1
TABLE OF CONTENTS
EXECUTIVE SUMMARY
1. INTRODUCTION
1.1 Overview
1.2 Municipalities within the District
1.3 Political and Administrative Leadership and Seat of District
1.4 Political Representation
2. SERVICE DELIVERY
2.1 Household Infrastructure
2.2 Sanitation
2.3 Water
2.4 Electricity
2.5 Refuse Removal
2.6 Service Provider
3. AUDIT OPINIONS
4. STATE OF LOCAL GOVERNMENT ASSESSMENT
4.1 Overview of findings on assessment in the Municipality
4.1.1 Governance
4.1.2 Financial Management and Viability
4.1.3 Service Delivery
5.
6.
7.
INFRASTRUCTURE PRIORITIES IN TERMS OF THE MUNICIPAL
TURN-AROUND STRATEGY
MIG PROJECTS
VULNERABILITY CLASSIFICATION
2
9
9
9
9
8
8
8
8
10
10
10
11
11
11
3
4
4
6
6
6
12
15
EXECUTIVE SUMMARY iLembe is the smallest of the ten district councils in KwaZulu-Natal, extending north of eThekwini Municipality along the east coast. The northern areas of Ndwedwe, the central corridor of Mandeni and KwaDukuza Municipality are the commercial farming hubs of the district. Areas of urbanisation in the district comprise KwaDukuza / Stanger,
Mandeni, the Dolphin Cost and Nkwazi. There are informal settlements with limited facilities or infrastructural services on the periphery of the developed areas and within the towns.
With almost half the total workforce unemployed and approximately three-quarters of households receiving a monthly income below R1 600, poverty in the district is severe.
The provision of basic infrastructure is hampered by topographical restraints, low densities and low affordability levels, particularly in rural and traditional areas. Service infrastructure needs upgrading and maintenance. Rural areas are severely affected by a lack of basic services and continued service delivery backlogs. Bulk water supply is a major constraint and is in urgent need of attention. Very few rural settlements have access to household electricity. iLembe district has an average access to infrastructure amongst the districts in the province. An overview of household access to infrastructure in the district shows an improvement in access from 38% in 1996 to 52% in 2009.
All municipalities in iLembe district obtained have improved audit outcomes over time to achieve financially unqualified audit outcomes with findings. iLembe District was not highlighted in the KwaZulu-Natal State of Local Government
Assessment in any specific category as in the most serious category of classification of municipalities, but Maphumulo Local Municipality has been identified as one of the municipalities that recorded serious challenges in most of the focus areas.
In terms of its Municipal Turn-Around Strategy iLembe has prioritised improving maintenance and reservoirs, installing generators at water schemes, as well as attending to asset register, systems and processes.
Two of the four local municipalities in the iLembe District have been classified as in the category of most vulnerable by DCoG in terms of functionality, socio-economic profile and backlog status. This profile confirms that infrastructure prioritisation in iLembe
District should focus on addressing water supply, as well as improving operations of water schemes and maintenance.
3
1. INTRODUCTION
1.1 Overview 1 iLembe District Municipality is referred to as the ‘Jewel of the Zulu Kingdom’ because of its wealth of cultural resources. There is international and local recognition and interest in King Shaka and Zulu culture and history. iLembe is the smallest of the ten district councils in KwaZulu-Natal. It extends north of eThekwini Municipality along the east coast. The district begins about 75 km north of the metro boundary and stretches some
25 km beyond the mouth of the Tugela River. The western boundary of iLembe runs roughly parallel to the coastline at an average distance of about 45 km from the coast.
The northern areas of Ndwedwe, the central corridor of Mandeni and KwaDukuza
Municipality are the commercial farming hubs of the district. These commercial areas
(31% of the land) are mainly under privately owned sugar cane. Areas of urbanisation in the district comprise KwaDukuza / Stanger, Mandeni, the Dolphin Cost and Nkwazi.
Land uses are typically urban mixed uses with high levels of infrastructural and service development and an adequate provision of social facilities and services to support the residents. Industrial development is concentrated in KwaDukuza, Isithebe and
Darnall.
There are informal settlements with limited facilities or infrastructural services on the periphery of the developed areas and within the towns.
The existence of village centres such as Maphumulo and Ndwedwe in the west and
Nyoni and Mbizimbelwa in the north depend on social services, a welfare office or a similar state service. Wholesale commercial activities have developed and the villages have emerged as supply centres and transportation hubs to the remote rural areas the district. iLembe offers easy access to the province’s other major attractions, such as game reserves, the St Lucia World Heritage Site, the Drakensberg Mountains, the battle fields and the city of Durban.
