The Private and Social Value of Blackout Risk Reduction Anand Govindarajan, Pennsylvania State University, Phone +1 814 865 3437, E-mail: axg5179@psu.edu Seth Blumsack, Pennsylvania State University, Phone +1 814 863 7597, E-mail: sethb@psu.edu Abstract Combined heat and power (CHP) systems provide a mechanism for individual electricity customers to generate energy locally rather than drawing from the power grid. During periods of normal operation this provides an energy savings benefit to CHP-enabled electricity customers, which has been well-discussed in the existing literature. We focus on another important source of benefits, namely those related to decreasing or avoiding the costs associated with power blackouts. These system benefits have both a “private” component that accrues to the CHP owner/operator and a “social” component that accrues to all other grid-connected customers. When blackouts do occur, CHP-enabled customers will be able to continue to receive electric service from local generation, provided that fuel supplies are not interrupted. This is the private benefit accruing to the CHP owner/operator. If CHP units are deployed at scale and operated in such a way as to decrease stress on power grids during times of peak demand, these CHP units provide a risk-reduction service to the grid as a whole (the “social” benefit) by reducing the probability of blackouts occurring. Using the Mid-Atlantic power grid as a case study, we use historical blackout data to estimate season-specific blackout risk as a function of total demand for grid-provided power and estimate the risk reduction associated with a modest deployment of CHP throughout the Mid-Atlantic region. Our analysis suggests that deployment of 1,000 building-integrated CHP units in the Mid-Atlantic would confer benefits of $2 million to $2.5 million per year to CHP owners. We estimate social benefits, in the form of blackout risk reduction, amount to $14 million to $40 million per year. The magnitude of these benefits is most sensitive to how building-integrated CHP units are operated. 1 1. Introduction Distributed generation (DG), including Combined heat and power (CHP), is being looked up as an alternative to the current structure of power grids with increased use of local generation near demand centers. Recent electrical blackouts caused by extreme weather events (such as Hurricane Sandy in 2013) and by the continued overloading of an aging electrical grid (the August 2003 blackout affecting much of the U.S. Midwest and Northeast) have reinforced the role that distributed power generation (DG) can play in “energy surety” or “survivability” – the ability of energy systems to continue delivery services in the face of extreme events. CHP is the onsite generation of electricity from generators (primarily fueled by natural gas) where the coproduced heat is captured and used for site specific purposes like room heating, water heating etc. CHP systems are highly efficient compared to the conventional method of delivering power through the grid1. Typical CHP systems power single-user buildings or a group of buildings in case of a shared micro-grid. Since the same fuel source is used to generate heat and power, CHP can be beneficial economically and environmentally. The onsite generators can also act as a back-up source of power during blackouts and provide continuous supply of power and heat/cooling to the site. Facilities which had installed CHP systems were able to continue normal operations during the August 14, 2003 blackout (Oak Ridge National Lab 2012) and power outages caused by Hurricane Sandy (ICF International 2013). Most of these facilities had invested on black start (and other services) to operate CHP independent of the grid. Both of these studies concluded that CHP was effective in providing 1 CHP Basics, U.S Department of Energy http://www1.eere.energy.gov/manufacturing/distributedenergy/chp_basics.html 2 continuous supply of power to the sites during blackouts. An interesting finding (as stated by CHP owners) was that the reliability benefit was more significant than the operational costs reduction from CHP. Several studies have examined and quantified the peak shaving benefits, savings from reduced operational costs and emission reduction benefits of CHP (King and Morgan 2007; P. J. Mago, Fumo, and Chamra 2009; P.J. Mago and Chamra 2009; Pedro J. Mago and Smith 2012; Maidment, Zhao, and Riffat 2001; Siler-Evans, Morgan, and Azevedo 2012; Strachan and Farrell 2006; Ziher and Poredos 2006). Our work has focused on quantifying the reliability benefit associated with increased CHP deployment. There are two such benefits. First, the owners of installed CHP units benefit because the CHP unit can act as a source of backup power during a blackout. We refer to this as the “private” reliability benefit since it accrues only to the CHP owner (or owners, in the case of a shared or district system). Second, with sufficiently large deployment levels CHP investments themselves may reduce the likelihood of a blackout occurring. Blackouts are more likely to be instigated during times when the electrical grid is under stress, and removing demand from the grid (onto local CHP systems) can reduce this stress. We refer to this as the “social” benefit of CHP since it accrues to others besides the CHP owner (i.e., anyone on the grid that