ISS Project Management Methodology Project Manager’s guide (Updated to encompass University Project Management Approach) Version 5.0 May 2011 Contents Table of Contents Contents ......................................................................................................................... 2 1 Purpose ................................................................................................................... 3 2 Context ................................................................................................................... 3 2.1 Alignment to the University Project Management Approach (UPMA) .......... 3 2.2 Project Governance: ........................................................................................ 5 2.3 Background to governance .............................................................................. 5 2.3.1 Project Roles: .......................................................................................... 6 2.3.2 IS projects ................................................................................................ 9 2.3.3 Non-IS projects ...................................................................................... 10 2.4 Dual roles: ..................................................................................................... 10 2.5 What constitutes a project: ............................................................................ 10 2.6 Project criteria ............................................................................................... 10 2.7 Example Project Flows.................................................................................. 12 2.7.1 Overall delivery ..................................................................................... 12 2.7.2 IS start-up (example of how project start up can work in ISS) .............. 13 3 The Project Manager ............................................................................................ 13 3.1 Role of the project manager .......................................................................... 13 3.2 Project management functions ...................................................................... 16 3.2.1 PROJECT SPECIFICATION ................................................................ 16 3.2.2 PROJECT DEFINITION & BUSINESS CASE PRODUCTION ......... 17 3.2.3 PROJECT IMPLEMENTATION - PID Production.............................. 19 3.2.4 Project Budgeting................................................................................... 23 3.2.5 PROJECT EXECUTION – start-up....................................................... 24 3.2.6 PROJECT EXECUTION - ongoing ...................................................... 26 3.2.7 PROJECT CLOSURE - Closure and Handover to Business as Usual . 32 4 Customisation of the methodology ...................................................................... 33 5 Associated documents for reference: ................................................................... 34 6 Appendix 1- Estimated Effort .............................................................................. 36 7 Appendix 2- Process flow – document production and approval ........................ 38 Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 2 of 38 1 Purpose This document seeks to define the activities that are expected to be undertaken by projects managers. In addition to a simple list of responsibilities it contains an assessment of the quality of output required e.g. in terms of level of detail and complexity and the anticipated effort (estimated from experience). In addition it provides some information about the context within which the project manager works and specifically performs the functions of project management. It is anticipated that the text will be used as a reference for project managers, project teams and line managers. 2 Context The project manager as a role and project management as a function do not operate in isolation. Other players and processes are material to their activity and the success they enjoy. This section outlines the context within which project managers need to operate. PROJECT GOVERNANCE PROJECT INITIATION Project Kick-off PROJECT DELIVERY & IMPLEMENTATION PROJECT CLOSE End Project meetings Stage Management Post implementation review System Development Demand Maintenance / Support / Enhance Evaluate Package Selection Benefit realisation This diagram shows the elements of a typical (generic) project. RAD Development Infrastructure Development TOOLS 2.1 Alignment to the University Project Management Approach (UPMA) This section covers how ISS have aligned their established Methodology to the UPMA and it includes the specific changes made. The rest of this document has been updated to reflect the new terminology. Purpose: This document summarises revisions to the project management methodology as a result of developing a Unified Project Management Approach for the University of Leeds. Introduction: The Unified Project Management Approach has been defined to ensure that projects are managed and delivered in a consistent manner across the University. It has Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 3 of 38 been produced collaboratively, with ISS, Estates and Project Management Group fully involved. It is based upon accepted best practice and the adoption of clear processes based around stages and decision gates, straightforward documentation and defined roles / responsibilities. Stage 2 Project Definition and Business Case Stage 1 Project Specification Gate 1 Initial view of why the project is being proposed & what it is aiming to achieve Why are we doing this? What are the aims? What are we going to deliver? What strategic gap are we addressing? Stage 2a Outline Business Case Stage 2b Full Business Case Stage 3 Project Implementation Gate 2 Plan, manage & deliver the outcomes Gate 3 Stage 4 Review & Benefits Realisation Including handover to business as usual Decision Key points of the Unified Project Management Approach: The approach has 4 stages each of which requires specific activities. These stages are: o Stage 1, Project Specification – this is the equivalent to ISS Project Mandate preparation and (for IS) 5 year planning activities o Stage 2, Project Definition and Business case preparation - this is the equivalent to ISS Project Brief (& Business case) preparation. Stage 2 may, for some projects be divided into 2a and 2b to enable a two step business case process to be followed (to support outline and full business cases) o Stage 3, Project Implementation – this is equivalent to Project Initiation document Preparation and Execution combined. This is the least defined element of Unified Project Management Approach as it is recognised that the different nature of projects in areas across the University require different approaches to delivery. Unified Project Management Approach requires that there is appropriate levels of planning and control in each area. o Stage 4, Project closure – ISS Project close is covered by this stage, however it extends beyond the current scope and moves to ensure realisation of benefits. A decision gate follows each of the first three gates Decision gates are supported by defined information requirements which translate into key documents. ISS documentation aligns to the key documents required by UPMA as follows: o Project Mandate becomes Project Specification Document - provides a summary of what is required, benefits to be achieved and high level estimate of resources required. It also shows how the following stage will be performed. o Project Brief becomes Project Definition and Business Case Document – provides a detailed rationale for the project, a costed options appraisal and resource implications. Again it will outline how the following stage will be performed. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 4 of 38 o Project Initiation Document is retained as a local document within ISS and is the first deliverable of the Project Implementation stage (previously Project Execution in ISS). This will continue to be used to summarise detailed planning and control aspects of the project and will be agreed locally. UPMA introduces a Capital Group style financial assessment of projects. These are produced during stage 2 (and can potentially require a 2 step process as described above). This financial assessment includes a Net Present Value calculation and structured option appraisal. The approach requires the establishment of project governance bodies: o Project Delivery Groups - these are the equivalent of ISS Project Boards and will provide the project with oversight and governance; directing the activities of the project and the project manager. o Working Groups – these direct the activities of project work-streams and as such there is no direct ISS equivalent of this body except the project team itself. o Clarity is still being sought regarding the relationship between these Project Delivery Groups and other University Committees. A number of specific roles have been identified and these are equivalent to and complement those already established for ISS projects: o Project Sponsor - provides strategic vision and leadership. Ultimate responsibility for the successful delivery of the project. o Business Owner – ensure that the project outputs will bring the positive outcomes set out in the business case. Often the same person as the Sponsor. o Project Manager – provides day to day management of the project. o All other roles previously identified for ISS projects still remain. All other tools, documents and reporting used during the project remain the same as currently used in ISS 2.2 Project Governance: Projects within ISS are formally governed, that is their worth is assessed, priorities awarded, their start authorised and their progress monitored. The governance that is applied to them, although different between IS and non-IS area, seeks to apply the same rigour and ensure that the most appropriate and beneficial projects are pursued. 