AHA #8 FOR CONSTRUCTION OF DRYWALL

advertisement
Risk Assessment Form
#8 Activity-Based Risk Assessment for Construction of Drywall Enclosure to One-Net Server Farm at CLWP N6
Inventory of Work Activities
Company: PNH Resources LTD PTE
No. Process Description – Demolition and Disposal of Debris
1
Site Preparation and Office Shifting
2
Construct Drywall Enclosure for One-Net Server
3
Painting
4
Electrical Works
18 April 2011
Work Activities
Disassemble and remove existing cubicle partitions in the
way of new drywall partitions. Deliver removed partitions to
a temporary storage designated by the customer. Supply
and install plastic sheet dust barrier around the site with
enough room for workers movement around the One-Net
Server Farm area. Cover the server equipment with plastic
sheets with the customer’s approval.
Construct new drywall enclosures from raised floor up to
ceiling height to enclose the existing One-Net Server Farm in
CLWP N6 Message Center. Provide opening for timber door
and frame. Bottom of drywall shall be installed on top of
existing raised flooring. Installation shall include installing
single leaf timber door and frame. Supply and install timber
skirting the same or similar to existing skirting commonly
used in Bldg. 7-4. Supply and install timber ceiling trims.
Tape and spackle joints on both sides of new gypsum board
enclosure surrounding the existing One-Net Server. Apply
one coat of wall sealer and two coats of interior wall paint to
match the interior painting within the message center.
Prepare surface and repaint with matching two coats to the
remaining interior surfaces of the new enclosure.
Install new lighting/points/switches, recess or surface
mounted complete with wiring in metal conduit or trunking.
Supply deliver and install additional 2-36 watts fluorescent
light fitting with electronic ballast symmetrically to the new
ceiling lay-out, complete with required control circuit,
diffuser/louver and wiring in metal trunking or conduit
connected to the existing DB’s. Trace existing electrical
circuits, then remove and/or relocate all affected fittings,
power points, wirings and conduits in the way of
construction. Re-label and update electrical circuit
distribution for all the affected power and lighting circuitry.
Supply and install new and approved master switch for
secondary emergency power shutdown to control all
incoming supply to the existing server farm equipment at the
newly renovated area complete with all of the necessary
ancillary equipment.
Risk Assessment Form
Activity-Based Risk Assessment Form
Company:
PNH RESOURCES PTE LTD
Process/Location:
Construction of Drywall Enclosure To OneNet Server at CLWP N6
Approved by:
(Name, designation)
(Date)
Mr. Lee Wilson
Senior Safety Manager
18 April 2011
1.
Hazard Identification
Jose Parrera/Boy C
FDS Engineers
18 April 2011
Last Review
Date:
18 April 2011
Next
Review
Date:
2d
3a
3b
Action Officer
Designation
2. Risk Evaluation
1a
1b
1c
1d
2a
No
Work Activity
Hazard
Existing Risk
Control
(if any)
Site Preparation
and Office
Shifting
Musculoskeletal –
workers are at
risk of strains,
sprains and other
muscle and
tendon damage.
Possible
Accident/
Ill Health &
Persons at Risk
Workers
disassembling
partitions and
moving them to
temporary
storage.
Cuts and
Lacerations when
handling the
partitions
Workers
disassembling
and moving
partitions
Sight – Hand held
power tools may
be used to
disassemble the
partitions
Hearing – Hand
held power tools
Workers
performing this
phase of the
construction.
1
Conducted by: (Names, designations)
(Date)
EM 385-1-1 &
Ministry of Manpower Requirements
Workers
performing this
2b
2c
01 November
2011 or when
project is
complete
3. Risk Control
Severity
Liklihood
Risk
Level
Additional Risk Control
Training on how to
employ good lifting
techniques and use
the best work
practices to avoid
these types of
injuries.
This potential
hazard should be
discussed during
musculoskeletal
training
All PNH Workers
have been issued
eye protection.
Moderate
Remote
Low
These risk evaluation ratings are
assuming effective training is provided
and consistently re-enforced for the
workers.
Safety
Manager
Minor
Remote
Low
Ensure that a first aid kit is maintained
on sight.
Safety
Manager
Minor
Remote
Low
Sight conservation training should be
part of Tool Box Talks during this
phase.
Safety
Manager
All PNH Workers
have been issued
Minor
Remote
Low
Hearing conservation training should
be part of Tool Box Talks during this
Safety
Manager
2
Construct
Drywall
Enclosure for
One-Net Server
may be used to
disassemble the
partitions
Musculoskeletal –
workers are at
risk of strains,
sprains and other
muscle and
tendon damage
Cuts and
Lacerations when
handling the
partitions
Sight – When
installing the
drywall there
maybe sight risks
when securing
gypsum wall
board, timber
door and door
frame and time.
Hearing if hand
held power tools
are employed.
3
Painting - Apply
one coat of wall
sealer and two
coats of interior
paints
Sight
Paint Vapors
phase of the
construction.
hearing protection.
Workers
handling/drywall
may be at risk of
strains, sprains
and other
muscle and
tendon damage.
Workers could
be cut while
assembling the
dry walls.
Training on how to
employ good work
practices to avoid
these types of
injuries.
Minor
Remote
Low
Ensure that good training is employed
to ensure that workers do not sustain
these types of injuries.
Safety
Manager
This potential
hazard should be
discussed during
musculoskeletal
training
All PNH Workers
have been issued
eye protection.
Supervisors must
enforce its use and
this should be
discussed during
10 minute tool box
talks.
All PNH Workers
have been issued
hearing protection.
Minor
Remote
Low
Ensure that a first aid kit is maintained
on sight.
Safety
Manager
Minor
Remote
Low
PNH discusses Sight Conservation on a
regular basis with workers but this
safety aspect must be constantly reenforced.
Safety
Manager
Minor
Remote
Low
Hearing conservation training should
be part of Tool Box Talks during this
phase.
Safety
Manager
Wear eye
protection and
cover this hazard
in the morning 10
minute tool box
talk as applicable
The paint and wall
sealer are not very
toxic and are water
based so they
should not present
a significant
hazard, however,
Minor
Remote
Low
Project supervisors must enforce the
use of eye protection.
Safety
Manager
Minor
Remote
Low
Respiratory protection should not be
required because of the low toxicity of
the paint and sealer.
Safety
Manager
Workers
performing this
phase of the
construction.
Working with
power tools
during this phase
of the
construction.
Workers
applying the
paint
Workers
applying paint
and other people
in the area.
phase.
4
.
Electrical Works
Electric Shock –
There will be
significant work
involving
installation of
new lighting and
associated
conduits,
switches, etc.
Personnel doing
the electrical
work.
workers need to be
cognizant of the
fact that some
people are more
sensitive to these
products than the
general population
which may make it
necessary to move
workers (other
than the
construction
workers) outside of
the area where
painting is being
conducted.
Ensure that
electrical
components are
tagged out. Never
work on energized
circuitry unless
authorization is
obtained from
NAVFAC Far East.
Minor
Remote
Low
Contact Mr. Fred Bigcas from FDS
Safety for all Lock Out/Tag Out issues.
Safety
Manager
Download