HYDRAULIC EVALUATION OF LEVEE REPAIR TECHNIQUES A Project Presented to the faculty of the Department of Civil Engineering California State University, Sacramento Submitted in partial satisfaction of the requirements for the degree of MASTER OF SCIENCE in Civil Engineering by Syada Iffat Ara SPRING 2012 © 2012 Syada Iffat Ara ALL RIGHTS RESERVED ii HYDRAULIC EVALUATION OF LEVEE REPAIR TECHNIQUES A Project by Syada Iffat Ara Approved by: __________________________________, Committee Chair Saad Merayyan, Ph.D. ____________________________ Date _______________________________, Second Reader Kevin Flora, P.E. __________________________ Date iii Student: Syada Iffat Ara I certify that this student has met the requirements for format contained in the University format manual, and that this Project is suitable for shelving in the Library and credit is to be awarded for the Project. __________________________, Graduate Coordinator Cyrus Aryani, Ph.D., P.E., G.E. Department of Civil Engineering iv ___________________ Date Abstract of HYDRAULIC EVALUATION OF LEVEE REPAIR TECHNIQUES by Syada Iffat Ara This project presented the techniques of levee erosion repair and their hydraulic evaluation. For the project purpose a site located at San Joaquin River at River Mile 71.5, Right Bank (SJR RM 71.5R) has been selected. The site is located at as outside bend of a tight meander and is subjected to severe erosion. In this study, a simulation model using HEC-RAS hydraulic model has been performed to determine the existing hydraulic characteristics for the project design flow and 100-year flow and another simulation model has been performed to determine the impact of the repair to the existing system. The design of the erosion site involved alternative analysis and selection of most appropriate repair alternative, determining site existing hydraulic characteristics, determining repair cross-section using hydraulic characteristics, and evaluating impact of the repair on existing system. For alternative analysis, four alternatives have been considered and analyzed, and most feasible alternative – waterside repair (rock slope protection) has been selected as a repair option. Hydraulic characteristics of the River have been determined by using HEC-RAS hydraulic model. Using hydraulic characteristics and physical parameters of the site, the minimum required rock size for the v site has been determined by using CHNL PRO software. The repair section for the erosion site has been determined by D50 rock size. As the repair is a waterside repair and is going to encroach into the available conveyance area, a hydraulic analysis is required to evaluate the impact of the repair to the existing system. Once the repair section of the site has been finalized, the impact of the repair to existing system has been analyzed by using HEC-RAS hydraulic model. The results of the analysis show that the repair has very little or insignificant impact on the existing system. If there were any adverse impact on the existing system due to the waterside repair, another alternative other than waterside repair would be considered as a remedy of the erosion problem. _______________________, Committee Chair Saad Merayyan, Ph.D. _______________________ Date vi ACKNOWLEDGEMENTS I am heartily thankful to my advisor, Professor Saad Merayyan for allowing me to pursue this work and for his support and guidance throughout the completion of the project. I would also like to thank Department of Water Resources (DWR) for letting me use the data for the project. Lastly, I offer my gratitude to my husband, Muhammad Waliullah for his support and encouragement during the completion of the project. Finally and above all, Rohaan and Liyana (my two little kids), this is all for you. vii TABLE OF CONTENTS Page Acknowledgements ................................................................................................................ vii List of Tables ............................................................................................................................ x List of Figures .......................................................................................................................... xi Chapter 1. INTRODUCTION ……………. ……………………………………………………….. 1 1.1 Background ............................................................................................................ 1 1.2 Purpose .................................................................................................................. 2 2. GENERAL DESCRIPTION OF THE STUDY AREA ...................................................... 3 2.1 Location ................................................................................................................. 3 2.2 Levee Geometry and Erosion Description ............................................................. 4 3. ALTERNATIVE ANALYSIS ............................................................................................ 7 3.1 Introduction............................................................................................................ 7 3.2 Alternatives ............................................................................................................ 7 3.2.1 Alternative 1 - No Action ...................................................................... 7 3.2.2 Alternative 2 – Waterside Repair........................................................... 8 3.2.3 Alternative 3 – Setback Levee ............................................................. 12 3.2.4 Alternative 4 – Relief Channel ............................................................ 15 3.3 Recommended Alternative................................................................................... 19 4. DESIGN PARAMETERS FOR FEASIBLE ALTERNATIVE ....................................... 20 4.1 Data Gathering and Processing ............................................................................ 20 4.2 Hydraulic Analysis .............................................................................................. 21 4.2.1 Calibration of the Model ...................................................................... 25 4.2.2 Simulation Run .................................................................................... 28 4.3 Riprap Design ...................................................................................................... 32 4.3.1 Stone Shape.......................................................................................... 33 4.3.2 Stone Size and Weight ......................................................................... 33 4.3.3 Layer Thickness ................................................................................... 33 4.3.4 Side Slope Inclination .......................................................................... 34 viii 4.3.5 Channel Roughness, Shape, Alignment and Gradient ......................... 34 4.3.6 Selection of Rock Size ......................................................................... 34 4.3.7 Gradation of Riprap ............................................................................. 37 4.4 Repair Section Design.......................................................................................... 38 4.4.1 Launch Rock ........................................................................................ 39 4.4.2 Riparian Bench .................................................................................... 39 4.4.3 Rock Slope Protection ......................................................................... 39 5. EVALUATION OF REPAIR IMPACT ON EXISTING RIVER HYDRAULICS ................................................................................................................. 46 5.1 Introduction.......................................................................................................... 46 5.2 Hydraulic Analysis .............................................................................................. 46 6. CONCLUSIONS AND RECOMMENDATIONS ........................................................... 56 6.1 Conclusions.......................................................................................................... 56 6.2 Recommendations ................................................................................................ 57 Appendix A Site Photographs .............................................................................................. 58 Appendix B CHANLPRO Program – Input and Output....................................................... 62 Appendix C CDEC Data – Summer Water Surface Elevation Calculation .......................... 65 Appendix D HEC-RAS Output ............................................................................................. 70 Appendix E Compact Disk (CD) – HEC-RAS Model .......................................................... 73 References ............................................................................................................................... 74 ix LIST OF TABLES Tables Page 1. Table 2.2.1 – Standard Levee Prism Geometry ..................................................... 