DESIGN AND SUPERVISION OF WORKS FOR THE CONSTRUCTION OF THE LUKUGA BARRAGE BARRAGE DRAFT DESIGN REPORT May, 2013 PREPARED BY: Otieno Odongo & Partners Consulting Engineers P.O. Box 54021, Nairobi Tel : +254 020 3870022 Fax : +254 020 3870103 Email:oopkenya@wananchi.com Lukuga Barrage Draft Deisgn Report CLIENT Secretary General COMESA Secretariat BEN BELLA ROAD P.O BOX 30051 LUSAKA,, ZAMBIA Tel: 260 1 229725 Fax 260 1 225107 Page 1 TABLE OF CONTENTS ABBREVIATIONS ........................................................................................................................................... 4 Chapter 1 EXECUTIVE SUMMARY ................................................................................................................ 5 1.1 Objective ............................................................................................................................................ 5 1.2 Recommended Layout ........................................................................................................................ 5 1.3 Cost estimate ...................................................................................................................................... 6 Chapter 2 INTRODUCTION AND DAM SITING ........................................................................................... 7 Introduction ....................................................................................................................................................... 7 2.1 Purpose and objective ........................................................................................................................ 7 2.2 Background information .................................................................................................................... 7 2.3 Hydrology .......................................................................................................................................... 8 2.4 Site investigations and field work ...................................................................................................... 8 Geotechnical Conditions at site ........................................................................................................................ 9 2.5 Figure 1: geophysical survey point, old barrage location ................................................................. 9 2.6 Figure2: curves of interpreted VES, old barrage location .............................................................. 10 2.7 Table 1: geophysical survey data analysis, old barrage location .................................................... 11 2.8 Figure 3: geophysical survey point, ................................................................................................. 12 2.9 Figure4: curves of interpreted VES, away from old barrage location ............................................. 13 2.10 Table 2: geophysical survey data analysis, away from old barrage location .................................. 14 Grouting procedures ....................................................................................................................................... 15 2.11 Introduction ..................................................................................................................................... 15 2.12 Site location and topography ........................................................................................................... 16 Chapter 3 BARRAGE SELECTION AND DESIGN CRITERIA ................................................................. 19 3.1 General ............................................................................................................................................ 19 3.2 Barrage type selection ..................................................................................................................... 19 3.3 Classification as per function and use ............................................................................................. 19 3.4 Classification as per hydraulic design ............................................................................................. 20 3.5 Classification as per material use .................................................................................................... 20 Barrage design criteria.................................................................................................................................... 21 3.6 Seismic Dyke .................................................................................................................................... 21 3.7 Zoned rockfill Dam .......................................................................................................................... 22 3.8 Blanketed rock fill dam .................................................................................................................... 22 3.9 Precast concrete caisson .................................................................................................................. 23 3.10 Concrete Gravity weir with central overflow spillway .................................................................... 23 3.11 PROPOSED BARRAGE ................................................................................................................... 24 3.12 Bridge .............................................................................................................................................. 24 Hydraulic design .............................................................................................................................................. 25 3.13 Design against overtopping-Freeboard ........................................................................................... 25 3.14 Wave height...................................................................................................................................... 26 3.15 Spillway Design ............................................................................................................................... 28 3.16 Stilling basin and energy dissipaters ............................................................................................... 30 3.17 Design input data ............................................................................................................................. 30 3.18 Stilling basin and energy dissipaters ............................................................................................... 31 3.19 Sluice gate sizing.............................................................................................................................. 33 3.20 Mechanical Facilities Design .......................................................................................................... 34 3.21 Fish Ladder and Fish ways .............................................................................................................. 35 BRIDGE DESIGN ........................................................................................................................................... 36 3.22 Selection of bridge type. ................................................................................................................... 36 3.23 Geotechnical Investigation .............................................................................................................. 39 3.24 Bridge Superstructure design........................................................................................................... 39 3.25 Bridge Substructure design .............................................................................................................. 40 Chapter 4 STRUCTURAL SYSTEM AND MATERIALS ............................................................................ 