site monitoring report

advertisement
SITE MONITORING REPORT
File Ref: 32 421 02
Date: 21 Dec 2012
Visit no: 3 of 4
Monitoring Officer: Claire Tomalin &
Time on site: 11:19 Time off site: 12:15
Suzanne Armstrong
Tel No: 01245 437577
Site Co-ordinator: Claire Tomalin
Tel No: 01245 437541
Site Name: Pitsea Landfill, Pitsea Hall Lane, Pitsea, Basildon
Operator: Veolia
Site Representative: Keith Crawley
Planning Permission no’s:
ESS/08/94/BAS, ESS/09/98/BAS, ESS/19/95/BAS – Offices, weighbridge
ESS/92/97/BAS - Utilise landfill gas for electricity generation
ESS/22/02/BAS - Leachate and surface water lagoon
ESS/15/11/BAS& ESS/19/12/BAS - Green waste composting operation.
ESS/35/06/BAS - Landfill recontouring – main permission
ESS/51/96/BAS, ESS/50/70/BAS, ESS/43/08/BAS, ESS/39/10/BAS - Landfill gas
generation plant
ESS/50/08/BAS - Inert waste recovery
ESS/36/12/BAS WTS for food waste
ESS/57/11/BAS – Aircom plant for food 7 green waste
Constraints:
Weather:
Noise:
Approach Roads:
Ground:
Access:
Wheel Cleaning:
Hose:
Machinery:
In correct position:
Stockpiles:
Bunds:
Dry/ Windy / Rain / Snow
Acceptable/ Not acceptable N/A
Dry / Dusty / Wet / Muddy / Flooded/ Damp
Dry / Dusty / Wet / Damp / Muddy / Flooded
Obstructed / Not Obstructed / Mud on haul Road
Washer / Spinner / Sweeper / none
In use / Not in Use / N/A
Working / Not working N/A
Yes / No / N/A
Height = 4m
Profiled / Grassed / Weeds/N/A
Inspection results summary:

Green waste composting operational and well managed. Green waste currently
operating east to west i.e. new material deposited east and slowly turned heading
west. In New Year direction to be reversed, to allow use of existing building as WTS
for food waste when needed.

 Inert recycling operation for restoration material operational and tidy, stockpiles
accumulating ready for restoration in summer
 Wharf, empty.
 Landfilling now taking place in phases N & M
 Phases ABC restored to grassland, needs weed control.
Phases E & F restoration completed and planted with willows. Up take upward of
the access track growing well. Planting below track seemed vary spare and/or not
taken as well. The surface of this area is littered with large rocks, bricks etc. These
need to be cleared to improve growth chances and prevent damage to cutting
machinery when the area is cut for bio fuel.
Phases D & I deposited with calcareous material.
J awaiting and K awaiting restoration, but landfilling completed.
 Haul roads very wet and muddy, some mud being carried out on to public
highway. Keith explained the long period of wet weather this year has made
maintaining haul roads very difficult; the water is just not soaking away. Some
sections of the concreted haul road are breaking up. Unofficial laybys on the
concrete haul road (particularly by weighbridge), should be blocked off, as these are
very muddy and being closer to the exit there is less opportunity for mud to clear
from wheels before the public highway.
 Original Bio-fuel area , dominated by weeds
 On arriving on site lorry partly parked on pavement on Pitsea Hall Lane by café,
details passed to Veolia
Actions before next visit:
Manage weeds on restored areas
Stone pick all restored areas to remove material greater than 150mm on the surface
Block off unofficial laybys on haul road
Note: The next visit will take place in Jan –Mar 2013. The actions noted in this
report are required in order to ensure adequate progress is made and to avoid
potential enforcement action against a breach of planning control.
Download