Terms of Reference (Design and Build) TERMS OF REFERENCE (DESIGN AND BUILD) TABLE OF CONTENTS 1.0 PROJECT INFORMATION 2 2.0 SCOPE OF THE CONTRACT 3 3.0 CONCEPTUAL DESIGN 5 4.0 PRELIMINARY SURVEY AND INVESTIGATIONS 6 5.0 PERFORMANCE SPECIFICATIONS AND PARAMETERS 6 6.0 DETAILED ENGINEERING REQUIREMENTS 8 7.0 APPROVED BUDGET FOR THE CONTRACT 10 8.0 ELIGIBILITY CRITERIA FOR BIDDERS 11 9.0 CONTENTS OF THE BID 11 10.0 PROCEDURE AND CRITERIA FOR BIDS EVALUATION 12 11.0 DATA TO BE PROVIDED BY THE DPWH 13 12.0 DOCUMENTS TO BE PROVIDED BY THE CONTRACTOR DURING CONTRACT IMPLEMENTATION 14 Page 1 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) TERMS OF REFERENCE (DESIGN AND BUILD) For the PROPOSED REHABILITATION OF QUEZON BRIDGE AND APPROACHES IN MANILA OUTLINE FRAMEWORK 1.0 PROJECT INFORMATION 1.1 Project Description and Significance The Quezon Bridge provides a critical link to vehicles traveling to and from inner Manila. However, the structural condition of the Quezon Bridge needs to be checked based on the current design codes so that it would be seismic resistant and safe to carry the present live load. Moreover, the bridge was damaged by fire and also at risk from damage due to earthquake forces. As such, the proposed structural assessment and rehabilitation of Quezon Bridge is one of the traffic mitigation projects proposed for immediate implementation by the National Capital Region (NCR). The project involves the repair and rehabilitation of the superstructure to conform to the current code, and strengthening/retrofitting of existing substructure. If necessary, the bridge shall likewise retain its original configuration conforming to the National Heritage Act of 2009, preserving a historical structure built 50 years and older within a historical site. The existing bridge approaches will be repaired to suit the existing horizontal alignment. Existing Bridge Condition Quezon Bridge was constructed in 1939 and is one (1) of seventeen (17) bridges crossing Pasig River on the Quiapo side connecting Quezon Boulevard to Lawton on the Ermita side in the city of Manila. Quezon Bridge is a combination of Arch Steel Bridge with a length of 106.40 meters and a PSC Girder Bridge with a length of 142.80 meters with approaches of 197.80 meters long on both approaches. The bridge has a total length of 447.00 meters and with a total width of 22.50 meters including sidewalks and islands, with two (2) traffic lanes on each direction. The main structural members below the deck are very seriously affected by corrosion, particularly the main lower chord members and the connections of longitudinal stringers and transverse girders near expansion joints and along the lower chords. Due to fire incident, the slab soffit was heavily damaged at Quiapo side including the structural members of the bridge. 1.2 Contractual Framework Page 2 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) The contractual arrangement to be used for the project is the Design and Build Scheme. Under this scheme the procuring entity awards a single contract for the architectural/ engineering design and construction to a single firm, partnership, corporation, joint venture or consortium. 1.3 Minimum Qualifications of Proponent The eligibility requirement shall comply with the provisions of Sections 9, 10, and 11 of Annex “G” of the Revised IRR-A of RA 9184. 2.0 SCOPE OF THE CONTRACT 2.1 Obligations of the Contractor a. Undertake Detailed Engineering Design (DED) including Detailed Design Estimate (DDE) with the corresponding Detailed Unit Price Analysis (DUPA) per item (subject to evaluation and acceptability of the DPWH), the conduct of topographic, hydrographic, and cross-section surveys, geotechnical and geological investigation and hydrologic investigation which conforms with the performance specifications (minimum design standards) prescribed by the Department of Public Works and Highways (DPWH). Only upon the submission and acceptance of these documents will the Contractor be allowed to proceed with the construction of the project. As just prudence, the Contract Price may be subject to increase or decrease, depending on the justifiability of the submitted DDE. b. The project shall be constructed according to the DED prepared by the winning Bidder and approved by the DPWH, and in compliance with the Minimum Performance Specifications and Parameters (MPSP) for Construction herein prescribed. The said MPSP for construction includes conformance to the provisions pertaining to highways under the DPWH Standard Specifications for Public Works and Highways, 2004 Edition, Volume II – Highways, Bridges and Airports (Blue Book). The Blue Book incorporates pertinent provisions of the AASHTO, American Society for Testing and Materials (ASTM), and ACI, among other standards. The following works and other incidentals shall be undertaken as described hereunder: 1. Scope of work for rehabilitation of Quezon Bridge superstructure and substructure (per abutment) will depend on the result of