2.3 Background to governance The demand on ISS for development work far exceeds its capacity to deliver. Therefore, ISS needs help and direction to ensure that we are delivering the work that is most important for the University and adds the most value to the institution. Governance can be defined as “the processes which ensure the effective and efficient use of IT in enabling an organisation to achieve its goals." The purpose of governance for ISS developments at the University of Leeds is to: provide an organisational structure for decision making and formalised reporting lines for ISS developments Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 5 of 38 clarify the roles and responsibilities of all stakeholders in the governance process consolidate a university-wide understanding of system development requirements and thus achieve the correct balance between the interests of multiple stakeholders align ISS development and organisational need exert financial control over the ISS development budget exert control on resource allocation enhance the performance of the ISS system development plan to maximise the Return on Investment for the University of Leeds 2.3.1 Project Roles: The role of Project Manager The primary responsibility of the Project Manager is to provide the day to day management required to successfully steer the project through the planning and delivery stages and to ensure delivery against the agreed business case. Specific responsibilities include: The project manager is responsible for delivering the project to the agreed project plan – and achieving the outputs that underpin the project’s business case To undertake/have oversight of the planning for the project. To manage the day to day delivery of the project ensuring delivery against the project plan. To report to the project delivery group on the delivery of the project, gathering and presenting the necessary information to enable the project delivery group to understand the actions and progress of the project. To identify and subsequently manage risks which might jeopardise the successful delivery of the project and to communicate these to the project delivery group. To maintain an accurate picture of the progress of the project To manage costs To deal with issues and risks as they occur and work closely with the project sponsor to evaluate progress and take corrective action. Within ISS This translates as: With Project Sponsor develop project documentation (Project specification / Project definition & business case / PID) With the Project Team scope and define business solutions. Service the Project Delivery Group and Project Sponsor. Plan, manage and deliver projects to time, cost and quality. Monitor, control and co-ordinate projects, escalating issues and reporting progress. Managing issues and risks. Communicate project information to all stakeholders. Formally close projects. The role of the Project Delivery Group The primary responsibility of the Project Delivery Group is to direct the activities of the project and the project manager to ensure the delivery of the project against agreed expectations and timescales as set out in the high level project plan. Specific responsibilities include :Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 6 of 38 To provide specialist input to ensure the successful delivery of the project where that is required. To receive and appraise the information received from the project manager regarding the delivery of the project. To manage inter dependencies between the project and other on-going projects To communicate the purpose and activities of the project To undertake a project assurance role, identifying how the project is delivering against the business case To monitor risks to the successful delivery of the project and to agree mitigation To authorise, where appropriate, deviation form the original plan, in the light of developments within the project or the acquisition of new information. To consider the allocation of time and resources required to meet the requirements of the project To act as a champion of the project To agree the completion of the project stage and successful delivery of expectations On ISS projects this translates as (and includes): Be accountable for the quality of the solution delivered Quality assurance of documentation (e.g. project initiation document) The right people with right skills are involved Project plan is realistic Communications are adequate The business case is sufficiently well defined & realistic Business is ready and able to implement solution Provide operational support & direction for the project Monitor progress vs. plan Be a point of escalation for issues Advise on risk mitigation Authorise changes to the project Communicate with Business Systems Steering Group(s) Approve key milestones (e.g. go-live) Ensure the business case remains valid Benefits are achievable, quantifiable and documented Measures & timing of benefits realisation are understood Costs are understood and realistic Any changes are fully assessed and don’t invalidate the business case The project is stopped if the business case becomes invalid The specific roles of Project Delivery Group members The Project Sponsor The Project Sponsor is a key role – with overall responsibility for the project and its outcomes, providing high level direction throughout the life of the project and acting Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 7 of 38 as the primary champion for the project, and providing ongoing high level direction throughout the life of the project. The primary responsibility of the Project Sponsor is to provide the strategic vision and operational leadership necessary to ensure the completion of project planning, which aligns to University strategic objectives and then to secure the successful delivery of the project against the expectations of the Business Case, delivering the required outputs and outcomes within timescale and budget. Specific responsibilities include: Overall responsibility for the success of the project in delivering the business impact and business benefits as outlined in the original business case To provide strategic leadership to the project delivery group and the project manager. To chair and work with the project delivery group to oversee and ensure the successful planning and delivery of the project. To champion the project, communicating with stakeholders to secure their support and commitment. To provide the University wide strategic context for the project To identify and secure the resources necessary to ensure the successful delivery of the project. Within ISS this translates as (and includes): Overall accountability for delivery of the project Preparation of the Project Definition & Business Case Appoint Project Delivery Group and ensure it fulfils its remit Chair Project Delivery Group meetings Maintain focus on project delivery : Solution good enough but not over engineered Communication with groups Additionally, ISS Projects require other project delivery group roles that need to be filled include: The Senior User (Role specific to ISS Projects) Represent the views of the user community Ensure that business personnel with the correct skills are made available to the project at the right time Quality assurance on behalf of the user community, i.e. plan is achievable; solution is usable; benefits can be realised Ensure user community risks are understood & mitigated Resolution of escalated issues associated with the user community The Senior Supplier (Role specific to ISS Projects) Represent the views of supplier community (most of the time ISS) Ensure that supplier personnel with the correct skills are made available to the project at the right time Quality assurance on behalf of the supplier(s), e.g. plan is achievable; solution is usable; benefits can be realised Ensure supplier (community) risks are understood & mitigated Resolution of escalated issues associated with supplier (community) Also additionally UPMA recognises a role of Business Owner which on ISS projects is not always separated from Sponsor. The role is defined as: Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 8 of 38 The Business Owner is the Head of School/Service/Faculty that has the responsibility for taking the outcomes of the project and using them to deliver the benefits outlined in the business case. (For example – this could be a Head of School for a restructure project, a Head of Service for a process development, or a Head of School for a major building project). For most projects, the realisation of benefits will occur well beyond the life of the “project organisation”, hence the importance of the Business Owner having a considerable role and stake in the project. The Business Owner will normally be the person responsible for the benefits realisation, reporting to the sponsor (stage 4). Where the eventual business ownership falls across more than one area, it is still useful to nominate one Head to represent the group of business owners. There isn’t however a “one size fits all” Business Owner role, this should be considered on a project by project basis taking into account the nature of the project (and the need for specific project management skills), the project management experience of the Business Owner, and their capacity to contribute to the project. Models that work well include: Business Owner as a member of the Project Delivery Group Business Owner acting as the Project Manager supported by specialist Project Management advice/support. Business Owner working in close partnership with the Project Manager to deliver the project. Business Owner - Key responsibilities The primary responsibility of the Business Owner is to ensure that the outputs from the project are such that they will translate into the desired positive outcomes identified in the business case. Specific responsibilities include : To ensure that what is specified and delivered is fit for purpose, meeting user needs and requirements To ensure that the project maintains a focus on user needs. To brief potential business users on the actions and developments of the project, ensuring broader business engagement in the successful delivery of the project. To consider business risks. 