SEISMIC UPGRADE OF AN EXISTING MASONRY BUILDING A Project Presented to the faculty of the Department of Civil Engineering California State University, Sacramento Submitted in partial satisfaction of the requirements for the degree of MASTER OF SCIENCE in Civil Engineering (Structural Engineering) by Joshua Johannes Plenert SPRING 2014 © 2014 Joshua Johannes Plenert ALL RIGHTS RESERVED ii SEISMIC UPGRADE OF AN EXISTING MASONRY BUILDING A Project by Joshua Johannes Plenert Approved by: __________________________________, Committee Chair Benjamin Fell, Ph.D., P.E. ____________________________ Date iii Student: Joshua Johannes Plenert I certify that this student has met the requirements for format contained in the University format manual, and that this project is suitable for shelving in the Library and credit is to be awarded for the project. ________________________________, Graduate Coordinator ________________ Matthew Salveson, P.E. Date Department of Civil Engineering iv Abstract of SEISMIC UPGRADE OF AN EXISTING MASONRY BUILDING by Joshua Johannes Plenert This report proposes a seismic retrofit strategy of a 1-story existing building with reinforced masonry walls and a flexible wood diaphragm. Significant structural deficiencies are identified from procedures described in ASCE 31 (2003) and include diaphragm to shear wall connections, collector element, and out-of-plane anchorage for the masonry shear walls. Equivalent lateral seismic loads are applied to the structure such that all critical load paths are designed and detailed for a base shear using a seismic response coefficient, R = 3.5, and an importance factor, I = 1.25. Capacity design and retrofit checks followed procedures details in ASCE 7-10 and ASCE 41. Considering the seismic deficiencies this structure has, the retrofit strategy and proposed details could be applicable to a plethora of reinforced masonry structures in high, or moderate, seismic regions. _______________________, Committee Chair Benjamin Fell, Ph.D., P.E. _______________________ Date v TABLE OF CONTENTS Page List of Tables ........................................................................................................................ viii List of Figures ........................................................................................................................... x Chapter 1. INTRODUCTION ............................................................................................................... 1 1.1 Motivation.............................................................................................................. 1 1.2 Objective and Scope .............................................................................................. 3 1.3 Organization and Outline ....................................................................................... 5 2. STRUCTURAL OVERVIEW AND DESCRIPTIVE EVALUATION ............................. 6 2.1 Lateral Load Resisting Systems .............................................................................. 6 2.2 Site Hazards and Design Requirements ................................................................. 9 2.3 Identified Deficiencies ......................................................................................... 12 3. FLEXIBLE WOOD DIAPHRAGM AND ASSOCIATED COMPONENTS.................. 16 3.1 Diaphragm Shear Forces ...................................................................................... 17 3.2 Tensile Capacity of Diaphragm Chords ............................................................... 21 3.3 Tensile Capacity of Continuous Cross Ties ........................................................ 25 4. DIAPHRAGM TO SHEAR WALL LOAD TRANSFER ELEMENTS .......................... 29 4.1 Out-of-plane Force Resisting Elements ................................................................ 29 4.2 In-plane Force Resisting Elements ...................................................................... 34 4.3 Masonry Shear Wall Capacities ........................................................................... 36 5. SPECIAL CONDITIONS .................................................................................................. 41 5.1 Special Condition 1 .............................................................................................. 41 5.2 Special Condition 2 .............................................................................................. 43 vi 6. SUMMARY ....................................................................................................................... 45 Appendix................................................................................................................................. 46 References ............................................................................................................................... 67 vii LIST OF TABLES Page Table 2.1 Structural Components at High Roof Areas ..................................................... 8 Table 2.2 Structural Components at Low Roof Areas ...................................................... 8 Table 2.3 Soils Information at Site under Consideration ................................................ 10 Table 2.4 Seismic Hazard Information ........................................................................... 11 Table 2.5 Windstorm Characterization ........................................................................... 12 Table 2.6 Identified Deficiencies Illustrated in Figure 2.5 ............................................. 15 Table 3.1 Diaphragm Seismic Demands, As-built Capacity and Retrofit Strategy ........ 20 Table 3.2 Chord Retrofit Strategies Identified in Figure 3.7 .......................................... 24 Table 4.1 Summary of Out-of-plane Anchorage Retrofit Strategy ................................. 32 Table 4.2 Summary of Shear Wall Stresses .................................................................... 39 Table A.1 Base Shear Summary ...................................................................................... 