would benefit from avoiding a blackout), and the CHP owner is not compensated by those who benefit. In other words, there is a “positive network externality” associated with blackout risk reduction via CHP installation decisions. Our approach integrates four separate modelling components: An econometric model of blackout risk in the Mid-Atlantic region (the PJM transmission grid); an econometric model of locational electricity prices within PJM; a simulation model of building-integrated CHP operation; and building energy models that generate electricity demands for commercial 3 buildings with and without integrated CHP. Each of these modelling elements is described briefly below: (1) Our econometric model for blackout risk is estimated using a rare-events logit approach, using data on reported blackouts within the PJM region reported to the U.S. Department of Energy (excluding those related to extreme weather) and data from PJM on historical hourly system loads. We estimate a rare-events logit model that estimates the likelihood of a blackout being initiated in each hour as a function of electric loads in PJM and temporal characteristics such as seasons and time of day. (We compare our results from the rareevents logit model with those of a conventional logit model and find few differences in estimated blackout probabilities.) We also estimate an econometric model for blackout duration as a function of blackout size (customers affected) and temporal variables. (2) Locational electricity prices within PJM are estimated using the econometric approach developed in Sahraei-Ardakani and Blumsack (2014), which estimates locational supply curves within regional power grids that accounts for spatial differences in fuels utilization and congestion on the electric transmission grid. This model utilizes hourly demand and pricing data from PJM, as well as fuel prices from the U.S. Energy Information Administration. (3) CHP usage profiles are developed for specific commercial building types using the BCHP tool available from the U.S. Department of Energy. (4) Building energy profiles with and without CHP are developed using the BCHP tool and a building-integrated CHP assessment approach from the Berkeley National Laboratory. 4 Our overall modelling approach is to estimate baseline hourly blackout risk and locational electricity price profiles for the PJM region. We then simulate hourly energy profiles for up to 1,000 commercial buildings in PJM with and without integrated CHP systems. As more buildings add CHP systems, these customers save on electricity costs and the building energy loads removed from the grid will lower wholesale power prices. These two effects together constitute the private benefit of CHP adoption by commercial buildings. Removing loads from the grid and placing them on CHP also reduces the risk of blackouts, which amounts to the social value in our study. This social value of blackout risk reduction is monetized using an approach suggested by Sullivan, et al. (2010). We find that a modest level of CHP deployment, relative to the overall size of the PJM market as a whole, can yield blackout risk reduction benefits to the PJM system as a whole amounting to between $14,000 and $40,000 annually for each CHP unit. This social reliability benefit is roughly an order of magnitude larger than the private reliability benefit that we estimate. Moreover, the estimated private reliability benefit (based on blackout costs from the existing literature) is several times smaller than the benefit associated with avoided energy purchases. These findings suggest that potential CHP adopters should not be influenced by their private reliability benefits but that a side payment or subsidy based on the social blackout risk reduction would be appropriate. 2. Modeling the likelihood and expected duration of blackouts in PJM The U.S electricity grid operates at high reliability and power outage events are relatively infrequent. But, the complex structure of power grids makes it vulnerable to failures. Historical data suggests that occurrence of blackouts have increased over time (Hines, Apt, and Talukdar 5 2009; Simonoff, Restrepo, and Zimmerman 2007). Blackout events are instigated when there is a disturbance in the power system because of hurricanes or storms, equipment failures, targeted attack on the infrastructure or other external causes. The power grid is also vulnerable to cascading failures when disturbances initiated in a region propagate to other parts through subsequent components failure. The likelihood of a smaller outage events growing into a big cascading failure sharply increases when the grid is already under stress (Dobson et al. 2007). Concurrently, historical data suggests that the odds of a blackout increases significantly during mid-afternoon hours when the grid is under stress due to peak demand (Hines, Apt, and Talukdar 2009). The North American Electric Reliability Corporation (NERC) requires electric utilities to report power outage events and this data is available with the Disturbance Analysis Working Group. Hines et al. (2009) compiled and filtered this data for regions within the PJM electricity market.2 We use this data in our statistical blackout model. Descriptive statistics for various primary causes triggering the blackouts in PJM between 1984 and 2006 are shown in Table 1. Weather is the primary cause of power outages in PJM, triggering more than one-third of events, followed by natural disasters (e.g. hurricanes and ice storms). Table 2 shows the mean duration and the frequency of blackouts initiated during various seasons and times of day in PJM. About half of the blackouts in our data set occurred during summer months with a mean duration of about 18 hours. Blackouts are more likely to be triggered during afternoon hours (12 -5 pm) and blackouts triggered during evening and night-time hours tend to have longer restoration times. 