78079 rd As of May 27 , 2013 Vietnam Industrial Pollution Management Project (P113151) I. General Project Information Country: Vietnam Borrower: The Socialist Republic of Vietnam Project name: Vietnam Industrial Pollution Management Project –VIPM (P113151) Credit No:5175-VN Project Implementing Agency: 1) Ministry of Planning and Investment (MPI) 2) Ministry of Natural Resources and Environment (MONRE) 3) Vietnam Environment Protection Fund (VEPF) 1. Bank’s approvalDate of the procurement Plan Original: August 9th 2012. Revision 1: May 27rd 2013 2. Date of General Procurement Notice: April 4th 2013 3. Period covered by this procurement plan: June 2013 – December 2014 II. Goods and Works and non-consulting services. 1. Applicable Procurement Procedures: World Bank’s “Guidelines: Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers” dated January 2011(the Procurement Guidelines); “Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers” dated January 2011 (the Consultant Guidelines). 2. Prior Review Threshold applicable for procurement under Project Component 1 & 3: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Category Goods Works Notes: Contract Value (US$) Procurement Method >/=1,000,000 ICB <1,000,000 NCB <100,000 Shopping NA DC >/=10,000,000 ICB <10,000,000 NCB <200,000 Shopping NA DC ICB – International Competitive Bidding NCB – National Competitive Bidding DC – Direct Contracting NA – Not Applicable Bank Prior Review All contracts First 03 contract None All DC contracts All contracts First 03 contract None All DC contracts 1 As of May 27rd, 2013 3. Prequalification. Prequalification if any shall be implemented in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Reference to Project Implementation Manual (PIM) approved under the Decision No 1201/QD-BKHDT dated September 18th 2012. 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of Procurement packagesplanned from June 2013 to December 2014 2 1 2 3 Development 17 AMSs (Procurement of 3,937,500 AMS equipment and AMS’s IT equipment) Procurement of field monitoring 1,253,200 equipment Procurement of laboratory 3,854,166 equipment 4 Procurement of 6 vehicles for field sampling (2 for VEA; 04 for 4 project provinces and tax included) 5 Procurement of IT equipment system 6 Procurement of Office equipment for MPI PMU and 4 project provinces Contract duration Contract Start Contract Signing Bid/quotation submission Issuance of RFQ/BD Issuance of IFB Review by WB (Prior or Post) Type of Contract Procurement Method (ICB, NCB, SH, etc.) Funding Source Package No. Ref. Description Cost Estimate incl. VAT (USD) As of May 27rd, 2013 G1/VEA IDA ICB Unit prices Prior Aug-13 Aug-13 Nov-13 Jan-14 Jan-14 36 months G2/VEA IDA ICB Lump sum Prior Sep-13 Oct-13 Dec-13 Mar-14 Mar-14 06 months G3/VEA IDA ICB Lump sum Prior Aug-13 Aug-13 Nov-13 Jan-14 Jan-14 06 months 345,000 G4/VEA IDA NCB Lump sum Prior Jun-13 Jul-13 Sep-13 Dec-13 Dec-13 06 months 1,301,000 G5/VEA IDA ICB Lump sum Prior Jan-14 Feb-14 Apr-14 Jun-14 Jun-14 06 months 60,000 G6/MPI IDA SH Lump sum Post Jun-13 Aug-13 Aug-13 03 months 3 7 Procurement of Office equipment for MONRE PMU 40,000 G7/VEA IDA SH Lump sum Post 8 Procurement of the accounting software of VEPF (Building a credit software in compliance with the accounting software in order to enhance the efficiency of the debt collection; setting up the database and training for the manual) 20,000 G8/VEPF IDA SH Lump sum Post 9 Procurement of Accounting Software for the entire project FM 20,000 G9/MPI IDA SH Lump sum Post 10 Vehicle for MPI PMU 80,000 G10/MPI IDA SH Lump sum Post Aug-13 Contract duration Contract Start Contract Signing Bid/quotation submission Issuance of RFQ/BD Issuance of IFB Review by WB (Prior or Post) Type of Contract Procurement Method (ICB, NCB, SH, etc.) Funding Source Package No. Ref. Description Cost Estimate incl. VAT (USD) As of May 27rd, 2013 Jun-13 Aug-13 Aug-13 03 months Jul-13 Jul-13 Aug-13 Aug-13 03 months Jul-13 Jul-13 Aug-13 Aug-13 03 months Aug-13 Sep-13 Dec-13 Dec-13 05 months 4 As of May 27rd, 2013 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Expenditure Category Consultant Services Notes: Contract Value (US$) >/=300,000 Procurement