2.3.2 IS projects Governance around IS is business led and business focussed. The highest level governing body is the Information Systems Prioritisation Group (ISPG) which is comprised of VCEG members and other senior management from Faculties and Corporate Services across the University. ISPG is supported by interaction with particular aspect of the Business, for example: Research Learning & Teaching Enterprise & Knowledge Transfer Students Staff Corporate Finance & Purchasing Project Delivery Groups have responsibility for individual projects. They are led by a Project Sponsor who is a senior manager from the business who will have a good knowledge of the area in which the project is being implemented. The Project sponsor is supported on the Project Delivery Group by senior representatives of the user community and the supplier community. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 9 of 38 2.3.3 Non-IS projects The ISS Executive (as attendees of the Programme review meeting) perform governance for ISS projects that are not covered by ISPG (e.g. non-IS projects). This is because there are no similar University wide bodies / external steering groups for the non-IS aspects of the ISS Programme. They will therefore provide governance to projects that are not directly associated with a business systems steering group. During the meeting they will consider: Key project progress Rolling programme / initiation of new projects Issue and risk review Change management / Project exceptions Project closure Again, sitting beneath the Executive, Project Delivery Groups have been established for most projects. They are led by a Project Sponsor who is a senior manager (normally an Exec member) who is likely to be head of the function within which the project is being implemented. The Project sponsor is supported on the Project Delivery Group by senior representatives of the user community and the supplier community. Note that it is anticipated that project governance will be affected by the implementation of the UITD project. 2.4 Dual roles: Should the project manager take on other roles within the project in parallel to their project management tasks, for example some project managers also perform an analysis function on their projects and some non-dedicated project managers perform project management in parallel to their normal job, these tasks should be accounted for (estimated, planned and scheduled) separately. There must be a distinction made between the project management time and effort, and time and effort on other tasks. Neither set of functions should be considered free with the other. This document concentrates solely on the project management aspects and estimates of time given here, as guides, only concern project management. 2.5 What constitutes a project: We should now consider a project as a “way in which a work request is delivered” rather than as a “type of work request”. In this way it becomes more straightforward to define exactly what a project is. There are various theoretical definitions of “a project” and the one presented below is adequate for this document: temporary organisation/arrangement established to deliver specific objectives (e.g. specific product or service) and has distinct start and finish times. 2.6 Project criteria In terms of this organisation, criteria are used as a guide to when a project approach should be used and what level of effort is required top manage the project. The information is meant as a guide and the distinction between minor and major projects is a sliding scale. There will always be exceptions to this. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 10 of 38 Title/Level Sensitivity Risk Resource Minor Project Major Projects Budget Cross functional, £10,000 one team involved £25,000 Effort Timescale Impact (Elapsed) 8-60 man days 1.5 to 3 months Not sensitive Low Sensitive Cross functional, >60 several High >£25,000 man resources/teams days involved 11-50 users >3 months >50 users Whether we manage a piece of work as a major or a minor project will be decided on the merit of each project Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 11 of 38 2.7 Example Project Flows 2.7.1 Overall delivery Decision points (gates) Approval to start Approval to spend Approval to progress Acceptance / closure Approval to launch Review benefit PROJECT GOVERNANCE Demand Post Implementation Review (report & agree) & Benefit realisation End Project meeting (report & agree) Manage Handover PROJECT CLOSE Manage changes Manage governance Manage risks / issues / dependencies Reporting Work Packages / delivery Monitor events / progress against plan PROJECT DELIVERY & IMPLEMENTATION Create / agree PDR Set-up team (Kick -off meeting) Create / agree Brief PROJECT INITIATION STAGE MANAGEMENT Maintenance / Support / Enhance Handover Deploy Train Test Build Design Evaluate Maintain Handover Deploy Train Benefit realisation Maintain Review Test Pilot Amend Install / configure Requirement Evaluate / select Infrastructure Development Ad-hoc request Concept design Annual Plan Analysis System Development TOOLS: Risk log; Issues log; Action log; Lessons learned log etc . (as appropriate) This diagram shows the components of a typical project and illustrates that the approach taken to implementation can vary depending on the project and the area concerned. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 12 of 38 2.7.2 IS start-up (example of how project start up can work in ISS) UPDATED – Nov 2009 ISS SGL General Project Management Management Business ISPG ISS PO / Finance Receive work request Small works or support No Delivery requires a project approach? Yes Indicative costs added to Proj Spec by ISS (& business) Request Project Specification to be prepared by the business (uncosted) ISPG approves the Project Specification? PO Store Project Specification in Pool (of potential projects) Yes No Stakeholder management – stop project or review scope Undertake annual prioritisation of Proj Specs PO Produce revised 5 year plan (projects and priorities) ISS FIN produce / update financial position ISS SGL assigns Project Management resource ISPG assigns project sponsor ISS produce Project Definition (with input from sponsor) 1 ISS FIN update financial position from Budgeting workbooks ISS and Sponsor approves Project Definition Stakeholder management – stop project or review scope ISPG review & assess impact on programme ISPG authorise project to proceed? No 1 Sponsor appoints project board No Yes PO receives update from ISPG PO Create / update programme schedule Yes Project Manager, with the sponsor & project board produce PID No Project Board Approve PID? ISS FIN update financial position from Budgeting workbooks Yes No PO Produce revised rolling plan No significant difference in Time, cost, scope. No Yes ISSG approve revised B’Case Rework PID Execute project Rework PID or cancel? Yes No Cancel project Stakeholder management – stop project 3 The Project Manager The functions described below are those expected of project managers (and others) who have the responsibility for managing projects. They are translated into the specific tasks that the project management performs. This is a restatement of the principles contained in section 2.3.1. 