47 Table A.2 Diaphragm Shear Summary ............................................................................ 48 Table A.3 Chord Forces ................................................................................................... 49 Table A.4 Box A: Flexible Diaphragm Seismic Forces .................................................. 50 Table A.5 Box B: Flexible Diaphragm Seismic Forces ................................................... 51 Table A.6 Box C: Flexible Diaphragm Seismic Forces ................................................... 52 Table A.7 Box D: Flexible Diaphragm Seismic Forces .................................................. 53 Table A.8 Box E: Flexible Diaphragm Seismic Forces ................................................... 54 Table A.9 Box F: Flexible Diaphragm Seismic Forces ................................................... 55 Table A.10 Box G: Flexible Diaphragm Seismic Forces .................................................. 56 Table A.11 Box H: Flexible Diaphragm Seismic Forces .................................................. 57 viii Table A.12 Box I: Flexible Diaphragm Seismic Forces .................................................... 58 Table A.13 Box J: Flexible Diaphragm Seismic Forces .................................................... 59 Table A.14 Box K: Flexible Diaphragm Seismic Forces .................................................. 60 Table A.15 Box L: Flexible Diaphragm Seismic Forces ................................................... 61 Table A.16 Box M: Flexible Diaphragm Seismic Forces .................................................. 62 Table A.17 Box N: Flexible Diaphragm Seismic Forces .................................................. 63 Table A.18 Box O: Flexible Diaphragm Seismic Forces .................................................. 64 Table A.19 Special Condition 1 RISA Results .................................................................. 66 ix LIST OF FIGURES Page Figure 2.1 Three-dimensional Schematic View of Religious Meetinghouse in Fremont, CA ..................................................................................................... 6 Figure 2.2 Architectural Floor Plan.................................................................................... 7 Figure 2.3 Architectural Roof Plan .................................................................................... 7 Figure 2.4 Re-entrant Corner Failure ............................................................................... 14 Figure 2.5 Locations of Deficiencies Listed in Table 2.6 ................................................ 15 Figure 3.1 Free Body Diagram of Forces Acting on Diaphragm and Diaphragm Components .................................................................................................... 16 Figure 3.2 Layout Box and Grid Line Assignments for Diaphragm Analysis ................. 17 Figure 3.3 Diaphragm Seismic Upgrade Illustrating Deficient Areas Retrofitted with Blocking or Plywood Sheathing ..................................................................... 20 Figure 3.4 Chord Force Illustration .................................................................................. 21 Figure 3.5 Chord Failure .................................................................................................. 22 Figure 3.6 Chord Retrofit Strategy ................................................................................... 23 Figure 3.7 Location of Chord Discontinuities Summarized in Table 3.2 ........................ 25 Figure 3.8 Cross Ties Example ........................................................................................ 26 Figure 3.9 Detail of Continuous Cross Tie Retrofit Strategy ........................................... 27 Figure 3.10 Plan Showing Low Roof Continuous Cross Tie and Chord Reinforcement Locations......................................................................................................... 28 Figure 3.11 Plan Showing High Roof Continuous Cross Tie and Chord Reinforcement Locations......................................................................................................... 28 x Figure 4.1 Out-of-plane Anchorage Failure ..................................................................... 29 Figure 4.2 Results of Out-of-plane Pushover Analysis on Masonry Wall ....................... 30 Figure 4.3 Layout of Walls and Associated Seismic Weights ......................................... 31 Figure 4.4 Detail of Out-of-plane Anchorage Retrofit Strategy at Face of Perpendicular Masonry Wall ................................................................................................. 32 Figure 4.5 Detail of Out-of-plane Anchorage Retrofit Strategy at Face of Parallel Masonry Wall ................................................................................................. 33 Figure 4.6 Detail of Out-of-plane Anchorage Retrofit Strategy at top of Parallel CMU Partition........................................................................................................... 33 Figure 4.7 Detail of Out-of-plane Anchorage Retrofit Strategy at top of Perpendicular CMU Partition ................................................................................................ 34 Figure 4.8 Detail of In-plane and Out-of-plane Anchorage Retrofit Strategy at Joists .... 35 Figure 4.9 Detail of In-plane and Out-of-plane Anchorage Retrofit Strategy at Truss .... 36 Figure 4.10 Results of In-plane Pushover Analysis of Masonry Wall ............................... 37 Figure 4.11 Plan Identifying Shear Walls and Associated Weights and Equivalent Thicknesses ..................................................................................................... 38 Figure 4.12 Discontinuous Shear Wall Upgrade Detail ..................................................... 40 Figure 5.1 Plan Showing Locations of Special Conditions .............................................. 41 Figure 5.2 Detail of Special Condition 1 Retrofit Strategy at Failed Connection ............ 43 Figure 5.3 Detail of Special Condition 1 Retrofit Strategy at Un-failed Connection ...... 