the evaluation of the analysis under the prevailing seismic codes of the Philippines 2. Scope of work for rehabilitation of North approach (Quiapo side) of the bridge will depend on the result of the evaluation of the analysis under the prevailing seismic codes of the Philippines 3. Prepare three (3) concepts of Architectural Lighting Design suitable to the existing bridge structure 4. Prepare concept design for the restoration of aesthetic elements of the bridge including access side stairs and pylons. c. The contractor shall be held liable for design and structural defects and/or failure of the completed project within the warranty period specified in Section 62.2 of the revised IRR-A of RA 9184. Page 3 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) d. Coordinate with the different utility providers and/or concerned agencies with regards to the existing utility lines such as electrical line, telephone line, water pipeline and all other utilities affected by the Project, including the existing streetlights and traffic lights to be removed and reinstalled. The contractor shall be responsible for the retrieval and/or turnover of all salvageable materials. e. Coordinate with the Philippine Coast Guard regarding the schedule of activities to be undertaken on the bridge structure. f. Traffic Management During Construction g. Soil investigation using Core Penetration Test (CPT) and same tests h. Testing of structural members of the steel bridge i. Analysis of the bridges under AASHTO 2012 to determine the rating of the structure. Traffic Management Plans for Construction (if applicable) The winning Bidder must submit to the DPWH for approval, detailed Traffic Management Plan for Construction based on the preliminary Traffic Management Plan submitted as part of the Technical Proposal in its bid. The detailed Traffic Management Plan must provide for the following: (1) The minimum disruption set out in Section 2.1g above (2) The proposed timing of road or lane closures for existing roads to facilitate the construction of the bridge structure and road approach, having regard to the minimum disruption obligations. The winning Bidder shall ensure that, during the Construction of the bridge structure, the minimum number of lanes on detour road is kept open and passable. Construction activities shall be so scheduled as to cause the least congestion during peak hours (3) The roads in and around the Construction Area that are to be used as alternate or detour routes by motor vehicles during construction, to reduce traffic congestion. (4) The arrangements for the clearing of obstructions and patching and repair of pavements along the alternate routes as well as along the at-grade, roads, in coordination with the DPWH and local government units (LGUs) (5) The setting up of directional and informative signs leading to and along the alternate routes to aid motorists. A map of the alternate routes shall be provided to LGUs, including barangays, and communities affected (6) The personnel of the winning Bidder /Contractor and their qualifications who will be managing and providing the traffic enforcement and management services. The Plan shall also include their proper training and orientation on these services (7) The consultations and coordination with the Police, LGUs, community leaders, residential and business establishments affected. Before the traffic Management Plan is finalized, the consultations will inform them of the Project and proposed Plan including the alternate routes, obtain their views and suggestions as inputs is finalizing the Plan, and seek their cooperation to effectively carry it out. The Plan shall include arrangements for the agencies mentioned to deploy additional traffic enforcers as needed. (8) The information, education and communication program to advise the motorists, residents, business, and general public on the above. This program shall involve the Page 4 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) use of media – print, radio, TV and internet – including flyers and billboards to inform the public on the Traffic Management Plan before and during Construction. It shall include a mechanism to give updates on the traffic situation, to receive complaints on traffic and road conditions, accidents and emergencies, and to respond to these incidents so as to ease traffic congestion in the Construction Area and on the alternate routes. j. Analysis of the bridge under AASHTO 2012 to determine rafting for the structure k. Staged Construction (1) During the early stage of construction, one side of the bridge is kept open to traffic (partial closure), thus minimizing the Bridge’s total closure. (2) Waterway under the span of the bridge shall be maintained for the navigation during construction. 