2 Hines et al. (2009) have shared the raw data used for their study at http://www.uvm.edu/~phines/publications/2009/blackouts.html. (Last accessed 10/9/2014). 6 Table 1. Descriptive statistics for different primary causes of blackouts in PJM between 1984 -2006 Primary Causes Natural disaster Weather Fire Intentional attack3 Supply shortage Other external causes Equipment Failure Operator Error Voltage reduction/Volunteer reduction % of events Mean duration (hours) Mean size in MW lost Mean size in Customers affected 10 36.15 1.54 1.54 3.85 5.38 20 5.38 31.00 26.05 4.12 50.94 8.75 1.54 3.55 1.98 423.46 295.82 100 0 151.6 102.57 142.76 333.57 299250 171477 33764 0 465013 3500 16203 73925 16.15 23.77 224.04 10666 Table 2. Mean duration of blackouts initiated at different seasons and time of day Time Variable Season Summer Winter Fall/Spring Mean Duration (hours) % events 18.82 17.15 15.93 50.74 22.06 27.21 9.75 11.43 28.28 25.19 22.79 34.56 24.26 18.38 Time of day Morning Noon Evening Night For this study, voltage reduction/volunteer reduction events (which do not affect electricity service) and events with no recorded sizes (MW and number of customer affected) are 3 There were no recorded size (MW or number of customers affected) for these events. 7 excluded. Also, the data may be incomplete as the utilities are not required to report small power outage events as pointed out by Hines et al (2009). Power outage costs depend on both the likelihood and the duration of a blackout. The aim is to develop a model for hourly blackout likelihood and the expected duration given a blackout in PJM. Existing analyses have developed models using historical data on recorded power outage events. For example, Zerriffi et al (2007) uses historical data on blackout events in North America to construct statistical models and predict expected outcomes (the size, duration etc.) of an attack on the power grid. Holmgren and Molin (2006) examine the vulnerability of power systems using disturbance data in Swedish power transmission and distribution systems. A logit regression model is used to model the hourly blackout likelihood in PJM. The dependent variable is dichotomous i.e. the response is coded as 1 if a blackout is initiated in an hour or 0 otherwise. Blackouts are relatively infrequent events, which poses some challenges for the application of the logit model. When events are rare (a large number of zeros relative to ones in the dependent variable), the conventional logit probability estimates can be downward biased (King and Zeng, 2001). The origin of this problem is small sampling bias in maximum likelihood estimation of the logit model. While there is no strict definition for what constitutes ‘rare events,’ King and Zheng (2001) rare events data as “binary dependent variables with dozens to thousands of times fewer ones than zeros”. Our blackout data set meets this definition of rare events. We thus employ the “rare events logit regression” methodology proposed in King and Zeng, (2001) to address this bias4. This method implements the corrections for small sample bias generating approximately unbiased and lower variance estimates of logit coefficients. The logit regression model for hourly blackout likelihood is specified as, 4 This method is available as a software package, ‘relogit’ executable in STATA. 8 ππ,π‘ = ππ₯π(ππ,π‘ π½ + ππ,π‘ ) Where, ππ,π‘ π½ = π½0 + π½1 ∗ ππππ πππ,π‘ + π½2 ∗ πππππππππ¦π,π‘ + π½3 ∗ πππππππ¦π,π‘ + π½4 ∗ π·ππππππ,π‘ + π½5 ∗ πΌππ‘π,π‘ (1) The dependent variable ‘Y’ is coded 1 if there is a blackout triggered in hour t or 0 otherwise. Season and Timeofday are categorical variables which explains seasonal and time of day trends in blackout likelihood. The variable Season is a vector consisting of summer, winter (reference variable) and fall/spring. The variable Timeofday is a vector consisting of morning, noon, evening and night (reference variable). Weekday is a dummy variable which is coded 1 if the blackout is triggered during a weekday or 0 otherwise. Demand is the hourly total system demand in PJM. Data for total system demand in PJM was available starting from 1993, hence blackout events occurring before 1993 were excluded for this analysis. There is also an interaction variable Int capturing interaction between Timeofday and Demand. We use a similar approach as Zerriffi et al (2007) to model the expected duration of a blackout. Linear regression is used to model the natural logarithms of duration of a blackout. The OLS regression model is specified as, ππ,π‘ = π½0 + π½1 ∗ ππππ πππ,π‘ + π½2 ∗ πππππππππ¦π,π‘ + π½3 ∗ πππππππ¦πππ’π ππ,π‘ + π½4 ∗ πΆπ’π π‘πππππ π,π‘ + βπ,π‘ (2) The dependent variable ‘Y’ is the natural logarithm of duration of a blackout, Season and Timeofday are categorical vector variables which explains seasonal and time of day trends in 9 blackout duration. Primarycause is a categorical variable for various primary causes triggering blackout. Customers is the natural logarithms of the number of customers affected. 