THIRD QUARTER PERFORMANCE EVALUATION REPORT OF THE STELLENBOSCH WASTEWATER TREATMENT PROJECT WCR023 STELLENBOSCH LOCAL MUNICIPALITY WESTERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 1 OCTOBER 2014 – 31 DECEMBER 2014 i REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 Table of Contents 1 2 INTRODUCTION ............................................................................................................ 1 BACKGROUND TO THE PROJECT .............................................................................. 1 2.1 Project description ................................................................................................. 1 2.2 Project History ....................................................................................................... 2 2.3 Project concept, design and plan ........................................................................... 3 2.4 Start date duration of the programme .................................................................... 4 2.5 Funds allocated to the project ................................................................................ 4 3 PROGRESS TO DATE ................................................................................................... 4 3.1 Milestones ............................................................................................................. 4 Implementation of the approved business plan ............................................................... 5 3.2 Schedule of work and phasing of the activities ...................................................... 5 3.3 Risks taken and management thereof ................................................................... 7 3.4 Capacities dedicated to the programme ................................................................ 7 3.5 Key challenges within the project ........................................................................... 7 4 PROJECT RESULTS AND BENEFICIARIES ................................................................ 8 4.1 Outcomes and outputs........................................................................................... 8 4.2 Beneficiaries and project results ............................................................................ 8 4.3 Jobs created .......................................................................................................... 8 5 CONCLUSIONS/ LESSONS LEARNT ........................................................................... 9 5.1 Lessons learnt ....................................................................................................... 9 5.2 Ownership and sustainability of infrastructure works ............................................. 9 6 RECOMMENDATIONS................................................................................................... 9 ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS .................................................. 10 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT ......................................... 11 ANNEXURE C: DETAILS OF CONTRACTS ....................................................................... 12 ANNEXURE D: PROJECT SCHEDULE .............................................................................. 13 1 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 1 31 December 2014 INTRODUCTION In terms of Section 10(7)(b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit an annual performance report for Schedule 6 within 45 days after the end of each quarter. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide a performance evaluation report covering the 3rd quarter of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 3of the 2014/15 fiscal year, is for the Stellenbosch Waste Water Treatment Works being implemented by the Stellenbosch Local Municipality in the Western Cape Province. The Department of Water and Sanitation (DWS) is co-funding, and Stellenbosch Municipality is the main funder. 2 BACKGROUND TO THE PROJECT 2.1 Project description The Stellenbosch WWTW is located in the town of Stellenbosch in the Western Cape and falls under the Stellenbosch Local Municipality’s jurisdiction. It is the only WWTW currently serving the town of Stellenbosch, which is in the Western Cape (see Figure 1 on overleaf), and further serves the surrounding suburbs and various large industries in the area. The Works was commissioned in 1924. The following is noted for the existing works: The Works has a hydraulic capacity, namely an average dry weather flow (ADWF) of approximately 20 Mℓ/day. Based on this capacity, the Works can handle a maximum peak wet weather flow factor of 2.5; The Works comprises of an activated sludge process, but only includes for COD removal and nitrification. The works cannot biologically remove nitrate and phosphate; Based on the above, the Works is organically and hydraulically overloaded and is currently receiving an ADWF in excess of 23 Mℓ/day; and The sludge treatment facilities are deficient and cannot adequately treat and accommodate existing sludge