42 4.1 Structural system .............................................................................................................................. 43 4.2 Loadings........................................................................................................................................... 43 4.3 Foundations ..................................................................................................................................... 43 4.4 Column piers .................................................................................................................................... 43 4.5 Walls ................................................................................................................................................ 43 4.6 Fire resistance ................................................................................................................................. 43 4.7 Concrete ........................................................................................................................................... 43 4.8 Reinforcement bars .......................................................................................................................... 43 Lukuga Barrage Draft Deisgn Report Page 2 4.9 Welding consumables....................................................................................................................... 44 4.10 Foundation Condition and Seismic loading Considerations ........................................................... 44 Chapter 5 STRUCTURAL DESIGN CALCULATIONS ............................................................................... 45 BARRAGE ....................................................................................................................................................... 45 Forces acting on the Barrage .......................................................................................................................... 45 5.1 Figure 7: Diagram showing forces acting on the barrage .............................................................. 45 Load Combinations for Barrage .................................................................................................................... 48 ACCESS ROAD AND BRIDGE .................................................................................................................... 49 Forces acting on the Bridge ............................................................................................................................ 49 5.2 Characteristic Loads ........................................................................................................................ 49 Live Loads ..................................................................................................................................................... 49 Chapter 6 REFERENCES ................................................................................................................................. 50 Chapter 7 annex ................................................................................................................................................. 51 Lukuga Barrage Draft Deisgn Report Page 3 ABBREVIATIONS A Flow area a.m.s.l above sea level a.m.s.l above mean sea level BS British Standard C drowned weir formula Constant DRC Democratic Republic of Congo Fcu concrete strength grade Fr Froude Number fy Yield strength L length M metres OO&P Otieno Odongo & Partners consulting engineers q Flow rate m3/s Q Volume of Discharge, m3 S channel slope USBR United State Bereu of Reclamation V Velocity, m/s VES Vertical Electric Sounding Lukuga Barrage Draft Deisgn Report Page 4 CHAPTER 1 EXECUTIVE SUMMARY The COMESA Secretariat commissioned M/s Otieno Odongo & Partners Consulting Engineers, to undertake the Engineering design and supervision of the reconstruction of the Lukuga Barage on Lake Tanganyika. The Lukuga River originates from Lake Tanganyika and flows into the Congo River, which is the only outlet for the water flow of Lake Tanganyika. 1.1 Objective The overall objective of the report is finalize the general layout of the Lukuga barrage project: selection of the type of barrage, localization and sizing of the spillway, localization and sizing of stilling basin and sluices, and access bridge. 1.2 Recommended Layout The finally recommended layout is: Concrete Gravity dam Crest elevation; 778m Normal retention level; 774m Height above river bed varies with a minimum of 5 m and maximum of 8m. Type: The planned barrage structure will be a concrete gravity ogee with central overflow spillway, with sluices to manage silt deposition and also when fitted with gates to allow discharge of flood flow when in open position and retain water discharge during low flow. Spillway Spillway design flood: 5000 years return period. It is an overflow weir at the centre of the barrage with a crest length of 180m, stilling basin and energy dissipators. Bridge The bridge is 480m long with a two lane deck with column piers at 20m centres. It is founded at the same level with barrage and friction piles incorporated on the column bases. The soffit of the beams rest at the crest elevation of 778m a.s.l. Lukuga Barrage Draft Deisgn Report Page 5 1.3 Cost estimate Below is a summary extracted from the detailed bill of quantities. SUMMARY OF THE BILLS OF QUANTITIES Bill No. Description Amount ($USD.) 1,763,826.04 1 PRELIMINARIES AND GENERAL 2 SETTING OUT 3 SITE CLEARANCE AND TOP SOIL STRIPPING 4 RIVER PROTECTION EARTHWORKS 3,138,962.21 5 EXCAVATION AND FILLING FOR STRUCTURES 2,288,744.30 6 CONCRETE WORKS 7 ROAD FURNITURE 8 GROUTING 499,808.75 9 SITE INVESTIGATION 121,715.00 10 ROADS AND PARKING 378,083.47 11 Dayworks 151,406.25 SUB - TOTAL Contingency = 10% 22,844.09 670,661.00 43,340,288.57 6,312.50 52,382,652.18 523,826.52 Variation of Prices 6.5% 3,404,872.39 16% VAT 8,381,224.35 TOTAL PROJECT SUM FOR THE WORKS Lukuga Barrage Draft Deisgn Report 64,692,575.44 Page 6 CHAPTER 2 INTRODUCTION AND DAM SITING Introduction Lake Tanganyika is situated within the western Great Rift Valley and is confined by mountainious walls of the rift valley. The main ports on the lake are kalemie railhead to DRC rail network, Kigoma railhead to Dar es Salam in Tanzania, Mupulungu railhead for Zambia and Bujumbura port. 2.1 Purpose and objective The purpose of the Dam/ Barrage studies is to provide a control structure at source of river Lukuga that will maintain the predetermined water level. The objective of this study is aimed at preparing a design for the appropriate water control structure at the beginning of river Lukuga that will regulate and stabilize the lake water levels to desired levels which will enable the ports to operate at all times. 2.2 Background information The Lukuga River is the main outlet of water from Lake Tanganyika. It is located on the western part of the lake with its source at Kalemie in Katanga Region. It flows into River Congo eventually entering Pacific Ocean. Lake Tanganyika has catchment area that is riparian to Republic of Tanzania, Republic of Burundi, Republic of Zambia and Democratic Republic of Congo. The major rivers from the above catchments feeding into the lake includes; River Ruzizi from Lake Kivu, River Malagarasi from Tanzania, and River Kalambo from Malawi. The Lake Tanganyika has a number of ports including kigoma, kalemi, uvira, etc serving the riparian countries, and the flacuation of the lake levels often adversely affects the operations of these ports. In order to reduce the adverse impacts of the flacuations of the lake levels it is necessary that water balance thereon be maintained such that levels fluctuations is limited to a predetermined minimum that will allow use of the ports at all times. The purpose of the Dam/ barrage studies is to provide a control structure at mouth of river lukuga that will maintaion the predetermined water level. The design looks into geotechnical studies at the proposed control structure location, metrology and hydrology of the catchment area and lake water balance and levels fluctuations, design of the control structure options. Lukuga Barrage Draft Deisgn Report Page 7 2.3 Hydrology From hydrological report, the required level for Kalemie port for optimal operations of port shipping was found to be 774.0m a.m.s.l. and the proposed height of the dam above the current water level of 770m a.m.s.l (from 2011 field study) is 4m. The location of the barrage from the river source is approximately 1.12km, where the distance to contour 774 is relatively small and up stream of the railway bridge. 