5 2. Table 3.2.2.1 – Soft Costs ...................................................................................... 10 3. Table 3.2.2.2 – Design Estimate Considerations for Alternative 2 ................... 11 4. Table 3.2.2.3 – Cost Estimate for Alternative 2.......................................................... 11 5. Table 3.2.3.1 – Design Estimate Considerations for Alternative 3............................. 14 6. Table 3.2.3.2 – Cost Estimate for Alternative 3.......................................................... 15 7. Table 3.2.4.1 – Design Estimate Considerations for Alternative 4............................. 18 8. Table 3.2.4.2 – Cost Estimate for Alternative 4.......................................................... 18 9. Table 4.2.1.1 – Manning’s n-Value ............................................................................ 27 10. Table 4.2.2.1 – HEC-RAS Output .............................................................................. 29 11. Table 4.3.7.1 – Gradation Table ................................................................................. 38 12. Table 5.2.1 – Manning’s n-Value for Post Repair Condition ..................................... 47 13. Table 5.2.2 – Comparison of WSE and V for Existing Condition and Post Repair Condition ......................................................................................................... 52 x LIST OF FIGURES Figures Page 1. Figure 2.1 Location Map of SJR RM 71.5R........................................................... 3 2. Figure 2.2 Vicinity Map of SJR RM 71.5R ............................................................ 4 3. Figure 2.3 Erosion Progression at SJR RM 71.5R ................................................ 6 4. Figure 3.2.2.1 Alternative 2 Repair Footprint ........................................................ 9 5. Figure 3.2.2.2 Typical Repair Section ................................................................... 10 6. Figure 3.2.3.1 Alternative 3 Repair Footprint ...................................................... 13 7. Figure 3.2.3.2 Typical Repair Section ................................................................... 14 8. Figure 3.2.4.1 Alternative 4 Repair Footprint ....................................................... 17 9. Figure 3.2.4.2 Typical Cross-Section .................................................................... 18 10. Figure 4.2.1 Presentation of Terms in the Energy Equation (Gary W. Brunner, 2010) .......................................................................................................... 22 11. Figure 4.2.2 HEC-RAS Conveyance Subdivision Method (Gary W. Brunner, 2010) .......................................................................................................... 24 12. Figure 4.2.1.1 HEC-RAS Channel Alignment ..................................................... 26 13. Figure 4.2.1.2 Location of VNS Gauging Station ............................................... 27 14. Figure 4.4.1 Typical Cross-Section ....................................................................... 41 15. Figure 4.4.2 Repair Footprint – Plan 1 of 3 .......................................................... 42 16. Figure 4.4.3 Repair Footprint – Plan 2 of 3 .......................................................... 43 17. Figure 4.4.4 Repair Footprint – Plan 3 of 3 .......................................................... 44 xi 18. Figure 4.4.5 Full Repair Footprint ......................................................................... 45 19. Figure 5.2.1 – Cross-Section with Repair on Existing System with 100-Year Water Surface Elevation (From River Station 71.59 to 71.486) ................................. 49 20. Figure 5.2.2 – Water Surface Profile for 100-Year and Design Flow for Existing and Post Project Condition.......................................................................................... 50 21. Figure 5.2.3 – Velocity Profile for 100-Year and Design Flow for Existing and Post Project Condition ................................................................................................ 51 22. Figure D.1 – Cross-Section with Repair on Existing System with 100-Year Water Surface Elevation (From River Station 71.66 to 71.625) ................................. 71 23. Figure D.2 – Cross-Section with Repair on Existing System with 100-Year Water Surface Elevation (From River Station 71.451 to 71.35) ........................................... 72 xii 1 Chapter 1 INTRODUCTION 1.1 Background The purpose of this project is to repair erosion site at the right bank of the San Joaquin River, River Mile 71.5R (SJR RM 71.5R). The SJR RM 71.5R is located in Reclamation District 2064 (RD 2064). RD 2064 is located in San Joaquin County and includes approximately 11.5 miles of levee along the right banks of San Joaquin and Stanislaus Rivers. Levees along the San Joaquin and Stanislaus Rivers provide direct protection to adjacent agricultural land within Reclamation District No. 2064. A levee can be defined as an earthen embankment which protects a region of floodplain from the floodwaters of a river. A levee offers complete protection until either the embankment fails or is overtopped. Levees are the primary method of flood protection along many rivers where floodplains are used primarily for agriculture or are inhabited. An erosion site is defined as a site that is at risk of failure by erosive forces during floods and/or normal flow condition. This study, involved analyzing alternatives to determine the most feasible solution to address the problem, determining hydraulic characteristics of the existing system, designing the most feasible alternative for the erosion site using hydraulic parameters, and finally finding impact of the repair on water surface elevation and velocity of the existing river system. In order to determine the most suitable gradation of the rock material to be used in repair application software called CHANLPRO has been used, and the HEC-RAS has been used to define the hydraulic 2 parameters of the river’s existing condition and to evaluate the impact of repair to the system. 1.2 Purpose The purpose of this study is to determine the most appropriate scour countermeasure and its impact to existing river hydraulics. This study will provide the procedures to be followed in erosion repair and will assess the impact of the erosion repair on the hydraulic performance of the existing system. Based on the levee repair technique, the objective of this study has been group into three different phases. Phase 1: Alternative analysis Phase 2: Design parameters for feasible alternative Phase 3: Evaluate hydraulic impact of the selected alternative to the existing system Chapter 2 3 GENERAL DESCRIPTION OF STUDY AREA 2.1 Location The project site is located along the right bank of the San Joaquin River; about 8 miles southwest of Ripon and 9 miles south of Lathrop, in San Joaquin County, California. The site can be accessed via a County Road off of South Airport Way, 200 feet south of the intersection with Division Road. See Figure 2.1 – location map of the SJR RM 71.5R. Figure 2.1 - Location Map of SJR RM 71.5R 4 The Reclamation District 2064 levees provide flood protection to the Durham Ferry Educational Facility as well as to agricultural and rural residential uses in the vicinity. See Figure 2.2 – vicinity map of the SJR RM 71.5R. Figure 2.2 – Vicinity Map of SJR RM 71.5R 2.2 Levee Geometry and Erosion Description The levee in the project area is generally 10 to 14 feet in height, with a 14 to 15 feet wide crown. The waterside slope is approximately 3H: 1V (horizontal: vertical), while the landside slope is generally 2H: 1V. Maintenance access ramps exist at the north end, mid-section, and south end of the proposed repair, allowing for access to the 5 levee crown. According to United State Army Corps of Engineers (USACE), standard levee prism geometry should follow Table 2.2.1 below. Table 2.2.1 – Standard Levee Prism Geometry Levee Location Crown Width (feet) Riverside Slope (feet/feet) Landside Slope (feet/feet) Freeboard (feet) River and Tributary Levees 20 3H:1V 2H:1V 3 Bypass Levees 20 4H:1V 3H:1V 6 The crown width of the levee in the project area does not match with USACE’s standard levee prism geometry but for this project purpose only erosion problem will be addressed and no work will be done on levee prism. SJR RM 71.5R is located at an outside bend of a tight meander (Radius of Curvature/Channel Width < 2). The direction of flow of the San Joaquin River changes from northeasterly to due west through the course of this bend. Consequently, the right bank of this river bend is subject to significant erosional forces as flows are redirected to the west. During 2006 and 2011 flood seasons, the portion of this repair site was about to fail and emergency placement of revetment were required to protect the levee. The eroded bank is typically 8 to 12 feet in height with slope gradients ranging from 0.5H:1V to vertical. Overhanging (undercut) zones are also locally present and commonly lead to tension cracks and caving of tall, narrow wedges. The tall vertical height and mode of failure are indicative of sandy soils, which are exposed in the bank. Photographs of the eroded bank are in Appendix A. 6 Aerial photographs from November 23, 2004 and May 5, 2009 (five flood seasons) show ongoing erosion throughout the majority of the proposed repair site (see Figure 2.3). Based on these photographs, erosion rates vary along the proposed reach from a minimum of about 2 feet per year to a maximum of about 10 feet per year. Along the downstream reach the average erosion rate is about 8 feet per year. Figure 2.3 – Erosion Progression at SJR RM 71.5R 7 Chapter 3 ALTERNATIVE ANALYSIS 3.1 Introduction Analysis of Alternatives is the analytical comparison of multiple alternatives to be completed before committing resources to one project. The practice of comparing multiple alternative solutions has long been a part of engineering practice. It can be done by proposing a single alternative and justify this option or proposing multiple options with the goal of choosing the best one. For this project purpose four alternatives have been evaluated and the best alternative has been selected as a repair for the erosion site. The best alternative will be able to mitigate the on-going erosion, will have minimum environmental impact, will require minimum maintenance and minimum real estate land acquisition, will have minimum impact on existing infrastructure and will comparative cheaper than other alternatives. 