Terms of Reference (Design and Build) TERMS OF REFERENCE

advertisement
Terms of Reference
(Design and Build)
TERMS OF REFERENCE
(DESIGN AND BUILD)
TABLE OF CONTENTS
1.0
PROJECT INFORMATION
2
2.0
SCOPE OF THE CONTRACT
3
3.0
CONCEPTUAL DESIGN
5
4.0
PRELIMINARY SURVEY AND INVESTIGATIONS
6
5.0
PERFORMANCE SPECIFICATIONS AND PARAMETERS
6
6.0
DETAILED ENGINEERING REQUIREMENTS
8
7.0
APPROVED BUDGET FOR THE CONTRACT
10
8.0
ELIGIBILITY CRITERIA FOR BIDDERS
11
9.0
CONTENTS OF THE BID
11
10.0
PROCEDURE AND CRITERIA FOR BIDS EVALUATION
12
11.0
DATA TO BE PROVIDED BY THE DPWH
13
12.0
DOCUMENTS TO BE PROVIDED BY THE CONTRACTOR DURING
CONTRACT IMPLEMENTATION
14
Page 1 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
TERMS OF REFERENCE (DESIGN AND BUILD)
For the
PROPOSED REHABILITATION OF QUEZON BRIDGE AND APPROACHES
IN MANILA
OUTLINE FRAMEWORK
1.0 PROJECT INFORMATION
1.1
Project Description and Significance
The Quezon Bridge provides a critical link to vehicles traveling to and from inner Manila.
However, the structural condition of the Quezon Bridge needs to be checked based on the
current design codes so that it would be seismic resistant and safe to carry the present live
load. Moreover, the bridge was damaged by fire and also at risk from damage due to
earthquake forces.
As such, the proposed structural assessment and rehabilitation of Quezon Bridge is one of the
traffic mitigation projects proposed for immediate implementation by the National Capital
Region (NCR). The project involves the repair and rehabilitation of the superstructure to
conform to the current code, and strengthening/retrofitting of existing substructure. If
necessary, the bridge shall likewise retain its original configuration conforming to the National
Heritage Act of 2009, preserving a historical structure built 50 years and older within a historical
site. The existing bridge approaches will be repaired to suit the existing horizontal alignment.
Existing Bridge Condition
Quezon Bridge was constructed in 1939 and is one (1) of seventeen (17) bridges crossing Pasig
River on the Quiapo side connecting Quezon Boulevard to Lawton on the Ermita side in the city
of Manila.
Quezon Bridge is a combination of Arch Steel Bridge with a length of 106.40 meters and a PSC
Girder Bridge with a length of 142.80 meters with approaches of 197.80 meters long on both
approaches. The bridge has a total length of 447.00 meters and with a total width of 22.50
meters including sidewalks and islands, with two (2) traffic lanes on each direction. The main
structural members below the deck are very seriously affected by corrosion, particularly the
main lower chord members and the connections of longitudinal stringers and transverse girders
near expansion joints and along the lower chords. Due to fire incident, the slab soffit was
heavily damaged at Quiapo side including the structural members of the bridge.
1.2
Contractual Framework
Page 2 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
The contractual arrangement to be used for the project is the Design and Build Scheme. Under
this scheme the procuring entity awards a single contract for the architectural/ engineering
design and construction to a single firm, partnership, corporation, joint venture or consortium.
1.3
Minimum Qualifications of Proponent
The eligibility requirement shall comply with the provisions of Sections 9, 10, and 11 of Annex
“G” of the Revised IRR-A of RA 9184.