2.2 Obligations of the DPWH a. Undertake Environmental Impact Study (EIS) and secure Environmental Compliance Certificate (ECC) from the DENR/ EMB (if applicable) b. Approve the Contractor’s design without diminishing the Contractor’s full and sole responsibility for the quality and integrity thereof c. Supervise and monitor the implementation of the project d. Pay the accomplishment accepted in conformance with the minimum performance specification included under the Design and Build Contract 2.3 Contract Terms of Reference The Standard Bidding Documents in the approved Government Procurement Policy Board (GPPB), 4th Edition, CY-2010, including Form of Contract, shall be used, with appropriate modifications to incorporate pertinent provisions of Annex “G” of the Revised IR of RA 9184. 3.0 CONCEPTUAL DESIGN 3.1 Bridge Concept Design 3.1.1 Rehabilitation of Quezon Bridge 3.1.1.1 Superstructure a. Structural evaluation of existing steel arch bridge including approach at Quiapo site and provision of superelevation. b. Restoration of aesthetic elements of the bridge, including access side stairs and pylone. c. Bridge Lighting Facilities such as Architectural/ Aesthetic lightings shall be provided. Likewise, existing road lighting facilities shall be retained. d. Retrofitting of deck slab at slab soffit. e. Reinforce / strengthening of structural members of the bridge. 3.2 Road Concept Design 3.2.1 Miscellaneous Works Traffic, warning, regulatory, informative signs, reflectorized pavement markings and guardrails shall be provided at appropriate locations of the roadway including at bridge sites. Street Lights shall be provided when necessary. Page 5 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) 4.0 PRELIMINARY SURVEY AND INVESTIGATIONS 4.1 Bridge Survey – for the bridge, the following survey activities were undertaken by DPWH: a. Site investigation b. Reconnaissance c. Topographic survey d. Soil Data (confirmatory boring test shall be included in the proposed contract) 4.2 Road Survey – for the construction of bridge approaches, the following survey activities were undertaken by DPWH: a. Site investigation b. Reconnaissance c. Topographic survey d. Road profile and alignment a. Environmental Conditions The following are important environmental conditions to be considered by the contractor in their construction operations during project implementation. Although it is the responsibility of the DPWH to secure an Environmental Compliance Certificate from the DENR, the contractor is obliged under the contract to adhere to the agreement specified in the ECC relative to the protection of the environment: Marine Environment Land Environment Air Environment Noise, air and water pollution b. Utility Location – The project will affect existing utility lines attached to the bridge when lifted. There are also existing street lights/lamp posts & traffic lights that have to be removed & reinstalled during the construction of bridge approaches. Although it is the responsibility of the DPWH to coordinate for its removal/relocation with the concerned utility office & to the local residents who will be affected by such removal/relocation, the contractor should consider the existence of these utilities in their construction schedule, specifically, time necessary for its removal in order not to affect any project activity. 5.0 PERFORMANCE SPECIFICATIONS AND PARAMETERS The Contractor shall provide design-build services to repair and rehabilitate the existing steel bridge which shall meet the following minimum performance specifications or parameters: 5.1 Minimum Performance Specifications for Bridges 5.1.1 Loading Specifications The bridge structures shall be proportioned to the following loads and forces when they are completed and opened to traffic: Page 6 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) 5.1.1.1 5.1.1.2 5.1.1.3 5.1.1.4 5.1.1.5 5.1.1.6 Loading Parameter Live Load Dead Loads – The dead load shall consist of the weight of the complete structure, including the roadway, sidewalks, car trails, pipes conduit, cables and other public utility services. Additional loads for future wearing surface should be added. Live Loads – The live loads shall consist of the weight of the applied moving load of vehicles, cars and pedestrians which is equivalent to MS 18 (HS-20) design live load. The structure shall also be checked against alternate military loading and permit design live load. Impact or Dynamic Effect on the Live Load Wind Load Other forces, when they exist as follows: longitudinal force, centrifugal forces, thermal forces, earth pressure, buoyancy shrinkage stresses, rib shortening, erection stresses, current pressure, and earthquake stresses. Minimum Loading: Minimum Loading MS 18 (HS 20-44) truck loading or an Alternate Military loading of two axles 1.22 meters apart with each axle weighing 107 KN, or permit loading whichever governs Dead Load: Concrete Steel Earth Gravel Wind Load Seismic Loading 5.2 24 KN/cu.m. 77.0 KN/cu.m. 18.90 KN/cu.m. 3.59 KPa In accordance with division IA of the 2002 AASHTO Standard Specifications for Highway Bridges using Acceleration Coefficient of 0.40 and Seismic Performance Category D Project Completion Considering that this is a flagship, priority and fast track infrastructure project that needs to be completed on a tight schedule, the Contractor shall complete the design-build services under the contract, its number of days to be determined upon the completion of the design. Total closure of the bridge to all vehicles shall be determined upon completion of the design. 