2.4 Site investigations and field work Extensive geophysical survey was undertaken during February 2011 along Lukuga River with the main objective of determining the underground lithology within and along the 1200m long stretch of the river. The geophysical survey carried out 11 No. deep lithology and plotted the river underground soil and rock conditions. From the review of the 11 number lithology plots two sites were selected across the river as potential locations of the proposed dam design options. These are the locations where the firm hard ground is at shallowest depth. The existing barrier which was constructed in the year 1952 was damaged and vandalized, rendering it ineffective in controlling the flow. Lukuga Barrage Draft Deisgn Report Page 8 Geotechnical Conditions at site Location A: Construction of barrage at the previuosly constructed site through the following locations 2.5 Figure 1: geophysical survey point, old barrage location Lukuga Barrage Draft Deisgn Report Page 9 VES 14 – 35M 0743292; UTM 9345930, on HEP 04 VES 03 – 35M 0743209; UTM 9345838, on HEP 01 VES 04 – 35M 0743090; UTM 9345554, on HEP 02 VES 09 – 35M 0743073; UTM 9345412, on HEP 03 The curves of the interpreted Vertical Electrical soundings are as follows: 2.6 Figure2: curves of interpreted VES, old barrage location Lukuga Barrage Draft Deisgn Report Page 10 Curve No. VES 09 LUKUGA RIVER KALEMIE DRC SOUTH OF LUKUGA RIVER Curve No. VES 04 LUKUGA RIVER KALEMIE, DRC, SOUTH OF LUKUGA RIVER Curve No. VES 04 LUKUGA RIVER KALEMIE DRC, NORTH OF RIVER AT THE EXISTING BARRAGE Curve No. VES 14 LUKUGA RIVER KALEMIE DRC, NORTH OF LUKUGA RIVER AT THE EXISTING BARRAGE 124m NE OF VES 03 Formation Thickness (m) True Resistivity (ohm m) Expected Geological Formation 0 – 0.92 517 Sands deposits 0.92 – 3.80 57 Sandstone 3.80 – 10.07 14 Gravels 10.07 – 18.20 56 Gravels Over 18.20 6 Clayey soil 0 – 0.37 1934 Sands deposits 0.37 – 1.59 184 Sandstone 1.59 – 15.17 26 Gravels 15.17 – 36.84 9 Clayey soil Over 36.84 20 Gravels 0 – 0.77 1577 Sands deposits 0.77 – 2.87 130 Sandstone 2.87 – 17.40 27 Gravels 17.40 – 45.25 9 Clayey soil 45.25 – 56.77 26569 Quartzite Sill Over 56.77 30 Gravels 0 – 0.53 862 Sands deposits 0.53 – 2.30 80 Sandstone 2.30 – 3.26 8 Clay soil 3.26 – 38.17 16 Gravels Over 38.17 20 Gravels 2.7 Table 1: geophysical survey data analysis, old barrage location Lukuga Barrage Draft Deisgn Report Page 11 Location No B: CONSTRUCTION OF WEIR/BARRAGE DOWNSTREAM OF THE EXISTING BARRAGE FOUNDATION REMNANTS SITE THROUGH THE FOLLOWING LOCATIONS 2.8 Figure 3: geophysical survey point, Lukuga Barrage Draft Deisgn Report Page 12 VES 14 – 35M 0743292; UTM 9345930, on HEP 04 VES 01 – 35M 0743209; UTM 9345838, on HEP 01 VES 05 – 35M 0743063; UTM 9345658, on HEP 02 VES 09 – 35M 0743073; UTM 9345412, on HEP 03 at 90m downstream When plotted on Topographic Map forms a straight line with distance across the river being approximately 256m. The curves of the interpreted Vertical Electrical soundings are as follows: 2.9 Figure4: curves of interpreted VES, away from old barrage location Lukuga Barrage Draft Deisgn Report Page 13 Formation Thickness (m) True Resistivity (ohm m) Expected Geological Formation 0 – 0.92 517 Sands deposits 0.92 – 3.80 57 Sandstone 3.80 – 10.07 14 Gravels 10.07 – 18.20 56 Gravels Over 18.20 6 Clayey soil Curve No. VES 05: 0 – 0.37 4360 Sands deposits LUKUGA RIVER KALEMIE, DRC SOUTH OF LUKUGA RIVER 0.37 – 1.59 321 Sandstone 1.59 – 8.24 30 Gravels 8.24 – 31.95 9 Clayey soil Over 31.95 20 Gravels 0 – 0.37 2320 Sands deposits 0.37 – 1.59 136 Sandstone 1.59 – 7.02 19 Gravels 7.02 – 44.52 9 Clayey soil 44.52 – 48.90 146 Sandstone Over 48.90 20 Gravels 0 – 0.53 862 Sands deposits 0.53 – 2.30 80 Sandstone 2.30 – 3.26 8 Clay soil 3.26 – 38.17 16 Gravels Over 38.17 20 Gravels Curve No. VES 09: LUKUGA RIVER KALEMIE DRC SOUTH OF LUKUGA RIVER Curve No. VES 1 LUKUGA RIVER KALEMIE, DRC, NORTH OF RIVER 70m downstream of existing barrage Curve No. VES 14 LUKUGA RIVER KALEMIE DRC, NORTH OF LUKUGA RIVER AT THE EXISTING BARRAGE 124m NE OF VES 03 2.10 Table 2: geophysical survey data analysis, away from old barrage location Lukuga Barrage Draft Deisgn Report Page 14 OBSERVATION: one of the findings of the geophysical survey was the determination of the apex of the lukuga river sill which is consistent with positions marked option site A and B, the ground conditions became better as you move away from the lake. From the measurements interpretation (given in table above) the underground foundation strata is determined to be that of sandstone is found at depths varying from 1m to 3m, as the first layer of rock lying above gravel. Gravel extends to lengths not less than 17m. With reference to BS 8004:1986, table 1, a bearing pressure of 450kn/m2 has been adopted for the design. The required foundation treatment consists of cleaning the top sands deposit and part of the top mudstone up to depth of 3m from original bed level. Below the excavation curtain and contact grouting to 10m and 6m respectively is applied to close the area from leakage/seepage. Grouting procedures 2.11 Introduction All holes for grouting, shall be drilled at the locations, in the direction, angle, and to the depths indicated or as directed by the Engineer. A maximum tolerance for deviation in angle and direction shall be (30) the first series of holes to be drilled and grouted shall be at (5) - foot intervals and hereinafter are referred to as primary holes. The location of secondary and succeeding series (intermediate) holes shall be determined by the split spacing method as defined in paragraph SPLIT SPACING. The number of grout holes shall be increased, progressively, by the split spacing method as defined in paragraph SPLIT SPACING. The number grout holes shall be increased progressively, by the split spacing method as deemed necessary by the Engineer until the amount of grout used indicates that the foundation is tight. Each hole drilled shall be protected from becoming clogged orobstructed by means of a cap or other suitable device on the collar and any hole that becomes clogged or obstructed due to fault of the contractor before completion of operations shall be cleaned out in a manner satisfactory to the Engineer or another hole provided by and at the expense of the Contractor. Records: The Engineer will keep records of all grouting operations, such as a log of the grout holes, results of washing and pressure testing operations, time of each change of grouting operation, pressure, rate of Lukuga Barrage Draft Deisgn Report Page 15 pumping, amount of cement for each change in water/cement ratio, and other data deemed by him to be necessary. The Contractor shall furnish all necessary assistance and cooperation to this end. 2.12 Site location and topography Location of the dam/dyke is within the mouth of the lukuga river for effective control of the flooding impacts of the river ponding area upstream of the dam and erosion of the sandy river banks. The Lake Tanganyika lies