][اكتب عنوان المستند ][اكتب العنوان الفرعي للمستند Abdul Jalil 2010-2011 Approximate Estimation Approximate estimation (fast estimation): The approximate estimation is prepared before laying the final designs & specification and general specification of the project. The purpose of approximate estimation is: 1. Determine the cost of the structure quickly. 2. Make a comparison between several alternatives. 3. Checking the final cost of the structure which determined by detailed estimation. Method of used for approximate estimation: 1. Floor – Area method. (Price of one square meter of building). Use to determine the cost of the following building: (Offices, Schools, Houses, Apartments, Hospitals …..Etc.) . It is the best method for determining the cost of the new building , depending on the results getting from old buildings ( buildingsbuiltbefore ). For the multi-story building there are two assumptions : A. The cost of all floors with in basement and roof are in equal costs for one meter square. B. The cost of the basement is (60%) and roof is (40%) of the other floors. 2. Cubic method , (volumetric method ) This method is more accurate than the floor-area method. For multi-story buildings apply the following assumptions: A. All floors are in equal costs for one cubic meter. B. The cost of the basement is (60%) of the cost of other floors. The volume of the floor is calculated as: 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝐴𝑟𝑒𝑎 × 𝐻𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑜𝑛𝑒 𝑓𝑙𝑜𝑜𝑟 The height of the floors is determined as follows: a. Ground floor : From the top of the footing to the mid height of the parapet. b. Top floor : From the top of the ground roof to the mid height of the parapet. c. Middle floors : From floor to floor. 28 ][اكتب عنوان المستند ][اكتب العنوان الفرعي للمستند Abdul Jalil 2010-2011 Middle floor Top floor Ground floor Example: Building of dimensions ( 20m * 35m ) , have been executed and composed of ( basement , ground floor , first floor , second floor , & roof ) . The total cost of the building was (1,100,000,000 ID). Determine the rate of one meter square of the building depending on the following assumptions: A. The (three floors, basement & roof) have equal cost per one meter square. B. The cost of the basement is 60% of the cost of the other floors & the cost of the roof is 40% of the cost of the other floors. Solution: A/ First assumption : 𝑏𝑎𝑠𝑒𝑚𝑒𝑛𝑡 𝑎𝑟𝑒𝑎 = 700 𝑚2 𝑔𝑟𝑜𝑢𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑎𝑟𝑒𝑎 = 700 𝑚2 1𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 𝑎𝑟𝑒𝑎 = 700 𝑚2 2𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑎𝑟𝑒𝑎 = 700 𝑚2 𝑟𝑜𝑜𝑓 𝑎𝑟𝑒𝑎 = 700 𝑚2 𝑇𝑜𝑡𝑎𝑙 = 3500 𝑚2 ∴ 𝑟𝑎𝑡𝑒 𝑜𝑓 𝑜𝑛𝑒 𝑚𝑒𝑡𝑒𝑟 𝑠𝑞𝑢𝑎𝑟𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑏𝑢𝑖𝑙𝑑𝑖𝑛𝑔 = 1100000000 = 315000 𝐼𝐷 3500 B/second assumption: 𝑏𝑎𝑠𝑒𝑚𝑒𝑛𝑡 𝑎𝑟𝑒𝑎 = 0.6 × 700 = 420 𝑚2 𝑔𝑟𝑜𝑢𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑎𝑟𝑒𝑎 = 700 𝑚2 1𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 𝑎𝑟𝑒𝑎 = 700 𝑚2 29 ][اكتب عنوان المستند ][اكتب العنوان الفرعي للمستند Abdul Jalil 2010-2011 2𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑎𝑟𝑒𝑎 = 700 𝑚2 𝑟𝑜𝑜𝑓 𝑎𝑟𝑒𝑎 = 0.4 × 700 = 280 𝑚2 𝑇𝑜𝑡𝑎𝑙 = 2800 𝑚2 1100000000 ∴ 𝑟𝑎𝑡𝑒 𝑜𝑓 𝑜𝑛𝑒 𝑚𝑒𝑡𝑒𝑟 𝑠𝑞𝑢𝑎𝑟𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑏𝑢𝑖𝑙𝑑𝑖𝑛𝑔 = = 393000 𝐼𝐷 ≈ 322$ 2800 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑠𝑞𝑢𝑎𝑟𝑒 𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑏𝑎𝑠𝑒𝑚𝑒𝑛𝑡 = 0.6 × 393000 = 235800 𝐼𝐷 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑠𝑞𝑢𝑎𝑟𝑒 𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑟𝑜𝑜𝑓 = 0.4 × 393000 = 157000 𝐼𝐷 Example: Building of dimensions ( 40m * 60m ) , have been executed and composed of ( basement , G. floor , 1st floor , 2nd floor ) . The height of floors is as follows: H. for basement = 2.80m. H. for other floors = 3.0m. Total cost of the building is (4,000,000,000 ID). Determine the cost of the cubic meter, using the following assumptions: A. Cost of all floors is equal. B. Cost of basement equal 60% of the cost of other floors. Solution: A/ 1st assumption: = 40 × 60 × 2.8 = 6720𝑚3 = 40 × 60 × 3.0 = 7200𝑚3 = 40 × 60 × 3.0 = 7200𝑚3 = 40 × 60 × 3.0 = 7200𝑚3 = 28320𝑚3 4,000,000,000 = = 141000 𝐼𝐷/𝑚³ 28320 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑏𝑎𝑠𝑒𝑚𝑒𝑛𝑡 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓𝑡ℎ𝑒 𝑔𝑟𝑜𝑢𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓𝑡ℎ𝑒 1𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓𝑡ℎ𝑒 2𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑇𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 ∴ 𝑟𝑎𝑡𝑒 𝑜𝑓 𝑜𝑛𝑒 𝑐𝑢𝑏𝑖𝑐 𝑚𝑒𝑡𝑒𝑟 B/ 2nd assumption: = 0.6 × 40 × 60 × 2.8 = 4032𝑚3 = 40 × 60 × 3.0 = 7200𝑚3 = 40 × 60 × 3.0 = 7200𝑚3 = 40 × 60 × 3.0 = 7200𝑚3 = 25632𝑚3 4,000,000,000 𝐼𝐷 ∴ 𝑟𝑎𝑡𝑒 𝑜𝑓 𝑜𝑛𝑒 𝑐𝑢𝑏𝑖𝑐 𝑚𝑒𝑡𝑒𝑟 = = 156000 3 25632 𝑚 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑏𝑎𝑠𝑒𝑚𝑒𝑛𝑡 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓𝑡ℎ𝑒 𝑔𝑟𝑜𝑢𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 1𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓𝑡ℎ𝑒 2𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 𝑇𝑜𝑡𝑎𝑙 𝑣 𝑜𝑙𝑢𝑚𝑒 3. Approximate quantities : Calculating of the approximate quantities of all general items of the work , like ( foundations , walls, roofs , doors , D.P.C. , tiles , ceramics , sanitary services , electrical services ……etc. ), then .multiply by the approximate rate of each item to get the approximate cost of the building . 30 ][اكتب عنوان المستند ][اكتب العنوان الفرعي للمستند Abdul Jalil 2010-2011 4. Modifications on the previous rates for approximate estimation: Before calculating the approximate estimation, the previous rates should be modified in order to be close to the existing rates therefore the following notes should be taken into consideration: 1- The specifications and properties of the previous and existing project . 2- The date of execution of the two projects. 3- The position of the two projects. 4- The general and special stipulations. 5- The composition of the building (frame or bearing wall). 6- Shape of the buildings and their heights. 31