5.3 Warranty The Contractor shall guarantee the completed structure against structural defects & failure for its satisfactory performance vis-à-vis the prescribed minimum performance specifications during the lifetime of the structure, reckoned from the final acceptance of the project in accordance with the provisions set forth under Section 62.2.3.2(a) of the Revised IRR of RA 9184. For this purpose, the Contractor shall post a Warranty Security in the form of surety bond, callable on Page 7 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) demand issued by a reputable institution equivalent to 30% of the bid/contract price. 6.0 DETAILED ENGINEERING REQUIREMENTS The Contractor shall coordinate and report to the Bureau of Design. DPWH for uniformity and cohesiveness in the preparation of related documents, consistent with the latest edition of the Design Guidelines, Criteria and Standards for Public Works and Highways, AASHTO guidelines and other applicable provisions of existing laws, codes and Department Orders. All reports and other related documents prepared by the Contractor shall be in a format agreed and accepted by the Bureau of Design. The detailed engineering study shall include but will not be limited to the following works: a. Review the current design and standards proposed for the project, taking into consideration such factors as economics, potential for stage construction, right of way availability and constraints (where relevant), social environmental impact and costs, among others. b. The following surveys/investigation/study should be undertaken including preparation of plans, drawings and Program of Work: 1. Topographic survey plans 2. Geotechnical and geological investigation report 3. Hydrology, hydraulic and drainage design report 4. Highway/geometric and pavement design report 5. Bridge existing condition survey report 6. Structural analysis and calculations for bridges, culverts and other structures 7. Foundation analysis 8. Drainage design 9. Slope stability analysis 10. Detailed specifications 11. Detailed quantity calculations 12. Value engineering studies 13. Environment Impact Assessment Studies 14. Electrical/Lighting Design 15. River cross-section survey for possible dredging works c. Technical reports in electronic files and hard copies for the work prepared must be submitted by the Build-Design Contractor to the Bureau of Design (BOD) DPWH for review and approval. d. Design Guidelines and Codes to be followed: Design for this bridge should satisfy the provisions under the latest edition of the ASSTHO Specifications for Highway Bridges and shall conform to the requirements of Department Order No. 75, Series of 1992, DPWH Advisory for Seismic Design of Bridge AASHTO Guide for Design of Pavement and Structures, (Latest Edition) Design Guidelines, Criteria and Standards of the DPWH, Volumes 1 and 2 National Structural Code of the Philippines, Volume II (Latest Edition) Page 8 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) The contractor shall prepare the following plans in accordance with D.O. No. 56, Series of 1995, re: Quality of Plans, and D.O. No. 32, re: Guidelines in the Submission of Plans General: 1. 2. 3. 4. 5. 6. Cover Sheet General Index Vicinity and Key Map Locations Plan/Lay out/Topographic Survey Plan Legend, Abbreviation and Symbols General Notes (Highways and Bridges) Road Plans: 1. 2. 3. 4. 5. 6. Typical Roadway Section Summary of Quantities Soils and Materials Investigation Maps/Plans Grading Quantities Drainage Schedule/Quantities Plan and Profile with the final alignment incorporated in the Topographic/Hydrographic Plans 7. Detailed Cross Section 8. Detailed Drainage Plans, Profile and Cross Sections 9. Geometric Road Design Elements and Standards 10. Road Design Standards and Details 11. Pavement Joint Details 12. Slope Protection Details 13. Drainage Standards and Details 14. Schedule Listing of Road Signs, Guardrails, Lined Ditches, Protection Works, Road Intersections and Other miscellaneous works 15. Pavement, Drainage and Slope Protection Design Parameters 16. Boring Logs and Location of Boreholes/Auger Logs and Soil Profile 17. Reference of Horizontal and Vertical Control 18. Table of Coordinates and Elements of Curves 19. Plan and Profile of affected side/minor streets 20. Details of Geometric improvement at intersections 21. Standard drawings of miscellaneous structures (Road Signs, Pavement Markings, Guardrails, etc.) 22. Street Lighting Plan, Layout, Details Bridge Plans: 1. 2. 3. 4. 5. General Plans and Elevation Boring Logs and Locations of Boreholes Summary of Quantities Details of Superstructures Details of Substructure Page 9 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) 6. 