Development Project: Present government has given top priority for developing port facilities up to international standard. To develop the port 7 development projects have been undertaken. It is expected that after implementation of those projects port will be operated efficiently. Project wise description is as follows: 1. Procurement of Cargo Handling Equipment: For procuring cargo and container handling equipment the project has been undertaken. The project was approved on 04.11.2007. Under the project 2 Straddle Carrier, 2 Terminal Tractor and 2 Container trailer has been procured and to procure 6 nos. Forklift truck L.C has been opened on 19.09.2010. Forklift trucks are expected to arrive at Mongla Port soon. The project is scheduled to be completed by Dec. 2010. 2. Navigational Aids to Mongla Port: To assist movement of sea-going vessels in the channel day and night the project has been undertaken. The project was approved on 13.05.2008. Under this project 62 nos. buoys, 2nos. beacons, 6nos. light towers with lanterns and anchors will be procured and installed. To procure proposed navigational aids 3rd time tender was called on 09/03/2010 and opened on 01/04/2010. Activities of tender were suspended by the Ministry of Shipping. Recently Ministry of Shipping has withdrawn the suspension. New Project Director has been appointed and further activities of the project have been started. 3. Dredging at the Outer Bar in the Pussur Channel: The project has been undertaken to increase navigability at the Outer bar area of the Pussur Channel to facilitate entrance of more than 9 meter draft ships into Mongla Port area easily. The project was prepared to dredge about 3.2 million cubic meter silt in the Outer Bar area. The project was approved by ECNEC on 27.09.2006. Under the project five times tender was floated, due to non receipt of any tender it was called for sixth time and only one tender was received, but the quoted price was about 91% above than the approved cost of the project. As per decision of ECNEC meeting RDPP of the project was prepared and sent to the Planning Commission through Ministry of Shipping for approval. The project is under process of approval. 4. Dredging in the Harbour Channel of Mongla Port: To increase the navigability of the Harbour Channel of the Pussur River the project has been undertaken. Implementation period of the project is 2010- 2011 to 2012-2013. 5. Procurement of Cutter Suction Dredger, Pilot and Dispatch Boat for Mongla Port: For regular maintenance, dredging and smooth functioning of the port 1 cutter suction dredger, 1 pilot boat and 1 pilot dispatch boat will be procured. The project was approved on 13-04-2010. Tender evaluation of dredger, Pilot boat, Pilot dispatch boat, shore pipe, floating pipe, floater & house boat have been completed and under process for approval. The project is scheduled to be completed by June 2013 6. Port & Logistics Efficiency Improvement: To prepare Master Plan and short, medium and long term plan for improving efficiency of Mongla Port the study project has been with the financial assistance of Asian Development Bank. After completion of the study project investment project will be undertaken as per recommendation of the consultant. 7. “Procurement of 6 Dredgers and Ancillary Crafts & Accessories for Ministry of Water Resources & Ministry of Shipping (Mongla Port-1, BIWTA-3, BWDB-2) : The procurement of 6 dredgers has been approved on 17.08.2010 by ECNEC. Under the project 1 dredger with ancillary equipment will be procured for Mongla Port. The project will be implemented with the financial assistance of Indian Govt. The future prospect and potentiality of Mongla Port especially after completion of the Padma Bridge Mongla Port is one of the Sea Ports of Bangladesh. It is situated on the south-western part of the country at the confluence of