eq p q d r Ra iq e p R i 0 a 0 0 (4) Rotor voltage equations: e fd p fd R fd i fd 0 p R i 1d 1d 1d 0 p 1q R1qi1q 0 p 2 q R2 qi2 q (5) Stator flux linkage equations: d ( Lad Ll )id Lad i fd Lad i1d q ( Laq Ll )iq Laqi1q Laqi2 q L i 0 0 0 Rotor flux linkage equation: (6) fd L ffdi fd L f 1d i1d Lad id L i L i L i 1d f 1d fd 11d 1d ad d 1q L11qi1q Laqi2 q Laqiq 2 q Laqi1q L22qi2 q Laqiq (7) Table.2 Definitions of parameters in the model of synchronous generator Name Description ed , eq , e0 Instantaneous stator phase to neutral voltage in dq0 axes id , iq , i0 Instantaneous stator currents in dq0 axes e fd Field voltage d , q , 0 Stator flux linkage in dq0 axes fd , 1d , 1q , 2 q Filed and rotor flux linkage in dq0 axes Ra Armature resistance per phase R fd , R1d , R1q , R2 q Field and rotor resistances in dq0 axes Lad , Laq , L0 Mutual inductances between stator and rotor circuits in dq0 axes L ffd , L11d , L11q , L22q Self-inductances of rotor circuits L f 1d Mutual inductances in d-axis i fd , i1d , i1q , i2 q Instantaneous rotor currents of field in d-axis, amortisseur-1 in d-axis, amortisseur-1 in q-axis, amortisseur-2 in q-axis The equivalent circuits, shown in Fig. 4, present the complete electrical characteristics of the machine. Damping circuits, mutual interactions between the armature windings and the excitation circuit are included, and the rotor is assumed cylindrical without saturation. The electromechanical torque is expressed in Eq. (8). Te d iq qid Ra r q Ll L f 1d Lad id ed d d dt (8) i1d Lad d 1d dt i fd L1d L fd R fd d fd e fd dt R1d d-axis equivalent circuit r d Ra Ll iq eq d q dt i1q Laq d 1q i2 q L1q R1q L2 q R2 q d 2q dt dt q-axis equivalent circuit Fig.4 Complete d-axis and q-axis equivalent circuits The automatic voltage regulator (AVR) is modeled as Westinghouse AVR in [3]. It includes the regulator, exciter and stabilizer to maintain the generator terminal voltage at the reference value. Fig. 5 shows the structure of the voltage regulator/exciter. The feedback block in the schematic implements the function: f out ( K E AEX e BEX EX out ) EX out Where AEX, BEX and KE are constants. (9) Voltage Feedback - + Reference Voltage - KA A1 s 1 1 A2 s 1 + Saturation - 1 Es 1 Exciter EXout f out KF s F s 1 Stabilizer Fig.5 Automatic voltage regulator / exciter 2.3. Droop Setting and Automatic Synchronization The synchronization process is based on the droop scheme. Droop is a straight-line function, with a certain speed reference for every fuel position [4]. Its fuel position is related to the load. The frequency-droop control and voltage-droop control are separately used to control active power and reactive power. As the frequency (voltage) decreases the active power (reactive power) increases. Therefore, the frequency (voltage) droop controls the power sharing between generators, as shown in Fig. 6. V (volt,p.u.) f (Hz,p.u.) 1.04 1.04 1.00 0 P (W) PNominal (a) Frequency droop 1.00 0 Q (VA) QNominal (b) Voltage droop Fig.6 Frequency droop and voltage droop (Droop setting = 4%) The automatic synchronizer gets signals from power meter, voltage sensors and control signals “On / Off” and “First”, which are from supervisory controller. Automatic synchronizer sends out speed (voltage) reference bias to turbo-generators and switch signals to the bus-ties or breakers. The Fig. 7 shows the scenario of automatic synchronizer. Fig. 7 Scenario of automatic synchronizer After the trigger signal from supervisory controller becomes true, the turbo-generator gradually reaches the reference speed and reference voltage. During this starting time, the speed (voltage) reference bias is zero. After the turbo-generator reaches the steady state (voltage and frequency closes to the reference values), the process of synchronization starts. The automatic synchronizer sends out the speed (voltage) reference