between Lat 30 20’ to 8048’ S and Long 2905’ to 31015’. OO&P carried out topographical survey of the river lukuga mouth and a topo plan produced. The topo plan covered a stretch of 2km of the river from the source, with 1m contour intervals. The remains of the damaged barrier were also captured. The site is generally gentle with elevations varying from 766m a.m.s.l to 774m a.m.s.l. This Topography allows fitting of a weir of crest height of 5m from riverbed to raise water level to 774m to as proposed on the hydrological study. From site topography and the required crest elevation of 774m, the following Weir parameters were noted, The crest height from river bed is 774 -769 = 5m. The weir height above river bank is 774 –774 =0m. Lukuga Barrage Draft Deisgn Report Page 16 Figure 5: barrage location at Kalemie Lukuga Barrage Draft Deisgn Report Page 17 Figure 6: barrage location at Kalemie (topography) Lukuga Barrage Draft Deisgn Report Page 18 CHAPTER 3 BARRAGE SELECTION AND DESIGN CRITERIA 3.1 General Barrage structure is designed to facilitate the control of water flow to river lukuga, to raise the head of the lake by 4m within Kalemie Port (as per the hydrological report). The water level required for port is 774m a.m.s.l. a bridge will be running above the barrage for vehicular transport. Considering the foundation condition where depth of firm materials range from 1 to 3 metres along the proposed barrage alignment above the lukuga river, the foundation of the weir is proposed to be at elevation 769-3=766m, (769 is the river bed level) the overall height of the weir is 774-766=8m on the overflow potion. 3.2 Barrage type selection The geological conditions on site and geometry of valley dictate that a rigid gravity dam are considered practical. The selection of the dam type options are as follows: LUKUGA BARRAGE USE HYDRAULIC DESIGN MATERIALS USED HEIGHT STORAGE OVERFLOW CONCRETE LARGE DIVERSION NON OVERFLOW MASONRY MEDIUM EARTHFILL SMALL DETENTION ROCKFILL 3.3 Classification as per function and use Storage Barrage This is the most common type of barrage normally constructed to store excess flood water which can be utilized later when demand exceeds the flow in river. The Storage dams may be constructed for various purposes such as irrigation, water supply, hydro-power generation etc. they may be made of concrete, stone or earth or rock fill etc. Lukuga Barrage Draft Deisgn Report Page 19 Detention barrage These types of barrage are mainly constructed to control flood. This type of barrage stores water temporarily and releases it gradually at a safe rate when the flood recedes. Detention barrage provides safeguard against possible damage due to flood on the downstream side of it. Sometimes a detention dam may also be used as storage dam. Diversion Barrage The purpose of diversion dam is necessarily different. It is constructed to divert the river water into canal, conduit etc. For this purpose, mostly a weir or low level dam is constructed across the river to raise the water level which can be diverted as per the needs. This type of dam may be used for water supply, irrigation or some other purposes. 3.4 Classification as per hydraulic design Overflow Barrage/Dam: An overflow dam is built to allow the overflow of surplus discharge above the top of it. They are generally built of masonry or concrete and they are gravity type of dam. Usually dams are not designed as overflow for their entire length. Only few meters of its length is kept as overflow section Non-Overflow Barrage/Dam: In this type of dam, water is not allowed to overtop the dam. The top of the dam is fixed at a higher elevation than the expected maximum flood level. Since water is not allowed to overtop, it can be constructed of large variety of materials such as earth, rock fill, masonry, concrete etc. 3.5 Classification as per material use The dam type options considered are: Embankment dam which includes; Seismic dyke Earth dam Rock fill dam Zoned rock fill dam Concrete dams which include; Precast concrete caisson Gravity concrete weir Lukuga Barrage Draft Deisgn Report Page 20 Barrage design criteria These dam/dyke options design concepts have been elaborated on in order to determine their technical viability. 3.6 Seismic Dyke This option consists of an embankment constructed in dry and compacted materials in embankment designed to resist earthquake loading. The embankment is zoned and consists of sand and gravel shoulder fills separated with silt/clay core and filter. The area where the embankment is constructed is dewatered dry using constructed upstream and downstream parallel sets of temporary cofferdams. The embankment is built in sections to allow reusing the cofferdam materials. Considering the foundation soils consisting of sandstones and gravel materials the embankment design considered in this option has the following particulars:a) Slope inclinations of 5:1(horizontal: vertical) on the upstream slope and 7:1 on the downstream slope. b) The crest of the dam would be 10m wide ( to allow for 2way traffic) and provide for 2.5m of freeboard above mean lake level. c) An overexcavation depth of 3m is provided under the embankment crest, and an overexcavation depth of 5m is provided under embankment toes. An additional embankment volume computed on basis of average settlement of 6% of the unexcavated soft soils over the entire width of the embankment. The main advantage of this option is that the dry construction method allows compaction of the embankment materials that makes it stable. The disadvantages: Extensive cofferdams are required for temporary dewatering and staging of construction is complex. Expensive river diversion works required. The location does not have suitable material for construction of impermeable core. A large river diversion channel required Require a side spillway Lukuga Barrage Draft Deisgn Report Page 21 All the disadvantages combined makes the option time consuming and expensive to construct. 3.7 Zoned rockfill Dam This option consists of an embankment built with rockfills in its outer shells and soil core. This is constructed in the wet, and this do not allow for compaction of the embankment materials. Rock is preferred, as compacted rockfills do not have substantial strength losses during earthquake, compared to uncompacted soil fills. As for seismic dyke, 3 to 5m loose foundation soils will be excavated and replaced with embankment material. An additional embankment volume computed on basis of average settlement of 6% of the unexcavated soft soils over the entire width of the embankment. Slope inclinations of 5:1(horizontal: vertical) on the upstream slope and 7:1 on the downstream slope. The crest of the dam would be 20m wide (to allow for construction of the multiple lift rock dykes) and provide for 2.5m of freeboard above mean lake level. Large volumes of rocks, makes it expensive and time comsuming. They require a separate spillway away from the main dam.They require heavy maintenance cost and constant supervision.They are more susceptible to be damaged by floods than any other type of dam. 3.8 Blanketed rock fill dam This is an option that consists of an embankment built in wet and entirely out of rockfills. To mitigate seepage through the dam, ablanket would need to be placed on the upstream slope. Conventionally, this is usually an asphalt or concrete pavement. However, construction below sea level precludes those for this option. The upstream blanket will therefore consist of depositing fine grained soils on the upstream slope to plug the rock fill. Alternately, bentonite slurry would be constructed through the dam along its crest to provide a seepage barier. As for seismic dyke, 3 to 5m loose foundation soils will be excavated and replaced with embankment material. An additional embankment