Australian Industry Participation (AIP) plan Summary – Project Phase

advertisement
Australian Industry Participation (AIP) plan Summary
– Project Phase
1. Project Details
Designated project proponent: BHP Billiton Olympic Dam Corporation Pty Ltd
Description of the project BHPB Olympic Dam will undertake optimisation and improvement
activities including the development of a large scale demonstration plant.
Estimated project value: >$500m
Project location: Olympic Dam - Roxby Downs, South Australia
Link to project information: TBC – ICN Gateway SA. http//gateway.icn.org.au/
Project contact for procurement information: Glenn Hunt, Manager Supply. Ph:.+61884052049,
E: glenn.hunt@bhpbilliton.com
Other project proponents involved in the project: N/A
2. Opportunities to supply Goods and Services
Opportunities for
Australian entities
Expected opportunities
Opportunities for
non-Australian
entities
Goods
Acid Storage Tanks
Yes
Yes
Supply of Nitrogen
Yes
No
Anode Storage
Yes
No
Loader/Truck
Yes
Yes
Upgrade Conc. filter
Yes
Yes
Change rooms
Yes
Yes
Cathode Storage Area
Yes
No
Upgrade HC Thickeners
Yes
Yes
Step down transformers
Yes
Yes
Upgrade blister launder
Yes
Yes
Pumps and Cyclones (Debottleneck)
Yes
Yes
Solvents and Reagents - larger capacity APM
Yes
Yes
AIP plan Summary – Project Phase
Australian Industry Participation Authority
Version 1.1 April 2014
1
Scavenger tails pumps
Yes
Yes
CCD Pump upgrade, including HV substation
Yes
Yes
Mills, cleaner flotation, capacity and regrind
Yes
Yes
Solvents and Reagents – Larger Capacity CSM
Yes
Yes
Mine Southern Power and Transformer
Yes
Yes
CDT Crusher Level infrastructure
Yes
Yes
Feed system and cons burner
Yes
Yes
JP Crane
Yes
Yes
CCD upgrade feedwalls
Yes
Yes
Storage Shed
Yes
Yes
Pump Stations and substations
Yes
Yes
Blister launder upgrade
Yes
Yes
Surge Tank upgrade
Yes
Yes
Filtrate Tank Upgrade
Yes
Yes
Mill Water Pond Liner
Yes
No
Co-jet burner
Yes
Yes
Scrap bailer
Yes
Yes
Upgrade Cooling
Yes
No
Borefield services
Yes
No
Upgrade to slimes treatment and gold room
Yes
No
Tails leach debottlenecking
Yes
No
Water and Air upgrade
Yes
No
Automatic throat cleaning
Yes
No
Mine planning and development
Yes
No
Services
AIP plan Summary – Project Phase
Australian Industry Participation Authority
Version 1.1 April 2014
2
SX circuit upgrade
Yes
No
HV to LV conversion
Yes
No
Mill reline
Yes
No
Coke injection study
Yes
No
Extend anode furnace capacity
Yes
No
Disclaimer: The information provided in the table above is based on an initial assessment by the company. Any questions or issues should
be raised with the project contact.
3 Standards to be used in the project

The Project will ensure that the engineering design is based on Australian Standards and/or
International Standards in common use in Australia.
4. AIP activities undertaken by the Project Proponent




The Project will create a supplier portal dedicated to the project detailing the types of
opportunities available to Australian Industry and how they can respond to these opportunities
– i.e. ICNSA Gateway Facility.
The Project will hold public/industry briefings, conferences and/or workshops to communicate
the types of opportunities available to Australian industry and information on how Australian
industry can respond to opportunities, including how to pre-qualify.
The Project will make direct contact with Australian Industry (e.g. personal letters or emails)
inviting tender responses or informing about opportunities and how to respond to these
opportunities.
The project will use its current memberships with SACOME and AMMA along with regional
industry board like the Upper Spencer Gulf maintenance group to promote supply opportunities
amongst their respective networks.
5. AIP activities to be undertaken by procurement entities

Project Proponent is undertaking the key procurement activities.