2.0 SCOPE OF THE CONTRACT
2.1
Obligations of the Contractor
a. Undertake Detailed Engineering Design (DED) including Detailed Design Estimate (DDE)
with the corresponding Detailed Unit Price Analysis (DUPA) per item (subject to
evaluation and acceptability of the DPWH), the conduct of topographic, hydrographic,
and cross-section surveys, geotechnical and geological investigation and hydrologic
investigation which conforms with the performance specifications (minimum design
standards) prescribed by the Department of Public Works and Highways (DPWH). Only
upon the submission and acceptance of these documents will the Contractor be allowed
to proceed with the construction of the project. As just prudence, the Contract Price
may be subject to increase or decrease, depending on the justifiability of the submitted
DDE.
b. The project shall be constructed according to the DED prepared by the winning Bidder
and approved by the DPWH, and in compliance with the Minimum Performance
Specifications and Parameters (MPSP) for Construction herein prescribed. The said MPSP
for construction includes conformance to the provisions pertaining to highways under
the DPWH Standard Specifications for Public Works and Highways, 2004 Edition, Volume
II – Highways, Bridges and Airports (Blue Book). The Blue Book incorporates pertinent
provisions of the AASHTO, American Society for Testing and Materials (ASTM), and ACI,
among other standards.
The following works and other incidentals shall be undertaken as described hereunder:
1. Scope of work for rehabilitation of Quezon Bridge superstructure and substructure
(per abutment) will depend on the result of the evaluation of the analysis under the
prevailing seismic codes of the Philippines
2. Scope of work for rehabilitation of North approach (Quiapo side) of the bridge will
depend on the result of the evaluation of the analysis under the prevailing seismic
codes of the Philippines
3. Prepare three (3) concepts of Architectural Lighting Design suitable to the existing
bridge structure
4. Prepare concept design for the restoration of aesthetic elements of the bridge
including access side stairs and pylons.
c. The contractor shall be held liable for design and structural defects and/or failure of the
completed project within the warranty period specified in Section 62.2 of the revised
IRR-A of RA 9184.
Page 3 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
d. Coordinate with the different utility providers and/or concerned agencies with regards to
the existing utility lines such as electrical line, telephone line, water pipeline and all
other utilities affected by the Project, including the existing streetlights and traffic lights
to be removed and reinstalled. The contractor shall be responsible for the retrieval
and/or turnover of all salvageable materials.
e. Coordinate with the Philippine Coast Guard regarding the schedule of activities to be
undertaken on the bridge structure.
f. Traffic Management During Construction
g. Soil investigation using Core Penetration Test (CPT) and same tests
h. Testing of structural members of the steel bridge
i. Analysis of the bridges under AASHTO 2012 to determine the rating of the structure.
Traffic Management Plans for Construction (if applicable)
The winning Bidder must submit to the DPWH for approval, detailed Traffic Management
Plan for Construction based on the preliminary Traffic Management Plan submitted as
part of the Technical Proposal in its bid. The detailed Traffic Management Plan must
provide for the following:
(1) The minimum disruption set out in Section 2.1g above
(2) The proposed timing of road or lane closures for existing roads to facilitate the
construction of the bridge structure and road approach, having regard to the
minimum disruption obligations. The winning Bidder shall ensure that, during the
Construction of the bridge structure, the minimum number of lanes on detour road is
kept open and passable. Construction activities shall be so scheduled as to cause the
least congestion during peak hours
(3) The roads in and around the Construction Area that are to be used as alternate or
detour routes by motor vehicles during construction, to reduce traffic congestion.
(4) The arrangements for the clearing of obstructions and patching and repair of
pavements along the alternate routes as well as along the at-grade, roads, in
coordination with the DPWH and local government units (LGUs)
(5) The setting up of directional and informative signs leading to and along the alternate
routes to aid motorists. A map of the alternate routes shall be provided to LGUs,
including barangays, and communities affected
(6) The personnel of the winning Bidder /Contractor and their qualifications who will be
managing and providing the traffic enforcement and management services. The Plan
shall also include their proper training and orientation on these services
(7) The consultations and coordination with the Police, LGUs, community leaders,
residential and business establishments affected. Before the traffic Management Plan
is finalized, the consultations will inform them of the Project and proposed Plan
including the alternate routes, obtain their views and suggestions as inputs is
finalizing the Plan, and seek their cooperation to effectively carry it out. The Plan
shall include arrangements for the agencies mentioned to deploy additional traffic
enforcers as needed.