3.2 Alternatives 3.2.1 Alternative 1 - No Action Alternative 1 consists of no present action. Under this alternative, erosion will continue along the exposed bank and into the already compromised levee prism. Catastrophic failure is possible during a single storm or flood water event. Emergency flood fighting efforts and repairs would be anticipated, as required during the 2006 flood event and the 2010-2011 high water event. In addition, further erosion will remove the existing vegetation as the bank migrates landward. 8 Alternative 1 requires no present expenditure. Future costs to implement Alternatives 2 or 3 will likely escalate relative to their present costs due to on-going erosion and the inflation of construction costs. 3.2.2 Alternative 2 – Waterside Repair Alternative 2 consists of armoring the eroding bank of approximately 2,000 lineal feet (including transitions) with rock slope protection (RSP). Specifications for the rock have been presented later in this report based on site’s hydraulic and physical characteristics. Figure 3.2.2.1 illustrates the extend and location of repair of Alternative 2. For this analysis, it has been considered that a minimum 2 feet thick rock slope protection will be provided above summer mean water surface elevation at 2H: 1V slope, 10 feet wide riparian bench will be provided on 2 feet above summer mean water surface elevation and launch rock (discussed later in this report) will be provided below summer mean water surface elevation at 1.5H: 1V slope. 0.75 foot thick agricultural soil will be provided on top of upper rock slope protection to help growth of vegetation. Typical repair section for this alternative has been presented in Figure 3.2.2.1, and soft costs, design estimate considerations and cost estimate for alternative 2 have been presented in Table 3.2.2.1, Table 3.2.2.2 and Table 3.2.2.3 respectively. Alternative 2 mitigates ongoing erosion and enhances the stability of the existing stream bank. Real estate costs and impacts on existing infrastructures and improvements are anticipated to be minimal under this alternative. Maintenance cost associated with this Alternative is expected to be minimal. Under this Alternative the levee height remains as originally constructed and no additional protection is provided for flood/storm events greater than design flow. 9 Figure 3.2.2.1 - Alternative 2 Repair Footprint The estimated cost for Alternative 2 is about $4.2 million a total and about $2,000.00 per linear feet. 10 [Type aFigure quote 3.2.2.2 from the document or theSection summary of an interesting point. You can – Typical Repair position the text box anywhere in the document. Use the Text Box Tools tab to change the formatting of theCosts pull quote text box.] Table 3.2.2.1 - Soft Escalation to bid-point of construction 5% Change order reserve 5% Design and Engineering (Pre-Bid)1 10% Design Contingency (Post-Bid) 3% Engineering Support During Construction 2% Permitting and Legal2 5% Construction Management and Site Inspection 5% Estimated Soft Costs (total) 35% 11 Table 3.2.2.2 - Design Estimate Considerations for Alternative 2 Length of Repair (ft) 2000 Average waterside slope 2:1 Agricultural Soil Thickness (ft) 0.75 Average Riparian Bench Width(ft) 10 Bedding layer thickness (ft) 1 to 2 Table 3.2.2.3 - Cost Estimate for Alternative 2 Item No. Description Unit Quantity Unit Price Total Cost 1 Mobilization and Demobilization Lump Sum 1 $225,000.00 $225,000.00 2 Clearing and Grubbing Acre 3.00 $25,000.00 $75,000.00 3 Earthfill Ton 9,987 $30.00 $299,610.00 4 Agricultural Soil Ton 3,677 $35.00 $128,695.00 5 Bedding Layer Ton 1,390 $51.00 $70,890.00 6 Rock Slope Protection Ton 5,788 $55.00 $318,340.00 7 Launch Rock (Rockfill) Ton 27,384 $50.00 1,369,200.00 8 Beaver Fence 9 Erosion Control Fabric LF 3,909 $8.00 Sq 11,584 $9.00 Yd Subtotal Construction Costs: $31,272.00 $104,256.00 Environmental Mitigation Costs: $2,622,263.00 $655,565.00 (25% of Subtotal Construction Cost) Estimated Soft Costs: $1,147,017.00 Estimated Total Costs: $4.195,620.00 Total Estimated Repair Cost Per L.F.: 2,097.81 12 Notes: 1. Includes geotechnical exploration and topographic/bathymetric surveys. 2. Includes land and right-of-way and environmental permitting activities. 3.2.3 Alternative 3 – Setback Levee Alternative 3 consists of the construction of a setback levee that parallels the existing levee for approximately 3,000 feet including tie-ins. The levee would be constructed approximately 25 feet from the landside toe of the existing levee providing approximately 100 feet of additional erosion protection (See Figure 3.2.3.1 – Alternative 3 Repair Footprint). The setback levee will be constructed with a 3 Horizontal to 1 Vertical (H: V) waterside slope, 20-foot wide crown, and 2H: 1V or 3H: 1V landside slope which is consistent with USACE’ standard levee prism geometry criteria. The crest elevation will be designed to match the existing levee crown elevation and will tie-in upstream and downstream of the erosion site. This alternative will not directly mitigate on-going erosion and bank migration. Ultimately, the setback levee could be subject to the same erosional processes if not provided with some form of protection (i.e. rock slope protection). This alternative would increase the duration of flood protection but will not provide protection against erosion. Alternative 3 has a larger construction footprint relative to Alternative 2 but may result in less environmental impacts by avoiding in-stream construction activities. Maintenance associated with Alternative 3 is anticipated to be low until the river reaches the setback levee. 13 Figure 3.2.3.1 - Alternative 3 Repair Footprint The estimated cost for Alternative 3 is about $7.6 million a total and $2,500.00 per linear foot. The higher cost is attributed mostly to land acquisition, utility and roadway relocation, and import material costs. Typical cross-section for this alternative has been presented in Figure 3.2.3.2, and design estimate considerations and cost estimate have been presented in Table 3.2.3.1 and Table 3.2.3.2 respectively. Soft cost will be same as it is used for Alternative 2. 14 [Type a quote from the document or the summary of an interesting point. You can Figure 3.2.3.2 Typical Repair Section Use the Text Box Tools tab to change position the text box –anywhere in the document. the formatting of the pull quote text box.] Table 3.2.3.1 - Design Estimate Considerations for Alternative 3 Length of Setback Levee (ft) Approx. Height of Setback Levee (ft) Approx. Length of Relocated Access Rd (ft) 3000 13 2000 Average Waterside Slope (H:V) 3:1 Average Landside Slope (H:V) 2:1 Crown Width (ft) 16 15 Table 3.2.3.2 - Cost Estimate for Alternative 3 Item No. 1 2 4 5 6 Description Mobilization and Demobilization Land Acquisition and Temporary Easement Clearing and Grubbing Imported Embankment Fill and Placement Seeding and Erosion Control Unit Quantity Unit Price Total $ Lump Sum 1 $225,000.00 $225,000.00 Acre 20.0 $5000.00 $100,000.00 Acre 9.50 $25,000.00 $237,500.00 Ton 108,761 $35.00 $3,806,635.00 Acre 9.50 $18,000.00 $171,000.00 7 Levee Access Road Sqft 42,000 $2.50 $105,000.00 8 SJC Board of Education Access Road Relocation Sqft 59,800 $7.50 $448,500.00 9 Power Line Relocation LF 3,000 $50.00 $150,000.00 Each 1 $180,000.00 $180,000.00 Each 1 $80,000.00 $80,000.00 LT 3,000 $50.00 $150,000.00 10 11 12 18” Pump Intake Relocation Relocation of Gate and Kiosk at School Entrance GTE Telecommunication Line Relocation Subtotal Construction Costs: $5,653,635.00 Estimated Soft Costs: $1,978,772.00 Estimated Total Costs: $7,632,407.00 Total Estimated Repair Cost Per L.F.: 2,544.00 3.2.4 Alternative 4 – Relief Channel Alternative 4 consists of constructing a relief channel through the point bar upstream of the proposed erosion repair site. The proposed design relief channel is 16 approximately 300 feet in width and 2000 feet in length (see Figure 3.2.4.1 – Alternative 4 Repair Footprint). This alternative may reduce flow in the existing channel during moderate and high water events. However, erosion is still anticipated during high flow conditions with an unprotected bank. Additionally, this alternative may require permanent realignment of the river channel and additional rock slope protection to other areas impacted by the new channel alignment and hydraulics. Maintenance cost associated with this alternative will be higher than other two alternatives as this alternative will have two channels to maintain. Alternative 4 includes the excavating of about 450,000 cubic yards of unconsolidated soil with an impacted area of about 16 acres. Disposal will be off-site and will require additional land acquisition. 