Method QCBS, QBS, FBS, LCS <300,000 QCBS, QBS, FBS, LCS, or CQS NA SSS NA IC Bank Prior Review Firms: >/=$300,000 (for competitive selection) plus the first contract for each method regardless of value. For SSS, $50,000 (Para 3.9 of Consultant Guidelines, January 2011); Individuals: only in exceptional cases (for competitive selection); for SSS, $20,000 (Para 5.6 of Consultant Guidelines, January 2011); Audit contracts: all QCBS – Quality and Cost Based Selection QBS – Quality Based Selection FBS – Fixed Budget Selection LCS – Least Cost Selection CQS – Selection Based on Consultants’ Qualification SSS – Single (or Sole) Source Selection IC – Individual Consultant selection procedure NA – Not Applicable 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 5 May-14 Jul-14 Oct-14 Oct-14 12 months 550,000 CS2/VEA IDA QCBS Lump sum Prior Aug-13 Aug-13 Oct-13 Jan-14 Jan-14 12 months Contract Duration (months) May-14 Contract Start Prior Contract Signing Lump sum Proposal Submission QCBS Issuance of RFP IDA Issuance of REOI CS1/VEA Review by WB (Prior or Post) 545,000 Type of Contract Selection Method (QCBS, CQS, ICS and etc.) 2 Inputs for issuance of legal documents providing guidelines for execution of new LEP at central level and provincial level Inputs for revision and elaboration of legal documents regulating general issues relating to environment protection of IZ and river basin Funding Source 1 Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 6 3 4 5 Revision and issuance of legal documents on collection, treatment and discharging of industrial wastes Revision of Decree 29/2008/NDCP on industrial parks, export processing zones, and economic zones Development of Law on economic zones Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 130,000 CS3/VEA IDA CQS Lump sum Prior Aug-13 Aug-13 Sep-13 Dec-13 Dec-13 12 months 50,000 CS4/MPI IDA CQS Lump sum Post Sep-13 Sep-13 Oct-13 Dec-13 Dec-13 12 months 198,000 CS5/MPI IDA CQS Lump sum Post Aug-14 Sep-14 Oct-14 Nov-14 Nov-14 12 months 7 Mar-14 Jun-14 Sep-14 Sep-14 06 months 198,000 CS7/MPI IDA CQS Lump sum Prior Aug-13 Sep-13 Oct-13 Dec-13 Dec-13 12 months Contract Duration (months) Mar-14 Contract Start Prior Contract Signing Lump sum Proposal Submission QCBS Issuance of RFP IDA Issuance of REOI CS6/VEA Review by WB (Prior or Post) 1,007,000 Type of Contract Selection Method (QCBS, CQS, ICS and etc.) 7 Development of information system for integrated management of industrial pollution in the 2 river basins of Nhue-Day and Dong Nai Development of manuals and special books on planning, management and control of industrial pollution for IZs in NhueDay and Dong Nai river basins Funding Source 6 Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 8 8 9 10 Research and development of Sustainable Industrial Structures (industrial ecosystems, Eco-Industrial parks, Resource recovery parks, etc) Research and develop the methodology for assessment of total maximum daily loads and apply to river basin Research on developing the online, automatic, mobile measurement Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 150,000 CS8/MPI IDA CQS Lump sum Post Dec-13 Dec-13 Dec-13 Jan-14 Jan-14 12 months 198,000 CS9/VEA IDA CQS Lump sum Post Jan-14 Jan-14 Feb-14 Apr-14 Apr-14 12 months 150,000 CS10/VEA IDA CQS Lump sum Post Feb-14 Mar-14 Apr-14 Jun-14 Jun-14 12 months 9 Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 system for water environment 11 12 Development of Operation and maintenance, Performance monitoring guidelines for CETP Research, development and pilot application of environment management models including some management tools (economic, technological, 150,000 CS11/MPI IDA CQS Lump sum Post Oct-13 Nov-13 Nov-13 Dec-13 Dec-13 12 months 350,000 CS12/MPI IDA QCBS Lump sum Prior Feb-14 Apr-14 June-14 Aug-14 Aug-14 12 months 10 Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 technical, CP,..) for IZs 13 Research and develop the methodology for assessment of contaminated sites and propose remediation and recovery measures for severe polluted sites 198,000 CS13/MPI IDA CQS Lump sum Post Jan-14 Feb-14 Mar-14 Mar-14 Mar-14 12 months 11 14 15 Development of rating methodology to be applied