(8) The information, education and communication program to advise the motorists,
residents, business, and general public on the above. This program shall involve the
Page 4 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
use of media – print, radio, TV and internet – including flyers and billboards to
inform the public on the Traffic Management Plan before and during Construction. It
shall include a mechanism to give updates on the traffic situation, to receive
complaints on traffic and road conditions, accidents and emergencies, and to
respond to these incidents so as to ease traffic congestion in the Construction Area
and on the alternate routes.
j. Analysis of the bridge under AASHTO 2012 to determine rafting for the structure
k. Staged Construction
(1) During the early stage of construction, one side of the bridge is kept open to traffic
(partial closure), thus minimizing the Bridge’s total closure.
(2) Waterway under the span of the bridge shall be maintained for the navigation during
construction.
2.2
Obligations of the DPWH
a. Undertake Environmental Impact Study (EIS) and secure Environmental Compliance
Certificate (ECC) from the DENR/ EMB (if applicable)
b. Approve the Contractor’s design without diminishing the Contractor’s full and sole
responsibility for the quality and integrity thereof
c. Supervise and monitor the implementation of the project
d. Pay the accomplishment accepted in conformance with the minimum performance
specification included under the Design and Build Contract
2.3
Contract Terms of Reference
The Standard Bidding Documents in the approved Government Procurement Policy Board
(GPPB), 4th Edition, CY-2010, including Form of Contract, shall be used, with appropriate
modifications to incorporate pertinent provisions of Annex “G” of the Revised IR of RA 9184.
3.0 CONCEPTUAL DESIGN
3.1
Bridge Concept Design
3.1.1 Rehabilitation of Quezon Bridge
3.1.1.1
Superstructure
a. Structural evaluation of existing steel arch bridge including approach at Quiapo site and
provision of superelevation.
b. Restoration of aesthetic elements of the bridge, including access side stairs and pylone.
c. Bridge Lighting Facilities such as Architectural/ Aesthetic lightings shall be provided.
Likewise, existing road lighting facilities shall be retained.
d. Retrofitting of deck slab at slab soffit.
e. Reinforce / strengthening of structural members of the bridge.
3.2
Road Concept Design
3.2.1 Miscellaneous Works
Traffic, warning, regulatory, informative signs, reflectorized pavement markings and guardrails
shall be provided at appropriate locations of the roadway including at bridge sites. Street Lights
shall be provided when necessary.
Page 5 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
4.0 PRELIMINARY SURVEY AND INVESTIGATIONS
4.1
Bridge Survey – for the bridge, the following survey activities were undertaken
by DPWH:
a. Site investigation
b. Reconnaissance
c. Topographic survey
d. Soil Data (confirmatory boring test shall be included in the proposed
contract)
4.2
Road Survey – for the construction of bridge approaches, the following survey
activities were undertaken by DPWH:
a. Site investigation
b. Reconnaissance
c. Topographic survey
d. Road profile and alignment
a. Environmental Conditions
The following are important environmental conditions to be considered by the contractor
in their construction operations during project implementation. Although it is the
responsibility of the DPWH to secure an Environmental Compliance Certificate from the
DENR, the contractor is obliged under the contract to adhere to the agreement specified
in the ECC relative to the protection of the environment:
 Marine Environment
 Land Environment
 Air Environment
 Noise, air and water pollution
b. Utility Location – The project will affect existing utility lines attached to the bridge when
lifted. There are also existing street lights/lamp posts & traffic lights that have to be
removed & reinstalled during the construction of bridge approaches. Although it is the
responsibility of the DPWH to coordinate for its removal/relocation with the concerned
utility office & to the local residents who will be affected by such removal/relocation, the
contractor should consider the existence of these utilities in their construction schedule,
specifically, time necessary for its removal in order not to affect any project activity.