17 Figure 3.2.4.1- Alternative 4 Repair Footprint Alternative 4 will cost about $12 million to implement. Future costs may escalate due to unknowns associated with future hydraulics and the need for additional rock slope protection. Typical cross-section of this alternative has been presented in Figure 3.2.4.2, and design estimate considerations and cost estimate have been presented in Table 3.2.4.1 and 3.2.4.2 respectively. Soft cost will be same as it is used for Alternative 2. 18 [Type a quote from the document or the summary of an interesting point. You can Figure 3.2.4.2Typical Cross-Section position the text box anywhere in the document. Use the Text Box Tools tab to change the formatting of the pull quote text box.] Table 3.2.4.1 - Design Estimate Considerations for Alternative 4 Approx. Length of Channel (ft) 2000 Approx. Depth of Channel (ft) 24 Channel Bottom width (ft) 200 Channel Side Slope (H:V) 2:1 Approx. Cross-sectional Area (sqft) 6000 Approx. Excavated Material (cy) 450,000 Table 3.2.4.2 - Cost Estimate for Alternative 4 Item No. 1 2 3 Description Mobilization and Demobilization Vegetation Clearing Channel Excavation and Hauled off Excavated Material Unit Quantity Unit Price Lump Sum 1 $225,000.00 $225,000.00 Acre 26.0 $25,000.00 $650,000.00 CY 450,000 $16.00 $7,200,000.00 Subtotal Construction Costs: Total $ $8,075,000.00 19 Estimated Environmental Mitigation Cost (10% of Construction Cost): $807,500.00 Estimated Soft Costs: $2,826,250.00 Estimated Total Costs: $11,708,750.00 Total Estimated Repair Cost Per L.F.: $4,037.50 Note: Channel cross-sectional area was assumed to be same as the existing main channel and depth is also considered to be same as main channel. 3.3 Recommended Alternative Based on the analysis above, Alternative 2 – Waterside Repair has been selected for remedy of erosion problem for the following reasons: Alternative 2 provides direct mitigation to on-going erosion. This Alternative requires minimal easement and land acquisition. Implementation of Alternative 2 has minimal conflict with existing infrastructure. This has minimum environmental impact and has the ability to mitigate onsite. This Alternative is the cheapest alternative among three possible alternatives discussed in this report. 20 Chapter 4 DESIGN PARAMETERS FOR FEASIBLE ALTERNATIVE 4.1 Data Gathering and Processing Detailed topographic and bathymetric surveys of the erosion site were conducted by the California Department of Water Resources (DWR) and were used for design purpose (Figure 4.4.1 to Figure 4.4.5). The survey used the North American Datum (NAD83) and North American Vertical Datum 88 (NAVD88). The UNET model developed by USACE was converted to HEC-RAS one dimensional steady state model by PBS&J, was used as a base model to determine the hydraulic characteristics (i.e. velocity, stage etc) of the channel. The UNET is a one-dimensional unsteady open-channel flow model that can simulate flow in a single reach on complex networks of interconnected channels. The UNET model for the San Joaquin River Basin was developed by the US Army Corps of Engineers Sacramento District. Unsteady flow UNET model for San Joaquin River Basin was obtained and converted to steady-flow HEC-RAS models by PBS&J, a private consultant for Department of Water Resources to evaluate and analyzed the hydraulic characteristics of the San Joaquin River System. For this project purpose the steady state Hydrological Engineering Center- River Analysis System (HEC-RAS) UNET model converted by PB&J was used as a base model as sufficient geometry data was not available to create a base model for this project purpose. 21 4.2 Hydraulic Analysis The HEC-RAS 4.1.0 model developed by USACE will be used for this study. The HEC-RAS is capable performing one-dimensional water surface profile calculation. Water surface profiles are computed from one cross section to the next by solving the energy equation with an iterative procedure called the standard step method. The energy equation is written as follows: Z2 + Y2 + α2 V2 2g 2 = Z1 + Y1 + α1 V1 2g 2 + he Where: Z1, Z2 = elevation of the main channel inverts in ft Y1, Y2 = depth of water at cross sections in ft V1, V2 = average velocities (total discharge/ total flow area) in ft/sec α1, α2 = velocity weighting coefficients g = gravitational acceleration in ft/sec2 he = energy head loss in ft 22 Following diagram shows the term of Energy Equation: Figure 4.2.1 – Presentation of Terms in the Energy Equation (Gary W. Brunner, 2010) The energy head loss (he) between two cross sections is comprised of friction losses and contraction or expansion losses. The equation for the energy head loss is as follows: he =LS̅f + C | α2 V 2 2 2g α1 V - 1 2g 2 | Where: L = discharge weighted reach length S̅f = representative friction slope between two sections C = expansion or contraction loss coefficient The discharge weighted reach length, L, is calculated using the following equation: L= Llob ̅̅̅̅̅ Qlob + Lch ̅̅̅̅̅ Qch + Lrob ̅̅̅̅̅ Qrob ̅̅̅̅̅+ ̅̅̅̅̅ ̅̅̅̅̅ Q Q +Q lob ch rob 23 Where Llob, Lch, Lrob = cross section reach lengths specified for flow in the left overbank, main channel, and right overbank, respectively ̅̅̅̅̅ ̅̅̅̅̅= arithmetic average of the flows between sections for the left Qlob , ̅̅̅̅̅ Qch ,Q rob overbank, main channel, and right overbank, respectively To determine total conveyance and the velocity coefficient for a cross section, HEC-RAS subdivides the flow area into units for which the velocity is uniformly distributed. The approach used in HEC-RAS is to subdivide flow in the overbank areas using the input cross section n-value break points (locations where n-value change) as the basis for subdivision (See Figure 4.2.2). The total conveyance for the cross section is obtained by summing the three subdivision conveyances (left, channel, and right). HECRAS uses following equation to determine conveyance for the subdivisions: Q=KS0.5 f K= 1.486 2 AR ⁄3 n Where: K = conveyance for subdivision n = Manning’s roughness coefficient for subdivision A = flow area for subdivision R = hydraulic radius for subdivision (area / wetted perimeter) 24 Figure 4.2.2 – HEC-RAS Conveyance Subdivision Method (Gary W. Brunner, 2010) HEC-RAS computes velocity coefficient (α) using the following equation: (At )2 [ α= K3lob K3ch K3rob + + ] A2lob A2ch A2rob K3t Where: At = total flow area of the cross section Alob, Ach, Arob = flow area of left overbank, main channel and right overbank, respectively Kt = total conveyance of the cross section Klob, Kch, Krob = conveyance of left overbank, main channel and right overbank, respectively HEC-RAS compute friction loss using following equation: Hf = S̅f L Where, L = discharge weighted reach length S̅f = representative friction slope for a reach which is calculated by the following equation: 25 Q1 + Q2 2 S̅f = ( ) K1 + K2 Contraction and expansion losses in HEC-RAS are calculated by the following equation: hce = C | α1 V 1 2g 2 - α2 V 2 2g 2 | Where, C = the contraction and expansion coefficient 4.2.1 – Calibration of the Model HEC-RAS model has been used for the hydraulic analysis of the project. HECRAS UNET model was used as a base model to do the analysis. The available San Joaquin River hydraulic cross sections nearest to the site were selected from the UNET model and interpolated to represent the extents of the eroded site. These sections were then updated based on actual survey data. The survey data only covers the right half of the channel since that is where the repair is needed. So the left half of the channel sections are stayed unchanged as interpolated. This updated hydraulic model served as the base model for the project. Figure 4.2.1.1 shows the alignment of the river and crosssection into the model. United State Geological Survey (USGS) and DWR gauging station, SAN JOAQUIN RIVER NEAR VERNALIS (VNS) which is located approximately 0.75 mile upstream of SJR RM 71.5R site has been used to calibrate the model. Figure 4.2.1.2 shows the location of the Gauging station. The station provides both flow and stage data at every 15 minutes. The model was run with a known flow and calibrated by changing the n-values until the desired stage was obtained. 