Pussur River and Mongla Nulla approximately 71 nautical miles upstream of the Bay of Bengal. The port is well protected by the largest mangrove forest Sundarbans. Mongla Port has the capacity to handle 6.5 million M. tons of cargo and 50,000 TEUS of container per year. In the year 2009-10, 1.65 million M. tons of cargo and 20,500 TEUS of container were handled. The present capacity of this port is not fully utilized. In Bangladesh, the industries are located in and around Dhaka-Chittagong. The business community of Dhaka and its surrounding areas is less interested to import and export their cargo through Mongla Port because of lack of fair roads and bridges connection. The present government has given emphasis for the development of Mongla Port and pushes the construction of the Padma Bridge at Mawa point. When Padma bridge will be operational, the distance from Dhaka to Mongla will be 170 Km. So, the business community of Dhaka and its surrounding areas will be more interested to use Mongla Port for importing & exporting cargos as the transportation distance from Dhaka to Mongla will be shorter than Dhaka to Chittagong. At present, Jute & jute goods, frozen cargo and other general cargo are exported from Mongla port. Moreover, import of heavy machinery & equipments, fertilizer, food grain, sugar, motor vehicles, raw materials of industry etc. through Mongla Port will increase. As a matter of consequence, the act of establishing different types of new industries in the south-western part of the country, scope of huge employment, expansion of trade & business and overall activities of Mongla Port will increase and develop rapidly. • The Port is surrounded as well as well protected by the mangrove forest Sundarban and free from all types of congestion of ships and cargo. • River and road transport facilities available comparatively at lower cost from Mongla port to all over the remote places of the country. • Constraint free large channel available for anchorage and loading/unloading facilities on both sides for 33 ships at a time. • Due to construction of Khanjahan Ali as well as Lalonshah bridge, good transport connection system has been developed from Mongla Port to all the hinterland of North Bengal. • Unique opportunity for Dhaka-Mongla-Dhaka transportation only within 4.30 (four & half) hours time by Dhaka-Maowa Road, in spite of a ferry service on the way. • As there is no by-crossing, the goods can be transported easily without any constraint by inland coaster/barge from Mongla port. • Up to 225meter long ship can enter into the port for discharging cargo. • No constraints in berth and less turn-around time. • In compare with Chittagong Port, the Landing charge, Shipping charge and River dues are lower in Mongla port. • 15 days free time available in case of handling empty container (Import). • The port is open for 24 hours. • Infrastructural facilities available for storage of both specialised and General cargo. • Handling & parking facilities of motor vehicles available. Port Performance Maximum Length: Maximum length of vessel that can enter in the anchorage is 225 m and for the mooring buoys it is 185 m. Efforts are made to increase this permissible length to 225 m. Maximum Draught: Vessel of 9,0 m, 8,0 m and 7,0 m maximum draught can take berth in the anchorage, Mooring Buoys and Jetties respectively. Tidal Range: The tides are important for navigation as they determine the possibility of crossing the shallow area within the port limit. The tides are semi diurnal. The approximate tidal range in between 1,2 m and 3,5 m. Pilotage: Pilotage is compulsory. The pilotage ground extends from the Fairway Buoy, approximately at position Lat. 21° 26´ N Long 89° 34´ E to the northern limit of the port but master of the vessel navigates himself up to the pilot boarding ground at the Hiron Point and then the Port Pilot