The increased focus on tourism has resulted in a substantial increase in coastal developments. The sub-tropical climate positions the area as an all-year-round holiday destination and the warm Indian Ocean provides comfortable swimming at any time of the year. Other significant competitive advantages that iLembe District offers include strong cultural and historical links to India, the United Kingdom and Mauritius; its location between the ports of Durban and Richards Bay; excellent transport infrastructure; the beautiful coastline and beaches; and the quality of its environmental control. The main urban and economic settlements are located along the R102 and north-south rail linkage, in particular at the intersection of the R102 with the R614 and
1 1 Source: Gaffney’s, November 2009: Local Government in South Africa 2009 – 2011, Official
Yearbook: p 752 - 753
4
R74. This includes the development of Tongaat (located outside the district) in the south, Groutville, Stanger, Darnall and Mandeni / Isithebe in the north.
Rural settlements are emerging in the areas to the west of the commercial agricultural enterprises. There are low density rural settlements in the inaccessible areas of the west.
A high proportion of the population is under the age of 34, with 49% being younger than
19. This poses challenges in relation to future education, health, recreation and other social services. The combination of population migration away from rural to urban areas and the direct impact of HIV/AIDS accounts for the negative population growth in two of the local areas. At approximately 10% and 12% respectively, the levels of illiteracy in
Mandeni and KwaDukuza are relatively low. Illiteracy in Maphumulo and Ndwedwe are higher at approximately 21% and 24% respectively. There is thus a great need for adult education facilities and programmes. In addition, access for school leavers to tertiary education is limited. The low levels of education will be a major constraint to future economic development.
Unemployment in the region as a whole stands at 48% – considerably higher than the national average of 36%. With almost half the total workforce unemployed and approximately three-quarters of households receiving a monthly income below R1 600, poverty in the district is severe. The major sectors of employment in the district are manufacturing (35.5%), community service (18.4%), agriculture (13.9%) and wholesale / retail (10.8%). A number of well established industries operate in the district, specifically in the clothing and textile sector. iLembe has sugar and paper mills, and a variety of light industries has also developed.
The provision of basic infrastructure is hampered by topographical restraints, low densities and low affordability levels, particularly in rural and traditional areas. Service infrastructure needs upgrading and maintenance. Rural areas are severely affected by a lack of basic services and continued service delivery backlogs. Bulk water supply is a major constraint and is in urgent need of attention. Some 38% of the population still obtain water from rivers and streams and rural areas either have no sanitation or rely on pit latrines. Very few rural settlements have access to household electricity. Electricity provision at schools and health facilities is especially critical. Refuse removal is limited to urban areas. Dumping of refuse has become a problem, particularly in denser rural settlements. Social facilities are generally inadequate, especially in rural areas. Housing in the rural areas consists largely of traditional rural dwellings. Urban centres are characterised by the private residential developments of the well developed Dolphin
Coast that cater for the wealthy. Surrounding low-cost housing and informal settlements have proliferated as job seekers flock to the district. Significant progress has been made in the delivery of housing to the poor in Mandeni and KwaDukuza municipal areas but limited progress has been made in Ndwedwe and Maphumulo where dispersed settlement patterns pose a challenge to housing delivery.
5
1.2 Municipalities within the iLembe District
The details of the four local municipalities within the District is tabled below:
Table 1: Statistics of the iLembe District and Local Municipalities
Municipalities within the
District
Area (km ²) in 2009
Area (km
2
) after 2011
Local Govt Elections
& % change
Population No. of
Households
Poverty Rate iLembe District Municipal 3,269.26 3,269.26 - 534,766 126,078 79.00%
KwaDukuza Local Municipality 670.43 734.98 9.63% 164,072 45,033 43.04%
Mandeni Local Municipality 545.48 545.48 - 124,197 34,123 45.40%
Maphumulo Local Municipality 895.91 895.91 - 110,514 20,182 75.59%
Ndwedwe Local Municipality 1,157.44 1,092.89 -5.58% 135,984 26,740 66.59%
1.3 Political and Administrative Leadership and Seat of District 2
Political Leadership: Executive Mayor: Mr S W Mdabe
Administrative Leadership: Municipal Manager: Mr M D Newton
Leading
Parties in the
Elections
1 st
2 nd
3 rd
4 th
Totals
The head office of the District is located in KwaDukuza.