3.1 Role of the project manager Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 13 of 38 The following items are a summary the role of the project manager. Later, in this document, the component elements of these points are explored in more detail. The primary responsibility of the Project Manager is to provide the day to day management required to successfully steer the project through the planning and delivery stages and to ensure delivery against the agreed business case. Specifically: Project initiation With Project Sponsor develop project documentation (Project specification / Project definition & business case / PID) With the Project Team scope and define business solutions. Delivery The project manager is responsible for delivering the project to the agreed project plan – and achieving the outputs that underpin the project’s business case To manage the day to day delivery of the project ensuring delivery against the project plan. Planning and control To undertake/have oversight of the planning for the project. Service the Project Delivery Group and Project Sponsor. Plan, manage and deliver projects to time, cost and quality. Monitor, control and co-ordinate projects, escalating issues and reporting progress. Formally close projects. Reporting To report to the project delivery group on the delivery of the project, gathering and presenting the necessary information to enable the project delivery group to understand the actions and progress of the project. To maintain an accurate picture of the progress of the project Communicate project information to all stakeholders. Risk & Issue Management Managing issues and risks. To identify and subsequently manage risks which might jeopardise the successful delivery of the project and to communicate these to the project delivery group. To deal with issues and risks as they occur and work closely with the project sponsor to evaluate progress and take corrective action. Budgetary control To manage costs Documents by stage Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 14 of 38 ISPG / PRM approve Project specification Governance (decision points) 2 1 Governance documents Input Project Initiation Annual plan Project Specification Project Definition & Business Case Assessment material Supported by - Project Budgeting tool - Outline business case - Approach (steps) / Milestones - Outline plan - Project Budgeting tool - other Business Case calculations Ad-hoc request PROJECTS Project Management Working Documents Associated documents Governance (decision points) ISPG / PRM approve Project definition and sanction implementation Steering Group (PB) approve detailed planning Steering Group (PB) approve move to next internal-stage 2 3 Project Implementation Governance documents PROJECTS Project Management Working Documents Associated documents Summary of detailed planning activities: e.g. Project Initiation Documents - Business case - Plan (w ork schedule, Communicationsetc.) + other associated document (see below ) Supported by - Project Budgeting tool - Business case calculations - Plan (w ork schedule, Communicationsetc.) - Project organisation / team involvement Set-up project logs - Issue Highlight reports For end of stages - Manage / Revise plans - Manage / Revise Business Case + Other stage management documents as appropriate to the project Work package documentation (as appropriate) Process documentation - Issue - Change Maintain project logs - Risk - Issue - Change - Risk - Lessons learned - Change + other associated document (see below ) - Lessons learned Impact Analysis Development doumentation e.g. Project structure - Business requirements analysis Risk Analysis - System functional & technical designs Initial requirements - Test specification / scripts - Acceptance documentation - Training documentation - Handover material - User / support documentation Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 15 of 38 Governance (decision points) Steering Group (PB) approve launch PB - Approve closure 3 Project Close Governance documents Handover to Business as Usual Benefits realisation Project Management Working Documents End Project report Post implementation review PROJECTS Close project logs - Issue - Risk - Change - Lessons learned Associated documents 3.2 Project management functions This section describes the specific activities expected of those people managing projects (e.g. project managers). 3.2.1 PROJECT SPECIFICATION The creation of the Project Specification and the effort associated with it are “one offs” for each project and the Project Specification is used to 'trigger' or start up a project. The Project specification contains a very brief outline of the proposed/requested activity, stating why it is needed, outline objectives and deliverables and also an overview of the benefits (the reasons behind the request) The Project specification should be seen as the pre-cursor to the Project Definition & Business Case and by adding information to it the Project specification is transformed into the project definition & business case. The originator of the idea creates the Project Specification and sends it to ISS in an un-costed form. This is then analysed for value / benefits and the costs / resources required are estimated (plans and estimates for the next phase plus an overall – Rough Order of Magnitude – for the project as a whole). Depending of which area of ISS is to undertake the project a project budgeting workbook will be prepared to capture the costs. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 16 of 38 There is very little detail required for the Project specification and as can be seen for the estimates of time given in the appendix very little time is given. If the project manager becomes involved in capturing the originators ideas or in any initial analysis of the requirement then additional time will be required. The Project Specification is agreed by ISS and the Originator and then subjected to the appropriate governance - full details of which can be found in associated documentation. Template Content Background & Context High level • Description • Purpose, • Timescales, Objectives Anticipated benefits Key strategic drivers & alignment High level cost estimate For ISS use (consider including): • • • • Assessment of resource requirements (roles / skills / effort) Initial view of scheduling Any immediate concerns Stakeholders In summary, if involved, the project manager will: Prepare project costs (including, if appropriate, the set-up and population of the project budgeting workbook). Prepare a draft project plan. This will be in detail for the next phase preparing the Project Definition & Business Case - and in summary (milestone level) for further phases. Finalise the Project specification (to a point where it can be reviewed and decisions can be made by the governing bodies). Obtain sign-off from the appropriate stakeholders (SGLs / systems managers, ISS Executive etc.). Distribute to the Programme Office, SGLs / systems managers, ISS Executive. 3.2.2 PROJECT DEFINITION & BUSINESS CASE PRODUCTION The Project Definition & Business Case is key to the initiation stage of the project and, again, is a one off task in terms of project delivery. It is the document that management will: Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 17 of 38 formally sign-off to accept that effort should be expended to progress the project to the next stage, have an understanding of the whole project and sanction further activity. It is an extension of the Project Specification and provides outline details of the project - greater detail than the Project specification but less than the PID, for example initial statements of scope, objectives and business case etc. Planning / estimating of costs, timescales and resources are enhanced. Where appropriate the project budgeting workbook is updated. The project definition & business case informs the discussions that take place to secure resources (in principle) and supports project kick-off with the project team. The Project Definition & Business Case contains high level information on WHAT needs to be done and WHY, WHO will need to be involved in the process and HOW and WHEN it will be done. Details of the job to be done are also present and the purpose of this document is to decide whether there is sufficient justification to warrant further expenditure. In addition to the Project Definition & Business Case the following other activities happen in parallel: The Project Plan is produced which identifies the management stages and other major control points/milestones of the project and is used by ISS Management as a baseline against which to monitor project progress and cost stage by stage. Setup of Project Tools workbook - This tool provides project managers with an integrated resource by which they are able to record and manage the risks, issues, changes and lessons learned relating to their project. The workbook consists of: Risk Log, Managed Risks – Control Log, Issues Log, Change Request Log and Lessons Learned Log Communications Plan – as part of project planning (next stage etc.) communications are considered and planned. The PM may use the stakeholder management material that is available. Communications – some aspects of the project may need to be communicated at this stage and the PM will lead this work. The detailed level of planning will related to the PID (product initiation document) Production. Template Content Background & Context Detailed description of: • scope, • objectives, • deliverables, • outputs • outcomes, • project rationale Benefits & Timescales and options appraisal Key strategic drivers & alignment Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 18 of 38 Costs, Resources and Funding – investment appraisal High Level Risk Overview Organisation, Roles, Governance, Structure High Level Overview of Phases / Outline Plan Key Management Controls Handover & Acceptance For ISS use (consider including): • Cross Team involvement including an assessment of resource requirements • Likely schedule scheduling • Dependencies on teams, systems and other projects. In summary the project manager will: Produce and agree the Project Definition & Business Case - obtaining agreement from Project Delivery Group, SGLs / systems managers, ISS Executive etc. Prepare a project plan. This will be in detail for the next phase - preparing the Project Initiation Document - and in summary (milestone level) for further phases. Update the project costs / business case (including, if appropriate, the updating of the project budgeting workbook). Carry out initial stakeholder analysis and use the information to plan communications. (Some communication may take place). Finalise the Project Definition & Business Case (to a point where it can be reviewed and decisions can be made by the governing bodies). Obtain sign-off from the appropriate stakeholders (Project Delivery Group, SGLs / systems managers, ISS Executive etc.). Distribute to the Programme Office, SGLs / systems managers, ISS Executive. 