guides the master rest of the passage up to Mongla. Anchorage: The anchorage is safe and holding ground is good. The bed of the river is soft mud. Night Navigation: Night Navigation is continuing for outward and inward movement of vessels up to 145 m LOA and 6,5 m draught. Radio Communication: Port control, Harbour control and Hiron Point Pilot Station maintain VHF Channel 16 and 12 for 24 hrs. Installation of GMDSS equipment in Hiron Point Pilot Station and New Port Control Station are in the process. Port Dues Vessels chargeable Rate of port dues Rate of port dues 0,241 $ per GRT Sea-going vessel engaged in lightering within port 0,150 per GRT limits Sea-going vessels not engaged in lightering have not left 0,050 $ the port after 30 days from the date of entry Sea-going vessel entering for taking fuel, stores and water, etc 0,08$ Vessels working within port limits, excluding seagoing lighters Not exceeding 10 GRT: 25 Tk per vessel Between 10 – 100 GRT: 200 Tk Between 100 - 200 GRT: 500 Tk Exceeding 200 GRT: 3 tk per GRT Barge/flat: 1,5 Tk per GRT Country boat/Shampan: 0,25 per GRT Pilotage Fees The Pilotage ground extends from the fairway buoy, approximately at position Lat. 21026.9'N Long. 89034.4'E, to the northern limit of the port (Up to a line drawn between Lat. 22038.00' N Long. 89020.00' E and Lat. 22038.00' N Long. 89040.00' E). The sharply defined "Swatch of No Ground" - the northern tip of which almost touching the Pilotage ground, a nature’s boon to the mariners is approaching this port. A fairly accurate position of vessels can be obtained by watching the Echo-Sounder indicating entry of vessel into the "Swatch of No ground". It is usual for the navigators making approaches from Calcutta and Chittagong to proceed between 20 and 30 meter contour which is quite well defined and converge on the northern most tip of the “Swatch of No Ground ". The lighted Buoy painted “MONGLA FAIRWAY" and fitted with a radar reflector flashing white light every 10 seconds, makes the approach to the Pilotage ground reasonably easy and safe. From the ' fairway Buoy' to Pilotage ground (Near Hiron Point) the channel is marked by 9 pairs of lighted buoys with Radar reflectors. Masters of Vessels before approaching the Pilotage ground should await instructions from the Hiron point pilot stations. Mariners are cautioned that they may have to take appropriate corrective measures as the vessels are likely to set towards North-West during flood tide. Ship approaching Mongla Port will send their ETA and draft to their respective agents and to PORT KHULNA vis Khulna Radio ( Call sign S3E) at least 24 hrs. before their actual time of arrival at the Fairway Buoy. On receipt of the ETA directly from the ship the pilot is detailed in order of priority of arrivals. Further instructions are issued by the pilot himself on VHF. On or before arrival at the Fairway Buoy, the Master is to contact the Hiron Point pilot Station on W/T (Call sign S3K) or on channel 16 on VHF for bar crossing instructions. It must be emphasized that the instructions so received should be repeated by the ship receiving such messages. The banks of the river are stable and have continuous belt of forest with small creeks at places throughout the passage up to the Mongla Harbour area. The controlling bar at the entrance of Pussur River has a minimum datum depth of 6.0 M. This sets limit to the draft of ships entering and leaving Mongla Port. Tides and semi diurnal with spring rise between max. 2.80 M. in winter to max. 3.35 M. in Monsoon. Tidal stations at Hiron Point, Joymonirgol and Mongla are maintained for observation and record of daily tides. Unlike other riverine ports of the Bay of Bengal there are no incidents of bore tides or freshets. During Monsoon the Hinterland Rivers are in spate and current may attain strength upto 6 knots. The bottom is mainly of