1.4 Political representation 3
Local Government Elections 2006
Party Party Votes and
%
Ward Votes and
%
Councillor Seats
Party Seats %
ANC
IFP
DA
MF
Other
65,271 53.1% 64,100 52.1%
46,247 37.7% 46,696 37.9%
7,111
725
3,471
5.8%
0.6%
2.8%
7,102
575
4,593
5.8%
0.5%
3.7%
ANC
IFP
DA
Other
122,825 100% 123,066 100% Totals
Provincial Elections 2009 National Elections 2009
Party Votes and % Party Votes and %
15 51.7% IFP
12 41.4% ANC
2 6.9% DA
COPE
Other
29 100%
141,186 70.7% ANC
41,139 20.6% IFP
11,194 5.6% DA
1,870 0.9% COPE
4,201 2.1% Other
199,590 100%
143,639 71.1%
38,035 18.8%
13,052 6.5%
2,045 1.0%
5,231 2.6%
202,002 100%
2
Source: Ilembe DM, August 2011
3 UPDATE Aug’09: DC40 seats - ANC(50%) 6 seats, IFP(42%) 5 seats, DA(8%) 1 seat, Total 12 DC40 seats
6
Figure 1: 2011 Local Government Election results and seat allocations:
The ANC is the leading party in terms of proportional DC40 Seats in iLembe, with 8 seats of 12 seats.
7
0,60
0,50
0,40
0,30
0,20
0,10
0,00
2. SERVICE DELIVERY 4
2.1 iLembe District Municipality Household Infrastructure
KZN - DC29 iLembe District Municipality
0,80
0,70
KZN - DC29 iLembe…
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
Source: IHS Global Insight Regional eXplorer version 574 iLembe district has an average access to infrastructure amongst the districts in the province. An overview of household access to infrastructure in the district shows an improvement in access from 38% in 1996 to 52% in 2009.
2.2 Sanitation
With regard to access to sanitation, the district municipality’s household access to hygienic toilets has gone up from 34% in 1996 to 50% in 2009. The improvement in access to sanitation in general in the Municipality is mainly due to the increase in the use of pit latrines with ventilation which was around 30% in 2009.
2.3 Water
Access to piped water above RDP level increased from 36% to 58% from 1996 to 2009.
Similarly, there has been a slight increase as well in access to piped water below RDP level. About 25% of the households do not have access to piped clean water at all.
4 Sources: IHS Global Insight Regional eXplorer version 574 and Municipal Demarcation Board, 2008:
National Report on Local Government Capacity, District and Local Municipalities, MDB Capacity
Assessment, 2007/2008.
8
2.4 Electricity
The increase in electricity connections is the biggest infrastructure achievement in the municipality. In 1996, household access to electricity connections was at a lower level of
40%. Access has, however, increased over the years by almost 40% reaching 78% by
2009.
2.5 Refuse removal
Access to formal refuse removal service increased from 23% in 1996 to 30% in 2009 in the District Municipality. While this is the case, personal refuse removal went up over the years reaching 60% in 2009. The high levels of personal refuse removal must be taken in the context of low settlement densities, where on-site disposal or backyard burning of waste is sometimes appropriate.
2.6 Service provider iLembe district does not have authority and does not perform the electricity reticulation function. The district, however, has authority and performs potable water and sanitation functions. The district has no authority and is not performing the refuse removal, refuse dumps and solid waste disposal function.
3. AUDIT OPINIONS
Table 3: Audit Opinions of the District and Local Municipalities
Municipality Audit
Opinion
2005/6
Audit
Opinion
2006/7
Audit
Opinion
2007/8
Audit
Opinion
2008/9
Audit
Opinion
2009/10 iLembe DM
Mandeni LM
Financially unqualified with other matters
Qualified
KwaDukuza
LM
Financially unqualified with other matters
Maphumulo
LM
Financially unqualified with other matters
Ndwedwe LM Financially unqualified
Qualified
Qualified
Financially unqualified with other matters
Qualified
Financially unqualified
Qualified
Financially unqualified with other matters
Financially unqualified with other matters
Qualified
Financially unqualified
Financially unqualified with findings
Financially unqualified with findings
Financially unqualified with findings
Financially unqualified with findings
Financially unqualified
Financially unqualified with findings
Financially unqualified with findings
Financially unqualified with findings
Financially unqualified with findings
Financially unqualified
9
with other matters with other matters with other matters with findings with findings
Source: Auditor-General 2009 and 2011, see. www.agsa.co.za
KwaDukuza and Ndwedwe local municipalities secured financially unqualified audit outcomes from 2005/6 to 2009/10 in succession. In the five financial years starting from
2005/6 to 2009/10 iLembe district, Mandeni and Maphumulo each obtained qualified audit results twice.