26 Project Area RM 71.5R Figure 4.2.1.1 – HEC-RAS Channel Alignment 27 Figure 4.2.1.2 – Location of VNS Gauging Station Manning’s n-values obtained through the calibration process of the model has been presented in the following table. Table 4.2.1.1 – Manning’s n-Value Manning’s n-value Project Condition Existing Condition Left Overbank Main Channel Right Overbank 0.095 0.032 0.095 28 4.2.2 Simulation Run Few simulation runs have been performed using calibrated model to find out the maximum velocity the channel may experience and also the water surface elevation for that particular flow. Several simulations have been performed in order to determine the hydraulic characteristics of the system. Channel maximum velocity is required to compute rock size to mitigate on-going erosion. For this purpose, the flow for what the levee has been designed for (design flow) and project 100-year flow and few more random flows were used for simulation run. The levee in this project has been designed to convey the design flood of 52,000 cfs along San Joaquin River with a minimum freeboard of 3.0 feet. The project 100 year peak flow is 79,650 cfs which was obtained from UNET model. Hydraulic analysis for the existing system has been performed to find out the maximum velocity. One simulation has been run with project design flow (52,000 cfs), one simulation with 100 year flow (79650 cfs) and six more simulations have been run for different flow condition (70,000 cfs, 60,000 cfs, 40000 cfs, 30,000 cfs, 20,000 cfs, and 10,000 cfs) . Simulations with flows lesser than 100 year flow have been run as the channel may not experience maximum velocity at maximum flow. Maximum velocity can occur at flow lower than 100 year flow or design flow. However, the simulation result shows that the channel experience maximum velocity at 100 year flow and for that flow there is no available freeboard and flow overtop the levee. The result of the simulation has been presented in table 4.2.2.1. 29 Table 4.2.2.1 – HEC-RAS Output River Station Plan 71.73 71.73 71.73 71.73 71.73 71.73 71.73 71.73 100 YR Design 70000 60000 40000 30000 20000 10000 Flow Total (cfs) Min Ch El (ft) W.S. Elev (ft) Vel Chnl (ft/s) Flow Area (sq ft) Froude # Chl 79650 52000 70000 60000 40000 30000 20000 10000 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 38.31 32.97 36.78 34.72 30.15 27.53 23.68 18.66 5.04 4.53 4.81 4.66 4.29 4.06 3.61 2.81 33668.1 22655.5 30468.8 26236 16896.6 9598.03 5885.3 3555.59 0.17 0.17 0.16 0.16 0.17 0.17 0.17 0.16 Upstream End of Repair 71.695 71.695 71.695 71.695 71.695 71.695 71.695 71.695 71.66 71.66 71.66 71.66 71.66 71.66 71.66 71.66 100 YR Design 70000 60000 40000 30000 20000 10000 100 YR Design 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 38.28 32.94 36.75 34.69 30.11 27.49 23.65 18.63 38.29 32.95 36.76 34.7 30.13 27.52 23.68 18.64 5.10 4.58 4.87 4.71 4.34 4.11 3.59 2.75 4.53 3.98 4.3 4.13 3.69 3.41 2.88 2.14 33154 22183.5 29966.5 25751.3 16442.1 9175.56 5863.31 3636.37 33866.1 22952.5 30689.6 26500.8 17242.6 9558.68 6998.49 4670.45 0.17 0.17 0.16 0.17 0.17 0.17 0.17 0.15 0.15 0.14 0.14 0.14 0.14 0.14 0.13 0.12 71.625 71.625 71.625 100 YR Design 70000 79650 52000 70000 0.56 0.56 0.56 38.24 32.9 36.71 4.85 4.29 4.61 32873.9 22004.7 29713.1 0.16 0.15 0.15 30 Table 4.2.2.1 (Contd.) Flow Min W.S. Total Ch El Elev (cfs) (ft) (ft) 60000 0.56 34.65 40000 0.56 30.07 30000 0.56 27.46 20000 0.56 23.63 10000 0.56 18.61 Vel Chnl (ft/s) 4.44 4.01 3.69 3.13 2.31 Flow Froude Area # Chl (sq ft) 25543.3 0.15 15890.2 0.15 9145.93 0.15 6511.7 0.14 4323.92 0.12 River Station Plan 71.625 71.625 71.625 71.625 71.625 60000 40000 30000 20000 10000 71.59 71.59 71.59 71.59 71.59 71.59 71.59 71.59 100 YR Design 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 38.19 32.84 36.66 34.6 30.02 27.4 23.57 18.57 5.12 4.59 4.88 4.72 4.3 3.99 3.43 2.55 31933.5 20788.3 28791.5 24634.3 15403.1 8665.65 5965.42 3914.15 0.17 0.17 0.16 0.17 0.17 0.16 0.16 0.14 71.555 71.555 71.555 71.555 71.555 71.555 71.555 71.555 100 YR Design 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 38.17 32.82 36.64 34.58 29.99 27.38 23.55 18.55 5.11 4.54 4.85 4.69 4.25 3.94 3.38 2.49 31793.8 21059.1 28673.7 24474.7 15598.1 8825.41 6086.69 4012.86 0.17 0.16 0.16 0.16 0.16 0.16 0.15 0.13 71.52 71.52 71.52 71.52 71.52 71.52 71.52 71.52 100 YR Design 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 -0.19 -0.19 -0.19 -0.19 -0.19 -0.19 -0.19 -0.19 38.15 32.8 36.62 34.56 29.97 27.35 23.53 18.53 5.06 4.49 4.79 4.63 4.2 3.88 3.32 2.43 31993.2 21361.6 28915.7 24826.9 15815.2 9011.62 6294.88 4118.81 0.16 0.16 0.16 0.16 0.16 0.16 0.15 0.13 31 River Station Plan 71.486 71.486 71.486 71.486 71.486 71.486 71.486 71.486 100 YR Design 70000 60000 40000 30000 20000 10000 Table 4.2.2.1 (Contd.) Flow Min W.S. Total Ch El Elev (cfs) (ft) (ft) 79650 0.66 38.14 52000 0.66 32.8 70000 0.66 36.61 60000 0.66 34.55 40000 0.66 29.97 30000 0.66 27.35 20000 0.66 23.53 10000 0.66 18.53 71.451 71.451 71.451 71.451 71.451 71.451 71.451 71.451 100 YR Design 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 1.51 1.51 1.51 1.51 1.51 1.51 1.51 1.51 38.15 32.8 36.62 34.56 29.98 27.36 23.53 18.53 4.46 3.87 4.22 4.05 3.53 3.17 2.63 1.86 33677.6 22436.4 30493.2 25801.9 17055.3 10420 7642.24 5373.08 0.14 0.13 0.14 0.14 0.13 0.12 0.11 0.09 71.417 71.417 71.417 71.417 71.417 71.417 71.417 71.417 100 YR Design 70000 60000 40000 30000 20000 10000 79650 52000 70000 60000 40000 30000 20000 10000 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 38.14 32.78 36.6 34.54 29.96 27.34 23.51 18.51 4.45 3.91 4.23 4.04 3.58 3.23 2.71 1.97 33734.9 21962.3 30527.7 26290.5 16653.3 10119.6 7376.6 5088.05 0.14 0.14 0.14 0.14 0.14 0.13 0.12 0.1 71.382 71.382 71.382 71.382 71.382 71.382 100 YR Design 70000 60000 40000 30000 79650 52000 70000 60000 40000 30000 3.22 3.22 3.22 3.22 3.22 3.22 38.1 32.75 36.57 34.51 29.91 27.29 4.64 4.09 4.42 4.24 3.81 3.47 33560.9 22435.2 30335.3 26047.2 16002.1 9587.1 0.15 0.15 0.15 0.15 0.14 0.14 Vel Chnl (ft/s) 4.86 4.25 4.6 4.42 3.93 3.58 3 2.14 Flow Froude Area # Chl (sq ft) 32509.2 0.16 21729.2 0.15 29364.7 0.15 25143.1 0.15 16269.3 0.15 9560.01 0.14 6804.72 0.13 4666.62 0.11 32 River Station Plan 71.382 71.382 20000 10000 71.35 100 YR 71.35 Design 71.35 70000 71.35 60000 71.35 40000 71.35 30000 71.35 20000 71.35 10000 Downstream End of Repair 71.313 100 YR 71.313 Design 71.313 70000 71.313 60000 71.313 40000 71.313 30000 71.313 20000 71.313 10000 4.3 Table 4.2.2.1 (Contd.) Flow Min W.S. Total Ch El Elev (cfs) (ft) (ft) 20000 3.22 23.47 10000 3.22 18.48 Vel Flow Froude Chnl Area # Chl (ft/s) (sq ft) 2.92 6905.49 0.13 2.14 4678.13 0.11 79650 52000 70000 60000 40000 30000 20000 10000 4.07 4.07 4.07 4.07 4.07 4.07 4.07 4.07 38.07 32.71 36.54 34.47 29.85 27.23 23.41 18.42 4.74 4.28 4.54 4.4 4.1 3.81 3.32 2.6 33165.2 21926.2 29919.1 25579.4 15065.5 8752.43 6119.72 3846.33 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.15 79650 52000 70000 60000 40000 30000 20000 10000 4.92 4.92 4.92 4.92 4.92 4.92 4.92 4.92 38.06 32.69 36.53 34.46 29.84 27.21 23.38 18.39 4.66 4.2 4.46 4.32 3.98 3.75 3.31 2.64 33664.7 22335.2 30402.4 26025.6 16415.9 9436.76 6278.28 3783.74 0.16 0.16 0.15 0.16 0.16 0.16 0.16 0.15 Riprap Design The ability of riprap slope protection to resist the erosive forces of channel flow depends on the interrelation of the following factors: stone shape, size, weight, and durability; riprap gradation and layer thickness; and channel alignment, cross section, gradient, and velocity distribution. 33 4.3.1 Stone Shape Riprap should be blocky in shape rather than elongated. The stone should have sharp, angular, clean edges as the angular and cubical stone provide more resistant in movement than rounded stone. 4.3.2 Stone Size and Weight The ability of riprap revetment to resist erosion is related to the size and weight of stones. The relation between size and weight of stone is described by the following equation: 1⁄ 3 6W% D% = ( ) πγs Where D% = equivalent-volume spherical stone diameter, ft W% = weight of individual stone having diameter of D% γs = saturated surface dry specific or unit weight of stone, pcf 4.3.3 Layer Thickness All stone should be contained within the riprap layer thickness to provide maximum resistance against erosive forces. Layer thickness should not be less than D100 (spherical diameter of the upper limit W100 stone) or less than 1.5 times of D50 (spherical diameter of the upper limit W50 stone). When the riprap is placed under water, the thickness determined by using D100 or D50 should be increased by 50 percent for uncertainties associated with this type of placement. 34 4.3.4 Side Slope Inclination Side slope should ordinarily not be steeper than 1V on 1.5H, except in special cases where it may be economical to use larger hand-placed stone keyed into the bank, to provide stability of riprap slope protection. 