43 Figure 5.4 Detail of Special Condition 2 Retrofit Strategy .............................................. 44 Figure A.1 Special Condition 1 RISA Results .................................................................. 65 xi 1 CHAPTER 1 INTRODUCTION 1.1 Motivation Earthquakes pose a major threat to structures, human life, and economies in major urban centers worldwide. According to the USGS 2009 Earthquake Probability Mapping tool, the Bay Area of California has a 60-90% probability of experiencing an earthquake with a magnitude of 6.5 on the Richter scale within the next 50 years. On May 2, 1983, a magnitude 6.5 earthquake occurred approximately 9 miles north-northeast of the City of Coalinga, CA. The next day a damage survey team from the Earthquake Engineering Research Institute (EERI) arrived on-site to perform a visual survey of the main commercial district of downtown Coalinga. Approximately 20% of the 139 damaged buildings surveyed were reinforced masonry buildings similar to the building analyzed in this report. The majority of the failures observed were out-ofplane failures, many of which occurred at connections from the walls to the roof. The EERI reconnaissance team made the following sobering observation in the survey referenced at the end of this report. “Coalinga is typical of many older California communities. One can find similar construction material and structural types throughout the length of the state. What we saw in Coalinga could happen in any older California community." The EERI reconnaissance team also emphasized the importance of identifying potential failure modes in stating “the emphasis is not on whether the construction is poor or not, but rather on knowing the kind of damage that can occur” (Shah, 1983). Analysis and design practices for earthquake engineering are continuously evolving as our understanding of structural responses to seismic forces and the ability to predict seismic forces improves. However, many of the older structures built in California were not adequately 2 built to resist seismic forces. For example, with the introduction of ASCE 7 (2010), seismic design loads changed considerably from the previously used loads specified in ASCE 7 (2005). The seismic design maps used to determine a risk-target maximum considered earthquake (MCER) contained in Chapter 22 of ASCE 7 (2010), have replaced older maps in order to incorporate four major advances in our understanding of seismic events. First, the new maps incorporate current USGS source zone models, which have been improved using Next Generation Attenuation (NGA) relationships. Second, uniform-hazard ground motion was replaced with a risk-targeted ground motion in order to take into account site-to-site variability in the shape of ground motion hazard curves (Luco, 2007). Third, a switch from “geo-mean” ground motions (the mean ground motions of any two orthogonal directions) to maximum direction ground motions has resulted in a 10% increase in short period ground motion and a 30% increase in longterm ground motion based on work by Whittaker (2014). Fourth, 84th percentile ground motions (which is 180% of median ground motions) have replaced 150% ground motions. These changes have resulted in lower short-period ground motions in areas of low seismicity and higher shortperiod ground motions in areas of high seismicity, thus allowing for design parameters to be less uniform and more site specific. Older reinforced masonry buildings have common deficiencies, the most common of which is the out-of-plane anchorage from the roof system to the masonry walls. A typical connection detail is a toenail between the joist or truss and a wood plate secured to the top of masonry walls. Considering an approximate pull-out force of 55 lbs/nail which was calculated using Table 11.2C and Section 11.5.4 of AWC (2012), this type of connection is not able to ensure a positive connection between the diaphragm and shear wall. Considering that out-ofplane forces caused by large seismic events can be on the order of 0.12-0.56 kips for a lateral load resisting system comprised of heavy partially grouted masonry walls, it is critical to design a 3 positive connection with adequate capacity to prevent out-of-plane failure between the joists or trusses and the masonry shear wall. In-plane considerations for the masonry shear walls are also important to consider as many older masonry structures have insufficient reinforcement, relative to current seismic provisions. Without proper reinforcement, the shear walls will experience significant diagonal shear failures at window and door openings. Unreinforced masonry (URM) structures are common in older communities and pose a significant risk of collapse, due to their inability to dissipate lateral seismic forces through large inelastic deformations the way a properly reinforced masonry structure can (Bruneau, 1992). This report will provide in-depth analyses and design procedures to propose retrofit strategies for an existing masonry structure, which can be applicable to a wide-variety of masonry structures in California. Special attention is allotted to the out-of-plane anchorage issue (discussed previously), diaphragm load path connections and the design of collector elements. 