for evaluation and ranking of enterprises by their environmental performances Upgrading of The VEPF’s Credit Manual based on experience from Component 2 implementation, which reimburse the WB’s loan with the purpose of mobilizing additional capital and expanding CS14/VEA IDA CQS Lump sum Post 20,000 CS15/VEPF IDA IC Lump sum Post 180,000 Jan-14 Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 Jan-14 Feb-14 Apr-14 Apr-14 12 months May-14 Jun-14 Aug-14 Aug-14 12 months 12 16 17 reimbursement activities of VEPF Evaluation for the performance of the public disclosure and public participation activities at 4 project provinces Technical supervision of the procurement and implementation of G1/VEA, G2/VEA, G3/VEA and G5/VEA contracts Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 60,000 CS16/VEA IDA IC Lump sum Post Jun-16 Jun-16 Jul-16 Aug-16 Aug-16 06 months 40,000 CS17/VEA IDA CQS Lump sum Post Nov-13 Nov-13 Dec-13 Feb-14 Feb-14 36 months 13 18 19 Annual Auditing for 3 MPUs and project closing auditing Project Coordinator ($2,200/month * 60 man. months) Training Officer ($1,800/month * 60 man. months) Financial Manager ($2,000/month * 60 man. months) Accountant ($1,200/month * 60 man. months) IDA CQS Lump sum Prior 132,000 IDA IC Lump sum 108,000 IDA IC IDA IDA 120,000 120,000 72,000 CS18/MPI MPI PMU Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 Dec-13 Dec-13 Dec-13 (2013-2018) 12 months Post Jun-13 Jun-13 Jun-13 60 months Lump sum Post Jun-13 Jun-13 Jun-13 60 months IC Lump sum Prior Jun-13 Jun-13 Jun-13 60 months IC Lump sum Prior Jun-13 Jun-13 Jun-13 60 months Oct-13 Nov-13 14 Project Officer 1 ($600/month * 60 man. months) Project Officer 2 ($600/month * 60 man. months) Procurement Specialist ($1,800/month * 12 man. months) Project Officer at Ha Nam province ($1,200/month * 60 man. months) Project Officer at Nam Dinh province ($1,200/month * 60 man. months) Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 36,000 IDA IC Lump sum Post Jun-13 Jun-13 Jun-13 60 months 36,000 IDA IC Lump sum Post Jun-13 Jun-13 Jun-13 60 months 21,600 IDA IC Lump sum Prior Jun-13 Jun-13 Jun-13 12 months 72,000 IDA IC Lump sum Post Jul-13 Jul-13 Jul-13 60 months 72,000 IDA IC Lump sum Post Jul-13 Jul-13 Jul-13 60 months 15 20 Project Officer at Dong Nai ($1,200/month * 60 man. months) Project Officer at Ba ria -Vung tau ($1,200/month * 60 man. months) MONRE PMU Coordinator ($1,800/month * 60 man. months) Monitoring & Evaluation specialist ($1,800/month * 60 man. months) Project Officer ($1,200/month * 60 man. Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 72,000 IDA IC Lump sum Post Jul-13 Jul-13 Jul-13 60 months 72,000 IDA IC Lump sum Post Jul-13 Jul-13 Jul-13 60 months 108,000 IDA IC Lump sum Post Jun-13 Jun-13 60 months IDA IC Lump sum Post Jun-13 Jun-13 60 months IDA IC Lump sum Post Jun-13 Jun-13 60 months 108,000 72,000 MONRE PMU 16 Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 months) Accountant ($1,800/month * 60 months) Procurement Specialist ($1,800/month * 36 man. months) IT specialist ($1,800/month * 60 man. months) Project Officer ($950/month * 60 months) 21 Credit Risk Management Specialist ($1100/month * 30 months) 108,000 IDA IC Lump sum Prior Jun-13 Jul-13 Jun-13 60 months 64,800 IDA IC Lump sum Prior Jun-13 Jul-13 Jun-13 36 months 108,000 IDA IC Lump sum Post Jun-13 Jun-13 60 months 57,000 IDA IC Lump sum Post Jun-13 Jun-13 60 months IDA IC Lump sum Post Jun-13 Jun-13 30 months VEPF PMU 33,000 17 Social and Environmental Safeguard Specialist ($1100/month * 30 months) Project Accountant ($1,000/month * 60 months) 30,000 IDA IC Lump sum Prior 60,000 IDA IC Lump sum Prior Jun-13 Contract Duration (months) Contract Start Contract Signing Proposal Submission Issuance of RFP Issuance of REOI Review by WB (Prior or Post) Type of Contract Selection Method (QCBS, CQS, ICS and etc.) Funding Source Description Package No. Ref. Cost Estimate incl. VAT (USD) As of May 27rd, 2013 Jul-13 Jun-13 30 months Jul-13 Jun-13 60 months Note: All the project management officials of MPI PMU, MONRE PMU and VEPF PMU will be recruited on basis of a period of 12 months, and these contracts shall be extended based on the performance of PMOs. 18