3. Modeling Private and Social Reliability Benefits CHP provides locally generated power and sustains operations in a facility during a blackout as was seen during Hurricane Sandy. Our work has focused on quantifying the reliability benefit associated with increased CHP deployment. There are two such benefits. Firstly, the owners of installed CHP units benefit because the CHP unit can act as a source of backup power during a blackout. We refer to this as the “private” reliability benefit since it accrues only to the CHP owner (or owners, in the case of a shared or district system). The private benefits to CHP owners will be the avoided electricity purchase costs and the avoided customer interruption costs by operating CHP during a blackout. The gross savings from a single CHP unit will be, Gπππ π πππ£ππππ , ππ,π‘ = {ππ΅,π‘ × ππ΅,π‘ − π′ π,π‘ × π ′ π,π‘ } + {πΆπ (π, π) × ππ‘ } (3) The subscript i denotes the number of CHP units and t represents the hour. ππ and ππ are the baseline demand and electricity price in every hour without any CHP unit respectively , π ′ is the reduced demand with a portion of electric demand met by CHP and π′ is the new electricity price. In this case, the demand satisfied by a single CHP unit is small relative to the zonal demand, and will not reduce demand sufficiently to change the zonal electricity price or the blackout probability. So the baseline price (ππ ) and new electricity price (π′ ) will be the same. πΆ is the power outage cost incurred by the customer (without CHP) given the customer characteristics (c) and blackout characteristics (b). It is assumed that CHP system has the 10 capability to be operated throughout the duration of blackout. π is the average blackout probability for a given hour. A substantial number of CHP installations will, collectively, reduce the demand for electricity provided by the grid, thus reducing wholesale electricity prices. Equation 3 can be rewritten as, Gπππ π πππ£ππππ , ππ,π‘ = {ππ΅,π‘ × ππ΅,π‘ − π′ π,π‘ (π) × π ′ π,π‘ } + { πΆπ (π, π) × ππ‘ (π)} (4) where n represents the number of CHP units already deployed. When n is sufficiently large, the new electricity price (π′ ) will be lower than the baseline price(ππ ) depending on the level of CHP deployment. The average blackout probability for a given season also depends on number of CHP unis already installed. With incremental CHP adoption, the average blackout probability decreases. Secondly, as discussed above, sufficiently large deployment of CHP investments may reduce the likelihood of a blackout from occurring. Blackouts are more likely to be instigated when the electrical grid is under stress and removing demand from the grid (onto local CHP systems) can reduce this stress. The benefits to non-CHP owners or the societal benefits will be the reduced power outage costs resulting because of the reduced risk. ππππππ‘ππ π΅ππππππ‘π , ππ΅π‘ = βππ,π‘ (π) ∗ πΆπ (π, π) (5) π₯π is the blackout probability reduction corresponding to the demand reduction from n number of CHP units deployed, C is the sum of power outage costs experienced by non-CHP owners. 11 The reduction in the blackout risk corresponding to the level of CHP deployment is estimated by the logit model discussed in section 2 (equation1). The capital cost for CHP is the upfront cost of the power generating unit and the cost of black start services to operate CHP independent of the grid. The variable cost includes fuel (natural gas) cost for CHP system operation, the maintenance cost and additional fuel cost to operate CHP during a blackout. πΆπππ‘πππ πΆππ π‘π , πΆπ = πΆπ,πππ’ + πΆπ,π (6) ππππππππ πΆππ π‘π , ππΆπ = πΆπ,π + πΆπ,π&π + πΆπ,ππ (7) πΆπ,πππ’ is the cost of the power generating unit, πΆπ,π is the cost of black start services, πΆπ,π is the cost of fuel to run the CHP unit and πΆπ,π&π is the operating and maintenance costs, πΆπ,ππ is the additional fuel cost to operate CHP during a blackout. 4. Building a CHP Adoption Case Study 4.1 CHP adoption in commercial buildings This study focuses on the deployment of CHP among various types of commercial buildings in Philadelphia. We draw upon the approach illustrated in Govindarajan (2012) to simulate a large-scale adoption of CHP in commercial buildings. The approach uses building stock data and simulated energy load profiles for commercial buildings (with and without CHP) to estimate hourly CHP usage in a year. Table 3 shows the commercial buildings stock used in Govindarajan (2012). The ranking represents the most advantageous site for CHP deployment (hospital) followed by less advantageous sites. The energy load profiles were simulated using the BCHP screening tool. Simulations were done for three scenarios for each building type – 12 baseline without CHP, CHP system following thermal loads (FTL) and CHP system following electrical load (FEL). Table 3. Commercial buildings stock in Philadelphia Rank Building Type Number of buildings 1 Hospital 50 2 Hotel 74 3 Restaurant 29 4 Office 284 5 Supermarket 51 6 School 63 7 Motel 22 8 Warehouse 439 We simulate deployment of CHP units according to the priority rankings developed by the Lawrence Berkley National Laboratory (Lawrence Berkeley National Lab 1991). Our analysis assumes that CHP units will be installed at the most advantageous sites first (according to the LBNL rankings) followed by deployment at progressively less advantageous sites. We thus assume that CHP units will be installed first in all the hospitals (which are ranked the most advantageous single-use cases for CHP) followed by hotels and so on, as shown in Table 3. All CHP units are operated during peak demand periods in the grid and there is no operation during weekends. Reflecting a limitation in the building stock data, we assume that building types have homogeneous thermal and electric load profiles within type and those demand profiles are wellrepresented by the BCHP tool. For each CHP operation strategy (FEL/FTL), the difference between the building load with and without CHP represents the hourly demand reduction in the 13 grid. Following this, hourly demand in PJM electricity markets is reduced (using demand in 2006 as the baseline) with every CHP unit deployed. The hourly blackout probability reduction is estimated (using equation 1) with the reduction in hourly demand for each CHP operation strategy. 4.2 Power outage costs estimation We draw upon an approach illustrated by (Sullivan et al. 2010) to estimate power outage costs for different commercial buildings. Sullivan et al. (2010) uses a two-part econometric model that estimates the probability that an outage cost is greater than zero and the size of outage costs using survey data from electric utilities. The model uses expected outage conditions (duration, time of occurrence etc.) and customer characteristics (building type, annual MWh etc.) as inputs to estimate the level of outage costs. Table 4 summarizes the regression coefficients of the variables used in the econometric model developed by Sullivan et al (2010) and the source of inputs for our analysis. In order to calculate power outage costs, we use the expected blackout duration (from the OLS model, equation 2) and allow this duration to vary by season. We construct a weighted average of expected duration across all types of blackout instigators using the frequency of blackouts (for every primary cause) as weights for different seasons. The expected outage conditions reflect the blackout frequency from the historical data described in section 2. For example, since about 23 percent of the blackouts have occurred in the morning, the weight placed on the variable ‘Morning’ will be 0.23 (see table 2). The annual electricity consumption (in MWh) for different commercial buildings is obtained from the simulated load profiles (from BCHP tool). The industry mix listed (in table 6) excludes industry types like construction, 14 manufacturing and mining etc. since our focus is on commercial buildings. Restaurants and supermarkets were classified as ‘wholesale and retail trade’ and other buildings types (table 3) were classified ‘industry unknown’. To estimate outage costs for a supermarket, for example, the input for ‘wholesale and retail’ will be assigned 1 (and rest 0). Table 4. Regression coefficients of econometric model by Sullivan et al (2010) Variable Outage Characteristics Duration(in minutes) Regression coefficients from Sullivan et al (2010) Probit GLM Variable inputs used in this study Expected duration from OLS model (equation 2) 0.007 0.0091 0 0 Morning Noon Evening Summer Weekday 0.2002 0.3805 -0.0197 0.4608 0.1511 0.0185 0.28 0.3058 -0.0773 0.2522 Blackout frequency summarized in table 2 Advanced Warning 0.0762 -0.0883 No advanced warning 0.0852 0.4509 -0.0002 -0.0002 0 0 0.455 0.1642 0.1502 0.2727 0.5216 1.0763 0.0267 0.0804 0.2657 0.127 -1.7 4.5241 Duration Squared Customer Characteristics Natural log of Annual MWh Duration * ln MWh Duration squared *ln MWh Industry mix Wholesale and retail Services Industry unknown backup generation or power conditioning backup generation and power conditioning constant Annual consumption data from BCHP tool Building type classification Average values from Sullivan et al, (2010) 15 5. Results 5.1 Blackout likelihood and expected duration The results of our logit model for blackout probability (equation 1) are shown in table 5. The results suggest statistically significant seasonal and time of day trends associated with blackout likelihood. Blackouts are more likely during summer months as compared to winter months. Also, blackouts are more likely to be triggered during morning and afternoon hours as compared to night time. There is a positive and significant relationship between blackout likelihood and demand for electricity in PJM. A unit percent increase in demand will increase odds of a blackout by 0.0022 % holding other variables constant. In other words, demand reduction will lead to reduced blackout likelihood and this effect will be greater during summer months. Table 5. Logit regression model results: Hourly blackout likelihood in PJM Variables Season Summer Fall/Spring Time of day Morning Afternoon Evening PJM Demand Logit Model Rare Events Logit Model Logit Model (2nd order demand) 0.541* (0.304) 0.316 (0.321) 0.529* (0.303) 0.319 (0.322) 0.532* (0.305) 0.303 (0.321) 2.091** (0.903) 2.004*** (0.685) 0.441 (0.797) 2.20E-05 ** (1.08E-05) 1.854*** (0.692) 1.944*** (0.622) 0.471 (0.789) 2.4E-05** (1.06E-05) 1.138** (0.514) 1.558*** (0.423) 0.727 (0.512) 1.85E-10** (9.11E-11) Interaction