volume computed on basis of average settlement of 6% of the unexcavated soft soils over the entire width of the embankment. Slope inclinations of 5:1(horizontal: vertical) on the upstream slope and 7:1 on the downstream slope. The crest of the dam would be 10m wide and provide for 2.5m of freeboard above mean lake level. Lukuga Barrage Draft Deisgn Report Page 22 Blanket rockfill dam is prone to high permeability hence large seepage quantities are expected. This option also requires a separate spillwayaway from the main dam. 3.9 Precast concrete caisson This option utilizes large precast concrete circular caisons to form a dam structure. The concrete will provide for non corrosive structure, the caisons would be cast onshore and floated into position. The caisson would be sunk by excavating the soils within and immediately below the caisson. The remainder of the caisson would be filled with soil. The stability analysis requires that 22m in diameter and 25m high caisson is required; the width height ratio is kept the same for lower sea levels. The individual caisons will be tied together using steel sheet pile arcs, and the area between the arcs filled with lean concrete. Advantage of this option is that no over excavation of foundation soils would be required. However, the concept is unique for application as a dam, and the rigidity of the system would not be as accomodatind (as embankments) to seismic deformations. 3.10 Concrete Gravity weir with central overflow spillway This option consist of Construction of a concrete gravity overflow weir with central overflow spillway supported on reinforced concrete base on firm underground formation. Below the concrete weir a curtain grouting layer is constructed to reduce water loss through seepage. Advantages: It is Stronger and more stable than any other type of dam It can house an overflow spillway to pass excess flood water safely. It can be built of any height provided suitable foundation is available to bear all the loads coming on it. The failure of a gravity dam is not sudden at all. It gives sufficient time for evacuation of area downstream of it. Though its Initial cost is higher, and It needs skilled labor and mechanized plants for construction and It may take more time in construction, its is the most prefered option for Lukuga. From considerations of technical viability of construction of the above options it was considered that the concrete gravity dam with central overflow spillway was the suitable dam type for Lukuga Dam/Dyke. The design therefore adopted this type for futher hydraulic and structural design analysis. Lukuga Barrage Draft Deisgn Report Page 23 3.11 PROPOSED BARRAGE The planned barrage structure will be a concrete gravity ogee with central overflow spillway, with sluices to manage silt deposition and also when fitted with gates to allow discharge of flood flow when in open position and retain water discharge during low flow. The proposed barrage structure is 5m high above the river bed at deepest point and has a crest weir length of 180m, a non overflow concrete wall of 166 m and 134m on either sides of the 180m overflow weir and an 480m access concrete bridge deck to allow access to the sluices penstock gates for the control of sluices gates penstocks facilities and also vehicles connecting the north and south sides of Kalemie Port. 3.12 Bridge The bridge is to connect the two towns to the port. The bridge is a modular bridge 480m long composing of 24No. 20m span centre to centre bearings. 7.0m carriageway with 2 No. 1.9m clear walkways, 50mm thick surfacing. The beams grillage is composed of 5 No. 1500 deep by 500mm wide main beams simply supported on free bearings, 2No. 1500mm deep by 300mm wide Diagphrams each on support. The height of the freeboard is 4m above the barrage crest overflow width. Lukuga Barrage Draft Deisgn Report Page 24 Hydraulic design 3.13 Design against overtopping-Freeboard Overtopping waves can constitute a danger to the barrage when they exert lateral loads on the retaining gravity wall. Wave overtopping must therefore be prevented by giving the dam sufficient freeboard above the maximum design water level. Freeboard is the vertical distance between the maximum reservoir water level and the crest of the dam without camber. Free board (Ho) is the sum of the significant wave height (Hw), wave run-up (Rw) and wind set-up S computed using the following empirical relationships (based on UK Reservoir Flood Standards). Rw Hw Hw 0 .4 L 0 .5 Cot Zuiderzee formula: S U 2F 1400 * D L 5.12 * T 2 Where: Hw is significant wave height (m), Rw is wave run-up (m) S is wind set-up (m) U is the wind velocity over water (km/hr) F is reservoir fetch (km) L is wave length (m) D is average water depth along the central radial (m) F is reservoir fetch (m) Ho is the freeboard (m) is the angle of upstream face of the dam with horizontal T is the wave period (sec) Lukuga Barrage Draft Deisgn Report Page 25 3.14 Wave height Waves are generated on the surface of the reservoir by the blowing winds, which exert a pressure on the downstream side. Wave pressure depends upon wave height which is given by the equation Molitor's empirical Formula For F < 32 km, and for F > 32 km Where is the height of water from the top of crest to bottom of trough in meters. V – Wind velocity in km/hour F – Fetch or straight length of water expanse in km. Wind velocity overland is 110km/h associated over water is 1.15 times larger; giving 126.5 km/hr for design wind speed. variables velocity normal pool max reservoir Fetch norm. pool = max reservoir = (VF)^0.5 F^0.25 norm. pool = max reservoir = 127 km/hr 92 km/hr 2.64 km 0.58478632 m 0.498707449 m 0.032(FV)^0.5 0.032(FV)^0.5 18.2745725 1.274679442 1.10258301 m 1.007896252 m 9% of waves may exceed the significant wave height hence the corresponding design wave height is; 1.1x1.002348=1.1026m. Lukuga Barrage Draft Deisgn Report Page 26 Wave run-up Rw (m) and wind set-up, S (m) Hw F D U 1.10 2.64 1400 90 127 m km m km/hr S is wind set-up (m) Tm S= 0.021554051 m Tp=0.07118*F^0.3*U^0.4 F 2640 m U 35.13888889 m/s g 10 m/s T= 3.141625198 s 2.576132662 L is wave length (m) = 33.97867261 m Rw is wave run-up (m) Hw/L= Tan Cot 0.032449267 572.957213 0.001745331 Rw= 2.75 m Total Freeboard= Rw+Hw+S 3.88 m The freeboard adopted therefore is 4.0 m. Lukuga Barrage Draft Deisgn Report Page 27 3.15 Spillway Design Spillways are hydraulic structures designed to release excess water from a reservoir to a stretch downstream of the dam. This protects the dam from destruction from debris, wave action, and floods. A spillway is sized to provide the required capacity, usually the entire design flood, at a specific reservoir elevation. The spillway shall be designed as open earth channel broad crested weir. Spillway capacity (Q) and Dimensions Q 2 2 h * b gh 3 3 Q b 1.7 * h 3 2 Where; b is the spillway width (m) h is the design upstream water head above the spillway crest, Q is the design flood a. Spillway design flood The proposed return period has been checked from Q1000 and Q5000. The maximum Q is used for weir sizing. This flood is to be passed by the spillway after routing through the reservoir with full freeboard allowance on the barrage meaning that with a 127km/hr wind the waves so produced will not overtop the crest of the barrage. Lukuga Barrage Draft Deisgn Report Page 28 b. Probable Maximum Flood (PMF) This flood is to be passed by the spillway after routing through the reservoir with a nominal 0.50m freeboard on the barrage and the waves produced by 127km/hr wind may be allowed to run on the wave wall provided on the crest. PMF METHOD ln(PMF+1)=1.175*(ln(CA+1))^0.755+3.133 where PMF, Probable Maximum Flood, m3/s CA, Catchment Area (km2) CA >32 take 200km2 = 7.27367 PMF 1440.83 m3/s design floods are calculated