Case study: № 1. When the sanitary survey treatment plant aeration "Boz-su" established that the waste water of the city of Tashkent in the amount of 80,000 cubic meters day passes cleaning on these plants: grille, sand traps, circular tanks, aeration tanks, secondary circular tanks. Wastewater disinfection with chlorine is carried out. The contact time is 30 minutes, if the index after chlorination effluent 650 - 950, residual chlorine of 1.6 - 1.7 mg / l. Rate purification scheme, the conditions and the effectiveness of chlorination. Solutions. The purification scheme for the purification WWTP "Boz-su" correctly. Terms and effectiveness of chlorination meets the hygienic requirements as for 0056-96 SanPin contact time must be at least 30 minutes, if the index is not more than 1000 chlorine residual of at least 1.5 mg / lСитуационная задача: № 2. When the sanitary survey WWTP "Boz-su" set that sewage of the city of Tashkent in the amount of 150,000 cubic meters day passes cleaning on these plants: sand traps, circular tanks, aeration tanks. Wastewater disinfection with chlorine is carried out. The contact time is 30 minutes, if the index after chlorination -1000 700 sewage, residual chlorine of 1.5 mg / l. Rate purification scheme, the conditions and the effectiveness of chlorination. Solutions. The purification scheme for the purification WWTP "Boz-su" wrong, because according to KMK "Sewerage. Internal and external networks "should be grille and secondary sedimentation tanks. Terms and effectiveness of chlorination meet hygienic requirements, as for 0056-96 SanPin contact time must be at least 30 minutes, if the index is not more than 1000 chlorine residual of at least 1.5 mg / l Case study number 3. When the sanitary survey WWTP "Boz-su" set that sewage of the city of Tashkent in the amount of 150 cubic meters day passes cleaning on these plants: sand trap grille, circular tanks, aeration tanks secondary sedimentation tanks. Wastewater disinfection with chlorine is carried out. The contact time is 25 minutes, if the index wastewater after chlorination 1600 - 1900, residual chlorine of 1.2 - 1.4 mg / l. Rate purification scheme, the conditions and the effectiveness of chlorination. Solutions. The purification scheme for WWTP "Boz-su" wrong, because according to KMK "Sewerage. Internal and external networks' money had to be aeration tanks and secondary sedimentation tanks. Terms and effectiveness of chlorination does not meet hygienic requirements, as for 0056-96 SanPin contact time must be at least 30 minutes, if the index is not more than 1000 chlorine residual of at least 1.5 mg / l Case study number 4 Assess the effectiveness of wastewater treatment aeration station "Boz-su" according to this protocol №35.Spusk wastewater is carried out in the river Boz-Su within the city limits. Protocol №35. Studies wastewater purification steps. Location of sampling -ochistnye facilities. Time-sampling 25.12.2008g. indicators analysis waste water Incoming After circular tanks BOD, mg.02 / l 125.0 110.0 after aeration after chlorination 12.0 10.0 11.0 37.0 99.0 99.0 Relative stability,% 55.0 55.0 50.0 50.0 Chlorides, mg / l 18.2 18.0 10.2 9.8 Ammon nitrogen, mg / l 0.0 0.0 0.1 0.14 Nitrite Nitrogen, mg / l 0.0 0.0 9.6 9.0 nitrate nitrogen ------- -------- -------- 1.5 Solutions In assessing the biological treatment should first clarify the analysis of waste water availability indicators reflecting 1 (BOD stability) and 2 (ammonia nitrogen, nitrate nitrogen) phase oxidation of organic substances. To assess the technical efficiency of biological treatment is necessary to focus on the performance analysis of wastewater BOD aqueous stability of the compounds of group nitrogen (ammonia nitrogen, nitrite nitrogen, nitrate nitrogen). Method of determining the technical efficiency izlazhena above. Results: The technical efficiency for BOD. Is 96%, which meets the requirements of CMC Sewerage. From the analysis it follows that the process of oxidation of organic substances is evidenced: 1 snizheniyayae ammonia nitrogen concentration from 18 to 10.2 mg / l 2-appearance of nitrite and nitrate nitrogen (0.1 and 9.6 mg / l) Assessing the relative stability of the wastewater should be aware that the biological treatment is effective in terms of the relative stability of at least 80% in the above analysis .Poskolku wastewater stability after biological treatment is 99% it can be otsenina positive. Case study number 5 Assess the effectiveness of wastewater treatment aeration station "Boz-su" according to this protocol №215.Spusk wastewater is carried out in the river BozSu within the city limits. Protocol №215. Studies wastewater purification steps. Location of sampling -ochistnye facilities. Time-sampling 20.10.2008g. indicators analysis Waste water Incomin After after g circular aeration tanks Temperatura.S 22.5 22 19.5 after chlorination 20 transparency 1.5 9.5 12.0 19.0 Precipitate volume 2.1 1.1 0.9 0.2 suspended solid matterin mg / l 115.0 50.0 95.0 20.0 Total mikrob. 