4.3.5 Channel Roughness, Shape, Alignment, and Gradient As boundary shear forces and velocities depend on channel roughness, shape, alignment, and invert gradient, these factors must be considered in determining the size of stone required for riprap revetment. Manning’s n for riprap placed in the dry (section is dry during placement of riprap) can be calculated using the following form of Strickler’s equation: 1⁄ 6 n = K[D90 (min)] Where K = 0.034 for velocity and stone size calculation D90(min) = size of which 90 percent of sample is finer, from minimum or lower limit curve of gradation specification, ft 4.3.6 Selection of Rock Size Rock size computation should be conducted for flow condition that produces maximum velocities at the riprap boundary. The method for determining rock size uses depth-average local velocity. Local velocity and local flow depth are used in the procedure to quantify the imposed forces. Riprap size and unit weight quantify the resisting force of the riprap. The depth average local velocity over the slope, Vss can be calculated at a point 20 percent of the slope length from the toe of slope. A two dimensional hydraulic analysis is preferable to determine Vss. However, Vss also can be 35 determined by using the average channel velocity, Vavg using following equation (USACE, 1990 EM 1110-2-2302): Vss Vavg =1.74-0.52log(R⁄W) Where Vavg = average channel velocity at the upstream end of bend R = center-line radius of the bend W = water surface width R and W are based on flow in the main channel only and do not include overbank areas. The basic equation for the representative rock size in straight or curved channels is as follows: 1⁄ 2 γw D30 =Sf Cs CvCT d [(γ - γ ) s w 2.5 V √K1 gd ] Where; D30 = riprap size of which 30 percent is finer by weight Sf = safety factor (safety factor used to increase rock sizes to resist hydrodynamic and a variety of nonhydrodynamic-imposed forces and/or uncontrollable physical conditions. The minimum value of safety factor is 1.1) Cs = stability coefficient for incipient failure = D85/D15 = 1.7 to 5.2 = 0.30 for angular rock = 0.375 for rounded rock Cv = vertical velocity distribution coefficient = 0.10 for straight channels, inside of bends = 1.283 – 0.2lg(R/W), outside of bends (1 for (R/W) > 26) 36 CT = thickness coefficient d = local depth of flow (same location as V) γw= unit weight of water V = local depth average velocity K1 = side slope correction factor g = gravitational constant The relation between D30 and D50 is follows: 1 D85 ⁄3 D50 = D30 ( ) D15 Where; D30 = riprap size of which 30 percent is finer by weight D50 = riprap size of which 50 percent is finer by weight D85 = riprap size of which 85 percent is finer by weight D15 = riprap size of which 15 percent is finer by weight For this project purpose, CHANLPRO software, developed by USACE was used to find the required minimum rock size. CHANLPRO provides riprap design guidance for channels subjected to high velocity forces with low turbulence flows. The program gives different stable gradation results depending on the depth, water surface width, bend radius, and local velocity. The CHANLPRO program version 2.0 (USACE, 1998) was used to select a gradation to adequately protect the site. The program uses the equations that were presented in section 4.3.6. Selection of Rock Size to find gradation of riprap. Average channel velocity at upstream end of bend (River Station 71.695) has been used as an input and the program will calculate the local depth average velocity. From Table 37 4.2.2.1, at River Station 71.695 average channel velocity is 5.10 ft/sec but for design purpose an average velocity of 5.5 ft/sec has been used. The following parameters were used as input to the model Specific weight, pcf = 150 Local flow depth, ft = 32.0 Average channel velocity, ft/sec = 5.5 Channel bank slope, ft/ft = 1.5H:1V Center-line radius of the bend, R, ft = 250 Water surface width, W, ft = 250 The computer program (CHANLPRO) identified D50 size of minimum 10.5 inches is required for this project condition. Program input and output is attached in Appendix B. 4.3.7 Gradation of Riprap The gradation of rock in riprap revetment affects the riprap’s resistant to erosion. Rock should be reasonably well graded throughout the in-place layer thickness. The rock shape should be angular with the minimum dimension of the rock not less than one third of the maximum dimension. Slope protection rock should be clean, free of dirt or mud, loose concrete or mortar, trash, and organic matter. Table 4.3.7.1 shows the proposed gradation to be used for this site based on CHANLPRO result: 38 Table 4.3.7.1 – Gradation Table Size D100 D90 D50 D30 D15 D5 4.4 Diameter (in) Max. 18.0 12.0 9.5 3.0 Min. 13.3 12.7 10.5 8.8 7.1 0 Weight (Ib) Max. 265 78 39 10 Min. 106 94 53 31 17 0 Repair Section Design According to section 4.3.3, the minimum thickness of riprap for repair section will be 18 inches as the D50 size of rock is 12 inches. The maximum thickness of repair section depends on its impact to river hydraulics as this repair encroaches into the channel available conveyance area and also depends on cost as cost goes up with thickness increment. Most of the places along the repair length require more than minimum required thickness of riprap as erosion in some places were more than other places resulted in irregular channel bank. Various layer thicknesses (atleast 18 inches) have been provided all along the repair length to provide smooth and regular bank to the channel and to improve hydraulics of the existing system. The repair section comprises three major components: 1. Launch rock, 2. Riparian bench, and 3. upper rock slope protection. Typical cross section of the repair has been presented in Figure 4.4.1. and repair footprint has been presented in Figure 4.4.2., Figure 4.4.3., Figure 4.4.4., and Figure 4.4.5. 39 4.4.1 Launch Rock Toe scour is the most frequent cause of failure for wide variety of protection technique including rock revetments. Channels with highly erodible bed and banks can experience significant scour along the toe of the new revetment. This can be prevented by providing sufficient launch rock. Launch rock is defined as the rock that is placed along expected erosion areas at an elevation above the zone of attach. As the attack and resulting erosion occur below the stone, the stone is undermined and rolls/ slides down the slope, stopping the erosion. Thickness of launch rock should be 1.5 times of thickness of upper rock slope protection for uncertainties associated with this the placement of rock under water. 4.4.2 Riparian Bench Riparian bench is provided at the top of launch rock typically at 2 to 4 feet above of summer mean water surface elevation. For this project a riparian bench is set at elevation 14.7 ft (summer mean plus 2 ft). See Appendix C for summer mean elevation calculation form CDEC data. The purpose of providing riparian bench is to create habitat for restoration of vegetation lost due to bank erosion. 4.4.3 Rock Slope Protection The upper rock slope protection sits on top of the riparian bench. The height that riprap is placed up a levee or bank can vary substantially and is site specific. For the project site, the height has been determined as the height of the existing berm of the levee. The slope of the riprap should not be steeper than 1.5H: 1V for stability purpose and can be as flat as 3H: 1V without affecting the existing hydraulics of the system. For this project, a slope 40 of 2H: 1V has been used as 3H:1V slope will encroach too much into channel available conveyance area and 1.5H:1V slope will be too steep to do regular maintenance. The void between the rock will be filled with agricultural soil and 9 inches thick layer of agricultural soil will be placed on top of rock slope to facilitate growth of vegetation. Figure 4.4.1- Typical Cross-Section 41 Figure 4.4.2 - Repair Footprint - Plan 1 of 3 42 Figure 4.4.3- Repair Footprint - Plan 2 of 3 43 Figure 4.4.4 - Repair Footprint - Plan 3 of 3 44 Figure 4.4.5 - Full Repair Footprint 45 46 Chapter 5 EVALUATION OF REPAIR IMPACT ON EXISTING RIVER HYDRAULICS 5.1 Introduction The proposed repair will encroach into the available conveyance area. The rock slope protection and proposed vegetation on the main channel repaired slope may also increase bank roughness for stream flow computations. A hydraulic impact analysis has been prepared to analyze the anticipated impacts of the proposed repairs on the San Joaquin River flow conveyance capacity in the vicinity of the repair. 