mud and fine sand. The channel is marked by buoys at various points conical shapes to be passed on the starboard hand and can shapes on the port hand when entering with the main stream of flood. Weather is mainly tropical with very mild winter with minimum temperature of 8'C and humidity 95% and during south westerly monsoon from June to August causing rainfall of average 200 cm. Tropical revolving storm is formed in the Bay of Bengal during the preceding (April-May) and succeeding (Sept-Oct.) two months of Monsoon. The intensity of the storm is lost on reaching the port after crossing the coast and the Sunderbans. A common weather feature is the Norwester in the months of March and April which are typical thunder storms of very short duration usually occurring at dusk with squally winds up to 40kts. NAVIGATIONAL AIDS AND NIGHT PILOTAGE The navigational track in the Pussur River and its approaches are marked by the lighted buoys at various points. “Conical shape" buoys has to be passed on the starboard hands and "can shape" buoys on the port hand when approaching with the main stream of flood. Fifty one lighted buoys have been placed along the channel. Navigational Aids As the Port is in the International Association of Lighthouse Authority (IALA) Region-A, the lighted buoys at various points mark the navigational track in the Pussur River and its approaches. "Conical Shape" green buoys have to be passed on the starboard hands and "can shape" red buoys on the port hand when approaching with the main stream of flood. All the 19 buoys in the outer bar were placed in positions during the last winter of 2006. Presently 2 buoys are missing and 11 buoys are unlit in the outer bar channel. In the inner channel is marked by another 30 nos. of buoys. Presently, except 4 buoys all are missing. However, ships are manoeuvred safely by the experienced pilots of the port. Night Navigation Night navigation is continuous for outward and inward movement of ships up to 140 m. LOA and 6.5 m. draft. Dues and charges on Ship Services Berth occupancy charges Mooring occupancy charge At mooring At Own anchor Sea-going ships 200 to 1.000 GRT Over 1.000 to 5.000 GRT Over 5.000 GRT Water supply charge At Roosvelt jetty At Mongla (local) At Mongla( to Ships) At Hiron pont (local) At Hiron pint(to ship) Basis Of charge Rate Per GRT per day Per GRT per day 0,03$ Per GRT per day 0,015$ Per Tug per Mct 55$ do 185$ do 396$ Per 1000 l 30TK Per 1000 l 60TK Per 1000 l Per 1000 l 7$ Per 1000 l 400Tk 15$ Jetty Crane Charge Use of Jetty crane Use of British crane Per crane per period of 8 hours 45$ 33,75$ If cancelled within less than 6 hours of booked period Idem 40$ Per crane If cancelled previous to 6hours 20$ Idem Holliday charge (working on jetty) Per ship per holyday 60$ Holliday charge (working on jetty) Per ship per night 30$ 3 Powerful Tugs Boats including 1 Fire Fighting Tug available. Shifting / Detention Fees Services Basis of Charge Rate Per movement 29,80$ Fees for such shifting taking place in whole or in part between Per movement 6:00 pm to 6:00 am 59,90$ Detention fees for failure of a vessel in arriving or at sailing from the port in time Per day 100$ Pilot detention fee Per day 20$ Berthing or unberthing at the time of arrival or sailing of the vessels Each occasion 88,5$ Same at the time of shitting Each occasion 44,25$ Fees for shifting vessels from one berth or mooring or swinging her to another Port and harbour dues Services River dues: Import cargo Domestic cargo Landing charge / Handling charge Bagged cargo-wheat and rice Other bagged cargo Cement, iron, steel, etc Basis of Charge Rate Per 1000 kg 33Tk idem 15,3 Per 1000 kg 33Tk Idem 32Tk Wheeled or tracked equip. All other import less than 3Mt All other import more than 3M All other import more than 20Mtt Raw material of cement Garments, cloths, cotton, etc Idem 60Tk Idem Idem 