AHA #38 FOR THE RENOVATION OF THE

advertisement
Risk Assessment Form
#38 Activity-Based Risk Assessment for the Renovation of the Installation Chapel
Inventory of Work Activities
Company: PNH Resources LTD PTE
18 October 2010
No.
1
Process Description
Re-upholstering the pews in the chapel
Work Activities
Removing existing padding material and replacing it with new material.
2
Paint the interior of the chapel
3
Re-carpet the interior of the chapel
Re-paint all of the existing painted surfaces within the chapel itself, Interior
of the chapel is very high, estimate >6 meters
Remove old carpet and re-place with new product
Risk Assessment Form
Activity-Based Risk Assessment Form
Company:
PNH RESOURCES PTE LTD
Process/Location:
Compound Chapel Renovation Project
Approved by:
Mr. Lee Wilson
(Name, designation)
Senior Safety Manager
(Date)
18 October 2010
1. Hazard Identification
1a
1b
1c
No
Work Activity
Hazard
1
Re-upholstering
the pews
Potential Sight
hazard
1d
Possible
Accident/
Ill Health &
Persons at Risk
Individuals
performing the
re-upholstery
work
Conducted by: (Names, designations)
(Date)
Mr. Bradamente Amoroso Jr.
(Martin)
Engineer
Last Review
Date:
Next
01 May 2011
Review
Date:
3. Risk Control
18 October 2010
2. Risk Evaluation
2a
Existing Risk
Control
(if any)
Training on
sight
conservation
and the use of
sight
conservation
PPE
2b
2c
2d
3a
3b
Severity
Liklihood
Risk Level
Additional Risk Control
Action Officer
Designation
Minor
Remote
Low
Ensure that tool box training reemphasize elements of sight
conservation program
Safety
Manager
2
Painting of the
chapel
Fall Hazard
Individuals
working at height
Sight
Painting ceilings
creates a
significant sight
hazard from
painting over
ones head at a
distance.
Workers
performing
painting
Inhalation from
paint vapors
Ladders,
potentially
scaffolding. It is
unclear at this
time what
means will be
employed by
workers to
accomplish this
job. A copy of
the company
fall protection
plan has been
forwarded to
the Contracting
Officer for
review along
with the AHA
for this project
Sight protection
(PPE)
Inhalation
hazards from
this phase are
not anticipated
due to the type
of paint
anticipated to
be used, (water
based), the
volume of the
chapel and the
ease of
supplying
additional
ventilation
and/or vapor
Minor
Remote
Low
A copy of the company fall protection
plan will be made available to the subcontractor for this project. A review of
this plan must be completed with all
sub-contractor workers.
Safety
Manager
Minor
Occas.
Remote
(as long as
sight
protection
is
provided
and used.
Low
Ensure that tool box training reemphasize elements of sight
conservation program
Safety
Manager
Minor
Remote
Ensure that sight protection is available
and used by all workers.
The planning for this phase of the
project will be monitored for changes
as the time to initiate it approaches.
Safety
Manager
3
Removal of old
carpeting and
Installation of
new carpeting
Musculoskeletal,
back injury,
strains and
sprains
Inhalation hazard
from the
adhesive used to
install the
carpeting
Work conducted
by subcontracted carpet
company
Work conducted
by subcontracted carpet
company
extraction
equipment if
needed.
Whatever their
company
advocates for
training
Inhalation
hazards from
this phase are
not anticipated
due to the type
of adhesive
anticipated to
be used, the
volume of the
chapel and the
ease of
supplying
additional
ventilation
and/or vapor
extraction
equipment if
needed.
Minor
Minor
Remote
Remote
Low
Low
Recommend that training include the
importance of good lifting techniques
to avoid these types of injuries.
Also recommend that training include
that studies have shown that back
support equipment does not
effectively protect workers against
injury and may actually put workers at
greater risk by creating a false sense of
security.
Ensure that a material safety data
sheet is available on sight for review
for this adhesive.
Safety
Manager
Safety
Manager
Download