December 6, 2012

University Of Wisconsin-Eau Claire

Challenge Ropes Course

Amendment One (1)

Request for Bid SS-1310

Questions and Answers

Changes to Specifications and Event Requirements

Changes to Itemized Bid Form

Q. 1 Are bidders required to provide line item prices for Lot Two and Lot Three?

A No, if it is preferred to provide just a lot total bidders can do that. In this case the bidder shall identify that all of the line items are included in the lot total.

Q. 2 For the de-construction phase is the contractor responsible for filling holes where poles are removed?

A Yes, contractor is responsible for filling holes where poles are removed. Holes shall be filled with sand and capped with six (6) inches of topsoil.

Q. 3 Do ground anchors need to be cut off at least three (3) feet down?

A No, we changed this requirement to read, beneath ground level, with the surface smoothed with topsoil.

Changes to Specifications and Event Requirements:

Lot One

Floating Islands will be retained at the present location ( Delete )

Lot Two

Floating Islands will not be rebuilt ( Delete )

Lot Three

4-pole Transfer Tower delete “bronze steel roof”, add “maintenance free brown roof”.

3-pole Transfer Tower remove “with bronze steel roof” requirement.

5-pole Transfer Tower delete

“bronze steel roof”, add “maintenance free brown roof”.

2-pole Transfer Tower delete “bronze steel roof”, add “maintenance free brown roof”.

Addition; 4 each Small Transfer Platforms

New pages 11 and 12 are attached. Please replace when responding to this RFB

Changes to Itemized Bid Form:

Lot Three

Removed bronze steel roof requirement for item 2

Items 1, 3 and 4 changed from bronze steel roof to maintenance free brown roof

Quantity for item 4 corrected to 2 each

Added item 18, 4 each Small Transfer Platforms

A new page 13 is attached. Please replace when responding to this RFB

Please return a signed copy of this amendment page with your bid response.

Amendment one (1) has been received by:

Company Name: ________________________________________

Signature: _____________________________________________

Date: ___________________________

Lot One De-construction:

The following events shall be taken apart including:

Removal of all poles

Removal of all hardware

Cut off ground anchors at least three (3) feet down

Events:

Specifications and Event Requirements

Request for Bid SS-1310

Multvine Traverse

Dangling Duo

High Wild Woosey, two-line & three line bridge

Incline Log

Cat Walk

11

Ties in the Sky

Giant Swing

Zip Line

Nitro Crossing (relocate)

Whale Watch (relocate)

Hour Glass-off climbing tower

Ships Crossing in the Night-between Zip Platform & Hours Glass pole

Note: List all materials and components, on the Itemized Bid Form, that will be re-used from the de-construction.

Lot Two Re-build the following events off the existing climbing tower area:

High Wild Woosey

Static Dangling Duo - design to be used by 4 participants

Nitro Crossing – Under Wheel Chair Bridge

Whale Watch (relocate from current location)

T-P Shuffle (relocate from current location)

Add (2) belay posts for each climbing wall side of the climbing tower x 2

Add (4) belay posts for the Static Dangling Duo

Add (1) belay adjacent to the pamper pole belay post

Lot Three New Course Design to Include:

Specifications:

All High rigging to be life – line capable (no false clip-in points)

1 each 4-pole Transfer Tower Design with maintenance free brown roof

 6’ Rappel wall on 2 sides of the tower to accommodate a dynamic lower or auto belay dismount

Accessible swing arm

LEAP anchors

1 each 3-pole Transfer Tower (No Roof Required)

1 each 5-pole Transfer Tower with maintenance free brown roof

Accessible swing arm

Non-belay cargo net access

Hand cranks to raise and lower cargo net for access

LEAP anchors

2 each 2-pole Transfer Tower Design with maintenance free brown roof

Accessible swing arm on platform dismount for giant swing

12

4 each Small Transfer Platform

New Course Events:

Floating Islands to accommodate 4 participants moving at the same time with separate belay cables per/participant

Mountain Tops initiative to accommodate up to 6 participants (2 per belay cable) 3 platforms built on 2 logs side by side. Mountain Top boards to be tethered

Kings Swing to accommodate 4 participants moving at the same time with separate belay cables per/participant

Zip Line towards existing course with gravity stop

Giant Swing seated with front attachment

Catwalk

Swing Beam

Hour Glass

Multivine Traverse

Horizontal Cargo Net

Bottomless Burma Loops

Low Static Training area to include:

Participant practice area

Facilitator/Training area to include LEAP anchor use and pole wraps

Zip transfer training area

Rescue bag & Atrie training area

Initiative to include:

Spider web (4) sides

Zig Zag

High All Aboard

Up & Over Beam

Lot Four Equipment:

35 each Static lanyards pairs without zorbers, with snap clips

35 each

12 each

40 each

Petzl Vortex Helmets

Headwall Chest Harnesses

Medium Universal Headwell sit harness

20 each

20 each

3 each

Small Universal Headwell sit harness

Steel screw gate carabiners

Rescue bags to include: 3 to 1 Sterling pulley system and rope

3 each

2 each

Atries

True Blue Auto Belays

Lot Five Services:

Employee/staff training, annually, ACCT level 1; Five-day training, for up to 14 participants

Course inspections once per year to meet ACCT certification

18

13

14

15

16

9

10

11

12

17

5

6

7

8

2

3

4

1

6

7

8

9

1

2

3

4

5

Challenge Ropes Course

Itemized Bid Form

Request for Bid SS-1310

Item Qty Description

Lot One

1 De-construction of the existing course per the Specifications and Requirements

Listed on page ______

Item

Price

Total Cost of Lot One

Please attach a list of materials and components that will be re-used in lot two.

13

Total

Price

$__________

1 ea.

Lot Two Re-build events using the existing climbing tower area and materials from the de-construction

High Wild Woosey

1 ea. Static Dangling Duo – design to be used by 4 participants

Floating Islands ( Delete from itemized bid form )

1 ea. Nitro Crossing – Under wheel chair bridge

1 ea.

1 ea.

Whale Watch (relocated from current location)

T-P shuffle (relocated from current location)

2 ea. Add belay posts for each climbing wall side of the climbing tower, X 2

4 ea. Add belay posts for the Static Dangling Duo

1 ea. Add belay post adjacent to the pamper pole belay post

Total Cost of Lot Two

Lot Three New Course

1 ea. 4-Pole Transfer Tower Design with maintenance free brown roof per specifications

1 ea. 3-Pole Transfer Tower Design no roof per specifications

1 ea. 5-pole Transfer Tower Design with maintenance free brown roof per specifications

2 ea. 2-Pole Transfer Tower Design with maintenance free brown roof per specifications

1 ea.

Lot Three Events

Floating Islands per specifications

1 ea. Mountain Tops per specifications

1 ea. Kings Swing per specifications

1 ea. Zip Line per specifications

1 ea. Giant Swing per specifications

1 ea. Catwalk

1 ea. Swing Beam

1 ea. Hour Glass

1 ea. Multivine Traverse

1 ea. Horizontal Cargo Net

1 ea. Bottomless Burma Loops

1 ea. Low Static Training Area to Include

Participant practice area

Facilitator/Training area to include LEAP anchor use and pole wraps

Zip transfer training area

Rescue bag and Atrie training area

1 ea. Initiatives to Include

Spider web (4) sides

$_________

$_________

$_________

$_________

$_________

$_________ $_________

$_________ $_________

$_________

$___________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

$________

Zig Zag

High All Aboard

Up and Over Beam

4 ea. Small Transfer Platform

Total Cost Lot Three

$________

$__________