5.0 PERFORMANCE SPECIFICATIONS AND PARAMETERS
The Contractor shall provide design-build services to repair and rehabilitate the existing
steel bridge which shall meet the following minimum performance specifications or
parameters:
5.1
Minimum Performance Specifications for Bridges
5.1.1 Loading Specifications
The bridge structures shall be proportioned to the following loads and
forces when they are completed and opened to traffic:
Page 6 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
5.1.1.1
5.1.1.2
5.1.1.3
5.1.1.4
5.1.1.5
5.1.1.6
Loading Parameter
Live Load
Dead Loads – The dead load shall consist of the weight of the
complete structure, including the roadway, sidewalks, car
trails, pipes conduit, cables and other public utility services.
Additional loads for future wearing surface should be added.
Live Loads – The live loads shall consist of the weight of the
applied moving load of vehicles, cars and pedestrians which is
equivalent to MS 18 (HS-20) design live load. The structure
shall also be checked against alternate military loading and
permit design live load.
Impact or Dynamic Effect on the Live Load
Wind Load
Other forces, when they exist as follows: longitudinal force,
centrifugal forces, thermal forces, earth pressure, buoyancy
shrinkage stresses, rib shortening, erection stresses, current
pressure, and earthquake stresses.
Minimum Loading:
Minimum Loading
MS 18 (HS 20-44) truck loading or an Alternate Military loading of
two axles 1.22 meters apart with each axle weighing 107 KN, or
permit loading whichever governs
Dead Load:
Concrete
Steel
Earth Gravel
Wind Load
Seismic Loading
5.2
24 KN/cu.m.
77.0 KN/cu.m.
18.90 KN/cu.m.
3.59 KPa
In accordance with division IA of the 2002 AASHTO Standard
Specifications for Highway Bridges using Acceleration Coefficient of
0.40 and Seismic Performance Category D
Project Completion
Considering that this is a flagship, priority and fast track infrastructure project
that needs to be completed on a tight schedule, the Contractor shall complete
the design-build services under the contract, its number of days to be
determined upon the completion of the design. Total closure of the bridge to all
vehicles shall be determined upon completion of the design.
5.3
Warranty
The Contractor shall guarantee the completed structure against structural defects
& failure for its satisfactory performance vis-à-vis the prescribed minimum
performance specifications during the lifetime of the structure, reckoned from
the final acceptance of the project in accordance with the provisions set forth
under Section 62.2.3.2(a) of the Revised IRR of RA 9184. For this purpose, the
Contractor shall post a Warranty Security in the form of surety bond, callable on
Page 7 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
demand issued by a reputable institution equivalent to 30% of the bid/contract
price.
6.0 DETAILED ENGINEERING REQUIREMENTS
The Contractor shall coordinate and report to the Bureau of Design. DPWH for uniformity
and cohesiveness in the preparation of related documents, consistent with the latest edition
of the Design Guidelines, Criteria and Standards for Public Works and Highways, AASHTO
guidelines and other applicable provisions of existing laws, codes and Department Orders.
All reports and other related documents prepared by the Contractor shall be in a format
agreed and accepted by the Bureau of Design. The detailed engineering study shall include
but will not be limited to the following works:
a. Review the current design and standards proposed for the project, taking into
consideration such factors as economics, potential for stage construction, right of way
availability and constraints (where relevant), social environmental impact and costs,
among others.
b. The following surveys/investigation/study should be undertaken including preparation of
plans, drawings and Program of Work:
1. Topographic survey plans
2. Geotechnical and geological investigation report
3. Hydrology, hydraulic and drainage design report
4. Highway/geometric and pavement design report
5. Bridge existing condition survey report
6. Structural analysis and calculations for bridges, culverts and other structures
7. Foundation analysis
8. Drainage design
9. Slope stability analysis
10. Detailed specifications
11. Detailed quantity calculations
12. Value engineering studies
13. Environment Impact Assessment Studies
14. Electrical/Lighting Design
15. River cross-section survey for possible dredging works
c. Technical reports in electronic files and hard copies for the work prepared must be
submitted by the Build-Design Contractor to the Bureau of Design (BOD) DPWH for
review and approval.