bias to make: (1) the frequency of the turbo-generator faster than the frequency of the synchronized ring bus; (2) the terminal voltages between the switches have the same magnitude. For frequency control, the offset value is set via automatic synchronizer, as Fig. 8 (a). For the terminal voltage control, the control figure is shown as Fig. 8 (b). The switch block presents the switches’ status, opening or closing. If the switches are opening, the switch block jumps to PI controller; if the switches are closing, the switch block jumps to the droop controller. Offset_Fre. Fre._Bus Fre._Gen + + + PI_Fre. Fre._Bias Droop_Fre. (a) Frequency controller Vol._Bus Vol._Gen + PI_Vol. Vol._Bias Droop_Vol. (b) Voltage controller Fig.8 Frequency controller and voltage controller When (1) the frequency difference reaches the offset and maintains stable, (2) the voltage difference is zero and (3) the phase difference is zero, the automatic synchronizer sends out the trigger signals to the bus-ties. At that moment, the power-generating subsystem unit is synchronized to the ring bus. After the synchronizing mode and the close of the switches, the automatic synchronizer becomes working in power sharing mode. The control process of automatic synchronization is illustrated in Fig. 9. If ( On / Off == True) No Yes If ( First == True) No Yes Measurement for: Voltage_ Magnitudes Frequencies and Phase_ Differences Bias_ Speed and Bias_ U for Isochronous Mode If ( If ( Steady == True & Active == False) Steady == True ) No Yes Active == True Yes Bias_ Speed and Bias_ U for synchronization process If ( Steady == True & Synchronization Limitation == True ) Active == True Fig.9 The control process of automatic synchronization No Bias_ Speed and Bias_ U for Droop Mode 2.4. AC Cable Model The three-phase shielded PI model of cable is presented in Fig. 10. The purpose of the model is to take the physical characteristics of a given and compute the electrical parameters of the given cable (resistance, capacitance, and inductance) [5]. The model was designed to provide modeling of three-phase PI model of cables in electric power systems. This version of the model is a RLC lumped parameter model. The electrical parameters are calculated in per unit length and then multiplied by the length of the cable to find the lumped parameter values. The one phase PI model is shown in Fig. 11 (a). The RLC lumped parameter model of three-phase PI model cable is shown as the red circle in Fig. 11 (b). Fig.10 Three phase PI model of cable in EntityBuilder (a) one phase PI model of cable (b) connection of three-phase PI model of cables Fig.11 PI model of cable The parameters are shown in Table. 3 and Fig. 12. Table.3 Parameters of PI model of cable Name aRadius bRadius Conductivity Frequency InitialCurrent Length Permeability Permittivity RelativePermeability RelativePermittivity Description As Fig. 8 As Fig. 8 Conductivity of the conductors Frequency of operation Initial current in the three phases Length of the cable Permeability of the material Permittivity of the dielectric Relative Permeability of the material Relative Permittivity of the dielectric Default Value 0.01262 0.0519 59000000 60 0 100 1.26E-06 8.85E-12 1 2.3 Units m m S·m-1 Hz A m H m-1 F/m - Fig.12 Geometrical parameters of the unshielded cable The distributed parameters of resistance, inductance, and capacitance are found in per unit/length values based upon the following equations. These distributed parameter values are then multiplied by the length of the cable to provide the lumped parameter values used for the modeling of the cable. 