between demand and time of day 16 Interaction 1 Interaction 2 Interaction 3 Weekday Constant -4.81E-05** (2.32E-05) -2.27E-05* (1.41E-05) 5.49E-06 (1.06E-05) 0.307 (0.287) -9.404 (0.612) -0.42E-05** (1.63E-5) -2.2E-05* (2.24E-05) 4.53E-06 (1.33E-05) 0.275 (0.289) -9.345 (0.598) Number of Observations 122,640 122,640 Log likelihood -581.861 LR chi2(10) 36.74 Prob > chi2 0.0001 Pseudo R2 0.0306 Standard errors in parentheses, *** p<0.01, ** p<0.05, *p<0.1 -5.17E-10** (2.72E-10) -2.22E-10** (1.21E-10) 3.56E-12 (1.06E-10) 0.307 (0.285) -8.901 (0.452) 122,640 -581.723 37.02 0 0.0308 We implemented both a conventional logit model and the rare events logit model (King and Zheng, 2001). The results of the rare events logit regression (Table 5) are similar to that of the logit model. This suggests that the small sample bias, pointed out by King and Zeng (2001), was not severe in the blackout data used in this study5. As a robustness check, the logit model was estimated for a second degree order of PJM demand and the results were similar (also shown in Table 5). Table 6. Linear regression model results: Expected duration of a blackout in PJM Variables Customers affected Season Summer Winter Time of day 5 Linear regression model Coefficients 0.664*** Standard Error 0.155 0.353 1.06 0.564 0.660 Collier and Hoeffler (2004) used rare events logit and found that the small sample bias was not severe in their data 17 Morning Afternoon Evening Primary cause Natural Disaster Weather Fire Equipment Failure -1.965** -0.92 -0.76 0.943 0.819 0.802 -0.43 0.19 2.32 -0.22 1.337 1.169 1.991 1.235 Operator Error -0.72 1.334 constant -3.75 2.330 Number of 57 observations Prob > F 0.0003 R-squared 0.508 Adjusted R-squared 0.388 Root MSE 1.559 Standard errors in parentheses, *** p<0.01, ** p<0.05, *p<0.1 The results of the regression model for blackout duration (equation 2) are shown in Table 66. The number of customers affected is significant and positively related to the duration of blackout. Adjusted predictions are used to explain seasonal and primary cause effects. Table 7 summarizes the adjusted predictions for primary blackout causes during different seasons. Adjusted predictions represent the estimated natural log of blackout duration at mean value of natural log of customers affected. The expected duration (in hours) is the exponential of the values provided in table 7. Holding other variables in the model fixed, weather and fire related blackouts has higher duration across all seasons. Power outages resulting from operator error has low restoration times. Natural disaster has lower restoration times than weather or equipment failure related blackouts. This result, though not intuitive, is consistent with the 6 Observations with no recorded duration were excluded. 18 findings by Simonoff et al. (2005). Restoration times are higher for blackouts occurring at night compared to morning and afternoon hours. Table 7. Adjusted predictions for primary causes at different season and time of day Primary Cause Natural Disaster Weather Fire Other External Causes Equipment Failure Operator Error Season (hours) Time of day (hours) Summe r 1.47 2.08 4.22 Winte r 1.11 1.73 3.87 Fall/Sprin g 2.18 2.79 4.93 Mornin g 0.66 1.27 3.41 Afternoo n 1.70 2.32 4.46 Evenin g 1.86 2.48 4.62 Nigh t 2.62 3.24 5.38 1.90 1.54 2.61 1.09 2.13 2.29 3.05 1.68 1.17 1.32 0.82 2.39 1.88 0.87 0.36 1.91 1.41 2.07 1.57 2.83 2.33 Based on simulated CHP deployment in the Mid-Atlantic region amounting to 1,000 single-user units for commercial buildings, reductions in grid-provided electricity are in the hundreds of Megawatts per hour (on average). The magnitude of loads taken off the grid depends on whether CHP units are operated to follow on-site electrical load (FEL mode) or on-site thermal load (FTL mode). Operating all 1,000 CHP units in FEL or FTL mode will reduce the blackout risk by about 1.7% and 0.6 % respectively. Figure 1 shows the reduction in hourly blackout probability (averaged across a year) with incremental CHP adoption. The blackout risk reduction is higher when CHP is operated in FEL mode through larger reductions in zonal demand. Figure 2 shows the hourly blackout probability (averaged across summer months) with incremental CHP adoption. The result suggests that while the likelihood of a blackout in any given hour is small, blackouts are more likely to occur during the summer peaks as during other times of the year (see Figure 2). While estimates in Figures 2 and 3 appear small in magnitude, 19 they translate to more substantial numbers when translated into expected economic losses associated with blackouts. 