d. Design Guidelines and Codes to be followed:
 Design for this bridge should satisfy the provisions under the latest edition of the
ASSTHO Specifications for Highway Bridges and shall conform to the
requirements of Department Order No. 75, Series of 1992, DPWH Advisory for
Seismic Design of Bridge
 AASHTO Guide for Design of Pavement and Structures, (Latest Edition)
 Design Guidelines, Criteria and Standards of the DPWH, Volumes 1 and 2
 National Structural Code of the Philippines, Volume II (Latest Edition)
Page 8 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
The contractor shall prepare the following plans in accordance with D.O. No. 56, Series of
1995, re: Quality of Plans, and D.O. No. 32, re: Guidelines in the Submission of Plans
General:
1.
2.
3.
4.
5.
6.
Cover Sheet
General Index
Vicinity and Key Map
Locations Plan/Lay out/Topographic Survey Plan
Legend, Abbreviation and Symbols
General Notes (Highways and Bridges)
Road Plans:
1.
2.
3.
4.
5.
6.
Typical Roadway Section
Summary of Quantities
Soils and Materials Investigation Maps/Plans
Grading Quantities
Drainage Schedule/Quantities
Plan
and
Profile
with
the
final
alignment
incorporated
in
the
Topographic/Hydrographic Plans
7. Detailed Cross Section
8. Detailed Drainage Plans, Profile and Cross Sections
9. Geometric Road Design Elements and Standards
10. Road Design Standards and Details
11. Pavement Joint Details
12. Slope Protection Details
13. Drainage Standards and Details
14. Schedule Listing of Road Signs, Guardrails, Lined Ditches, Protection Works, Road
Intersections and Other miscellaneous works
15. Pavement, Drainage and Slope Protection Design Parameters
16. Boring Logs and Location of Boreholes/Auger Logs and Soil Profile
17. Reference of Horizontal and Vertical Control
18. Table of Coordinates and Elements of Curves
19. Plan and Profile of affected side/minor streets
20. Details of Geometric improvement at intersections
21. Standard drawings of miscellaneous structures (Road Signs, Pavement Markings,
Guardrails, etc.)
22. Street Lighting Plan, Layout, Details
Bridge Plans:
1.
2.
3.
4.
5.
General Plans and Elevation
Boring Logs and Locations of Boreholes
Summary of Quantities
Details of Superstructures
Details of Substructure
Page 9 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
6.
7.
8.
9.
Details of Foundation
Bank/Abutment Protection Works and Scour Protection Works
Construction Sequence and Methodology
Temporary work such as cofferdams, craneways, detours, support system for jacking
operation
10. Bridge Lighting, it any
11. Traffic Management Plan during Construction
e. Technical reports in electronic files and hard copies for the work prepared must be
submitted by the Build-Design Contractor to the Planning and Design Division (PDD)
DPWH for review and approval by the Regional Director.
The road alignment, roadside appurtenance/structure and all the proposed improvements
are to be traced in layout at scale of 1:1,000m, together with all watercourses, which
require structural work. Cross sections at intervals not exceeding 20.0m including
intermediate breaks on the ground and at the bridge approaches and reaching at least
10.0m wide on both sides of the centerline, are to be surveyed and plotted at a scale
1:100m. The detailed cross-sections shall show but are not necessarily limited to the
following: pavement and shoulder width and corrections including super elevations where
required, new pavement thickness, slope of embankments and cuts including slope
protection structures where required, cross-falls of pavements and shoulders, existing
ground and finished grade elevations, including quantities of all works items involved.
