Analysis of Rock Mass – Support Interaction & Investigation of Stabilisation Techniques CSMM144 Underground Excavation Design 640046848 Dr J.Coggan April 2015 Introduction This report details the analysis of a planned excavation of a permanent 50m long tunnel, with a specified cross section of 10m x 5m – at a 1000m depth below surface. Provided geotechnical information has been incorporated into the design, and used to offer support recommendations – which have subsequently been further verified through comparisons with stability results derived from the use of several rock mechanics software programs (Examine2D, RocSupport, Phase2, UnWedge, RocLab). This investigation has been conducted for two tunnels of both South East (225o) and South West (135o) orientations; to evaluate the potential effects of different K-ratios due to a variation in in-situ stress and the influence held by discontinuities on the changing directions. For clarity, stereonets outlining the layout of both joint sets, tunnel orientations and bedding have been produced; included in the appendix (Figure A). Finally, comments related to the final design in terms of tunnel shape, and specific support recommendations have been provided. Note: numbered figures (1, 2, 3) are included in this report, and lettered figures (A, B, C) can be found in the attached appendix. Rock Mass Classification: Q-System The supplied geotechnical data included a Q value of 4, which was subsequently assessed using the Q system - to determine the methodology’s support recommendations for the excavation. It is assumed that the Q value applies to both tunnel orientations; despite changing in-situ stresses due to the change in bearing. Figure 1 shows the Q system graph used in to determine required support. ESR, the excavation support ratio, was taken as 1.6 to represent a permanent excavation. The span was taken as 10, giving a span over ESR ratio of 6.25. With the intersection point landing in category 3 – the corresponding support recommendation is then a combination of 5-6cm of fibre reinforced shotcrete with systematic rock bolting. Length of the rock bolts has been calculated as 2.9m in Equation 1 below, with 2.1m spacing as specified in Figure 1. Bolt length = 2 + (0.15 ∗ Width ) = 2 + (0.15 ∗ 6.25) = 3m ESR EQUATION 1 - ROCK BOLT LENGTH The recommended support has been considered as adequate for the excavation. The Q system has a proven history with many cases of successful implementation in the past. However, a key factor that the system does not consider is the influence of bedding on potential block caving. Better outlined in Examine2D illustrations included in the appendix (Figures X and Y), the specific placement of individual rock bolts has the potential to incur a detachment of a block of weak rock due to the alignment of joints in the local region. CSMM144 1 Underground Excavation Design F IGURE 1 - Q-SYSTEM SUPPORT TABLE (NGI, 2013) Examine 2D Examine 2D has been used to model both proposed excavation orientations. In addition to varying the in-situ stresses, the software allowed for the inclusion of joints and bedding – input according to the provided dip and dip directions relative to both tunnel orientations. Excavations were modelled according to the provided data using Hoek-Brown (UCS,GSI,mi,D) and Barton-Bandis (JCS, JRC, residual friction angle) variables, and were specified to 1000m depth. Factor of Safety Figure B shows the factor of safety analysis for the south western tunnel orientation, with a K-Ratio of 1.5. The factor of safety has been visualised through a contour system – highlighting areas of likely potential failure due to the direction and magnitude of the stresses acting upon the excavation. Expected low stresses in the roof (FoS of 0.2) and to a lesser extent, the floor (FoS 0.4) can be seen, but a key issue can be seen in the equally low factor of safety in the right sidewall. It is assumed that this is only not apparent in the left hand side due to the specific placement of joints – which have been approximated – and that the sidewall holds potential to be equally threatening. This low factor of safety would lead to spalling or potentially collapse of the wall, requiring the installation of support. The south eastern excavation has similar threats to stability as identified in the south west; shown in Figure C. As before, low stability can be seen in the sidewall as well as the ceiling, with an additionally unstable floor. Despite having around 30% less in-situ stress acting on it, the south eastern orientation appears to be more unstable than the south west – the reverse of what was expected at the outset of design. This has been attributed to the difference in the dip of the bedding; the SW drive includes horizontal bedding versus the 15o dipped bedding of the SE drive. This dip results in the creation of more hazardous local pockets of instability, as the bedding gets into CSMM144 2 Underground Excavation Design more severe angles of intersection with the joints, and in a closer proximity to the excavation – holding more chance for the creation of wedges. An example of this wedge creation can be seen in the lower left hand wall of the south east excavation (Figure 2). It should again be stated that the joints and bedding input into Examine2D have been created through approximations, and that the specific layout of the joints, and thus optimal rock bolt locations, needs to be physically determined. Stress Distribution F IGURE 2 – W EDGE CREATION Figures D & E show the distributions of horizontal stress (σ1) in MPa throughout both excavations. Key points to note are the areas of low stress and in the case of the SE excavation; negative (tension) forces in the floor and near the lower left corner. This is due to