3.2.3 PROJECT IMPLEMENTATION - PID Production The production of the PID as a result of detailed planning etc. is the first element of implementation and extends the project manager’s, the sponsor’s and the project team’s understanding what is required to further levels of detail. As its name suggests this document contains a detailed definition of the project and what is intended to be achieved. It should not be confused with a statement of requirements and this distinction allows project control to be distinguished from project delivery. In the PID this is apparent as it refer to other documentation including system delivery documents (e.g. User Requirements) rather than holding the details within this document. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 19 of 38 Information from the Project Definition & Business Case and/or Business Case can be transferred directly to the PID and the detail added to. In order to create a situation where the project can be fully understood and formally signed off (agreeing the PID) several other activities need to happen in parallel. . A Project Initiation Meeting or Kick-off meeting should be held – this is mandatory for the ISS methodology. The Plans and Estimates (costs and resources) are updated and further details added. The Budgeting Workbook, where used, and details of estimates (both in £s and people) are updated. The Project Plan is enhanced and (with elements of the PID) should provide a statement of how and when a project's objectives are to be achieved, by showing the major products, activities and resources required on the project. It will identify the management stages and other major control points/milestones. It is used by ISS Management as a baseline against which to monitor project progress and cost stage by stage. The Project Delivery Group is established and trained / briefed in their role. Where appropriate Timesheet Management is established. The Stakeholder Analysis previously undertaken is enhanced and the Communications Plan refined. Further aspects of the project may need to be communicated at this stage and the PM will lead this work. Risk Management and Issue Management are enacted according to the rules that prevail within ISS. The Project Manager will establish the controls and facilities that they require to perform formal document management. To confirm the end of the start-up / initiation phase the project manager will ensure that the PID is produced and signed off. Contents list; Record of Sign-off Executive Summary Background Project Definition o Concepts and Objectives Concept Objectives o Project Scope Inclusions Exclusions o Constraints o Assumptions o Interfaces o Method of Approach o Project Deliverables o Summary of Impact / Implications Summary of Business Case o Strategic Fit o Benefits o Costs (£k) and Resource Analysis (FTE) Project Organisation Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 20 of 38 Project Communications Plan Summary of Plans / Controls o Key Milestones / Timescales o Key Project Risks o Contingency Plans Project Filing Structure Associated Documents (as appropriate) o Project Organisation o Business Case o Project Plan o Communication Plan o ISS Departments/Teams Level of Involvement Checklist o Impact Analysis o Project Controls and Processes o Further Information In summary the project manager will: Produce and agree the project initiation document (with the Business Sponsor) - obtaining agreement from Project Delivery Group, SGLs / systems managers, ISS Executive etc. Produce an updated project plan. This will be in detail for the execution stage. Update the project costs/ business case (including, if appropriate, the updating of the project budgeting workbook). Carry out further stakeholder analysis and use the information to update the plans for communications. (Some communication may also take place). Update the project shared area with permissions for the project team. Update documentation within the shared area (establish “logs” for risks / issues etc. if not already completed) Set-up, run and minute the Kick-off meeting. Finalise the Project Initiation Document (to a point where it can be reviewed and decisions can be made by the governing bodies). Obtain sign-off from the appropriate stakeholders (Project Delivery Group, SGLs / systems managers, ISS Executive etc.). Distribute to the Programme Office, SGLs / systems managers, ISS Executive. Summary on use of the PID The PID is made up of extracts from other operational documents and logs etc. that are maintained throughout the project. It is these other documents and logs that are kept current as the project continues, for example risk and issue logs and project plans. The PID can therefore be said to be live because of these other documents and, should the need arise it can be reissued with the current state of play. The elements that should be maintained are, for example: Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 21 of 38 1. The project plan and associated assumptions (which would provide approach, milestones, teams / resources involved). 2. The project costs and associated assumptions (maintained and reviewed within the Project Budgeting Tool and should the need arise be used to reauthorise the project) 3. Project risks (and issues) logs (maintained as the project progresses) 4. Communications plan used to control stakeholder communications throughout the project (would provide the details in this section of the PID) There can be no hard and fast rules regarding a schedule of when the full PID should be republished within a project. This is likely to vary between projects and as a matter of course elements of it will be agreed with the project delivery group as the run-of -the-mill minor changes / fluctuations occur as the project unfolds. The guidelines should be that SGLs and Project managers will use their discretion (and be able to justify their actions) about the severity and impact of “changes” and the need to re-issue the document in its entirety. With the advent of the Project Definition and Business Case and the likely use of elements of that document to re-authorise projects that require refinancing, the relationship with the PID requires clarification. It is envisaged that where the project requires to be re-financed the Project Definition and Business Case is the best vehicle as this provides mechanisms to revisit the financial assessment of the project (e.g. risk appraisal and Net Present Value analysis). The PIDs would then need to be re-issued in the following circumstances: As part of the process, following a significant change to time, scope or costs. This will be supported by change control (and will be the result of the investigation of the implications of the change e.g. on the plan, costs etc.). If there has been significant over-run or over-spend that has resulted in needing governance approval for the changes (e.g. in circumstances where we have not estimated correctly). Where minor changes and fluctuations cannot be accommodated through flexibility/rescheduling by SGLs and are also beyond the level of discretion of the Head of IS. As a response to the re-issue / reauthorisation of the business case (to provide the PM and the Project Delivery Group with the updated tools necessary to manage the project e.g. to summarise the detailed plan, rebaseline project costs etc.). This essentially defines the PID as a vehicle for summarising the current and projected position of the project, in a degree of detail that is beyond the normal level included in the Project Definition and Business Case and project rep ======================================================== Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 22 of 38 Summary of creation of Major IS documents and decisions points / sign-off ISPG Sponsor (or nominees) Project Delivery Group IS SGL IS PM IS PO Review (create some material for input) Review (either as a group or as individuals) Project Specification Approve Create Project Definition / Business Case -stage 1 (where necessary) Project Definition / Business Case -stage 2 Project Initiation Document Approve Create Update Review Review (although this document identifies and sets up the PSG) Approve Update (create some material for input) Review Create / Update Review Update Review Review Update Update Review Review Update Review Review Create Review Approve * * Project Delivery Group can only approve if the costs contained within the PID are similar to those that have been approved by ISPG in the Project Definition / Business Case. Any significant deviation in costs must be referred back to ISPG (in most cases through a revised Project Definition / Business Case). The IS PM will be monitoring this and will initiate any escalation / resubmission of the Definition (required). 