has a proportion of the PMF, i.e. Q5000=0.46*PMF and Q1000=0.38*PMF Q1000 Q5000 PMF 547.516 m3/s 662.782 m3/s 1440.83 m3/s c. Spillway width Q 2 2 h * b gh 3 3 Q= 1440.83 m³/s h= h^(3/2)= 4 m freeboard max 8 b 105.943 m Since the current width of the channel at the proposed site is 180m, a spillway width of 180 m will be adopted. Lukuga Barrage Draft Deisgn Report Page 29 3.16 Stilling basin and energy dissipaters Hydraulic design is of 5m high concrete gravity overflow weir above the river bed supported on reinforced concrete base founded at the firm ground which is 3m below the river bed level. The overall height of the barrage from foundation is 8m. 3.17 Design input data river bed elevation planned weir crest level upstream face slope downstream face slope design discharge length of the weir 769 m 774 m vertical 0.75:1 600 m3/s 180 m hydraulic analysis to determine design head discharge Q=CxLxH^2/3 where, Q=600m3/s, L=180m, Cd=2.2 design head, H=(Q/(2.2X180))^2/3 1.31918 m height crest above riverbed P P/Hd=P/He=5/1.32 (Hd+P)/He=(1.32+5)/1.32 > 1.7 Therefore Cd is not affected by downstream apron and tailwater Lukuga Barrage Draft Deisgn Report 5 m >1.33 therefore velocity of approach effect is 3.787879 negligible 4.787879 Page 30 3.18 Stilling basin and energy dissipaters Selection of stilling basin USBR type, where the stilling basin is of the type where water returns to the river directly and this requires a bucket that dissipates Energy by Impact. Crest length L=180m Crest height D= 5m Discharge Q=600m3/s Consider rectangular channel Discharge/m width spillway q= 600/180 = 3.33m3/s Compute He from, drowned weir formula, q=2/3xCdx(2g)^1/2xHe^3/2 Discharge q=2/3 x C x (2g)^1/2 x He^3/2 C=0.7 He ={3.33/0.7)x 2/3 /2x9.8)^1/2 }^2/3 = 1.37m Average fall of water = 8+1.37/2 = 8.685m Theoretical velocity at foot of spillway V1= 2(gH) ^1/2 = (2x9.81 x 8.685) ^1/2 = 13.05m/s Velocity of approach V1= 0.92x13.05=12.006m/s Depth of flow at foot of spillway y1= q/V1 = 3.33/12.006 = 0.277m Froude no Fr= V1/ (gy)^1/2 = 12.006/(9.81x0.277)^1/2 = 7.278 Tail water depth Fr.=7.3 Tw/y2=1.0 Tw/y1=11 Tw=y1x11=0.277*11=3.047m Y2=Tw=3.047m Factor of safety Twmin /y1=10.5, Twmin =10.5x0.277=2.9085m FS= (TW-Twmi)/y2=(3.047-2.9085)/3.047 =4.5percent < 5% (recommended minimum margin of safety) To satisfy minimum margin Lukuga Barrage Draft Deisgn Report Page 31 Tw=Twmin+ 0.05y2= 2.9085+0.05*3.047=3.061m Determine the basin length Length of stilling Basin = 5x (y2-y1) = 5(3.061-0.277) = 16.65m Length of stilling Basin = 5x (y2-y1) = 5(3.061-0.277) = 16.65m Adopt 23m including the sill blocks. Fr=7.3 (> 4.5) V= 13.05m/s (<15m/s) Therefore use type II stilling basin USBR with chute Blocks and end sill. Blocks:Height 2y1= 2 x 0.345= 0.69m Width 2y1= 0.69m Length 2y1 = 2x 0.345 = 0.69m, use 1m Spacing between blocks 2.5 w= 2.5 x 0.345=0.86m use 1.0m spacing. Adopt 1m high, 1m wide, 1m long and 1m spacing. Dentated End sill Height 0.20y2= 0.2 x 3.061=0.6122m use 1m. Width 0.15y2= 0.15 x 3.061=0.459m use 1m. Spacing 0.15y2= 0.15 x 3.061=0.459m use 1m. Lukuga Barrage Draft Deisgn Report Page 32 3.19 Sluice gate sizing Sluice gates have been provided to allow for scouring and environmental flow for river Lukuga. At the Lukuga River, the flood flows of 402m3/sec. occurs during the month of May while the low flow of 252m3/sec occurs during the month of October and November. The average flow from hydrological study is as shown on the graph below; Average Monthly Flow in M3/sec. Average Monthly Flow of Lukuga River at Sill in M3/sec. 500 400 300 200 100 Series1 0 Month of the year The evarage annual flow is 292.333m3/s. Sluice sizing Q width height sluice dia INPUT DATA 250 River Channel 180 0.5 1.45 m3/s m m m Q VxA V=Q/A 2.77778 m/s environmental flow 1/3Q 83.3333 m3/s sluices total area for environmental flow A=Q/V 30 m2 area for one sluice 1.65046 m2 number of sluices 18 The sluice diameter is 1.45m with gates to control flow as appropriate. The gates will be manually operated. Lukuga Barrage Draft Deisgn Report Page 33 3.20 Mechanical Facilities Design The design provides for the provision of:(a) 18no. cast iron penstock/GMS gates at the gravity dam spillway width (a) Cast Iron Penstock Gate The design provides for 18 no. sluice openings at 5m depth to control flow through a 1.45m sluice fitted in the Low Gravity Concrete Diversion Weir. The sluice 1.45m diameter provided has a capacity of Q=C x A x (2gH)1/2 , Where Q= discharge (m3/s), A= sluice x section area (m2), C=coefficient (0.7) , H=Crest Head over the sluice H (m). These sluice will each discharge Q= 4.629m3/s total 83.33m3/s. at water level at spillway crest elevation. From reference to Ham and Baker Catalogue, a 1500 x 1800mm penstock gate with half frame thrust remote rising spindle, having the following particulars:(a)Thalf frame with remote spindle rising above water level, (b) Cast iron door (b) seating faces (c) Wedges adjustable with wear (d) Flush invert mounting (e) Cast iron thrust housing (h) Standard Invert seal (i) Phosphor bronze door nuts (j) Standard fasteners (k) Opening spindles with extensions. (l) Operating gears to lift or lower the gate door. Lukuga Barrage Draft Deisgn Report Page 34 Generally the gates will be left open during the period when river flow spills over the weir, but will be closed should river flow stop spilling over the weir. 3.21 Fish Ladder and Fish ways A fish ladder (or stair, fish way, fish pass) is a structure designed to allow fish the opportunity to migrate upstream and continue their function as part of the river ecosystem. With diverse fish types, it will need varying properties for the ladders hence may necessitate different types. The most appropriate pathways will be gated sluices for fish migration. Lukuga Barrage Draft Deisgn Report Page 35 BRIDGE DESIGN In the design of Lukuga Bridge we set out to undertake bridge designs to worldwide standards whose approach entails the following Selection of bridge type. o Safety o Economy o Aesthetics Geotechnical investigations and selection of foundation types. Bridge design. o Design standards o Loading o Methods of analysis o Analysis Results o Design of foundations and structural elements. Construction methodology and maintanance. 3.22 Selection of bridge type. Safety In the design of the bridge, we set out to ascertain that ideal structure adopted does not collapse in use. It must be capable of carrying the loading required of it with the appropriate factor of safety. The structure is designed not to suffer from local deterioration/failure, from excessive deflection or vibration, and it must not interfere with sight lines on roads above or below it. To ensure that the above is achieved, strict adherence to recommended codes of practice for bridge engineering governing loading and design of the various structural elements was ensured. Lukuga Barrage Draft Deisgn Report Page 36 At the preliminary stage, previous designs carried out worlwide can give a pointer as to the most adopted bridge decks for various spans. For bridges Up to 20m the following deck types are adopted Insitu reinforced concrete. Insitu prestressed post-tensioned concrete. Prestressed pre-tensioned inverted T beams with insitu fill. For bridges from 16m to 30m spans; Insitu reinforced concrete voided slab. Insitu prestressed post-tensioned concrete voided slab. Prestressed pre-tensioned Y and U beams with insitu slab. Prestressed pre-tensioned box beams with insitu topping. Prestressed post-tensioned beams with insitu slab. Steel beams with insitu slab. For bridges from 30m to 40m; Prestressed pre-tensioned SY beams with insitu slab. Prestressed pre-tensioned box beams with insitu topping. Prestressed post-tensioned beams with insitu slab. Steel beams with insitu slab. For bridges from 40m to 250m and beyond