380000 92000 38000 3000 if the index 2380000 238000 238000 800 Residual chlorine mg / l -------- ------- ------- 1.5 Solutions To evaluate the effectiveness of the mechanical cleaning technology primarily from analysis should identify indicators wastewater precipitate volume defined in further transparency (%) reduction in the concentration of suspended solids (x1) precipitate (x2) after the mechanical treatment compared to the incoming. Taking as 100% the amount of suspended solids or sludge volume in the incoming waste water find% suspended solids remaining in mg l and sludge volume. 50 x 100 1.0 x 100 X 1 = ---------------------- = 43.4%, X2 = -------------------- ------- = 43.4% 115 2 3 It follows that the technical efficiency of mechanical treatment is 43.4%. The analysis shows that, along with a decrease in the weighted substances increases the transparency of wastewater 1.5do 9.5sm. Assessing technical efficiency mechanical treatment should focus on the KVM Sewerage which provides for effectiveness delay the weighted substances in lagoons at 40 to 45%. To evaluate the effectiveness of disinfection should be in addition to determining the number of index% reduction rely on surface water from sewage pollution SanPin 0056-96 .Otsutstvie content in the water of pathogens achieved by disinfection of biologically treated wastewater to the number of index at most 1000pri residual chlorine to less 1.5 mg / l. Thus wastewater treatment both in mechanical stage shows low technical efficiency, but the effectiveness of decontamination meets the hygienic requirements. Case studies: № 6 Assess the effectiveness of wastewater treatment aeration station "Bozsu" according to this protocol №25.Spusk wastewater is carried out in the river Boz-Su within the city limits. Protocol №25. Studies wastewater purification steps. Location of sampling -ochistnye facilities. Time sampling-15.10.2008. indicators analysis Waste water Incomin After after after g circular aeration chlorination tanks Temperatura.S 24.5 22 19.5 22 transparency .See 3.5 8.5 15.0 19.0 Precipitate volume 2.7 1.9 1.0 0.5 suspended solid matterin mg / l 125.0 85.0 90.0 18.0 Total mikrob.chislo 375000 94000 35000 3000 if the index 2550000 245000 245000 850 Residual chlorine mg / l -------- ------- ------- 1.4 Case studies number 7 Assess the effectiveness of wastewater treatment aeration station "Boz-su" according to this protocol №15.Spusk wastewater is carried out in the river Boz-Su within the city limits. Protocol №15. Studies wastewater purification steps. Location of sampling -ochistnye facilities. Time-sampling 05.10.2008g. indicators analysis Temperatura.S 22.5 Waste water After after circular aeration tanks 21.2 20.7 Transparency. see 3.3 10.0 15.0 18.5 Precipitate volume 2.9 1.5 0.75 0.32 suspended solid matterin mg / l 118.0 57.7 96.5 17.9 Total mikrob.chislo 378000 92600 35000 3700 if the index 2415000 275000 23500 950 Residual chlorine mg / l -------- ------- ------- 1.3 Incomin g after chlorination 19.8 Case studies number 8 Assess the effectiveness of wastewater treatment aeration station "Boz-su" according to this protocol №17.Spusk wastewater is carried out in the river Boz-Su within the city limits. Protocol №17. Studies wastewater purification steps. Location of sampling -ochistnye facilities. Time-sampling 02.10.2008g. indicators analysis Waste water incoming After circular after after tanks aeration chlorination Temperatura.S 23.5 21.5 18.7 19.6 Transparency. see 2.0 8.5 13.2 18.4 BOD 125.0 110.0 12.0 10.2 relative stability 15.0 37.0 90.0 95.0 chlorides 58.0 57.0 55.0 52.0 if the index 2390000 239000 239000 760 Residual chlorine mg / l -------- ------- ------- 1.3 Case studies number 9 When san. Survey treatment plant orders. doctors established that the fault of the chief engineer of the sewage treatment plant control treatment plant is carried out once a week. These laboratory analysis showed that the effluent quality to allow epidemiological indicators consider water sbrasyvaemy open water epidemiological safety, but the chemical content exceeds health standards as Benzene content 5.2 mg / liter. Lead of 2.5 mg / l earlier by employees of the treatment plant violations were noted. Give solutions. Case studies number 10 When san. Survey treatment plant orders. doctors established that the fault of the chief engineer of the WWTP control of chlorination of water is carried out once a week. These laboratory analysis showed that the effluent quality to allow epidemiological indicators consider water discharged into open water epidemiological safety. Previously by employees WWTP violations were noted. Give a solution.