4. STATE OF LOCAL GOVERNMENT ASSESSMENT
4.1 Overview of findings on assessment in the municipality iLembe District was not highlighted in any specific category as in the most serious category of classification of municipalities. Three of the local municipalities (Maphumulo,
Ndwedwe, KwaDukuza) have been identified as facing serious challenges. These challenges are discussed in more detail below.
Maphumulo Local Municipality has been identified in the KwaZulu-Natal State of Local
Government Assessment as one of 19 municipalities that recorded serious challenges in most of the focus areas and should therefore be prioritised for immediate intervention.
4.1.1 Governance
Maphumulo Local Municipality is one of 17 municipalities in KwaZulu-Natal affected by political instability. The Provincial Report lists a number of causes of political instability including: the lack of understanding and adherence to the roles and responsibilities of political office bearers, interference in council matters from the regional and provincial political structures, a lack of deliberations on matters in council, domination of some councils by politically powerful administrations, power struggles between political office bearers from same party and a lack of communication and public participation frameworks creates environment for uncoordinated interaction with community.
Ndwedwe Local Municipality is among the nine municipalities in KZN that require immediate support to improve their public participation processes. Some of the challenges that the identified municipalities are facing include: lack of stakeholder consultation; no structured public participation framework; lack of delivery of services;
Ward Committees being political rather than service delivery oriented; and there is a need to clarify roles and functions of CDWs.
Ndwedwe Local Municipality is one of 24 councils that do not seem to perform any oversight function and should be supported to implement the oversight role. The
Provincial Report states that the lack of Councillor Oversight has emerged as the single most contributing factor to poor governance and service delivery. A large number of
Councillors appear not to appreciate the nature and importance of their oversight role and the administration seem to ignore the need for oversight due to the administrative and accountability implications it will have for them.
10
4.1.2 Financial Management and Viability
Maphumulo Local Municipality is also one of 30 municipalities in KwaZulu-Natal that are facing serious financial management challenges. The Provincial Report lists some of these concerns, including: poor financial planning, inadequately skilled staff appointed, lack of proper financial controls, poor financial competencies of elected representatives, and unemployment and poverty had a negative effect on credit control and income.
There is also a general perception that councils are not transparent when it comes to financial policies and activities and that the reason for this is to hide their corrupt practices from the public.
4.1.3 Service Delivery
KwaDukuza municipality is one of three local municipalities that have serious challenges in labour relations.
5. INFRASTRUCTURE PRIORITIES OF THE MUNICIPAL TURN-AROUND
STRATEGY
The iLembe District Municipality identified a number of priorities on aged infrastructure in the ILembe Turn-Around Strategy. The strategy is based on improving maintenance and reservoirs, installing generators at water schemes, as well as attending to asset register, systems and processes.
Table 4: Infrastructure delivery in terms of the MTAS
Water Service Generators at Asset Register Systems &
Interruption
Maintenance water schemes Processes
Challenges Install generators at other schemes
Update Asset
Register
Upgrade telemetry system
Municipal
Actions
Improve water supply
Finalise maintenance plan
Replacement of
CBD Mains where required, reactive maintenance of reservoirs, minimizing interruptions to water supply, leak detections, meter installations.