175Tk Idem 90Tk Idem 180Tk Idem 250Tk Per carton 60Tk 16Tk Hoisting charge Per 1000 Kg 100% of the landing or shipping charge for the cargo concerned Weight bridge charge Per 1000 Kg 2,5Tk Per 1000 Kg 150% of the landing charge Idem 200% of the landing charge Per 1000 Kg 21,7Tk % of landing charge 7 times of the landing charge Trans-shipment charge At the same wharf At different wharves Terminal charge on river traffic Removal charge With the MPA equip. Without equipment 2 times of the landing charge Idem Restacking charge % of landing charge 50% of the landing charge Container charges Services Basis of charge 20’ Container 40’ container 43,40$ 65,1$ Loading / Discharging: FCL Container Per container LCL Container Idem 130$ 195$ Empty Container Idem 22,1$ 33,7$ Loaded Container Idem 1,5$ 3,00$ Empty Container Idem First 7 days Idem 1,50$ 3,00$ Thereafter Idem 3,00$ 6,00$ Over height Container Idem 3,00$ 6,00$ Trailer less than 21’ Per day 1,00$ Trailer more than 21’ Idem 2,00$ Forklift less than 21’ Idem 1,00$ Forklift more than 21’ Idem 2,00$ Other equipment Idem 1,00$ Loaded container Idem 42,6$ 63,9$ Empty container Idem 21,7$ 32,5$ Pre-trip inspection Idem 2,00$ Supply of electricity Idem 5,00$ Monitoring service Idem 4,00$ Change of status charge Idem 10,00$ FCL Container Idem 408Tk 816Tk LCLContainer Idem 184Tk 368Tk Empty Container Idem 102Tk 204Tk Stuffing Per 1000kg 75Tk Unstuffing Idem 92Tk Loaded container Empty Container 1000Tk 1.500tk Empty Container Idem 500TK 750TK Container storage: Handling Equipment: Extra Container MT charge Reefer container Charge River dues on container Stuffing and unst. Charge Transhipment charge Due and charges on Goods Rent Charge (Wharf rent) for import cargo (covered storage) Basis of charge 0 to 7 days 8 to 14 days 15 to 21 days For each add days up to 22days Bagged cargo Per 1000kg 1,85Tk 4,62TK 7,39Tk 4,62TK Iron and steal Idem 1,85Tk 4,62TK 7,39Tk 4,62TK Wheeled or tracked vehicles Idem 16,2Tk 46,12Tk 73,88Tk 46,12Tk All other imports Idem 3,13Tk 7,88Tk 12,53Tk 7,88Tk Space rent charge Service Basis of charge rates Cargo inside the protected area: First month Per sq² / months 37,5Tk Second month Idem 45,00Tk Subsequent months Idem 56,25Tk Cargo outside protected area Idem 15Tk Storage of gears equip and other Idem 15Tk International transit Idem 30Tk Charges for general service Service Basis of charge rates Mechanical Equipment Mobile crane up 10 Mt Per hours 190Tk Mobile crane above 10 Mt Idem 300Tk Forklift truck up to 10Mt Idem 95Tk Forklift above 10Mt Idem 190Tk Prime Mover up to 10Mt 85Tk Prime mover above 10Mt 170Tk Trailer up to 10 Mt 30TK Trailer above 10MT 60Tk Battery Operated truck BOT 50tk Hire of tarpaulin Above 10sq² Per day 10Tk 10 to 100sq² Per day 20Tk 100 to 150 Per day 30Tk 150 to 200 Per day 40Tk 200 to 250 Per day 50Tk Up to 250 Per day 70Tk Hire of tub Each per day 31, 25Tk Above 3MT Each per day 45Tk 3 to 10Mt Each per day 90Tk 10 to 20Mt Each per day 180Tk Up to 20Mt Each per day 360Tk Hire of gangway Idem 3Tk Good Carrier on board water barges (Mongla to Khulna) Per MT 100Tk Security service engaged on the sea-going vessel Per person 150Tk Hire of Sling Performances Performance Type Year Vessels Calls 302 2010 – 2011 Container traffic (TEU's) 27.123 2010 – 2011 Total Cargo Handling (mt) 2.696.271 MT 2010 – 2011 Total Annual Capacity of the Port 6.5 millions MT 2010 – 2011 Capacity Capacity Type Bulk Container Conventional (mt/year) (TEU's/year) (mt/year) Export activity of the Port - Nil 166.418 Import activity of the port - 27.123 2.529.853 Import by Humanitarian Organisations N/A N/A N/A Top 1 Organisation <name> N/A N/A N/A Top 1 Organisation <name> N/A N/A N/A Capacity Type Bulk (mt/year) Container (TEU's/year) Conventional (mt/year) Imported for this LCA Country N/A N/A N/A Discharge Rates No information provided. Berthing Equipment