5.2 Hydraulic Analysis The purpose of the hydraulic modeling and analysis is to verify the hydraulic impacts of the proposed projects based on USACE design criteria. UASCE generally requires that based on existing conditions, the project water surface elevation not increase more than 0.1 foot and not encroach upon the minimum design freeboard of 3.0 feet. To analyze the impacts of the proposed repair, the calibrated model which was used for existing condition has been used as a base model. To simulate the post-project condition, the sections within the site limits were updated to include the rock slope protection repairs and the Manning’s roughness values were revised in each section to account for the rock slope protection and fully developed vegetation. The repair site is within the main channel and it will be covered with different plants on the lower and upper zones of the bank in addition to rock slope protection. These roughness changes within the main channel were considered in the modeling by assuming new Manning’s coefficients for main channel sections where the roughness changes. As the repair is on main channel, 47 during high flow this section will be covered with water and will provide less effective resistance. Based on Ven Te Chow (Open-Channel Hydraulics, 1973, Table 5-6), for irregular and rough section in major stream, the value of n varies from 0.035 to 0.1. Table 5.2.1 shows the Manning’s n-values that have been used in the model. Table 5.2.1 – Manning’s n-Value for Post Repair Condition Project Condition Existing Condition Post Project Condition Left Overbank Main Channel Repaired Slope Right Overbank 0.095 0.032 -- 0.095 0.095 0.032 0.045 0.095 In order to determine the hydraulic impacts of the proposed repair, this project uses the 100 year peak flow (79,650 cfs) as baseline for the engineering design. The model also has been run for design flow (52,000 cfs) just to evaluate the impact on the design condition of the system. The simulations results show that the repair has very insignificant impact on water surface elevation which is the main concern of the encroachment into the waterway. For 100 year flood (79,650 cfs), flow overtop the levee for existing condition and with repair on it with a maximum water surface elevation increment of 0.03 ft which is insignificant compare to USACE allowable limit. USACE allows a water surface elevation increment upto 0.1 ft for any encroachment into the waterway for 100 year flow. For design flood (52,000 cfs), the water surface elevation increment due to encroachment into the river is also 0.03 ft which is also very insignificant compare to available conveyance area. The result of the analysis is presented in table and figures. 48 Figure 5.2.1 shows the repair section on existing system with 100-year water surface elevation from River Station 71.59 to 71.486 (see Appendix D for more. Figure 5.2.2 represents the 100-year and design flow water surface elevation for existing system and post project condition. The figure depicts that there is very little or no change in water surface elevation due to repair on the right bank of the river. Figure 5.2.3 shows the velocity profiles for 100-year and design flow for existing condition and post project condition on left bank, right bank and main channel. The velocity profiles portray that there is insignificant impact of repair on velocity of the river system. In all figure legends, E-100 YR means existing condition with 100-year flow, PR-100 YR means post project condition with 100-year flow, Design- 52000 means existing condition with design flow of 52000 cfs and Post-Design means post repair condition with design flow. 49 Figure 5.2.1 – Cross-Section with Repair on Existing System with 100-Year Water Surface Elevation (From River Station 71.59 to 71.486) 50 Figure 5.2.2 – Water Surface Profile for 100–Year and Design Flow for Existing and Post Project Condition 51 Project Location Figure 5.2.3 – Velocity Profile for 100–Year and Design Flow for Existing and Post Project Condition 52 Table 5.2.2 shows the change in water surface elevation (WSE) and velocity (V) due to repair in the main channel. Table 5.2.2 – Comparison of WSE and V for Existing Condition and Post Repair Condition. River Station Plan Q Total Min Ch El W.S. Elev Change in WSE Vel Chnl Change in Vel (ft) 39.23 39.24 33.83 33.86 (ft/s) 6.06 6.06 5.01 5.00 (ft/s) E - 100 YR PR - 100 YR E - Design PR - Design (ft) -1.02 -1.02 -1.02 -1.02 (ft) 72.567 72.567 72.567 72.567 (cfs) 79650 79650 52000 52000 72.55 72.55 72.55 72.55 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 -0.02 -0.02 -0.02 -0.02 39.03 39.05 33.73 33.75 0.02 72.4 72.4 72.4 72.4 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 -5.64 -5.64 -5.64 -5.64 38.4 38.42 33.28 33.3 0.02 72.06 72.06 72.06 72.06 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 10.81 10.81 10.81 10.81 38.53 38.55 33.24 33.27 0.02 71.8 71.8 71.8 71.8 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 1.8 1.8 1.8 1.8 38.38 38.39 33.04 33.07 0.01 71.765 71.765 E - 100 YR PR - 100 YR 79650 79650 1.55 1.55 38.35 38.37 0.02 0.01 0.03 0.02 0.02 0.03 0.03 7.11 7.11 5.64 5.63 0.00 -0.01 0.00 -0.01 8.88 8.87 7.03 7.02 -0.01 5.07 5.06 4.36 4.35 -0.01 4.97 4.97 4.44 4.43 0.00 5.00 5.00 -0.01 -0.01 -0.01 0.00 53 Contd Table 5.2.2 River Station Plan Q Total Min Ch El W.S. Elev Change in WSE Vel Chnl Change in Vel (cfs) (ft) (ft) (ft) (ft/s) (ft/s) 71.765 71.765 E - Design PR - Design 52000 52000 1.55 1.55 33.01 33.03 0.02 4.50 4.49 -0.01 71.73 71.73 71.73 71.73 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 1.3 1.3 1.3 1.3 38.31 38.33 32.97 33 0.02 5.04 5.03 4.53 4.52 -0.01 5.10 5.09 4.58 4.58 -0.01 4.53 4.58 3.98 4.03 0.05 4.85 4.88 4.29 4.35 0.03 5.12 5.22 4.59 4.69 0.10 5.11 0.01 0.03 -0.01 Upstream End of Repair 71.695 71.695 71.695 71.695 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 1.05 1.05 1.05 1.05 38.28 38.3 32.94 32.96 0.02 71.66 71.66 71.66 71.66 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 0.8 0.8 0.8 0.8 38.29 38.31 32.95 32.98 0.02 71.625 71.625 71.625 71.625 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 0.56 0.56 0.56 0.56 38.24 38.26 32.9 32.92 0.02 71.59 71.59 71.59 71.59 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 0.31 0.31 0.31 0.31 38.19 38.2 32.84 32.84 0.01 71.555 E - 100 YR 79650 0.06 38.17 0.01 71.555 PR - 100 YR 79650 0.06 38.18 0.02 0.03 0.02 0.00 5.12 0.00 0.05 0.06 0.10 54 Contd Table 5.2.2 River Station Plan Q Total Min Ch El W.S. Elev Change in WSE Vel Chnl Change in Vel (cfs) (ft) (ft) (ft) (ft/s) (ft/s) 71.555 71.555 E - Design PR - Design 52000 52000 0.06 0.06 32.82 32.83 0.01 4.54 4.58 0.04 71.52 71.52 71.52 71.52 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 -0.19 -0.19 -0.19 -0.19 38.15 38.16 32.8 32.81 0.01 5.06 5.06 4.49 4.52 0.00 71.486 71.486 71.486 71.486 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 0.66 0.66 0.66 0.66 38.14 38.15 32.8 32.79 0.01 4.86 4.94 4.25 4.35 0.08 71.451 71.451 71.451 71.451 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 1.51 1.51 1.51 1.51 38.15 38.15 32.8 32.8 0.00 4.46 4.54 3.87 3.97 0.08 71.417 71.417 71.417 71.417 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 2.37 2.37 2.37 2.37 38.14 38.14 32.78 32.78 0.00 4.45 4.46 3.91 3.93 0.01 71.382 71.382 71.382 71.382 E - 100 YR PR - 100 YR E - Design PR - Design 79650 79650 52000 52000 3.22 3.22 3.22 3.22 38.1 38.1 32.75 32.74 0.00 4.64 4.66 4.09 4.13 0.02 71.35 71.35 E - 100 YR PR - 100 YR 79650 79650 4.07 4.07 38.07 38.07 4.74 4.74 0.00 0.01 -0.01 0.00 0.00 -0.01 0.00 0.03 0.10 0.10 0.02 0.04 55 River Station Plan 71.35 E - Design 71.35 PR - Design Downstream End of Repair 71.313 E - 100 YR 71.313 PR - 100 YR 71.313 E - Design 71.313 PR - Design 71.28 71.28 71.28 71.28 E - 100 YR PR - 100 YR E - Design PR - Design Contd Table 5.2.2 Min W.S. Q Total Ch El Elev (cfs) (ft) (ft) Change in WSE (ft) Vel Chnl (ft/s) Change in Vel (ft/s) 52000 52000 4.07 4.07 32.71 32.71 0.00 4.28 4.28 0.00 79650 79650 52000 52000 4.92 4.92 4.92 4.92 38.06 38.06 32.69 32.69 0.00 4.66 4.66 4.20 4.20 0.00 79650 79650 52000 52000 5.78 5.78 5.78 5.78 38.05 38.05 32.67 32.67 0.00 4.57 4.57 4.13 4.13 0.00 0.00 0.00 0.00 0.00 56 Chapter 6 CONCLUSIONS AND RECOMMENDATIONS 6.1 Conclusions This chapter provides a general discussion of the conclusions relating to this study and ideas for opportunities for future work. The purpose of this study was to evaluate the different alternatives to mitigate an erosion problem and select the most feasible alternative, determine cross-section of the selection alternative, and evaluate the hydraulic impact of the repair to the existing river hydraulics. The alternative that was selected is an in-place rock slope protection. The parameters that are required to determine the size of rock and cross-section of the rock slope protection were obtained by a one dimensional steady stead hydraulic analysis using HEC-RAS hydraulic model. As the repair was an on-site repair and it encroached into available conveyance area of the existing river system, a hydraulic analysis using HEC-RAS hydraulic model was performed to evaluate the impact of the repair into the system. The results of the hydraulic analysis indicate that the repair has very little or insignificant impact to the channel hydraulics. So the selected alternative is the cheapest and most appropriate alternative for this particular case and which can be implemented without affecting the channel hydraulics adversely. If the alternative affected the channel hydraulic system adversely, another alternative (in this case set back levee) would be considered to mitigate the erosion problem. The HEC-RAS results show that the water overtops the levee for 100-year flow but raising the height of the levee was not considered during this analysis and design 57 procedure. The levee height increment at this particular location will transfer the flow downstream which can create overtopping issue at the downstream of system. A system wide evaluation is required to determine the impact of levee height increment at any particular location. 