Secure generator at
Sander Street
Procure other generators for waterworks
Secure funding needs (R1.5 million) to secure generators
Appoint service provider to do asset registry
Secure funding
Update
Telemetry system –
KwaDukuza pahse 1, then extend programme to
Mandeni
Prepare Security
Plan – install
CCTV in phases
11
Approval of draft maintenance report and reservoir cleaning programme
6. MIG PROJECTS 5
Table 6: MIG projects
Municipality Project name MIG funds Actual expenditure in the 2010/11 financial year
Project status
(Registered/design/ tender/constructio n)
Project category
(e.g. water, sanitation, PMU)
Mandeni LM Masomonco water Project R 7,179,543.00 R 45,006.84
Macambini
Water Supply
Phase 2 (AFA)
R 101,076,781.00 R 7,601,917.99
Ndulinde Water
Supply Scheme R 116,579,664.00 R 8,725,279.88
Ndwedwe
Quartz Daffodil
Road Link
(AFA2) MIS
160517, 173813 R 5,786,156.95
Hlomendlini Bus
Route Phase 2
(AFA) MIS
175332, 191555 R 8,266,767.84
Tugela Mouth
Roads
Rehabilitation and Hard
Surface (AFA)
R 8,850,157.08 MIS 175333
Masomonce
Mini-Bus Route
(AFA) MIS
202109
Sundumbili
Roads Phase 4
(AFA) MIS
R 12,658,761.05
193790
Sundumbili
R 5,243,179.12
Roads Phase 5
(AFA) MIS
193791 R 7,086,085.38
Nyoni Taxi
Route - Phase 1 R 3,298,919.00
Ozwathini R 34,306,188.00
R 3,175.00
R 1,218,276.99
R 698,455.92
R 3,153,557.43
R 5,210,219.93
R 7,084,544.23
R 218,770.50
R 411,323.97
Completed
Construction
Construction
Completed
Construction
Construction
Design & Tender
Construction
Construction
Water
Water
Water
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Registered
Completed
Road & Stormwater
Water
5 According to the June 2011 non-financial report on Municipal Infrastructure Grant, KwaZulu-Natal has not adopted the new format of reporting on MIG projects in that province. As a result, it becomes a challenge to track the implementation of MIG projects in that province.
12
LM
KwaDukuza
LM
Water Supply
Scheme
(Gcwensa/
Mlamula)
(AFA1) MIS
167753
Ozwathini
Gcwensa
Phambela
Water Scheme
(AFA) MIS
192461
Luthuli CWSS
Phase 2 (AFA)
MIS 172015
Ozwathini -
Gcwensa /
Nodwengu
Water
Ndwedwe Ward
16 VIP
Sanitation
KwaPhewa
Access Road -
Ward 15
Njubanjuba
Road
Okhalweni
Road
Bhekamafa
Road
R 30,143,188.00
R 4,788,596.00
R 31,078,364.00
R 10,430,392.00
R 2,086,010.00
R 2,257,188.60
R 2,051,988.60
R 1,744,190.88
Esihlahleni
Road (AFA)
MIS 199205 R 2,403,110.88
Mahedeni Road R 7,337,917.80
Sanguphe Road R 7,694,960.10
Mavundla Road R 3,077,985.18
Magwaba to
Myongo Road R 3,180,584.04
Ehoqweni Road R 3,796,181.76
Refurbishment of Maurice
Perry Road
Sewer Pump
Station (AFA1)
R 2,482,064.54 MIS 165978
San Souchi -
Bulwer Farm
Water
Extension
(AFA) 195607
Lindelani VIP
Conversion
Sanitation
R 34,488,365.00
Project
Khuzwayo Bus
R 26,979,310.00
Route R 2,000,000.01
Hangoes Bus
Route Phase 3 R 749,999.99
R 1,150,976.91
R 2,309,617.91
R 7,549,142.39
R 5,255,555.19
R 489,200.15
R 2,038,113.68
R 918,213.95
R 620,840.86
R 2,105,952.99
R 2,484,998.66
R 4,315,280.82
R 1,968,077.48
R 2,343,000.52
R 2,839,537.89
R 326,636.01
R 8,446,822.47
R 26,979,310.00
R 1,771,157.38
R 652,288.88
13
Completed
Completed
Construction
Completed
Completed
Construction
Completed
Completed
Water
Water
Water
Construction
Construction
Construction
Construction
Construction
Construction
Design & Tender
Design & Tender
Registered
Registered
Construction
Sanitation
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Sanitation
Water
Sanitation
Road & Stormwater
Road & Stormwater
Maphumulo
LM
Dube Village
Bus Route R 800,000.00
Sakhumkhanya
Bus Route
Phase 3 R 2,000,000.01
Etete Phase 4
Community Hall R 950,000.00
Nonoti
Community Hall R 950,000.00
Mgigimbe
Community Hall R 950,000.00
Dendethu
Community Hall R 950,000.00
Nonoti Main
Road R 1,500,000.00
Ntshaweni
Priority 1 Bus
Route (Phase 2 and 3) R 2,000,000.00
Chief Albert
Luthuli Bus
Route R 1,265,000.00
Steve Biko Bus
Route Phase 3 R 2,000,000.00
Mnyundwini