and Specifications • Berthing facilities: 2 ships at the jetty, 5 ships at mooring buoy and 7 ships at anchorage and including private jetties total 14 ships can take berth at a time. Besides, there is wide scope of berthing of more ships in the anchorage. • Jetty/Warehouse/Yard facilities: 5 jetties (length 182.92 meter each), 4 transit sheds (4907 Sq m. each & total capacity in average 17932 MT), 2 warehouses (9815 Sq m.) each & total capacity in avr.15326 MT),120 refeer plug points and 3 container yards (35752 TEUS at one stack). • Facilities in the Channel: Channel draft is 6.0 to 8.5 meter. For safe guidance of ship in the channel there are 21 lighted buoys (inner channel-3 buoys, outer anchorage- 16 buoys and fairway buoy-1) and 1 Beacon (at Hironpont). Max. length of 200 meter ships can cross the Pussur channel. • Electricity Facilities: For constant supply of electricity there are 6 sub-stations and 5 power generating stations. Moreover, special facilities are provided for refeer container from own generator of MPA • Vessels & Crafts: 3 Tug boats, 01 Fire fighting tug, 2 Pilot launch, 4 dispatch launch, 3 Survey launch, 4 Mooring boats, 1 Buoy Tender Vessel, 3 Self propelled water crafts, 2 Inspection launch, 1 Oil storage vessel, 2 ferry launch- total 26 vessels and crafts are ready for smooth functioning of Port. Operations • Though the Berth Operating System has been implemented at Chittagong Port, the system is not yet functioning at Mongla. • The government ordered to implement the Berth Operating System for loading and unloading work from ship instead of ongoing system. • 40 license holder stevedores are under Mongla Port authority. Out of them, only 9 to 10 stevedores are active. Berthing Specifications Total Berths Quantity Length Draft General Cargo/ Container Berths 5 Max 225m 4,5 – 5,00 m River Mooring Buoys 7 Max 225m 3,00 – 8,00 m Anchorage Berths 14 Max 225m 4,7 – 9,00 m Total Berths Quantity Length Draft Mongla Cement Factory Jetty (Private) 1 Max 225m 6,1 m Meghna Cement Factory Jetty (Private) 1 Max 225m 6,5 m Klean Heat Gaz Factory (Private) 1 Max 225m 6,0m Summit United LPG Jetty 1 Max 225m 1,8m Summit United Petroleum Jetty 1 Max 225m Not available Dubai-Bangladesh Cement factory Jetty 1 Max 225m Not available Holcim Cement Factory Jetty 1 Max 225m Not available Vessel Concrete Jetty 1 Max 225m Not available Pontoon Berth (for Fresh Water 1 Max 225m Not available Pontoon berth (Inland vessels & Ferry) 1 Max 225m Not available Explosives Jetty Nil - - Berthing Tugs & Mooring Boats 3 - - Pilot Boats 3 - - Water Barges (Dumb) 4 * 500 MT - - Police Boats Nil - - Anti-pollution Boats Nil - - Speed Boats Nil - - Berthing Support Quantity Berthing Tugs and Mooring Boats N/A Pilot Boats N/A Water Barges N/A Police Boats N/A Anti-pollution Boats N/A Speed Boats N/A Port berthing details web page http://www.bsaakhulna.com/ Port Cargo Handling Equipment No information provided. Port Cargo Equipment (operational) Appliance Quantity Capacity Mobile Crane 1 100 (Existing capacity-30 M/Ton) Mobile Crane 1 40 (Existing capacity-24 M/Ton) Mobile Crane 1 35 (Existing capacity-30 M/Ton) Mobile Crane 1 25 Mobile Crane 2 19 Mobile Crane 2 10 Dockside Crane (Metalna) 7 5 Forklift Truck 5 5 Forklift Truck 2 3.5 Forklift Truck 3 3 Forklift Truck 1 2.5 Forklift Truck 8 2 Reefer cargo particularly export of frozen shrimps is predominant through this port. In the container yard no. 1 & 2 there are 120 plug points to connect reefer containers. Electricity is being supplied from electric substations to the reefer container. For constant and uninterrupted power supply MPA has its own generators which are capable to supply power to 40 containers. Provision of 110 volt power supply for reefer container is also available in the container yard. Container Storages Facilities Name Quantity Length/ Area Capacity Container