volumes. Further, the rapid urban expansion of Stellenbosch has placed pressure on the existing WWTW, and is currently hindering development within the urban edge of the town. The Works is currently in a poor condition and unused treated effluent from the WWTW is discharged into the Eerste River system via the Veldwachters River. This water body is one of the key water resources in Stellenbosch, and further supplies irrigation users downstream. The Department of Water and Sanitation has issued a notice of intention to Stellenbosch Municipality in respect of the poor quality of treated effluent being discharged into the Veldwachters River. As a result of the aforementioned, the Stellenbosch Municipality has decided to refurbish the existing Works, namely civil, mechanical, electrical and electronic works, so ensuring that wastewater received at the Works is treated appropriately by passing it through an effective 2 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 treatment process so protecting downstream users. The refurbishment works has been completed, and the contract is currently in the defects liability period. In addition, the Municipality plans to increase the treatment capacity (hydraulic and process) and upgrade the treatment process of the Works to cater for future growth within the catchment area. The aforementioned upgrade is referred to as the Extension Works and the Municipality has recently appointed a consultant for the Extension Works. The Extension contract will be phased as follows: Interim Works (emergency) related to the Extension of the works which was considered vital in order to improve performance of the Works. The refurbishment works Contract has been extended to include the aforementioned scope; and Main Extension Contract. This report shall provide progress feedback specifically on the aforementioned Extension Contract, which is being co-funded by RBIG. Figure 1: Locality Plan The GPS co-ordinates of the project are 33°56’40”S / 18°49’25”E. The project is situated in the Berg Water Management Area. 2.2 Project History In October 2010, the Stellenbosch Municipality appointed Aurecon for the following scope: Refurbishment of the Stellenbosch WWTW and sewer pump stations in Stellenbosch and surrounds. This work was completed at the end of 2013; and Technical planning and preparation of the Regional Bulk Infrastructure Grant (RBIG) reports for the extension of the Stellenbosch WWTW. This works was completed at the beginning of 2012. In November 2013, the Stellenbosch Local Municipality appointed Aurecon as consultants for the extension of the Stellenbosch WWTW and associated Works. The scope of works includes the extension of the existing Stellenbosch WWTW to 35 Mℓ/day and conversion of the existing works to a full biological nutrient removal (BNR) process. The main project stages are as follows: 3 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 2.3 31 DECEMBER 2014 Planning and design (preliminary and detailed); Preparation of contract documentation and tender evaluation; Contract administration and construction supervision; Project close-out; and Managing of other professional services including the environmental approval processes. Project concept, design and plan The project will entail the following scope which should be read in conjunction with the programme included under Annexure D: Project Schedule. Stage 1: Project Inception The project commenced with an inception (project start-up) meeting to finalise the scope of work. This meeting was held in mid-November 2013. Stage 2: Technical Feasibility This stage will include the following tasks: Data collection; Establish Design Parameters; and Options Analysis: An options analysis will be undertaken for alternative process technologies taking into account capital and lifecycle costs, space requirements, ease of operation, treated effluent quality, potential for effluent reuse, sludge handling as well as any other parameters which the Client deems to be important. Stage 3: Preliminary Design Finalisation of Design Parameters namely design flows and flow balancing requirements, wastewater characterisation and process design parameters, TSE discharge standards, reclamation requirements in terms of quantity and quality, required sludge treatment criteria, odour limits and level of odour control required and noise limits; Process Design; Finalise layout; Hydraulic design; Design of General Civil Works; Mechanical Design; Electrical/Electronic Design; and Preliminary Design Report. Stage 4: Site Investigations and EIA Geotechnical Investigation; and Environmental Impact Assessment, Waste License and Water Use License. Stage 5: Detailed Design Civil Design: Design, drawings, specifications and bill of quantities; Mechanical, Electrical and Electronic Design: Design, drawings, specifications, technical data sheets and bill of quantities; and Preparation of Tender Drawings. Stage 6: Tender Documentation Tender documentation will be prepared in accordance with the CIDB standards and project specific requirements