3.2.4 Project Budgeting From summer 2008 the IS part of ISS is required to complete a Project Budgeting Workbook for each of its project s (it is the intention to extend this to all of ISS at some stage). Project Budgeting has been introduced to: Standardise project costing Provide a basis for monitoring and control Visibility of project progress To ensure the business case remains justifiable Track and review actual costs against plan Understand resource requirements to deliver IS programme Provide project visibility so that management can take corrective action early when performance varies significantly from plan Understanding of actual cost and time leads to improved estimating Maximise output from the resource available Forecast future costs Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 23 of 38 Use of the workbook The Budgeting workbook is arranged by project phase and these align to the steps in the project initiation and result in the three initiation documents (Project specification, Project Definition & Business Case and Project Initiation Document). At the start up of any project the representative of ISS who is producing the project documentation (e.g. the Service Group Leader or Project Manager) is required to complete a project budgeting workbook which will calculate the cost element of the business case. The ISS representative is required to enter this information into the cost / benefit sections of the Project specification, Project definition & business case and PID. At each stage the intention if to produce the best estimate of the project cost as is possible and as the stages progress the estimates will become more accurate and detailed. For each stage of project initiation, the relevant tab is completed (explained in detail in the Budgeting Workbook Guidelines) in the budgeting workbook and inserted into the relevant document prior to submission. An estimate of how much ISS resource (which is split into various categories) in days for each future phase of the project (including execution) is entered. If it is anticipated that the project will incur non-staff costs the values of these is entered. For completeness if the business will be assisting on the project their effort (in days) is also estimated and entered. Recurrent Costs If the project is expected to incur ongoing recurrent costs e.g. annual software maintenance costs or support costs then these should be added against the relevant category within the workbook. These are entered as a percentage or a monetary value. In summary the project manager will: Produce and agree the Project Budgeting workbook. Enter estimates into the appropriate section of the workbook (that corresponds with the stage of the project). Calendarise costs for financial planning purposes (profile of spend) Store the workbooks in the appropriate folder. Record the assumptions that support the calculations Where available record actuals Keep updated to reflect the current forecasted execution cost For full details see ISS PRO website 3.2.5 PROJECT EXECUTION – start-up As the project moves into execution there are final one off tasks to complete, however these cannot be commenced until after PID sign-off. These are: The project manager will begin to execute their communications plan. Undertake a formal start-up meeting with all members of the project team to set the scene and to explain how the project will be run. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 24 of 38 Typical start-up meeting (may also be used for earlier kick-off meeting) Project Kick-off Meetings This section explains the use of project kick-off meetings to begin a project and is intended to be a guide to those organising and running such meetings. Scope/Purpose of the meeting – The Kick-off meeting will mark the official start of the project and should be used to ensure that all stakeholders/attendees have an understanding of, and agree with, how the project is going to be conducted. This will require the Project Manager (PM) to explain the following: the project’s objectives; the processes and methods to be used to progress the project and to govern it; any tools that will be used during the project (that will assist its progress – logs and reports etc.); the roles and responsibilities of the various team members; the desired outcomes; and how success will be measured. Topics for the meeting: Therefore several topics should be covered at the kick-off meeting and these are explained, below, in the form of a meeting agenda and description. Agenda items Introductions o PM ensures that all stakeholders know each other and sets the scene for why they have been invited. Context for project o The project owner, if in attendance, will explain why the project is going to be run and why at this time. This can be delivered as part of a “vision” statement. o Business vision o ISS rolling programme plan Project Governance o The PM explains how project governance will work (in terms of Project Delivery Groups and steering groups). The PM also explains the extent to which they have the authority to continue. o Terms of reference for project delivery groups, optional Steering Groups etc. Project organisation o The PM (endorsed by the project owner) will explain the project organisation and outline who will be involved (from which area) o Reference to Terms of Reference mentioned above Roles and responsibilities o The PM will explain the key roles within the project organisation and will outline responsibilities o Reference to Terms of Reference mentioned above Project approach o PM outlines the Project Management Methodology, reporting, controls, decision making processes etc. o Project Management Methodology documentation Scope o PM goes through an outline of the scope of the project and captures the input of other attendees to get to a detailed scope that can be agreed. From Project Definition & Business Case (or from previous discussions with key stakeholders). Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 25 of 38 Timeframes o PM explains the desired timescales and records any constraints etc. from attendees. - From Project Definition & Business Case (or from previous discussions with key stakeholders). Major Milestones o PM explains the likely milestones that will be used. - PM explains the desired timescales At any point in the meeting risks, issues or constraints may be mentioned and these should be recorded. Inputs: The theory says that the Project Definition & Business Case should be prepared before the kick-off meeting and be used as the main reference document within the meeting. In reality this is not always available in sufficient detail or completeness to be used in the meeting. Where this is the case the following should be available as a minimum: Vision / ideas, underpinning the project An outline statement of scope, Aims / goals for the project The desired timescales Sanction from the Governance Body to progress to the next decision point Outputs: The theory says that the Project Definition should be able to be prepared following the kick-off meeting. In reality the information gathered at the meeting is only part of the input to the PDR. From a practical point the following should be minimum output that PMs should strive to achieve: Sufficient information to confirm scope Confirmation of team details and a common understanding of roles and responsibilities Common understanding of the approach to be taken to drive and govern the project An initial view of the major risks, issues or constraints that are likely to affect the project Additionally, given sufficient time, an outline of requirements should be captured / confirmed (based around discussions of scope). Whilst this will not be presented as part of the PDR it will be useful as input to detailed estimating / planning. The PM needs to guard against getting into too much detail and straying into system design. 3.2.6 PROJECT EXECUTION - ongoing The tasks described in this section are the recurrent tasks that must be undertaken throughout the live of the project (for the purposes of this document and the estimates that back it, these have been designated as weekly tasks). Where implemented the project manager will use the information recorded via Activity Recording (where implemented) to control their project. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 26 of 38 Periodically the project manager with the Project Delivery Group will undertake a PID/Business Case review to ensure that the project remains viable. Periodically the PM will also be required to reforecast their projects. The project manager will be actively managing their Stakeholders and will be reviewing and assessing their importance to the success of the project. Communications is a key element of this and underpins the management of stakeholders. Stakeholder Management: Objectives: • Understand what stakeholders are • Understand who they are for your project • Understand their influence on your project • Define strategies for your project What stakeholders are • “For any decision or action, a stakeholder is someone who is affected by, or can influence, that decision or action” • They can be individuals or groups • They are especially important where there are multiple interests and multiple objectives. Stakeholder analysis: • Understanding who they are, their influence on, interest in and views of your project • Understand their requirements and expectations • Understand when they need to be involved Process: • Identify internal and external stakeholders and map • Remove uncertainty (meet, question, understand etc.) • Analyse attitudes and influence; understand requirements / options • Strategies and actions e.g. communications strategies (what do we want to do and how do we do it) for individuals and groups • Follow plans • Review progress, re-analyse and replan The project plan, including the communications plan, will be reviewed and revised as