Separate cross-sections shall be prepared, if necessarily, for road sections outside and
inside township, the latter indicating possible reduced width of pavement and/or shoulder
and for every station or location of drainage structure and facilities. To show or indicate the
sufficient height of the road above highest flood level (HFL), longitudinal sections at scales
of 1:100m and 1:100m vertical will be prepared for all sections where raising of
embankment is required.
Whenever there is a need for the relocation of utilities such as telephone, telegraph and
electricity poles, etc. as well as buildings, fences and major trees to be removed, such
details shall be indicated in the drawings and a separate list shall be prepared. In order to
facilitate the process of design review by Bureau of Design (BOD) of the concepts of the
proposed structures/facilities and review of the design estimate by Planning and Design
Division (PDD), the following activities shall be undertaken:
1.
2.
3.
4.
5.
Presentation to and discussion with PDD of Inception Report
Clearance with PDD of Design Criteria and Specifications
Presentation to and discussion with PDD of the Preliminary Designs
Presentation to and discussion with PDD of the Draft Final Designs
Presentation to and discussion with Construction Division (CD) of the Preliminary Design
Estimate
6. Presentation to and discussion with CD of the Final Design Estimate
Note: Presentation of documents shall include computer programs/software.
7.0 APPROVED BUDGET FOR THE CONTRACT (ABC)
Page 10 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
The Approved Budget for the Contract (ABC) is P79,244,821.09. This is the ceiling for
acceptable bids. Bids higher than ABC shall be automatically rejected.
8.0 ELIGIBILITY CRITERIA FOR BIDDERS
The Design and Build Scheme shall adopt the Annex “G” of the Revised Implementing Rules
and Regulations of R.A 9184 (e.g. Eligibility Requirement). However, the prospective bidder
who have no experience in design and build project on its own, may opt to enter a
subcontracting agreement with a design or engineering firms for the designs portion of the
project.
8.1
Legal Requirements
a. Valid Contractor’s License issued by the Philippines Contractor’s Accreditation
Board.
b. Valid license of the Contractor’s designer issued by the Professional
Regulatory Commission.
8.2
Technical Requirements
a. The Contractor must have built one structure similar to the project at hand
with a construction cost of at least 50% of the ABC.
b. The constructor’s designer must have designed one structure similar to the
project at hand with a construction cost of at least 50% of the ABC.
8.3
Financial Requirements
a. The Contractor must have a Net Financial Contracting Capacity (NFCC) of at
least the ABC or equivalent to P79,244,821.09.
b. The Contractor must submit a written commitment from the reputable bank
to extend to him a credit line at least 10% of the ABC, if the contract is
awarded to him.
9.0 CONTENTS OF THE BID
9.1
Technical Proposal – In the First Envelope
a. Preliminary Design Plans – Design scheme of the proposed Rehabilitation of
Ayala Bridge and Approaches, the road sections including the appurtenant
existing structures located thereto, that will comply with the prescribed
performance specifications and parameters. The plans should contain the
following:
Bridge Design Plan
1. Location Plan/Vicinity Map
2. General Notes on Design Parameter and Construction Procedures
3. General Plan and Elevation
4. Boring Data and Borehole Location
5. Typical Details of Superstructure
Page 11 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
6.
7.
8.
9.
Typical Details of Substructure (Piers and Abutments)
Typical Details of Foundations
Typical Details of Abutment and Pier Protection Works
Typical Details of Temporary Structure such as Craneway, Cofferdam,
Support System for Jacking Operation etc.
10. Construction Sequence and Methodology
11. Summary of Quantities
12. Typical Lighting Facilities
13. Traffic Management Plan during Construction
14. Other related structures
Road Design Plan
1. Location Plan/Vicinity Map
2. General Notes or Design Criteria/Parameters and Construction Procedure
3. Plans, Profile and Cross Sections
4. Typical Details of Slope Protection Works
5. Traffic Data/Information
6. Typical Details of Drainage Structures
7. Summary of Quantities
8. Typical Road Section
9. Typical Lighting Facilities
10. Traffic Management Plan
11. Other related structures
b.
c.
d.
e.
f.
g.