as stipulated by Stellenbosch Municipality. The Main 4 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 Extension will be executed as two contracts, namely a civil contract and a mechanical and electrical contract. Stage 7: Tender Process An allowance of seven weeks has been made for the Tender period for the Mechanical and Electrical Contract. For the Civil Contract, five weeks has been allowed for the Tender Period. Thereafter the Tender evaluation will be undertaken. Stage 8: Site Administration Stage 9: Project Close-out 2.4 Start date duration of the programme A detailed project programme is attached under Annexure D. The following is also noted: 2.5 Construction works for the Interim work related to the Main Extension Contract commenced in April 2013 and completion is anticipated for the end of January 2015; Aurecon was appointed as Consulting Engineers for the Main Extension Contract in November 2013; and It is anticipated that construction for the Main Extension Contract will commence during the beginning of 2015. Funds allocated to the project Table 1 below indicates the RBIG funding that was made available to the project to date. Table 1: Funding for the 4 last financial years (incl. VAT) 2011/12 Allocation / Spent amount R 2,000,000 (feasibility study) 2012/13 2013/14 2014/15 Total R 0.00 R 10,000,000 18 169 987 R30,200,000 The project is budgeted to cost R396 million (Aurecon estimate including VAT based on preliminary design and includes capital and indirect costs), funded as follows: 3 Stellenbosch Local Municipality Regional Bulk Infrastructure Grant Other funding : R246,312,000.00 : R149,688,000.00 : R 0.00 PROGRESS TO DATE A performance evaluation was conducted on 23 January 2015 by a team consisting of the following people: 3.1 Ms Penina Sihlali Lizemarie Tolken Ms Toni Belcher Neeren Govender Murray Raubenheimer Jaim Spear DWS Regional Office Stellenbosch Municipality Consultant: Blue Science Aurecon Aurecon Aurecon Milestones The project milestones are reflected in Table 2: 5 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 Table 2: Milestones Name of Organization compiling/ developing Product Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design/EIA approved INTERIM WORK RELATED TO THE EXTENSION CONTRACT Detailed Design Aurecon December 2013 January 2014 Construction Inenzo Water January 2015 January 2015 Operation and Maintenance Plan Inenzo Water January 2015 January 2015 MAIN EXTENSION CONTRACT Preliminary Design Aurecon March 2014 April 2014 EIA Aurecon June 2014 June 2014 WULA Aurecon October 2014 November 2014 Detailed Design Aurecon October 2014 November 2014 N/A January 2017 January 2015 N/A January 2018 January 2017 N/A February 2017 February 2017 N/A February 2018 February 2018 Construction (Phase One) Construction (Phase Two) Operation and Maintenance Plan (Phase One) Operation and Maintenance Plan (Phase Two) Implementation of the approved business plan In its capacity as Water Service Authority and Implementing Agent, Stellenbosch Municipality will provide specialized professional services, financial management and administrative support to the project. Stellenbosch Municipality has also appointed external professional service providers in terms of its supply chain management policies and procedures. These include: Aurecon for engineering consulting services for the Main Extension Contract; and Withers Environmental Consulting (contracting through Aurecon) for the environmental impact assessment and license application processes (Water Use License and Waste License). The details of the contracts are contained in Annexure C. 3.2 Schedule of work and phasing of the activities The overall progress for the “Main Extension Contract” is: Stage 1: Project Inception 100% 6 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Stage 2: Technical Feasibility Data collection: Parameters: Options Analysis: Stage 3: Preliminary Design Finalisation of Design Parameters: Process Design: Finalise layout: Hydraulic design: Design of General Civil Works: Mechanical Design: Electrical/Electronic Design: Preliminary Design Report: 31 DECEMBER 2014 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 60% Stage 4: Site Investigations and EIA Geotechnical Investigation: Completed August 2014 Environmental Impact Assessment (Submitted April 2014), Environmental Authorisation (Received June 2014), Waste License (Received August 2014) and Water Use License (anticipated November 2014). Stage 5: Detailed Design Civil Design: Design, drawings, specifications and bill of quantities; (90% Complete) Mechanical, Electrical and Electronic Design: Design, drawings, specifications, technical data sheets and bill of quantities; (100% Complete) and Preparation of Tender Drawings. (80% Complete) Stage 6: Tender Documentation Mechanical and Electrical Tender documentation prepared and advertised (Complete). Civil Tender documentation prepared and advertised (end of October 2014). Stage 7: Tender Process Mechanical and Electrical Tender: Currently on Tender and Contract award