the project progresses. This will include updating the Budgeting Workbook where it exists and re-forecasting the finances of the project. (Example plan template) Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 27 of 38 Risk and issue Management – the project manager will be managing project risks and issues, resolving them within the team and escalating them through the governance hierarchy as is appropriate. RISK LOG PROJECT NAME: PROJECT MANAGER: PROJECT ID: Template A N Other ABC123 DATE CREATED: LAST UPDATED BY: DATE UPDATED: Risk Details Risk No Date Identified Risk Type Raised By Description Deliverables / Milestones at Risk Effect Consequence Date of Last Update Impact Criteria Likelihood E R F B Total R-1 0 R-2 0 R-3 0 R-4 0 R-5 0 R-6 0 R-7 0 R-8 0 R-9 0 R-10 0 ISSUE LOG Template A N Other ABC123 PROJECT NAME: PROJECT MANAGER: PROJECT ID: Issue No Date Issue Type Raised By DATE CREATED: LAST UPDATED BY: DATE UPDATED: Description Escalation Status Allocated To RAG Status Issue last updated Resolution Resolution Details Priority I-1 I-2 I-3 I-4 I-5 I-6 I-7 I-8 I-9 I-10 Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 28 of 38 Risks and Issues Management Project Team Project Manager Decision Maker / Resolver PSU PM records issue/risk in log Analyse and evaluate impact Estimate magnitude of change Identify action required Resolve in team Decide on action No obvious action Seek advice Resolve without escalation Resolve in team Process / implement change and update log Advise PM Escalate outside of team (e.g. ISS MT) Inform PSU Inform / notify resolver of issue & action required (Meet / mail) End By exception for major issues Receive Issue / risk notification Consider & take action Monitor situation and progress chase, as required Report progress, through HLR process R+PM implement change Monitor situation / progress chase No (if requested by / agreed with PM) Able to resolve? No Yes Closed Feedback to originator R+PM to escalate to next level Yes Record resolution Close event in log End Inform PSU To HLR Process PSU record for information For Major issues PSU record for information To HLR Process The project manager will use a series of meetings with the Project Team to manage the project in all of its aspects and will produce reports e.g. Highlight Reports, to show project status at appropriate intervals. The purpose of the highlight report is to be the vehicle through which a project manager keeps their stakeholders aware of the status of the project. It should contain sufficient detail to inform any reader of: the purpose of the project, progress and performance to date, planned activities for the next period, an overview of progress against milestones and the issues that are affecting the overall status. It will also allow the project manager to record their own assessment of the status of the project at both high-level and in detail. The report is produced at an agreed frequency that is appropriate to the project and will be used to support the ISS Programme Review process. In addition it will be used as a source for other periodic reports. See below Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 29 of 38 HIGHLIGHT REPORT Overall Status: RED AMBER GREEN Date: Project Name: ISS Executive/Service Manager: Project ID: Project Manager (ISS/Bus): Project Start Date: Project End Date: Reporting Period: Project Board Members: Next Milestone: Report Author: Scope: PROJECT STATUS INFORMATION (against original PDR) 0% Variance: Days/Weeks Variance: PROJECT STATUS INFORMATION (against changes approved by PB) 0% Variance: Variance: Days/Weeks Variance: Variance: On Budget: On Time: On Budget: On Time: £'s £'s MILESTONE INFORMATION Baseline Date: Milestone: Revised Date: Achieved Date: Reason for Slippage: Key Activity This Period: Key Activity Next Period: RISK/ISSUE INFORMATION Open Major Issues: Description: Date Raised: Escalated to: Impact (days): Impact (£) Status Escalated to: Impact (days): Impact (£) Status Open Major Risks: Date Raised: Description: Project Status All project related documents whether project control or delivery orientated will be subject to formal document management and the project manager will maintain a repository of controlled documents that will contain the definitive versions of documents. These are stored and controlled in a central location A request for change regarding the specification or acceptance criteria for the project will require formal management. The details and impact of such change should be formally assessed before they are actioned and any changes required to project costs, timescales and or scope will be subject to authorisation. A process exists to assist in the management of project change. (see below) Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 30 of 38 CHANGE REQUEST PROJECT NAME: PROJECT ID: PROJECT MANAGER: DATE RAISED: AUTHOR: ISSUE LOG NO: DATE REQUEST LOGGED PROJECT LEVEL: WITH PSU: Please refer to the comments within appropriate cells for guidance on completing this form PROPOSED CHANGE INFORMATION: Priority (refer to comment) Business area Brief description of proposed change DETAILS AND IMPACT OF PROPOSED CHANGE AND OPTIONS AVAILABLE: Option 1 Option 2 Option 3 Do nothing/retain original specification Details of options available Benefits of option Issues/Risks of option Product(s) to be changed Effort required (days) Skill/resources required Cost (£) Timescales Recommended option (please detail order of preference where 1 is the preferred option) Change within Project Team tolerance? If No - Date of Issue Escalation to PSU DECISION INFORMATION: Project Team decision: Escalation decision: (if not within Project Team tolerance) AUTHORISATION DETAILS: Name Signature Date Business Owner ISS Executive Project Manager Project Plan updated to reflect impact Date decision/change logged by PSU ALLOCATION DETAILS Allocated to: Date allocated: Date completed: Date completion logged by PSU Management of change - process Project team Project manager Project board Complete change log Change required Determine course of action necessary Assess magnitude of impact of the change Update log (size of change etc.) Size of change Complete change request form Gain agreement from “suppliers” No impact on overall time cost or quality Progress at the discretion of the project manager Further analysis required Update log (action taken etc.) Significant impact on overall time cost or quality Feedback to stakeholders Send information to Project Board for consideration Review of change request Reject the change request Accept the change request Update log (action to be taken) Further action required No further action required Implement the change Accommodate the implications of not progressing with the change Update log (action taken etc.) Feedback to stakeholders The Project Delivery Group will meet periodically (normally fortnightly) and the project manager will service these meetings by preparing the paperwork – change requests, highlight reports, agenda’s and minutes etc. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 31 of 38 General Project Management – this final section covers all of the other aspects of the project managers role, for example the informal interactions with the project team to encourage progress on specific work-streams and tasks etc. In summary the project manager will: Review the project initiation document and business case (with the Business Sponsor and the Project Delivery Group) - obtaining agreement from Project Delivery Group, SGLs / systems managers, ISS Executive etc. Monitor, update and review the project plan (including accounting for time spent of the project – if appropriate). Monitor and update the project costs / business case (including, if appropriate, the updating of the project Budgeting workbook). Manage risks and issues. Manage changes in a structured way Capture lessons to be learned. Conduct project meetings (project team, Project Delivery Group etc.) and service them as appropriate. Carry out further stakeholder management activities and execute the plans for communications. Maintain the project shared area. Produce and circulate highlight reports (recipients are likely to be Programme Office, Project Delivery Group and the project team at least). Ensure that decisions are made when required and obtain appropriate signoffs from the stakeholders. 