I. THE RESPONDENT DID NOT LAWFULLY AVOID THE CONTRACT BECAUSE THE CLAIMANT DID NOT BREACH, AND THEREFORE DID NOT FUNDAMENTALLY BREACH THE CONTRACT. A. There was no valid avoidance on 7 July 2014 [R. 13, Cl. Ex. No. 7] 1. The Claimant did not breach the contract. a. Claimant issued a letter of credit as per the amended contract on 27 June 2014. i. The amount of the 27 June letter of credit was in compliance with the contract. Claimant performed its obligations under the contract and therefore there was no breach and could not been a valid avoidance by the Respondent on 7 July 2014. Article 4 of the contract required that the Claimant provide a letter of credit in the amount of 1,350,000 USD, within fourteen days after the Claimant received the Notice of Transport [R. 7, Cl. Ex. C1, Art. 4]. Claimant issued a letter of credit on 4 July 2014 [R. 11]. That letter of credit fully conformed to the contract requirements. The 4 July 2014 letter of credit was issued in the amount of 4,500,000 USD. Because the Respondent could have submitted documents that would draw on the letter of credit for the required amount of 1,350,000 USD, the letter of credit clearly complied with the contract requirement. Letter of credit law clearly provides that the beneficiary may submit documents requiring payment in amount less than the fully authorized amount under the letter of credit [citation]. Claimant’s provision of a letter of credit in an amount far in excess of that required by the contract clearly demonstrates the Claimant’s good faith compliance with the contract. [**Further optional language** As shown in (R34,P4,answer to request for arbitration) in the respondent own words . When taking about the previous conduct between the parties "there always had Been on several occasions last minute requests" by my client and the respondent acted to fulfill. These requests in the case in hand my client send a letter to the respondent to amend the 28 of March contract on the 27 June 2014 (R10,claimants EX.NO4) and waited for 8 days before issuing the first letter of credit as shown in (R11,claimant EX.NO5) now according to the article " 8(3) CISG the course of dealing between the parties created a duty on the part of the [seller] to object promptly and that is delay in objecting constituted acceptance of the [buyer's] offer." (Filanto v. Chilewich) Similar to the case in hand where my client provided the offer and the respondent none objection so it would be responsible for my client to have the impression that the contract has been amended And that the letter of credit of the 4 of July is not a breach of contract farther more Even if the arbitral. Tribunal finds that the article 8(3) don't apply to the case in hand.] ii. The contract was amended to provide for delivery of 100 metric tons of coltan. a. [Claimant’s offer/Respondent’s acceptance] b. Respondent’s offer/Claimant’s acceptance] iii. The letter of credit of 4 July 2014 clearly complied with the amended contract terms. b. Even if the contract was not amended, the letter of credit complied with the original contract. (Placeholder: provision of a letter of credit in amount exceeding what is required under the contract complies with the contract). c. Respondent specifically requested the CIP price delivery terms in the notice of transport, which Claimant provided in the letter of credit issued on 4 July 2014. 2. Even if the Claimant breached the contract, that breach was not a fundamental breach as defined in CISG Art. 25. B. The Respondent’s declaration on 9 July 2014 did not constitute a rightful avoidance of the contract of 28 March 2014, as the Claimant did not breach the contract. 1. Respondent did not rightfully avoid the contract on 7 July 2014, therefore the letter of credit on 8 July 2014 could not have been received too late. 2. Claimant provided the second letter of credit within the time provided for in the contract. a. The letter of credit conformed exactly to the specifications on the original contract of 28 March 2014. b. The Claimant issued the letter of credit on 8 July 2014, which was within the agreed deadline. C. The requirement that Respondent present a commercial invoice does not amount to a breach of contract. 1. Providing a commercial invoice is a standard element of international commercial transactions and does not constitute any additional obligations on the Respondent. II. THE EMERGENCY ARBITRATOR’S ORDER [“THE ORDER”] COMPELLING THE RESPONDENT NOT TO DISPOSE OF THE THIRTY TONS OF COLTAN IN DISPUTE UNDER THE CONTRACT WAS PROPER AND THEREFORE SHOULD NOT BE LIFTED BY THE ARBITRAL TRIBUNAL. The order to retain the coltan necessary to satisfy Respondent’s contract obligations should be continued so that those obligations may be fulfilled consistent with the final award in this case. This Tribunal may modify, terminate, or annul the order made by the Emergency Arbitrator [ICC Art. 29930]. Respondent continues to be obligated to deliver 30 tons of coltan because the contract has not been avoided. The burden of proof is on the Respondent to demonstrate why the Order should be lifted [A]. The substantive requirements for the granting of interim relief were met: irreparable harm will continue if the order is not maintained, and the facts demonstrate that the Claimant will succeed on the merits of the claim [B]. Article 21 of the contract does not prevent interim relief granted in arbitration under ICC Art. 29 [C]. A. Respondent has the burden of demonstrating that the Emergency Arbitrator’s order should be lifted. 1. The substantive test applied by the Emergency Arbitrator was applied in accordance with Art. 17A of the Danubian Arbitration law. a. Article 17A of the Danubian Arbitration law provides conditions for granting interim measures, which were applied by the Emergency Arbitrator as a substantive test in determining the Emergency Order. b. Respondent cannot meet its burden of demonstrating that the substantive test was not properly applied. B. The substantive requirements for granting interim relief were met. 1. Lifting the remaining part of the Emergency Order would cause irreparable harm to the Claimant. a. Irreparable harm to the Claimant was an imminent result had the Emergency Arbitrator not granted the requested Order on 26 July 2014. b. Lifting the emergency order by the Arbitral Tribunal and leaving the Respondent free to dispose the 30 metric tons of coltan would cause yet more impending harm to the Claimant. 2. The facts demonstrate that the Claimant is likely to succeed on the merits of the claim, and lifting the emergency order will consequently frustrate those claims. C. Art. 21 of the contract does not exclude the right of a party to apply to either an Emergency Arbitrator or this Tribunal for interim measures. 1. Article 21 authorizes the parties to go to court for the purpose of interim measures. a. The Emergency Arbitrator appropriately ruled that Article 21 does not prevent the issuance of interim measures by other than a court (the law of this case). i. Under Art 8 CISG it is appropriate to look beyond the simple language of the contract for the intent of the parties, and here the record clearly discloses that the intent of the parties was to allow concurrent jurisdiction of the court and the Arbitral Tribunal for interim measures. ii. ICC Arbitration Rules Art. 29(7) clearly provide for concurrent jurisdiction between courts and the Arbitral Tribunal for the issuance of interim measures, and Art. 21 is simply consistent with the choice of such concurrent jurisdiction in Art. 20 of the contract. III. RESPONDENT CANNOT DEMONSTRATE THAT GLOBAL MINERALS EVER CONSENTED TO BEING A PARTY TO THIS ARBITRATION AND THEREFORE GLOBAL MINERALS SHOULD NOT BE JOINED IN THE PROCEEDINGS. A. Global Minerals is not a party to the contract between Claimant and Respondent, and therefore, is not a party to the arbitration. B. Global Minerals is clearly a legal entity wholly separate from Claimant, and has not separately consented to arbitration. 1. Global Minerals is not liable for Respondent’s claim under the Group of Company Doctrine. 2. Global Minerals is not liable for Respondent’s claims under any other applicable legal doctrine. C. Good faith considerations do not justify the joinder of Global Minerals as a party to this arbitration.