𝛿= 1 √𝜋∗𝜇∗𝜎∗𝑓 𝑚 (10) 𝜌 𝑅 = 𝜋∗(𝑎𝑅𝑎𝑑𝑖𝑢𝑠2 ) Ω/𝑚 µ (11) 𝑏𝑅𝑎𝑑𝑖𝑢𝑠2 𝐿 = 2𝜋0 ∗ 𝐿𝑛 (𝑎𝑅𝑎𝑑𝑖𝑢𝑠2 ) 𝐻/𝑚 𝐶= µ0 𝑏𝑅𝑎𝑑𝑖𝑢𝑠2 ∗𝐿𝑛( ) 2𝜋 𝑎𝑅𝑎𝑑𝑖𝑢𝑠2 2 2 1 µ0 𝑏𝑅𝑎𝑑𝑖𝑢𝑠 µ 𝑏𝑅𝑎𝑑𝑖𝑢𝑠 2 (( ∗𝐿𝑛( )) −( 0 ∗𝐿𝑛( )) ) 𝜇𝜀 2𝜋 2𝜋 𝑎𝑅𝑎𝑑𝑖𝑢𝑠 𝑎𝑅𝑎𝑑𝑖𝑢𝑠2 (12) 𝐹/𝑚 Where: f = frequency of operation of the cable (Hz) µ = Permeability 𝜇0 = Relative Permeability ε = Permittivity 𝜀0 = Relative Permittivity σ = Conductivity of the conductor (Ω.m) δ = Skin depth (m) ρ = 2.08E-8 (Ω/m) 3. Demonstration of Power Generating System in VTB 2009 The MVAC power generating system is developed in VTB 2009, as shown in Fig.13. (13) Fig.13 Overview of simulation environment in VTB2009 The system is divided into four subsystems: 1. Subsystem - “Supervisory_Controller”: It defines the sequence of 4 turbo-generators connected to the ring bus. Fig.14 Connection of supervisory controller 2. Subsystem – “Two_36MW_Gens”: It composes of two units 36 MW turbo-generators with their automatic synchronization controller to make them automatically connect to the ring bus. Fig.15 Details of two MTGs with their automatic synchronizer (The same structure with two ATGs) 3. Subsystem – “Two_4MW_Gens”: It composes of two units 4 MW turbo-generators with their automatic synchronization controller to make them automatically connect to the ring bus. It has the same topology with “Two_36MW_Gens” subsystem, but the power level. 4. Subsystem – “Ring_Bus”: It connects the four turbo-generators via 4 buses in a ring arrangement. Each bus has a lupmed load connected.Now, the load centers are presented as lumped loads in simulations. Fig.16 Structure of 4 buses in ring arrangement The default parameters of the testbench are listed in Table.4. Table.4 Default parameters of testbench Main Turbine Generator Auxiliary Turbine Generator 2 Inertia Constant: HTurbine = 2.5 s Inertia Constant: HTurbine = 3.5 s Droop Setting: 4 % Droop Setting: 4 % Rated Power: P = 36 MW (pf = 0.95) Rated Power: P = 4 MW (pf = 0.95) Rated frequency: f = 60 Hz Rated frequency: f = 60 Hz Transient reactance: Xd’ = 0.3 Transient reactance: Xd’ = 0.3 Transient time constant: Td0’ = 8.0 s Transient time constant: Td0’ = 8.0 s Inertia Constant: HGenerator = 0.5 s Inertia Constant: HGenerator = 0.5 s Rated Voltage: V = 4.16 kV Rated Voltage: V = 4.16 kV Synchronous reactance: Xd = 1.81 Synchronous reactance: Xd = 1.81 Subtransient reactance: Xd’’ = 0.23 Subtransient reactance: Xd’’ = 0.23 Subtransient time constant: Td0’’ = 0.03 s Subtransient time constant: Td0’’ = 0.03 s Cable* Length = 20 m Resistance = 4.157E-005 Ohm / m Inductance = 5.67E-007 H / m Capacitance = 6.03E-011 F / m RFCL RHigh = 100 kOhm RLow = 0.001 Ohm increase = 100 microseconds decrease = 100 microseconds * the default values of PI model of cable are used for the calculation of RLC The sharing powers from turbine generators are presented in Fig. 17. During the synchronization process, as shown in Fig. 17(a), the total load is 32MW (lower than the capacity of MTG1 (36MW)) which is shard by 4 turbine generators. Two MTGs are 14.62MW individually, and two ATGs are 1.55MW individually after the synchronization process completed. After that, more loads were added to the ring-bus at 100s and the total produced power is 67.4MW (84.25% of the system capacity (80MW)). The two MTGs are 30.4MW individually, and the two ATGs are 3.3MW individually, as shown in Fig. 17(b). (a) Power sharing during synchronization process (b) Power sharing at 84.25% of system capacity Fig.17 Power distribution among the 4 turbine generators REFERENCE: [1] Rowen, W. I., 1983, "Simplified Mathematical Representations of Heavy-Duty Gas Turbines," ASME J. Eng. Power, 105, pp. 865 – 869 [2] Prabha Kundur; “Power System Stability and control”, EPRI, McGraw-Hill, 1993 [3] P. M. Anderson and A. A. Fouad “Power system stability and control”, IEEE Press, 2002 [4] Woodward, “Speed Droop and Power Generation”,application note 01302 [5] Nadir Idir, Yannick Weens and Jean-Jacques Franchaud, Skin Effect and Dielectric Loss Models of Power Cables, IEEE Transactions on Dielectrics and Electrical Insulation Vol. 16, No. 1; February 2009