3.2.7 PROJECT CLOSURE - Closure and Handover to Business as Usual Purpose: In this stage the outcomes / deliverables of the project are integrated into the day to day operation of the University; this is fundamental to ensuring that the project delivers the benefits set out in the original documentation. Scope of stage: The stage identifies whether the project has delivered against the plans specified earlier. It will incorporate an assessment of how successful the project delivery has been. It also accommodates the hand-over of the project to business as usual. Project Review and Benefits Realisation can assessed together or, more likely, there will be a time lag between the completion of the project and the review of benefits to enable the benefits to becoming apparent. The original business case will be fundamental to this stage (actuality is measured against the original objectives). This also enables any of the benefits not achieved to be identified and planned for. Who: It is the responsibility of the project sponsor to ensure the successful transfer of the project to business as usual. Outputs are: Benefits realisation process - which identifies activities required to ensure that the benefits are achieved. (Where necessary) A benefits realisation plan, to include: how the benefits will be realised Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 32 of 38 named individual responsible for delivery dates by which benefits are to be realised Measures by which benefit will be established How the plan will be managed. Lessons learned The extent to which the outcomes of the project have been adopted. It may also include an appraisal of the skills of expertise of the project team and working groups in delivering the project. Project Management “Closure Tasks” on ISS Projects. Once the project has delivered its objectives the project manager will undertake several one off tasks to formally close the project and disband the project team. These will be: Carry out the “End Project Review”, usually a formal meeting of the project team and stakeholders to assess the achievements of the project. As a result of the above review the project manager will prepare the End Project Report and ensure that this is formally signed off by the Project Delivery Group. This document formally closes the project and gives an evaluation of the management, quality and technical performance of the project and the achievement against objectives as defined in the PID. This details how well the project has been managed and will cover the following in detail: achievements, lessons learned and the overall performance of the project. When the EPR is complete it is signed-off by the Project Delivery Group and submitted into the Programme Review Meeting for formal Management closure. This is followed by the production of the Closure Notification as this indicates that the project has been officially ended. The final tasks for the project manager are housekeeping in nature. Project documentation is sorted and archived and communication mechanisms that have been used are decommissioned. This formal closure ensures that resources are released back into the “pool” for use on other projects and tasks. In summary the project manager will: Assist the Project Delivery Group by running the end project meeting. Produce and agree the end project report. Submit the end project report to the governing bodies (e.g. Programme Office, ISS Executive). Notify all stakeholders of project closure / completion. Archive project documentation. Decommission any specific project communication mechanisms. 4 Customisation of the methodology This section comments on the customisation of the methodology especially relating to “smaller” projects. The previous situation where there was an informal “lite” version of the methodology caused confusion and a tendency to treat all projects as a “lite” project irrespective of size. This led to problems for example non-delivery, late delivery, scope creep or delivery of inappropriate solutions. This situation will not be perpetuated and the Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 33 of 38 project management principles upon which the methodology is built will apply to all projects. However, although the principle is that all aspects of the methodology, especially governance and decision making, apply to all projects some concessions can be made to smaller, less risky projects, or some tasks that are managed using project management principles for expedient and pragmatic purposes. For example: At project initiation the three stage decision making process will apply, however, for small projects the documents will be expected to be far shorter and less detailed than for large projects. During execution we can consider a less frequent submission of highlight reports. The frequency can also be varied depending upon the level of activity of some projects. There will be a formal approach to determining whether concessions should apply to a particular project. This will be process and criteria based and decisions should be recorded for audit purposes. Suggested process: i) define project characteristics, ii) assess the criteria, iii) customise the method, document decisions (within a project document) iv) get agreement fro the governing bodies. We are striving to achieve an appropriate level of project management (and documentation) for the size and complexity of the project and this is likely to vary by project. Criteria to use when considering the application of the methodology: Team size and complexity, Experience of the personnel, Duration, Number of distinct user groups / communities, Technical complexity of the solution, Impact on business (processes etc.), Technology or software new to the University, Degree of technical innovation, Size of risk. 5 Associated documents for reference: To be found on the ISS PO web site http://iss-admin.leeds.ac.uk/info/351/programme_office Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 34 of 38 Project Specification template / guide Project Definition & Business Case template and guide Project initiation template and guide Project Management tools workbook (Risks, issues logs etc.) process and guide. Change management process, template and guide End project report template and guide Closure notification template and guide Project Budgeting workbook Key documents by project stage Guidelines for the project initiation meeting Project Management Model - estimate of time spent (in hours) Information pack – containing details of project governance (including roles of all parties and processes). Stakeholder analysis workbook and guide. Document1 09/02/2016 ISS/PO/AR Version 5.0 Page 35 of 38 6 Appendix 1- Estimated Effort (Version circulated on November 2009) PROJECT MANAGEMENT - estimate of time spent - in hours any other tasks carried out by the PM fall into a different category for estimating purposes eg Business Analysis STAGES Small PM Workload PROJECT Specification COSTING - one off Analyse if value and benefits are captured Planning/Estimating of costs and resource Costing Workbook - create and update Project Specification - circulation and sign off PROJECT Definition & Business Case PRODUCTION - one off Review Project Specification - and other info Planning/Estimating of costs and resource Costing Workbook - update Setup of Project Tools eg Risk Log Communications Plan Communications Plan for PID Production Project Definition & Business Case - production and sign off PID PRODUCTION - one off Review Project Definition & Business Case - and other info Project Initiation Meeting Planning/Estimating of costs and resources Project Board - set up and train Timesheet Management - set up Stakeholder Analysis Communications Plan Communications Costing Workbook Risk Management Issue Management Document Management - set up PID - production and sign off PROJECT Implementation - startup - one off Kick-off/Startup/Initiation Meeting Project Startup Notification to all Communications - set up PROJECT Implementation - ongoing - weekly Timesheet Management PID/Business Case - review Stakeholder Management Project Plan Communications Plan Communications Costing Workbook Risk Management Document1 09/02/2016 ISS/PO/AR Version 5.0 Medium PM Workload see scenarios Large PM workload 0.5 0.75 0.25 0.5 2 0.5 1.25 0.25 1 3 0.5 2.25 0.25 1 4 0.25 1 1 0.5 1 0.5 0.25 7 0.25 2 2 1 2 1 0.25 14 0.25 3 3 1.5 3 1.5 0.25 21 11.50 22.50 33.50 0.5 1 1.5 2 2 2 0.5 0.5 1 0.5 1.5 0.5 0.25 0.5 14 25.75 4 4 2 1 2 2 1 4 1 0.5 0.5 21 44.00 6 8 2 1.5 3 3 1.5 6 1.5 1 0.5 28 63.50 2.00 1.00 0.5 3.50 4.00 2.00 1 7.00 6.00 4.00 2 12.00 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 2 1 1 2 1 1 1 1 3 1.5 1.5 5 1.5 1.5 1.5 1.5 Page 36 of 38 Issue Management Project Team Meetings/Reports Highlight Reports Document Management Change Management Project Board - Fortnightly - Meetings and paperwork General Project Management PROJECT Implementation - CLOSURE - one off End Project Review End Project Report - production & sign off Closure Notification Document Management - archive Communications - decommission Document1 09/02/2016 ISS/PO/AR Version 5.0 0.5 0.5 0.5 0.5 0.5 1.5 1 9.50 2 2 1 0.5 1 1.5 2 20.00 4 4 1.5 0.5 1.5 1.5 3 33.00 1 1 0.25 0.5 0.5 3.25 2 2 0.25 1 0.5 5.75 3 4 0.25 1 0.5 8.75 Page 37 of 38 7 Appendix 2- Process flow – document production and approval Process – Project Documentation authorisation Project Specification Spon/ISSGL/ISPM Spon/ISMgr Prepare project specification + summary sheet (inc PBT) Submit to ISPG for approval PO Update 5 Year plan & finance report Project Definition & Business case (1 or 2 stages) ISPG Authorisation to prepare 1 or 2 step Business Case Spon/ISSGL/ISPM Prepare / revise Project Definition & Business Case + summary sheet (inc PBT) Spon/ISMgr Submit to ISPG for approval ISPG Authorise to prepare 2nd step Business Case or PID Go to 2nd stage business case Project Initiation Document ISPM/Spon/ISSGL PO Update 5 Year plan & finance report Go to PID Prep Prepare project PID (inc PBT) PID cost similar to Project Definition Cost ISPM/Spon/ISSGL Yes Submit to Project Steering Group for approval No PO Update 5 Year plan & finance report ISPM/Spon/ISSGL Need to revisit Project Definition / Business Case PM executes the project Project Implementation Yes One such action may be to revisit the business case / approach ISPG for more funding PM Escalates to SGL &Sponsor and with them decide course of action No Forecast still shows on budget (all okay)? PM Maintains PBT: Estimates, Actuals PM undertakes monthly reforecast PM Uses figures in Highlight reports (send to PSG and PO) Document1 09/02/2016 ISS/PO/AR Version 5.0 PO Take figures from PBTs for finance report and check 5 year plan Page 38 of 38