the displacement of the walls due to deformation (discussed below), pulling the rock in towards the centre of the excavation. This is important, as rock is substantially weaker in tension than it is in compression, so the requirement for these areas to be properly identified and subsequently rock bolted (strong in tension) is vital. Additionally, joints experiencing both shear and tension forces have been highlighted in purple and red respectively. Holding the potential to slip, these should ideally be rock bolted if in the immediate surrounding area of the excavation to prevent the knock on effects which could occur (rock fall). Displacement Examine2D is also capable of displaying the total expected displacement of the rock – shown in Figures F & G. For a clearer analysis, the maximum values for each excavation area have been tabulated and converted into mm (Table 1). Although sidewall deformations are relatively similar, differences in the roof and floor can be seen. While the SE drive has less overall vertical movement, the majority of it is in the floor, due to tensional stress forces and the shearing of surrounding joints. Creating a complex situation to deal with - the greater but simpler roof deformation within the SW drive, shown in this case, would be easier to prevent via a standard support setup of rock bolts and shotcrete. T ABLE 1 - MAXIMUM DISPLACEMENTS Limitations A key limitation of the Examine 2D software is that it can only create a simulation in one direction; it is not wholly representative of actual conditions. However, in this unique situation this mostly does not affect the analysis due to the perpendicular alignment of the tunnel & and joint orientations. While the program does well in outlining the issue of potential sidewall spalling and areas of low factor of safety around the excavation – it is not able to incorporate the effect of adding support, subsequently being unable to provide clarification as to the potential influence of a reinforcement design. CSMM144 3 Underground Excavation Design RocSupport The use of the RocSupport software provided an initial limitation in that it only supports circular excavations. While the specific shape of the access tunnel has not been defined, the change of a 10m x 5m excavation to a circular version is considered too great a change to recommend with only fundamental knowledge about the tunnel use requirements. However, the program was still used as a tool for comparison through analysing correlations between the conclusions drawn for a similar sized circular excavation in the same ground conditions. The size of the excavation was taken as a circle of 4m radius, which gives an area of 50.27m2; essentially equivalent to the 50m2 area of the specified excavation. A separate model was created for both individual orientations – the fundamental difference being in the in-situ stress. From the provided geotechnical data, the 37.5MPa stress was taken as acting on the south western tunnel, and the 26.0MPa stress on the south eastern tunnel. These correspond to K-Ratios of 1.50 and 1.04 respectively. In both cases, the distance to which support was installed from the face was found to substantially affect the calculated factors of safety – a factor not included in other systems. This is due to the reactionary stress forces from excavation works requiring time to redistribute throughout the surrounding rock; installing support too early would entrap this unnecessary additional stress. With consideration to this, a distance of 2m was incorporated to allow adequate stress redistribution; shown in Figures I & K. From the graphs, the support can be seen to only begin acting once the gradient of stress redistribution has begun to relax. The support in both directions was similar to the Q system recommendations for an easier comparison between the two support designs; using a combination of 5cm thick shotcrete and systematic rock bolting – though the length of these is only input as a visual factor, and does not affect the stability, unlike in Q. South West Orientation The south west drive originally saw much instability due to the higher in-situ stress – resulting in an original factor of safety of around 0.16; creating a plastic zone with a radius of 5.31m around the tunnel with an in-situ stress of 37.5MPa (K Ratio =1.5). Both shotcrete (50mm thick, 35MPa) and rockbolts (0.63MPa maximum pressure, 17mm bolts) spaced at 1.1m throughout the perimeter of the circular tunnel) were designed (Figure H). This gave a new sampled factor of safety of 1.61, meeting the target of 1.5 for long term stability. While the program does not factor in bolt length to the strength factor, it would need to be ensured that the bolts pass through the plastic layer to access suitably strong rock. South East Orientation Starting with an approximate 0.26 factor of safety with a plastic zone radius of 4.86m and an in-situ stress of 26MPa (K Ratio = 1.04), the south east orientation appears to be stable via the installation of shotcrete alone. As before, 50mm thick shotcrete - with a UCS of 35MPa – was used (Figure J); increasing the factor of safety to 1.51. Further analysis would be required to identify any potentially weak areas which would require rock bolting; especially because the presence of joints has not been taken into account. However, the shotcrete alone acts to bolster the factor of safety regarding the surrounding rock mass enough to only warrant spot bolting in determined weak spots due to discontinuities. Limitations CSMM144 4 Underground Excavation Design RocSupport offers a good means of comparison between the issues outlined by Examine2D and the effectiveness of the standard support systems recommended by rock classification systems (Q). However, it does