Box girder bridges suspension bridges cable stayed A 20m spans with expansion joints at every 40m has been adopted hence adopting the insitu reinforced concrete deck with insitu T Beams. Indeed Single or multi-cell reinforced concrete box Girder Bridge have been proposed and widely used as economic aesthetic solution for the over crossings, under crossings, grade separation structures and viaducts found in modern highway system examples including Nyali bridge at Mtwapa and the sabaki bridge in malindi. Lukuga Barrage Draft Deisgn Report Page 37 Economy. The structure must make minimal demands on labour and capital; it must cost as little as possible to build and maintain. The bridge being of concrete cast insitu is comparatively cheaper than any other form of construction. Appearance. Bridges being long lasting structural monuments, emphasis, in recent years, has been actually on the aesthetic appeal of the bridge. Bridges all over the world are fast becoming tourist attractions with their elegant forms. the blend of the bridge and the weir provides beautiful scenery to the area surrounding. Lukuga Barrage Draft Deisgn Report Page 38 3.23 Geotechnical Investigation It was established two areas that are potential for the construction of barrage with underlying stratum capable for holding foundations. Further downstream it was established presence of weak points due to some fractures in the ground which are believed to have contributed to the River formation and the flow out of the lake. The lake formation was a result of Greater Rift Valley formation due to faulting phenomenon episodes. The safe foundation strata varied from 2.3 - 8 m with clayey soil beneath. Friction piles have been incorporated in the design. 3.24 Bridge Superstructure design The bridge superstructure design was based on design width, loading and other parameters that were strictly in conformity with Bridge Design Manual Part IV – Draft October 1991 and as revised in August 1993. The other guidelines of BS 5400 (Parts 1 [General], 2 [Loads], 4[Concrete], 7[Workmanship], 8[Materials] and 9[Bearings]) have been taken on board. Reference was made to BS 8110 for reinforced concrete design. Reference has also been made to Y Maekawa’s (Bridges section, Ministry of Roads and Public Works / JICA) guidelines on calculations presentation dated December 1985. Design has been carried out for both permanent and transient loads on the bridge structure. The following loadings were considered: Dead loads, self weight, surfacing, fixings etc Live load surcharge: HA loadings with a check for a minimum of 30 units HB loading. Braking forces The effects of seismic activity were checked to be in conformity with the Kenyan Seismic Design Code as issued by the Building Centre, Ministry of Roads and Public Works especially for the rift valley belt. Lukuga Barrage Draft Deisgn Report Page 39 The following loads were considered in addition to the above for the Preliminary design. Erection loads, wind loads Effect of any skew Temperature changes Friction at bearings Differential settlement Skidding or centrifugal forces (if the bridge is on a curve) Parapet to be able to take some collision loads Detailed computerized design was carried out by use of Engineering softwares SAP 2000, bestech sam bridge, oasys gsa bridge. The details of the structural modeling, the computer analysis for both serviceability and ultimate limit states and the member design are attached as in the design calculations. 3.25 Bridge Substructure design The bridge sub-structural design involved the design of piers, abutments and associated foundations. Pier/abutment heights were determined by the required hydraulic openings and the vertical alignment at bridge crossings. Design was carried out for all the forces transmitted from the structure onto the substructure. In addition, horizontal forces from earth pressures and from the braking forces were considered. Various combinations of these were considered to evaluate the most onerous cases and appropriate factors of safety provided against bearing pressure, failure and overtopping. Abutments specified is solid reinforced concrete with transverse diaphragm beams to distribute the deck structure loading onto them. Wing walls have been designed as free-standing cantilevers but with continuity bars connecting the wing walls to abutments to eliminate longitudinal movement between the wing walls and the abutments which is fairly common in purely free standing wing walls unconnected to abutments. Piling has been included in the design together with spread footing as currently specified. The pile arrangements will be bored cast insitu piles. Alternatives may be made at construction stage. Bridge bearings Elastomeric bridge bearings were adopted Lukuga Barrage Draft Deisgn Report Page 40 Expansion Joints Expansion joints were designed to take into consideration expected movements during serviceability and ultimate limit states arising from loading, temperature, deck shortening due to creep and shrinkage and rotation. Lukuga Barrage Draft Deisgn Report Page 41 CHAPTER 4 STRUCTURAL SYSTEM AND MATERIALS The structural analysis and design for the proposed barrage, has been based on the Ultimate Limit State method. Factors of Safety as applied to materials and loadings are as specified in the Standards and Codes of practice currently in use. The softwwares used included masterseries, prokon and spreadsheets for analysis and design The following references have been used in the design:B.S 6399: Loading for Buildings CP3 Chapter V Part 2 1972: Wind Loading B.S. 8110 Part 1, 2 and 3: Structural Use of Concrete. B.S. 8007: Design of Concrete Structures for Retaining Aqueous Liquids. Reinforced Concrete Designer's Handbook: 10th Edition by Reynolds Structural Use of Timber to B.S. 5268 Eurocode 8 for seismic loads B.S 8004-Foundations Road Design Manual Part 1V, Bridge Design, August 1993. BS 5400 Part 1 General Statement. BS 5400 Part 2 Specifications for Loads Department of Transport Highway & Traffic Departmental Standard BD 37/88 loads for Highway Bridges 1989. BS 5400 Part 4 Code of Practice for Design of Concrete Bridges. BS 5896 High Tensile Steel Wire and Strand for Pre-stressed Concrete, 1980 AASHO Standard Specifications for highway Bridges BS Codes of Practice for foundations Lukuga Barrage Draft Deisgn Report Page 42 4.1 Structural system The weir is of ogee type mass concrete with a reinforced concrete base and stilling basin. The gravity wall has norminal reinforcement for anticrack on the surface of the wall. The barrage base and that of bridge piers will be founded at the same level, with friction piles on the column bases. All the column piers will be wall type. 4.2 Loadings Loading condition is usual which includes normal operating and frequent flood conditions. Dead load on the structure comprises of own weight of the designed structural elements and applied finishes. 4.3 Foundations Due to the interface between the pier bases and barrage base, a raft foundation have been used to spread the total loading coming from the columns and are optimally sized to be in tune with gravelly type of soils with Safe Bearing Capacity up to 450Kn/m2.. Additional friction piles have been incorporated on the pier bases. 4.4 Column piers Columns are rectangular reinforced concrete walls. The sizes relate to the height so that slenderness is minimized and will also depend on the anticipated intensity of loading. The columns are designed to carry the axial loads combined with fraction of framing moments and water floor loads. 6000x800mm Rectangular reinforced concrete columns have been used as structural supports in the entire bridge. 4.5 Walls Stilling basin walls are reinforced concrete walls and acts as retaining walls. 