yard 3 Nos. 35752 Sq m (Total) 2180 TEUS (at a time) Facility Types 20 ft (TEU's) 40 ft (FEU's) Container facilities yes yes Daily off-take capacity: No of containers/day 40 30 Container Freight Stations (CFS) yes yes Number of CFS 02 02 Capacity of CFS: No of containers/day 2015 2015 Refrigerated Container Stations yes yes Number of Reefer Stations (connection points) 120 120 General Cargo Handling Berths No information provided. General Cargo - Imports Berths Imports - Bagged Cargo N/A Exports - Bagged Cargo N/A Imports - Steel Goods N/A Imports and Exports -- Ro-Ro N/A Imports - Vehicles N/A Others Imports N/A Oil Handling Terminal Fuel oil can be arranged in limited quantities if 48 hours advance notice is given to the respective owner /declaring shipping agents. Multipurpose Terminal No information provided. Grain and Bulk Handling No information provided. Main Silo Terminal The Mongla Port hasn’t been equipped for the bulk grain handling. There are no vacuators, silo facilities and bagging machines. No Silo terminal It is mainly for that reason that the WFP agencies have decided to channel all their shipping activities through the Chittagong Port. Main Storage Terminal No information provided. Bagging - Grain Handling No information provided. Stevedoring No information provided. Handling and Charges Conventional Cargo No information provided. Containerised Cargo No information provided. Containerised Cargo Handling Charges Containerised Cargo Handling type 20 ft (TEU's) 40 ft (FEU's) Discharge, loading, shifting within the hold orshifting on deck without landing n/a n/a Containers handled via a conventional ship n/a n/a Containers handled on a Ro-Ro basis n/a n/a Empty containers n/a n/a Transhipment containers, overland containers, containersshipped & re-landed or landed & re-shipped or shiftedfrom hold to hold n/a n/a Stripping or Stuffing of Containers n/a n/a Stripping and re-stuffing transhipment cargo n/a n/a Shore Handling: Containerised Cargo No information provided. Shore Handling Types 20 ft (TEU's) 40 ft (FEU's) Import Containers n/a n/a Export Containers n/a n/a Stripping and re-stuffing for customs verification n/a n/a Stripping and re-stuffing of un-nominated or shut-out export cargo n/a n/a Stripping or re-stuffing of containers taken to Customs Warehouse n/a n/a Shore Handling Charges Cargo (per ton or part of) Charge Ten day removal charges, or transfer within the Port, or transfer to Customs n/a Import Containers handled at the Inland Container Depots n/a Exports Containers handled at the Inland Container Depots n/a Clearing Agents Port Security BIWTA provides in-house security at all river ports in Bangladesh. Security guards employed with BIWTA are responsible for port security. These security guards function under the supervision and control of the port officer who is responsible for port operations. Police from local police stations as well as Ansars are also deployed for maintaining law & order and providing security. The port area has been restricted for security reason. The Mongla Port Authority can provide a pass for the restricted area. Security ISPS Compliant: yes Security ISPS Level (current): Normal (1) Storage Facilities Name Quantity Length/ Area Capacity Transit Shed 4 Nos. 4.907 Sq m (each) 17.932 MT (Total Capacity) Warehouse 2 Nos. 4.907 Sq m (each) 15.326 MT (Total Capacity) Container yard 3 Nos. 35.752 Sq m (Total) 2180 TEUS (at a time) Storage Facilities Managed By Storage Facilities: Port Storage Total floor space Quantity Floor Area (m2) Main Quay Transit Sheds n/a n/a Back of Port Transit Sheds n/a n/a Lighterage Area Transit Sheds n/a n/a Customs Warehouses n/a n/a Other Comments There are almost 600 clearance agents and around 100 Stevedore Companies. They are appointed on a yearly base, after a call for tender process. List can be obtained at Mongla Port Authority.