not have the capacity to determine the extent to which the support is a success in smaller, specific regions which would experience instability due to jointing. This would need further analysis both numerically and on-site to provide optimal support design. Again, a further key limitation is in the circular only geometry. The comparison with Q does identifiy similarities – especially in success using similar reinforcement – however variations such as the exclusion of bolt length in RocSupport do cause issue. Phase2 & UnWedge Two alternative software programs which could offer valuable insight into the stability of the final excavation are the finite element analysis programs Phase 2 and UnWedge. UnWedge UnWedge acts to provide stability analysis and visualisations of the intersecting structural discontinuities in the form of wedges – which could be useful in further design analysis. Factors of safety for each wedge are also provided with the ability to input support. A quick setup of both excavation orientations has been included in the appendix; Figures L and M. The key advantage of the program is that it considers the specific development locations and sizes of wedges in the roof and spalling on the sidewalls; information lacking in the Q system which can be used to compare with Examine2D to best design specific bolt placements. The results correlate with the conclusions drawn from Examine2D; that sidewall spalling, shown in the form of wedges here, is likely to occur due to the stress influence held by the joint discontinuities. While it is difficult to accurately compare exact reinforcement designs (specific instability locations and bolt placements vary), some brief investigation proves that the program does suggest that these ‘danger areas’ can be satisfactorily dealt with the use of rock bolt support. Phase2 Phase 2 is an in-depth finite element analysis program, particularly useful in parametric studies by allowing results shown for multiple tabs of a changing variable value. With regards to further design of the excavation, Phase 2 could be used to assess the influence the young’s modulus of the surrounding rock has on the safety of the tunnel. This could extend to ensuring that prepared support will hold the strength to stabilise the tunnel even if the modulus drops in areas of the excavation. Examples have been included in the appendix, in Figures X Y AND Z. Orientation and shape of access tunnel Considering the differences outlined by Examine2D regarding the stresses, displacements and factors of safety expected to act upon the two potential tunnel orientations; it is recommended to excavate the tunnel towards the South-West – at a bearing of 225o. Despite having a 30% higher in-situ stress, the horizontal bedding planes do not threaten the excavation to the same degree as those dipped at 15o which hold much more potential for wedge creation in the roof and sides. CSMM144 5 Underground Excavation Design With regards to the shape of the tunnel, it is unrealistic to assume that the excavation can and should be driven with right angled corners, as suggested in the Examine 2D examples. The program itself has issues with calculating stresses around such sharp edged corners, and a drill and blast operation would not be expected to blast out right angled corners. Instead, it is expected that the actual access tunnel would form more of an oval shape, which is much more accepting of stress. This is additionally beneficial with regards to reducing floor heave, which is encouraged by sharp corners which can encourage tension. Curved corners act to reduce this effect – which can be seen in Figure 3. While a circular tunnel would be most beneficial with regards to stress redistribution and safety, the desired 10m by 5m excavation size would require a substantial change to convert it into a circular tunnel. Instead, a wide version of the rounded horseshoe seen in the bottom of Figure 3 is recommended to better meet the specified size. F IGURE 3 - TUNNEL SHAPE VS HEAVE Comparison of access tunnel support In addition to ensuring stability in the excavation walls, it is vital that support also ensures the stability of the rock in close proximity to the excavation. Figure B shows the extent of low factor of safety extends beyond the excavation ceiling – approximately 2.5m (while the program does not provide a measurement, the space between beddings is also 2.5m. The final rock bolt design should then be 3m, for full reach. The use of cable bolts to bypass the bedding was considered, to bypass the weakened layers due to bedding near the excavation. However, a cable bolt would be substantially less effective in reinforcing the surrounding rock – also highlighted in Figure D – unlike the standard rock bolt. Shotcrete set to the 5cm thickness suggested by the Q system is accepted as satisfactory in all cases. Conclusion and Recommendations Several conclusions can be drawn from this analysis, in relation to the final tunnel design: The rock mass consists of fairly competent sandstone which will only need general reinforcement in the form of shotcrete and systematic rock bolting. This is suggested by both the Q – system and RocSupport software. The combination of joint sets and bedding poses a sizeable threat with regards to areas of instability and potential rock fall. It is vital that these are properly assessed before work begins – and are continually monitored during and after construction with suitable spot bolting installed. This investigation only looked to setup a general design – further detailed analysis should be carried to fully investigate the suitability of the excavation once support is installed, potentially incorporating the use of Phase 2 software. CSMM144 6 Underground Excavation Design