4.6 Fire resistance Minimum cover to reinforcement has been proposed as 50mm. 4.7 Concrete Concrete class 30 is considered for all substructures and superstructures. The slump is between 75-125mm. 4.8 Reinforcement bars All rebars used are high strength d bars of 425N/mm2. Provide to full length of pile considering the possible tensile forces, both loading and construction. Lukuga Barrage Draft Deisgn Report Page 43 4.9 Welding consumables All welding consumables, including covered electrodes, wires, filler rods, and flux and shielding gases, should have be class 42. 4.10 Foundation Condition and Seismic loading Considerations The area where the barrage is located is considered to be of moderate seismicity and the design has adopted design peak acceleration of 0.34g vertically and 0.17g horizontally. Foundation treatment will consist of:Exposing and removal of top sand material and loose rocks to depth of 3.0m which will result into reduction of settlement from loose materials. Application of drilling and grouting foundation treatment to approximately 10m depth below weir foundation base to seal lenses between hard rocks which will seal leakages through these seepage potential seepage paths. Removal of loose material including sand will reduce potential occurrence of liquefaction in case of occurrence of seismic activity when the weir structure is built. Lukuga Barrage Draft Deisgn Report Page 44 CHAPTER 5 STRUCTURAL DESIGN CALCULATIONS BARRAGE Forces acting on the Barrage 5.1 Figure 7: Diagram showing forces acting on the barrage The forces are as listed below; 1. Water pressure 2. Uplift pressure 3. Earthquake 4. Silt pressure 5. Wave pressure 6. Weight of the dam Water pressure Water pressure act on the upstream and downstream face of the barrage. The water pressure on the upstream face is destabilizing (or overturning) force acting on the gravity dam. Tail water helps in stabilizing. Tailwater is generally small in comparison with water pressure on the upstream face. The water pressure p, (kn/m2) varies linearly with the depth of the water measured below the free surface (m). Lukuga Barrage Draft Deisgn Report Page 45 Uplift pressure Water has a tendency to seep through the pores and fissures of the foundation material. It also seeps through the joints between the body of the dam and its foundation at the base, and through the pores of the material in the body of the dam. The seeping water exerts pressure and was accounted for in the stability calculations. The uplift pressure is defined as the upward pressure of water as it flows or seeps through the body of the dam or its foundation. A portion of the weight of the dam will be supported on the upward pressure of water; hence net foundation reaction due to vertical force will reduce. The effective area is taken as approximately equal to the total area. Lukuga Barrage Draft Deisgn Report Page 46 Earthquake The earthquake sets up primary, secondary, Raleigh and love waves in the earth’s crust. The waves impart accelerations to the foundation under the dam and cause its movement. The earthquakes cause random motion of ground which can be resolved in any three mutually perpendicular directions (vertical and horizontal). This motion causes the structure to vibrate. Peak ground acceleration of 0.32g horizontal and 0.16g vertical have been adopted for analysis. This is the accelerations with expected increase by 10% in 50years. Hence the design acceleration is 0.34g and 0.17g respectively. Silt pressure Gravity dams are subjected to earth pressures on the downstream and upstream faces where the foundation trench is to be backfilled. Silt is treated as saturated cohessionless soil having full uplift and whose value of internal friction is not materially changed on account of submergence. Wave pressure In addition to the static water loads the upper portion of dam is subjected to the impact of waves. The force and dimensions of waves depend mainly on the extent and configuration of the water surface, the velocity of wind and the depth of reservoir water. Empirical formula adopted. Lukuga Barrage Draft Deisgn Report Page 47 Wave height was used in the determination of freeboard requirements due to wave run up. Weight of the dam The weight of the dam is the main stabilizing force in the gravity dam. The dead load to be considered comprises the weight of the concrete, such appurtenances as piers, gates and bridges. Load Combinations for Barrage Load combination 1: (normal operating condition) - full reservoir elevation, normal dry weather tailwater, normal uplift, silt. Load combination 2: (flood discharge condition) - dam at maximum flood pool elevation, all gates open, tailwater at flood elevation, normal uplift and silt. Load combination 3: (construction condition)- dam completed but no water in the reservoir and no tail water. Load combination 4: combination 1 with earthquake Load combination 5: combination 2 with earthquake Load combination 6: combination 3 with earthquake All the load combinations have been analysed for different section both at the overflow section and non overflow section. The requirements of stability satisfied by the design are as follows; 1) Safe against sliding on any plane and combination of planes within the dam, at the foundation or within the foundation. 2) Safe against overturning at any plane within the dam, at the base, or at any plane belw the base. 3) Safe unit stresses in the concrete of the dam and foundation have not been exceeded. Lukuga Barrage Draft Deisgn Report Page 48 ACCESS ROAD AND BRIDGE Forces acting on the Bridge 5.2 Characteristic Loads The following characteristic Loads based on the aforementioned codes, were considered; Live Loads Dead Loads Wind Loads Seismic Loads Dynamic River Current Load Live Loads The following traffic loads were considered in the design; HAU loading HA KEL Loading 30 Units HB loading Pedestrian loading Dead Loads The following dead loads were considered in the design by the previous consultant namely. Reinforced or pre-stressed concrete : gc=25KN/m3 Backfill soil : gs=18KN/m3 Asphalt concrete pavement : ga=23KN/m3 Handrail : 1KN/m Mean hourly wind speed was taken as 30m/s Wind Loads Lukuga Barrage Draft Deisgn Report Page 49 CHAPTER 6 REFERENCES 1. Request for Proposal for Consultancy Services for the Preparation of Engineering Design and Supervision of the works for the construction of the Lukuga Barrage by common Markets for Eastern Africa dated April, 2009 2. B.S 6399: Loading for Buildings 3. CP3 Chapter V Part 2 1972: Wind Loading 4. B.S. 8110 Part 1, 2 and 3: Structural Use of Concrete. 5. B.S. 8007: Design of Concrete Structures for Retaining Aqueous Liquids. 6. Reinforced Concrete Designer's Handbook: 10th Edition by Reynolds 7. Structural Use of Timber to B.S. 5268 8. Eurocode 8 for seismic loads 9. B.S 8004-Foundations 10. Road Design Manual Part 1V, Bridge Design, August 1993. 11. BS 5400 Part 1 General Statement. 12. BS 5400 Part 2 Specifications for Loads 13. Department of Transport Highway & Traffic Departmental Standard BD 37/88 loads for 14. Highway Bridges 1989. 15. BS 5400 Part 4 Code of Practice for Design of Concrete Bridges. 16. BS 5896 High Tensile Steel Wire and Strand for Pre-stressed Concrete, 1980 17. AASHO Standard Specifications for highway 18. Ham and Baker Catalogue-Sluice gates, slide gates and penstock. 19. Seismic Hazards in the DRC CONGO and Western Rift Valley of Africa- By T Mavonga and R J Durrheim. 20. Engineering Manual-Gravity Dam Design- By US Army Corps of Engineers 21. Y Maekawa’s (Bridges section, Ministry of Roads and Public Works / JICA) guidelines on calculations presentation dated December 1985 Lukuga Barrage Draft Deisgn Report Page 50 CHAPTER 7 ANNEX A-1: barrage and bridge Drawings A-2: barrage structural calculations Lukuga Barrage Draft Deisgn Report Page 51