6.2 Recommendations In this analysis, only one dimensional steady state hydraulic analysis was performed to determine velocity and water surface elevation of the channel. One dimensional analysis provides channel average velocity at any particular cross-section. It would be helpful to utilize different software and perform a two-dimensional analysis and compare the results. Armoring on a particular section of a bank could affect impact the other areas of the channel since the river will no longer be able to freely meander along the repair length. It would be very interesting subject to analyze how the river is going to behave after repair – is it going to erode the inner point bar and where the sediment is going to be stored etc. Also this study did not consider stability issue during the analysis. Stability analysis for existing condition and post project condition can be performed to see the impact of the repair to the stability of the system and enhance the findings of the study. During this study, no seepage analysis was performed. Seepage analysis for existing system can be performed and if the results indicate that the system is susceptible to seepage, a remedy for the seepage issue can be analyzed and strengthen the system. 58 APPENDIX A Site Photographs 59 RSP placed in 2006 Levee Crown Near vertical eroded bank Photograph 1 - View upstream (east) of eroded bank at SJR RM 71.5R. Note RSP placed in 2006 along levee’s waterside slope and near vertical bank. RSP from 2006 emergency repair Photograph 2 - View downstream (north) of SJR RM 71.5R erosion site, from approximate Station 12+00 (Levee Mile 2.8, Unit 1). 60 Power poles and lines along access road north of levee Localized undercut bank and caving Photograph 3 - View upstream (east) from approximate Station 31+50 (Levee Mile 2.4, Unit 1) of SJR RM 71.5R erosion site. RSP from 2006 emergency repair Photograph 4 – View downstream (north) from approximate Station 21+00 (Levee Mile 2.6, Unit 1) of SJR RM 71.5R erosion site. 61 Photograph 6 – Close-up of existing RSP at SJR RM 71.5R from 2006 emergency repair. 62 APPENDIX B CHANLPRO Program - Input and Output 63 PROGRAM OUTPUT FOR A NATURAL CHANNEL SIDE SLOPE RIPRAP, BENDWAY INPUT PARAMETERS SPECIFIC WEIGHT OF STONE,PCF 150.0 MINIMUM CENTER LINE BEND RADIUS,FT WATER SURFACE WIDTH,FT LOCAL FLOW DEPTH,FT 250.0 250.0 32.0 CHANNEL SIDE SLOPE,1 VER: 1.50 HORZ AVERAGE CHANNEL VELOCITY,FPS 5.50 COMPUTED LOCAL DEPTH AVG VEL,FPS 8.71 (LOCAL VELOCITY)/(AVG CHANNEL VEL) 1.58 SIDE SLOPE CORRECTION FACTOR K1 .71 CORRECTION FOR VELOCITY PROFILE IN BEND RIPRAP DESIGN SAFETY FACTOR 1.50 1.22 64 SELECTED STABLE GRADATIONS ETL GRADATION NAME COMPUTED D30(MIN) D100(MAX) D85/D15 N=THICKNESS/ CT THICKNESS D30 FT 2 FT .48 IN D100(MAX) 12.00 1.70 IN NOT STABLE 3 .61 .61 15.00 1.70 1.45 .90 21.7 4 .68 .73 18.00 1.70 1.00 1.00 18.0 D100(MAX) IN LIMITS OF STONE WEIGHT,LB FOR PERCENT LIGHTER BY WEIGHT 100 50 D30(MIN) D90(MIN) FT FT 15 15.00 153 61 45 31 23 10 .61 .88 18.00 265 106 78 53 39 17 .73 1.06 EQUIVALENT SPHERICAL DIAMETERS IN INCHES D100(MAX) D100(MIN) D50(MAX) D50(MIN) D15(MAX) D15(MIN) 15.0 11.1 10.0 8.8 7.9 6.0 18.0 13.3 12.0 10.5 9.5 7.1 65 APPENDIX C CDEC Data – Summer Water Surface Elevation Calculation 66 ID of CDEC Station: VNS River Basin: San Joaquin River Hydrologic Area: San Joaquin River Latitude: 37.676041 degree N Longitude: 121.266327 degree W Operator: USGS and DWR Datum: NGVD 1929 Monthly Average Stage Data from VNS Station: MonthYear 1/1993 1/1994 1/1995 1/1996 1/1997 1/1998 1/1999 1/2000 1/2001 1/2002 1/2003 1/2004 1/2005 1/2006 1/2007 1/2008 1/2009 10/1993 10/1994 10/1995 10/1996 Stage (Monthly Average), ft 12.37511547 9.774007628 11.56290937 10.97827957 28.40518317 13.99120606 12.92887525 9.957154363 10.01223761 10.3511454 9.498107229 9.327528635 12.82126344 19.17044355 11.28972709 12.68067231 8.81 11.42265544 …… 14.30373927 10.99426643 MonthYear 10/1997 10/1998 10/1999 10/2000 10/2001 10/2002 10/2003 10/2004 10/2005 10/2006 10/2007 10/2008 11/1993 11/1994 11/1995 11/1996 11/1997 11/1998 11/1999 11/2000 11/2001 Stage (Monthly Average), ft 11.32933691 14.2226198 10.40490757 10.78563205 9.612440233 9.140513196 9.586510051 9.383249182 10.86501344 13.08192491 11.21809694 8.485551075 9.783427118 8.999682522 10.99143606 11.15590278 10.50114747 11.76810732 9.990961957 10.2926093 9.731292984 67 Continued Table MonthYear 11/2002 11/2003 11/2004 11/2005 11/2006 11/2007 11/2008 12/1993 12/1994 12/1995 12/1996 12/1997 12/1998 12/1999 12/2000 12/2001 12/2002 12/2003 12/2004 12/2005 12/2006 12/2007 12/2008 2/1993 2/1994 2/1995 2/1996 2/1997 2/1998 2/1999 2/2000 2/2001 2/2002 Stage (Monthly Average), ft 9.256109903 9.204682367 9.252407367 10.12897557 11.46371007 9.686492065 8.642649155 9.564827527 9.011538443 10.81663219 18.43942204 10.5440784 12.71645545 9.396083596 9.871145873 9.705613003 9.590282258 9.078978495 9.16797043 11.5916129 11.18869176 9.407858692 8.840938406 11.39564312 10.09746413 15.13840941 18.48413974 28.67995924 26.21015157 18.05592715 14.63628942 10.8197422 9.550381082 MonthYear 2/2003 2/2004 2/2005 2/2006 2/2007 2/2008 3/1993 3/1994 3/1995 3/1996 3/1997 3/1998 3/1999 3/2000 3/2001 3/2002 3/2003 3/2004 3/2005 3/2006 3/2007 3/2008 4/1993 4/1994 4/1995 4/1996 4/1997 4/1998 4/1999 4/2000 4/2001 4/2002 4/2003 Stage (Monthly Average), ft 9.504345238 9.845431659 13.13287202 14.52883929 11.13914966 10.73221134 10.84727199 10.41498951 20.08869474 21.17056786 19.51448453 22.9156212 15.44999281 18.51319308 11.19507539 9.833974138 9.901263547 11.14010811 14.98947092 18.34622312 11.07209677 10.33810484 11.90214553 9.828344843 23.92011811 15.72280307 14.25320986 24.27294444 13.90497272 13.39182502 10.83327899 10.31426027 10.35948478 68 Continued Table MonthYear 4/2004 4/2005 4/2006 4/2007 4/2008 2/2003 2/2004 2/2005 5/1993 5/1996 5/1997 5/1998 5/1999 5/2000 5/2001 5/2002 5/2003 5/2004 5/2005 5/2006 5/2007 5/2008 6/1993 6/1994 6/1995 6/1996 6/1997 6/1998 6/1999 6/2000 6/2001 6/2002 6/2003 Stage (Monthly Average), ft 10.48908152 16.94904046 26.68501433 10.63078744 10.65124802 9.504345238 9.845431659 13.13287202 11.98308476 16.63667856 13.76774815 22.38389259 13.19436603 12.93101281 11.38210332 10.54971652 10.32199392 10.38443841 17.30332983 26.34927361 11.45799358 11.04971891 10.51243568 8.631145246 20.53095109 12.60432515 11.70438889 22.41919296 10.85321153 10.86236336 9.186522947 8.938483696 9.799964976 MonthYear 6/2004 6/2005 6/2006 6/2007 6/2008 7/1993 7/1994 7/1995 7/1996 7/1997 7/1998 7/1999 7/2000 7/2001 7/2002 7/2003 7/2004 7/2005 7/2006 7/2007 7/2008 8/1993 8/1994 8/1995 8/1996 8/1997 8/1998 8/1999 8/2000 8/2001 8/2002 8/2003 8/2004 Stage (Monthly Average), ft 8.948094807 17.06044444 21.63152995 10.37854003 8.537793358 9.363877741 8.68269969 18.12811145 10.74940451 10.63876179 19.89726785 10.10844979 9.918919737 8.921653226 8.715054348 8.785745676 8.536112085 12.83185484 14.05137242 10.14942181 8.200510753 10.10448356 8.29080446 13.12745627 10.56357362 10.55262511 14.29552419 9.915749569 10.19267648 8.821406615 8.502081073 8.717146447 8.514045699 69 Continued Table MonthYear 8/2005 8/2006 8/2007 8/2008 9/1993 9/1994 9/1995 9/1996 9/1997 9/1998 9/1999 9/2000 9/2001 9/2002 9/2003 9/2004 9/2005 9/2006 9/2007 9/2008 Stage (Monthly Average), ft 11.33034771 13.02441195 10.31826894 8.230085237 11.12444698 8.286662853 13.44601028 10.67441908 10.57591107 14.2491815 9.951892779 10.34393901 8.885111111 8.522282499 8.705879831 8.499119444 10.93700604 12.58439476 9.259441363 8.075402778 Calculation of Summer Mean Month/Year Stage, ft 8/1993 8/1994 8/1995 8/1996 8/1997 8/1998 8/1999 8/2000 8/2001 8/2002 8/2003 8/2004 8/2005 8/2006 8/2007 8/2008 10.10448356 8.29080446 13.12745627 10.56357362 10.55262511 14.29552419 9.915749569 10.19267648 8.821406615 8.502081073 8.717146447 8.514045699 11.33034771 13.02441195 10.31826894 8.230085237 Summer (August Mean) 10.28129293 Summer Mean WSE (NGVD 1988) = 10.3 + 2.4 = 12.7 ft 70 APPENDIX D HEC-RAS Output 71 Figure D.1 – Cross-Section with Repair on Existing System with 100-Year Water Surface Elevation (From River Station 71.66 to 71.625) 72 Figure D.2 – Cross-Section with Repair on Existing System with 100-Year Water Surface Elevation (From River Station 71.451 to 71.35) 73 APPENDIX E Compact Disk (CD) – HEC-RAS Model 74 REFERENCES 1. U.S. Army Corps of Engineers (1991/1994). Engineering Manual 1110-2-1601: Hydraulic Design of Flood Control Channel. U.S. Army Corps of Engineers, Washington, DC 20314-1000. 2. U.S. Army Corps of Engineers (2000). Engineering Manual 1110-2-1913:Design and Construction of Levees. U.S. Army Corps of Engineers, Washington, DC 20314-1000. 3. U.S. Army Corps of Engineers (1990). Engineering Manual 1110-22302:Construction with Large Stone. U.S. Army Corps of Engineers, Washington, DC 20314-1000. 4. Dr. Robert L. Barkau (2001). User’s Manual: UNET – One-Dimensional Unsteady Flow Through a Full Network of Open Channels. U.S. Army Corps of Engineers, 609 Second Street, Davis, CA 95616-4687. 5. Gary W. Brunner (2010). HEC-RAS, River Analysis System Hydraulic Reference Manual. U.S. Army Corps of Engineers, 609 Second Street, Davis, CA 956164687. 75 6. Stephen T. Maynord, Martin T. Hebler, Sheila F. Knight (1998). User’s Manual for CHANLPRO, PC Program for Channel Protection Design. U.S. Army Corps of Engineers, 3909 Halls Ferry Road, Vicksburg, MS 39180-6199. 7. Ven T Chow (1973). Open-Channel Hydraulics. McGraw-Hill Book Company.