expected December 2015. Civil Contract Tender: Tenders to be advertised end of October 2014, and Contract award expected January 2015 The project schedule is attached in Annexure D. The overall progress for the “Interim work related to the Extension Contract” is: In the period October to December 2014 the following happened: Fitted ultra-sonic sensors to the emergency overflow channel. Installed new grit classifiers and associated mechanical works to the vortex de-gritters. Installed new skip dolley systems to collect the washed grit before collection. Completed major earthworks for the new sludge lagoon and halted construction until September 2014 as the site became inaccessible for construction vehicles and prevented the adequate compaction of side slopes. 7 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 3.3 31 DECEMBER 2014 Risks taken and management thereof Major risks include: 3.4 Keeping the existing works operational and ensuring compliance throughout the construction process. These are high risks that could impact the treatment process, which could adversely impact on the effluent quality and odour. As a result, method statements will be developed by the Contractor and approved by the Engineer and Client before any construction works can commence. Quality of construction: The quality of construction is always of concern, and adequate where proper site supervision and regular inspections by the Engineer will form the pillars for maintaining quality on site. Operation and Maintenance of Membrane Technology: Membrane supplier provides a two year operation assistance and maintenance plan with the Municipality for three years, where the first year will be full time on site, and the second and third year will entail monthly inspections. Capacities dedicated to the programme The project is managed by the Department of Water and Sanitation, jointly through the Regional Bulk Infrastructure Programme and coordinated by the DWS Regional Office in Region. Project role-players and their roles include: 3.5 Water Services Authority – Stellenbosch Municipality; Water Services Provider – Stellenbosch Municipality; Funding – DWS – Regional Bulk Infrastructure Grant (RBIG) and Stellenbosch Municipality (co-funding); Regulator – DWS; Overall Programme and Project Management – Stellenbosch Municipality; Specialized professional services, financial management and administrative support – Stellenbosch Municipality; Design, contract administration and construction monitoring – Aurecon; and Construction work: o Interim work: Inenzo Water o Main Extension Contract: Two separate contracts, with appointments scheduled for December 2014. Key challenges within the project Key challenges include the following: The Principle Contractor for the Main Extension Contract and the Stellenbosch Municipality’s operators will be required to work together to ensure the plant operates efficiently even though certain processes at the plant may not be operational. This will prove to be a challenge and will require careful co-ordination by the Engineer. Project delays must be avoided at all costs. Typical delays experienced during the refurbishment contract included delays due to flooding, theft of new equipment etc. 8 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 4 31 DECEMBER 2014 PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs Currently the expected outcomes and outputs are on track for the phases under construction. The Planning and Preliminary design phases has been completed. The following is summarised: 4.2 Interim Works (emergency) related to the Extension of the works: This project was scheduled for completion at the end of March 2014. There have been recent scope changes, which will result in the Works being delayed to the start of December 2014. Main Extension Contract: The Design for the Mechanical and Electrical works has been completed, and this Contract is currently out for Tender. Aurecon is currently underway with the detailed design for the Civil Works and it is anticipated that the Tender process will commence during October 2014. The appointment of Contractor’s is anticipated for January 2015. Beneficiaries and project results The bulk project aims to meet the expected sanitation demand which will arise from the Municipalities projected urban growth in the Stellenbosch area. The housing backlog of 20,852 extracted from the 2011/2012 WSDP Draft Report of which 8,000 falls within the Stellenbosch area. This will increase the number of houses connected to the sewerage network and will add a further 5 Mℓ/day to the daily inflow at the Stellenbosch WWTW. The 2011 Census data extracted for the Stellenbosch surrounds identifies the following statistics in terms of access to sanitation facilities: 2,752 people have no access to any form of sanitation 2,595 people use the rudimentary bucket system The sanitation backlog equates to 5,347 people, however this value is likely to rise if the 2011/2012 WSDP figures of an additional 8,000 houses are to be built in the near future. The extension of the