7. 8. 9. Details of Foundation Bank/Abutment Protection Works and Scour Protection Works Construction Sequence and Methodology Temporary work such as cofferdams, craneways, detours, support system for jacking operation 10. Bridge Lighting, it any 11. Traffic Management Plan during Construction e. Technical reports in electronic files and hard copies for the work prepared must be submitted by the Build-Design Contractor to the Planning and Design Division (PDD) DPWH for review and approval by the Regional Director. The road alignment, roadside appurtenance/structure and all the proposed improvements are to be traced in layout at scale of 1:1,000m, together with all watercourses, which require structural work. Cross sections at intervals not exceeding 20.0m including intermediate breaks on the ground and at the bridge approaches and reaching at least 10.0m wide on both sides of the centerline, are to be surveyed and plotted at a scale 1:100m. The detailed cross-sections shall show but are not necessarily limited to the following: pavement and shoulder width and corrections including super elevations where required, new pavement thickness, slope of embankments and cuts including slope protection structures where required, cross-falls of pavements and shoulders, existing ground and finished grade elevations, including quantities of all works items involved. Separate cross-sections shall be prepared, if necessarily, for road sections outside and inside township, the latter indicating possible reduced width of pavement and/or shoulder and for every station or location of drainage structure and facilities. To show or indicate the sufficient height of the road above highest flood level (HFL), longitudinal sections at scales of 1:100m and 1:100m vertical will be prepared for all sections where raising of embankment is required. Whenever there is a need for the relocation of utilities such as telephone, telegraph and electricity poles, etc. as well as buildings, fences and major trees to be removed, such details shall be indicated in the drawings and a separate list shall be prepared. In order to facilitate the process of design review by Bureau of Design (BOD) of the concepts of the proposed structures/facilities and review of the design estimate by Planning and Design Division (PDD), the following activities shall be undertaken: 1. 2. 3. 4. 5. Presentation to and discussion with PDD of Inception Report Clearance with PDD of Design Criteria and Specifications Presentation to and discussion with PDD of the Preliminary Designs Presentation to and discussion with PDD of the Draft Final Designs Presentation to and discussion with Construction Division (CD) of the Preliminary Design Estimate 6. Presentation to and discussion with CD of the Final Design Estimate Note: Presentation of documents shall include computer programs/software. 7.0 APPROVED BUDGET FOR THE CONTRACT (ABC) Page 10 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) The Approved Budget for the Contract (ABC) is P79,244,821.09. This is the ceiling for acceptable bids. Bids higher than ABC shall be automatically rejected. 8.0 ELIGIBILITY CRITERIA FOR BIDDERS The Design and Build Scheme shall adopt the Annex “G” of the Revised Implementing Rules and Regulations of R.A 9184 (e.g. Eligibility Requirement). However, the prospective bidder who have no experience in design and build project on its own, may opt to enter a subcontracting agreement with a design or engineering firms for the designs portion of the project. 8.1 Legal Requirements a. Valid Contractor’s License issued by the Philippines Contractor’s Accreditation Board. b. Valid license of the Contractor’s designer issued by the Professional Regulatory Commission. 8.2 Technical Requirements a. The Contractor must have built one structure similar to the project at hand with a construction cost of at least 50% of the ABC. b. The constructor’s designer must have designed one structure similar to the project at hand with a construction cost of at least 50% of the ABC. 8.3 Financial Requirements a. The Contractor must have a Net Financial Contracting Capacity (NFCC) of at least the ABC or equivalent to P79,244,821.09. b. The Contractor must submit a written commitment from the reputable bank to extend to him a credit line at least 10% of the ABC, if the contract is awarded to him. 9.0 CONTENTS OF THE BID 9.1 Technical Proposal – In the First Envelope a. Preliminary Design Plans – Design scheme of the proposed Rehabilitation of Ayala Bridge and Approaches, the road sections including the appurtenant existing structures located thereto, that will comply with the prescribed performance specifications and parameters. The plans should contain the following: Bridge Design Plan 1. Location Plan/Vicinity Map 2. General Notes on Design Parameter and Construction Procedures 3. General Plan and Elevation 4. Boring Data and Borehole Location 5. Typical Details of Superstructure Page 11 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) 6. 