SAFETY IMPLICATIONS OF BIM 1. In October 2010 SEC Group published a report to the Health & Safety Executive (HSE) which was based upon a survey of 289 firms on their experience of the CDM Regulations [Experience of Working with the Construction (Design and Management) Regulations 2007]. One of the key proposals in that report was that there should be a statutory certification process by which the “delivery team” certifies to the client that the project is safe to construct. Given that the fundamental obligations within the Regulations require project participants to co-operate and co-ordinate their activities with other parties, this could only be made meaningful if the supply chain was appointed early enough in the delivery process. A statutory signing-off process prior to construction would help to achieve this. “Effective management of health and safety risks can only be achieved when such risks are actively considered at project conception and are addressed by the delivery team appointed early enough to buy into the decisions.” This was already written into paragraph 44 in the Approved Code of Practice. 2. The use of BIM will facilitate this objective. PAS 1192-2:2013 (Specification for information and management for the capital/delivery phase of construction projects using building information modelling) defines levels of model definition for building and infrastructure projects. The third level of model definition is developed design. One of the outputs listed is the production, at this level, of a health and safety risk management plan. This risk management plan should demonstrate that – through the modelling process – the design is safe to construct in the sense that risks have been identified and that either they have been managed out or otherwise reduced. 3. If this risk management plan could be considered as a statement by the team that the design is safe to construct this will imply that a number of matters have been addressed: access and sequencing of work issues which carry health and safety risks during the construction and maintenance phases (for example, in the M&E sector plant rooms are often designed with limited access that could make maintenance hazardous); A copy of the suggested actions in the Report is attached to this paper. 1 given that BIM is about identifying the “properties” in the objects displayed there is the opportunity to address hazards associated with use of particular materials or with lifting of excess weights; minimisation of operational hazards such as working at height. 4. The government is now using COBie UK 2012 (Construction Operations Building Information Exchange) as a means of auditing progress at certain stages of design and construction. As the COBie data file grows during the project there are a number of data drops at pre-defined stages of the project. For government projects there are four data drops: is the emerging design meeting the brief (e.g. this will require auditing against cost data or checking for carbon emissions)? is the design in a state of readiness for proceeding with construction? has the contract been awarded on the basis of Guaranteed and Maximum Price? is there full operating and building management data such that the project can be handed over to the asset manager? 5. It is perfectly feasible, therefore, to include within the second data drop the question as to whether the design is fit to be constructed from a health and safety perspective. There is already software that enables design to be checked for compliance with the Building Regulations and, no doubt, this could be extended to ensure that the design is audited against the requirements of the CDM Regulations. However the key element in this process is that early supply chain engagement will be necessary to ensure that the design is safe to be constructed. The question that will have to be asked is: who were the parties responsible for signing off the design as safe for construction? 6. An additional data drop could be introduced into the construction phase. This should ask the question: what site specific risks have been identified and measures taken to eliminate or minimise them? Furthermore have principal contractors provided pre-construction information to contractors prior to them bidding for work? The SEC Group’s Safe Site Access Certificate could be worked into software to facilitate effective risk management of on-site risks. Another pertinent question would be whether all project participants have met the “core criteria” for health and safety competence by 2 virtue of membership of a SIPP Scheme. PROPOSAL 7. The SEC Group has obtained agreement in principle with the Cabinet Office/BIS for a meeting in the autumn of practitioners involved in BIM or planning to become engaged in BIM. The purpose would be to identify a five year programme of activity to help BIM development in the supply chain. The agenda could include the degree to which the management of health and safety risks can be best addressed through the early engagement of the supply chain by deploying BIM. Rudi Klein July 2013 3