8.26E-04 Hourly blackout probability 8.24E-04 8.22E-04 8.20E-04 8.18E-04 8.16E-04 8.14E-04 8.12E-04 8.10E-04 8.08E-04 0 200 400 600 800 1000 Number of CHP units FTL FEL Figure 1. Hourly blackout probability with incremental CHP adoption 20 Hourly blackout probability (Summer) 1.14E-03 1.13E-03 1.13E-03 1.12E-03 1.12E-03 1.11E-03 1.11E-03 0 200 400 600 800 1000 Number of CHP units FTL FEL Figure 2. Hourly summer blackout probability as a function of incremental CHP deployment 6.2 Private benefits to CHP owners Private reliability benefits to CHP owners are the avoided power outage costs where building sites could use the local electricity generated from CHP and sustain critical operations during a blackout. CHP would be operated primarily following the site’s thermal /electric load during normal days and earn benefits from avoided electricity purchases. Figure 3 shows annual power outage costs for different commercial building types in Philadelphia. The private benefits from avoiding blackouts may reach into the thousands of dollars per event. The power outage costs are calculated as the product of the seasonal blackout probability (estimated from equation 1) and the seasonal power outage costs for a given building type (estimated using the approach in section 4.2). The seasonal values are then added up to get an annual estimates of power outage cost. 21 Annual Power Outage Costs ($) 7000 6000 5000 4000 3000 2000 1000 0 Figure 3. Power outage costs for commercial buildings in Philadelphia, based on the blackout risk model and Sullivan (2010) Figure 4 shows the total private benefits of up to one thousand single user CHP units for commercial buildings (equation 4). The primary axis (on the left) shows the avoided outage costs (i.e., reliability benefits) and the secondary axis (on the right) shows the net energy savings from avoided electricity purchases (net savings would incorporate the cost of natural gas to fuel the CHP unit, plus other operational or maintenance costs). The estimates (shown in figure 4) accounts for blackout risk reduction and electricity price reduction from incremental CHP adoption. 22 9 Reliabilty benefits FEL Reliability benefits FTL 8 Millions Millions 2.5 Energy savings FEL Energy savings FTL 7 Net Energy savings($) Annual power outage costs($) 2 6 1.5 5 4 1 3 2 0.5 1 0 0 0 200 400 600 800 1000 Number of CHP units Figure 4. Private reliability and energy-savings benefits from CHP adoption Our estimates of energy savings outweigh the reliability benefit from avoided power outage costs for both CHP operation modes (FEL and FTL). The annual power outage costs are higher in case of CHP-FTL as compared to CHP-FEL with incremental CHP adoption. Though the difference is not large, it arises because the CHP-FEL mode involves larger reductions in demand for grid-provided electricity thus resulting in larger blackout risk reduction. 23 The reduction in power outage costs for CHP-FTL and CHP-FEL with incremental CHP adoption (from blackout risk reduction) is shown in Figure 5. The reduction in outage costs associated with risk reduction (i.e., a lower likelihood of blackouts, as distinct from the ability for CHP units to continue providing services during blackouts) is up to two orders of magnitude smaller than energy savings during times when no blackouts occur. The savings from CHP-FEL is higher since there will be more onsite electricity generation, hence higher avoided electricity costs as compared to CHP-FTL. The savings curve tends to flatten as number of CHP unit Reduction in power outage costs ($) deployed increases indicating that the incremental savings from CHP decreases. 30000 25000 20000 15000 10000 5000 0 0 200 400 600 800 1000 Number of CHP units FTL FEL Figure 5. Monetized risk reduction for CHP owners and operators under CHP-FTL and CHP-FEL operational rules 6.3 Social benefits from large-scale CHP adoption With sufficient deployment scale and proper operational protocols (i.e., operating CHP to follow electrical loads during peak demand periods), CHP deployment may benefit the grid as a 24 whole by reducing stress and thus reducing blackout risk. There is a social value associated where customers who don’t deploy CHP will be benefited from reduced risk of a blackout. We estimate a baseline power outage cost for all commercial customers using the approach discussed in Sullivan et al (2010). We, then calculate the reduction in the baseline cost as a results of the reduction in blackout risk (using equation 5). Figure 6 shows the reduction in power outage costs to commercial customers (or non-CHP owners) with incremental CHP adoption. The social benefits amounts up to $39 million (or $39,000 per CHP unit) when CHP is operated in FEL mode. The social benefits are lower, amounting up to $14 million (or $14,000 per CHP unit) Billions when CHP is operated in FTL mode. 3.65 3.645 3.64 Blackout costs 3.635 3.63 3.625 3.62 3.615 3.61 3.605 3.6 0 200 400 600 800 1000 Number of CHP units FTL FEL Figure 6. Social benefits with incremental CHP adoption 25 7. Conclusion With sufficient deployment scale and proper operational protocols (i.e., operating CHP to follow electrical loads during peak demand periods), even modest levels of CHP deployment in regional electric grids can yield substantial reliability-related benefits. Using historical data on blackout frequencies, durations and scope (number of customers affected) from the Mid-Atlantic electricity market, we have quantified blackout risk as a function of system-wide electricity demand. Unsurprisingly, risk is highest during the winter and summer peaks, with summer blackout risk being somewhat larger than winter blackout risk. CHP units operated to ameliorate peak demand can benefit electricity consumers in two ways. First, CHP-enabled customers can continue to receive electricity service even when power-grid interruptions occur, as long as fuel supplies are not interrupted. This “private reliability benefit” would amount to between $2 and $2.5 million per year with a deployment level of 1,000 CHP units throughout the Mid-Atlantic region. The