9.2
10.0
Required Bid Security
Design and Construction Method and Schedule
Constructor’s Organizational Chart and List of Key Personnel for the Project
List of Equipment Owned/Leased/Under Purchased for the Project
Quality Control Program
Bank Commitment to provide the required Credit Line is the Contractor is
awarded the contract
Financial Proposal – In the Second Envelope
a. Fixed Lump Sum Bid Price
b. Supporting Detailed Estimates and Summary Costs
c. Warranty bond for Lifetime Performance of Completed Structure
PROCEDURE AND CRITERIA FOR BIDS EVALUATION
Bid Evaluation
For the detailed evaluation of the design and build proposal, a two-step procedure shall
be adopted by the BAC which shall apply in case of any inconsistencies with the
contents of Item 23 of the Tender Documents, to wit:
Page 12 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
1. First-Step Procedure:
A. The first step of the evaluation shall involve the review of the preliminary
conceptual designs and track record submitted by the contractor as indicated in
the bid documents using a non-discretionary “pass/fail” criteria that involve
compliance with the following requirements:
a. Adherence of preliminary design plans to the required performance
specifications and parameters and degree of details;
b. Concept of approach and methodology for detailed engineering, design and
construction with emphasis on the clarity, feasibility, innovativeness of the
plan approach, and the quality of interpretation of project problems, risk and
suggested solutions;
c. Quality of personnel to be assigned to the project which covers suitability of
key staff to perform the duties of the particular assignments and general
qualifications and competence including education and training of the key
staff.
B. For complex or unique undertaking, such as those involving highly specialized or
advance engineering technology, eligible bidders may be required, at the option
of the agency concerned, to make and oral presentation within (15) calendar
days after the deadline for submission of technical proposals.
2. Second-Step Procedure:
Only those bids that passed the above criteria shall be subjected to the second step
of evaluation.
The BAC shall open the financial proposal of each “passed” bidder and shall obtain
the correct calculated prices. The financial bids as so calculated shall be ranked, in
ascending order, from lowest to highest. The bid with the lowest price shall be
identified as the Lowest Calculate.
11.0
DATA TO BE PROVIDED BY THE DPWH
The following data shall be provided by DPWH:
(Note: These data are for reference only. The DPWH does not guarantee to the
contractor that the data provided are correct, free from error, and applicable to the
project at hand. The Contractor is responsible for the accuracy or applicability of any
data that he will use in his design-build proposal and services.)
11.1
11.2
Topographic Survey
Preliminary Survey and Geotechnical Investigation Data
Page 13 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Terms of Reference
(Design and Build)
11.3
11.4
11.5
11.6
Concept Design
Traffic Data – AADT and Axle Loading
Preliminary Horizontal and Vertical Alignment
Other Relevant Data
12.0 DOCUMENTS TO BE PROVIDED BY THE CONTRACTOR DURING CONTRACT
IMPLEMENTATION
The following documents shall be provided by the Contractor during Contract
Implementation:
12.1
12.2
12.3
12.4
12.5
12.6
12.7
12.8
12.9
12.10
Signed Contract
Approved “For Construction” Drawings
Approved Technical Specifications
Approved Detailed Cost Estimates with Unit Price Analysis
Detailed Engineering Plans
Design Analysis
Survey Data
Detailed Geotechnical Investigation Report
Design Report
As-Built Plans
Prepared By:
Checked By:
RICARDO C. DE VERA
Engineer III
LYDIA G. CHUA
Engineer V
Chief-Planning & Design Division, DPWH-NCR
Recommending Approval:
APPROVED:
TIBURCIO L. CANLAS
OIC - Asst. Regional Director
REYNALDO G. TAGUDANDO
Regional Director
6.1.8 EGA/RCV
Tor design build.docx
Page 14 of 14
Proposed Rehabilitation of Quezon Bridge and Approaches
Download
Study collections