Stellenbosch WWTW will provide enough capacity to accommodate these residents as their level of service improves towards waterborne sanitation, as well as dry sanitation users, using facilities such as VIP latrines. The inflow of grey water from these rural communities must also be accounted for as it contributes up to 60% of onsite wastewater typically generated. The completion of the project will also ensure the delivery of sustainable basic water services, the enhancement of economic development towards achieving the national services target by 2014, the objectives of water for growth and development, employment and redistribution. The communities and households expected to benefit are captured in Annexure B. As stated in Section 2.3 above, the purpose of the project is to extend the works in order for it to comply with effluent regulations and meet 35 Ml/day hydraulic requirements. 4.3 Jobs created It is anticipated that for the entire project period 80 jobs will be created. 9 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 In this 3rd quarter 5 new jobs were created as on-site construction of the sludge lagoon and associated pipeline works commenced under the Stellenbosch WWTW Refurbishment contract. 5 CONCLUSIONS/ LESSONS LEARNT 5.1 Lessons learnt The upgrade and extension of the Stellenbosch WWTW is seen as a priority project for the Stellenbosch Municipality as the Works has reached its design capacity, and is currently hindering development in the town which will adversely impact on the town’s growth and local economic development in the region. The plant will operate more efficiently once the Interim work has been completed, and will ensure compliance of treated effluent during construction of the Main Extension Contract (3 years). 5.2 Ownership and sustainability of infrastructure works The Stellenbosch Local Municipality is the Implementing Agent and is the owner of the existing infrastructure. The municipality is currently operating the existing waste water treatment works and will continue to do so with the upgraded Works. Stellenbosch has a good record of maintaining the existing treatment works and DWS is satisfied that they will be able to maintain the upgraded WWTW. Stellenbosch will budget for O&M appropriately. 6 RECOMMENDATIONS This project has just commenced as an RBIG-funded project. Progress will be monitored in the following quarter. 10 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS Figure 1: Earthworks of the new Sludge Lagoon 31 DECEMBER 2014 11 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT As highlighted in the RBIG Scoping Report (Report No. 5676/106508 prepared in February 2012), the number of households which lie below the adequate level of service mark are shown in the table below. As highlighted in the Scoping Report, the number of households which lie below the adequate level of service mark are shown in Table 3.1 below. There are no backlogs in terms of water and sanitation services, but as can be seen from the table below, the housing backlog is in the order of 8461 houses as abstracted from the 2010/11 WSDP. Table 1: Water & Sanitation Backlog Water (No. of Units) 0 Sanitation (No. of Units) 0 Housing Need (No Services) 201 29 Housing Need (Communal Services) 8260 8432 TOTAL 8461 8461 Service Level Basic Need (RDP) The proposed project will increase the hydraulic capacity of the Works by 15 Mℓ/day, while the process capacity of the Works will be increased by 23 Ml/day. Assuming 80 ℓ/person/day and 5 people per household for those households which form the housing backlog, results in a total annual average daily sewage yield of 3.4 Mℓ/day. As a result, the housing backlog will make up approximately 22.5% of the Extension Works hydraulic capacity. 12 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME SEPTEMBER 2014 ANNEXURE C: DETAILS OF CONTRACTS CONTRACT NO. AND NAME Interim work under B/SM 365/11: Mechanical, electrical and civil works for the refurbishment of the Stellenbosch WWTW Emergency extension work under B/SM 365/11: Mechanical, electrical and civil works for the refurbishment of the Stellenbosch WWTW B/SM 4/15 & 5/15: Mechanical, electrical and civil works for the extension of the Stellenbosch WWTW (Phases One and Two) NOTE: * ** CONTRACTOR CONTRACT VALUE (incl. VAT) CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE Inenzo Water (Pty) Ltd R24,459,361.20 Nov 2012 June 2014 June 2014 Inenzo Water (Pty) Ltd R4,238,055.94 Dec 2013 June 2014 January 2015 To be procured R370,000,000.00 Dec 2014/ Jan 2015 Jan 2018 Jan 2018 Retention monies withheld have been included as expenditure. All figures include 14% VAT. Estimated completion value. Estimated revised completion date. EXPENDITURE AS AT DECEMBER 2014 (incl. VAT) R23,680,809.10 R 1,562,573.00 R0 % COMPLETION 100% 37% 0% 13 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME SEPTEMBER 2014 ANNEXURE D: PROJECT SCHEDULE 14 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME SEPTEMBER 2014 15 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME SEPTEMBER 2014