average private benefit would thus amount to $2,000 to $2,500 per year. The reliability benefit is larger when CHP units are operated in a mode that follows electrical load versus following thermal load. The private reliability benefit, however, is smaller than the energy-savings benefit by a factor of 1.5 to 4. The energy-savings benefit is generally larger than the private reliability benefit, suggesting that building-integrated CHP units have little private incentive to operate in a way that maximizes blackout risk reduction for the grid as a whole. The second mode of reliability benefit from CHP deployment accrues to the grid as a whole through the reduction of stress and thus blackout risk. There is a social value associated where customers who don’t deploy CHP will be benefited from reduced risk of a blackout. We estimate that the social benefits of blackout risk reduction amount to $39 million annually (or 26 $39,000 per CHP unit) when CHP is operated in a way to follow electrical load during peak periods. Our estimated social benefits are lower - $14 million annually for deployment of 1,000 CHP units ($14,000 per unit) when CHP is operated to follow thermal load. Our work suggests that payments to CHP owners/operators for these reliability benefits would be economically justified, but our analysis does have some drawbacks. First, our blackout risk model is relevant only to blackouts that are related to equipment overloads, and not extreme events such as hurricanes or ice storms. CHP could provide a social reliability benefit in these circumstances in a type of micro-grid configuration, but our model is not able to capture this type of benefit. Second, the logit model can be used to estimate the impacts of relatively small changes in risk, but not large changes. In the scope of the PJM electricity market, with generating capacity of nearly 200 GW and peak demands of around 180 GW, we believe that simulating the removal of less than 0.5% of that demand is appropriate for the logit model. Removal of larger levels of demand, perhaps 10%, would be less appropriate. Our model thus has some limitations in terms of its ability to estimate blackout risk reduction with very large CHP deployments. References: ICF International. 2013. “Combined Heat and Power: Enabling Resilient Energy Infrastructure for Critical Facilities”. ORNL/TM-2013/100. ICF International. http://info.ornl.gov/sites/publications/files/Pub41761.pdf. Oak Ridge National Lab. 2012. “How CHP Stepped Up When the Power Went Out During Hurricane Sandy.” American Council for an Energy-Efficient Economy. December 6. Sullivan, M.J., M.G. Mercurio, J.A. Schellenberg, and J.H. Eto. 2010. “How to Estimate the Value of Service Reliability Improvements.” Power and Energy Society General Meeting, 2010 IEEE (July 25): 1–5. doi:10.1109/PES.2010.5589316. 27 King, Douglas E., and M. Granger Morgan, 2007. Customer-Focused Assessment of Electric Power Micro grids. Journal of Energy Engineering 133 (3) (September): 150–164. doi:10.1061/(ASCE)0733-9402(2007)133:3(150). Lawrence Berkeley National Lab, 1991. 481 Prototypical Commercial Buildings for 20 Urban Market Areas (Technical Documentation of Building Loads Database Developed for the GRI Cogeneration Market Assessment Project). Report No. LBL-29798. Online at <http://gundog.lbl.gov/dirpubs/29798.pdf.> Mago, P. J., N. Fumo, and L. M. Chamra, 2009. Performance Analysis of CCHP and CHP Systems Operating Following the Thermal and Electric Load. International Journal of Energy Research 33 (9) (July): 852–864. doi:10.1002/er.1526. Mago, Pedro J., and Amanda D. Smith, 2012. Evaluation of the Potential Emissions Reductions from the Use of CHP Systems in Different Commercial Buildings. Building and Environment 53 (July): 74–82. doi:10.1016/j.buildenv.2012.01.006. Maidment, G.G, X Zhao, and S.B Riffat, 2001. Combined Cooling and Heating Using a Gas Engine in a Supermarket. Applied Energy 68 (4) (April): 321–335. doi:10.1016/S03062619(00)00052-0. Oak Ridge National Lab,2005. BCHP Screening Tool, Version 2.0.1. Online at <http://www.coolingheatingpower.org/about/bchp-screening-tool.php.> Accessed November 12, 2011 Oak Ridge National Lab, 2008. Combined heat and power: Effective Energy Solutions for a Sustainable Future. ORNL/TM-2008/224. Online at < http://www1.eere.energy.gov/manufacturing/distributedenergy/pdfs/chp_report_12-08.pdf> PJM Interconnection, 2012. Historical metered load data. Online at < http://www.pjm.com/markets-and-operations/ops-analysis/historical-load-data.aspx>. Accessed February 21, 2012. Siler-Evans, Kyle, M. Granger Morgan, and Inês Lima Azevedo, 2012. Distributed Cogeneration for Commercial Buildings: Can We Make the Economics Work? Energy Policy 42 (March): 580–590. doi:10.1016/j.enpol.2011.12.028. Strachan, Neil, and Alexander Farrell, 2006. Emissions from Distributed Vs. Centralized Generation: The Importance of System Performance. Energy Policy 34 (17) (November): 2677– 2689. doi:10.1016/j.enpol.2005.03.015. Zerriffi, Hisham, Hadi Dowlatabadi, and Alex Farrell, 2007. Incorporating Stress in Electric Power Systems Reliability Models. Energy Policy 35 (1) (January): 61–75. doi:10.1016/j.enpol.2005.10.007. Ziher, D., and A. Poredos, 2006. Economics of a Trigeneration System in a Hospital. Applied Thermal Engineering 26 (7) (May): 680–687. doi:10.1016/j.applthermaleng.2005.09.007. 28