Bus Route R 1,000,000.00
Malende Bus
Route Phase 2 R 1,303,000.00
Sokiesimbone
Bus Route
Phase 3 R 1,800,000.00
Nyathikazi Bus
Route Phase 4 R 2,000,000.00
Shakaville
Wellness and
Fitness Centre R 707,000.00
Mbozamo
(North exit) Bus
Route
Ntshawini
(Ward 15)
Sports Field
R 1,140,000.00
R 2,399,739.53
Nyathikazi
Sports Field
Etete Bus
Route
R 83,886.47
R 1,000,000.00
Khatha Road
Ntombazane
Road
R 4,108,360.50
R 1,295,701.20
Nkoneni /
Mbusweni Road R 3,440,691.00
Gobuphahla
Road (A2764) R 1,070,350.56
Isihlwehlwe
Road (A2766)
Phase 2
Maphumulo
Town Internal
R 1,445,181.19 roads, related
Stormwater and R 10,752,890.40
R 187,519.46
R 247,628.81
R 950,000.00
R 950,000.00
R 407,634.44
R 950,000.00
R 820,845.71
R 613,746.74
R 286,460.63
R 382,948.52
R 200,287.46
R 287,713.26
R 373,421.54
R 1,320,280.99
R 222,336.04
R 295,542.48
R 872,289.75
R 83,886.47
R 147,572.72
R 870,779.06
R 312,676.57
R 56,981.47
R 51,488.24
R 697,076.27
R 5,893,527.30
14
Construction
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Road & Stormwater
Road & Stormwater
Multi purpose community halls
Multi purpose community halls
Multi purpose community halls
Multi purpose community halls
Road & Stormwater
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Design & Tender
Registered
Registered
Registered
Construction
Construction
Construction
Construction
Construction
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Local Amenities
Road & Stormwater
Sport Facility
Sport Facility
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Side Walks
Construction of
Town Hall R 4,998,987.78
Street Lighting R 1,785,703.98
Construction of
Sidewalks
Construction of
R 1,433,760.90
Ablution Blocks in Town Centre R 1,116,411.02
Ntunjambili
Roads
Construction of
Fundani Gravel
R 15,705,900.01
Road R 7,602,167.04
Mbusweni Road R 6,055,006.26
Samungu Road R 8,844,879.73
Phase 2 -
Construction of
Sidewalks R 1,234,620.00
Mambulu Road R 8,440,742.40
Emnyameni
Sports Complex R 15,988,498.86
Tunnel Farming R 6,982,199.06
Source: All MIG projects, June 2011
R 425,425.26
R 525,490.00
R 303,799.08
R 110,887.93
R 4,676,035.00
R 280,079.84
R 185,513.15
R 271,553.32
R 129,625.75
R 255,120.60
R 246,810.00
R 205,950.19
Registered
Construction
Construction
Registered
Registered
Registered
Registered
Registered
Registered
Registered
Registered
Registered
Multi purpose community halls
Street / Community
Lighting
Sidewalks
Sanitation
Road & Stormwater
Road & Stormwater
Road & Stormwater
Road & Stormwater
Sidewalks
Road & Stormwater
Sport Facility
Markets
The June 2011 non-financial report on MIG states that iLembe district and its locals did not submit their June MIG reports. In the district of iLembe all local municipalities have
MIG projects with roads and stormwater in dominance. However, in Maphumulo local municipality most projects have only been registered and as a result they are yet to advance to the construction stage.
7. VULNERABILITY CLASSIFICATION
The DCoG Municipal Spatial Classification System was designed to develop municipal profiles according to spatial location, based upon results from indicator sets on functionality, socio-economic profile and backlog status. Its purpose is to inform a differentiated approach to municipalities.
The four municipal classifications developed by DCoG are:
Class 1: Most vulnerable (57 local municipalities)
Class 2: Second most vulnerable (58 local municipalities)
Class 3: Second highest performing (58 local municipalities)
Class 4: Highest performing (58 local municipalities)
The four local municipalities in the iLembe District can be classified as follow:
15
Table 6: Vulnerability Classification
Local Municipality Classification
KwaDukuza Highest performing
Mandeni Second most vulnerable
Maphumulo
Ndwedwe
Most vulnerable
Most vulnerable
From this table it is evident that two of the four local municipalities in the iLembe District fall into the most vulnerable category.
16