7. 8. 9. Typical Details of Substructure (Piers and Abutments) Typical Details of Foundations Typical Details of Abutment and Pier Protection Works Typical Details of Temporary Structure such as Craneway, Cofferdam, Support System for Jacking Operation etc. 10. Construction Sequence and Methodology 11. Summary of Quantities 12. Typical Lighting Facilities 13. Traffic Management Plan during Construction 14. Other related structures Road Design Plan 1. Location Plan/Vicinity Map 2. General Notes or Design Criteria/Parameters and Construction Procedure 3. Plans, Profile and Cross Sections 4. Typical Details of Slope Protection Works 5. Traffic Data/Information 6. Typical Details of Drainage Structures 7. Summary of Quantities 8. Typical Road Section 9. Typical Lighting Facilities 10. Traffic Management Plan 11. Other related structures b. c. d. e. f. g. 9.2 10.0 Required Bid Security Design and Construction Method and Schedule Constructor’s Organizational Chart and List of Key Personnel for the Project List of Equipment Owned/Leased/Under Purchased for the Project Quality Control Program Bank Commitment to provide the required Credit Line is the Contractor is awarded the contract Financial Proposal – In the Second Envelope a. Fixed Lump Sum Bid Price b. Supporting Detailed Estimates and Summary Costs c. Warranty bond for Lifetime Performance of Completed Structure PROCEDURE AND CRITERIA FOR BIDS EVALUATION Bid Evaluation For the detailed evaluation of the design and build proposal, a two-step procedure shall be adopted by the BAC which shall apply in case of any inconsistencies with the contents of Item 23 of the Tender Documents, to wit: Page 12 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) 1. First-Step Procedure: A. The first step of the evaluation shall involve the review of the preliminary conceptual designs and track record submitted by the contractor as indicated in the bid documents using a non-discretionary “pass/fail” criteria that involve compliance with the following requirements: a. Adherence of preliminary design plans to the required performance specifications and parameters and degree of details; b. Concept of approach and methodology for detailed engineering, design and construction with emphasis on the clarity, feasibility, innovativeness of the plan approach, and the quality of interpretation of project problems, risk and suggested solutions; c. Quality of personnel to be assigned to the project which covers suitability of key staff to perform the duties of the particular assignments and general qualifications and competence including education and training of the key staff. B. For complex or unique undertaking, such as those involving highly specialized or advance engineering technology, eligible bidders may be required, at the option of the agency concerned, to make and oral presentation within (15) calendar days after the deadline for submission of technical proposals. 2. Second-Step Procedure: Only those bids that passed the above criteria shall be subjected to the second step of evaluation. The BAC shall open the financial proposal of each “passed” bidder and shall obtain the correct calculated prices. The financial bids as so calculated shall be ranked, in ascending order, from lowest to highest. The bid with the lowest price shall be identified as the Lowest Calculate. 11.0 DATA TO BE PROVIDED BY THE DPWH The following data shall be provided by DPWH: (Note: These data are for reference only. The DPWH does not guarantee to the contractor that the data provided are correct, free from error, and applicable to the project at hand. The Contractor is responsible for the accuracy or applicability of any data that he will use in his design-build proposal and services.) 11.1 11.2 Topographic Survey Preliminary Survey and Geotechnical Investigation Data Page 13 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches Terms of Reference (Design and Build) 11.3 11.4 11.5 11.6 Concept Design Traffic Data – AADT and Axle Loading Preliminary Horizontal and Vertical Alignment Other Relevant Data 12.0 DOCUMENTS TO BE PROVIDED BY THE CONTRACTOR DURING CONTRACT IMPLEMENTATION The following documents shall be provided by the Contractor during Contract Implementation: 12.1 12.2 12.3 12.4 12.5 12.6 12.7 12.8 12.9 12.10 Signed Contract Approved “For Construction” Drawings Approved Technical Specifications Approved Detailed Cost Estimates with Unit Price Analysis Detailed Engineering Plans Design Analysis Survey Data Detailed Geotechnical Investigation Report Design Report As-Built Plans Prepared By: Checked By: RICARDO C. DE VERA Engineer III LYDIA G. CHUA Engineer V Chief-Planning & Design Division, DPWH-NCR Recommending Approval: APPROVED: TIBURCIO L. CANLAS OIC - Asst. Regional Director REYNALDO G. TAGUDANDO Regional Director 6.1.8 EGA/RCV Tor design build.docx Page 14 of 14 Proposed Rehabilitation of Quezon Bridge and Approaches