1.2 Objectives and Scope The objective of this report is to provide a detailed explanation of the evaluation and analysis of an existing masonry building and the procedures used to design upgrades to identified structural deficiencies. The analyses and upgrade designs presented herein focus on elements of the masonry structure that are common to many masonry buildings throughout California. The procedures described in this report are intended to act as an example of common practices used in the evaluation of existing masonry buildings. A seismic evaluation of an existing building begins with a “Screening Phase” as explained in Chapters 2 and 3 of ASCE 31 (2003). The screening phase begins with a review of any available as-built drawings followed by a site visit intended to verify existing data, collect additional data, and asses the general condition of the building. Checklists prescribed by ASCE 4 31 (2003), Table 3-2, assist in the identification of potential deficiencies. Necessary checklists are identified based on the desired level of performance, the level of seismicity, and the building type. The specific checklists used in this report are discussed in Section 2.3 of this report. The desired level of performance will determine seismic demand as a percentage of the Maximum Considered Earthquake (MCE) and is determined by the building owner in consultation with the design professional and the local authority having jurisdiction. Typical levels of performance used in the evaluation of existing buildings include Life Safety (LS) and Immediate Occupancy (IO), both of which are defined in detail in Section 1.5 of FEMA (2000). The performance level used in the evaluation of the building discussed in this report is defined in Section 2.1 of this report. The level of seismicity is based on mapped response acceleration values and site amplification factors, which are discussed in detail in Section 2.2 of this report. The building type is based on the lateral-force-resisting system and the diaphragm type as defined by Table 2-2 of ASCE 31-03. The building type for the evaluation presented in this report is discussed in detail in Section 2.1 of this report. Once potential deficiencies have been identified, further analysis is performed during an “Evaluation Phase” as described in Chapter 4 of ASCE 31-03. The analysis includes calculating lateral forces to be distributed to lateral force resisting systems, calculating diaphragm forces, and calculating forces in individual components of the lateral force resisting system. For this building the diaphragm, the load path, and two special conditions are analyzed. The diaphragm is analyzed for shear capacity and diaphragm components, which include chords and ties, are analyzed for tensile capacity. The load path is analyzed to determine forces acting on out-of-plane connecting elements as well as in-plane connecting elements and shear walls. Two special conditions are analyzed at locations that were identified as deficiencies but are not typical. 5 1.3 Organization and Outline Chapter 2 contains a description of the structure including identification of relevant structural systems. Drawings of the structure were prepared based on as-built information. Onsite observations are presented in this chapter along with a discussion of relevant structural information, such as shear walls and diaphragms. Site hazards, design requirements, and identified deficiencies are also discussed. Chapter 3 presents the seismic retrofit approach and applicable analyses on the diaphragm including the diaphragm shear capacities, chord (collector) capacities, and continuous cross-tie capacities. Detailed drawings of possible upgrade measures at typical locations are presented. Chapter 4 presents the approach and results of an analysis of the load path from the diaphragm to the foundation. The load path analysis considers the capacities of out-of-plane lateral force resisting elements, in-plane lateral force resisting elements, and shear walls. Detailed drawings of recommended seismic upgrades are presented and discussed. Chapter 5 presents the approach and results of an analysis of atypical conditions identified as potential deficiencies. The first special condition was a drag element constructed of a steel wide flange girder. The second special condition analyzed was a location where trusses are resting soley on a ledger, rather than the masonry shear wall. Detailed drawings of recommended seismic upgrades are presented and discussed to mitigate these atypical conditions. 6 CHAPTER 2 STRUCTURAL OVERVIEW AND DESCRIPTIVE EVALUATION The structure evaluated in this report is a religious meetinghouse located in Fremont, CA. The building is approximately 21,000 square feet and constructed primarily of reinforced, partially grouted Concrete Masonry Units (CMU) with a flexible wood diaphragm. Built in 1956, the structure has had two major additions in the years 1961 and 1969. The structure is primarily one story, but does have a small section of second story over the foyer area. Figure 2.1 illustrates a three-dimensional view of the building created from as-built plans and on-site observations. Figure 2.1: Three-dimensional Schematic View of Religious Meetinghouse in Fremont, CA 2.1 Lateral Load Resisting System Archive drawings of the original construction and site visits were used to obtain an accurate evaluation of the building and its load resisting systems (vertical and lateral). The tables and figures presented in this subsection provide some of the information acquired. Figure 2.2 illustrates a floor plan of the structure. Understanding the wall layout including door and window locations is critical for determining seismic weights and load path, which are discussed in the later chapters. 7 Figure 2.2: Architectural Floor Plan Figure 2.3 illustrates the roof plan of the building. The high roof areas are identified with darker lines in order distinguish between the high roof diaphragm and the low roof diaphragm which are not continuous. Figure 2.3: Roof Plan Tables 2.1 and 2.2 describe the structural components of the building. Structural components of the walls and roof systems are described. This information is critical for proper analysis of the diaphragm and load path. 8 Table 2.1: Structural Components at High Roof Areas Horizontal Elements Sheathing: Diagonal 1x8 sheathing Joists: 2x8 wood joists at 24” o.c. Purlins: None Beams: 4x10 wood beams Roof Girders: 16” wide flange girders Truss Type 1: 2x truss with split ring connections Truss Type 2: 2x truss with split ring connections Truss Type 3: 2x truss with split ring connections Floors Type: 4” concrete slab on grad Vertical Elements Columns: Pipe and reinforced concrete columns Walls: Partially grouted reinforced masonry block Column Foundations: Concrete square footings Wall Foundations: Concrete strip footings *D-Structural Drawings, FO-Field Observation, T-Testing Source* D, FO D, FO D, FO D, FO D, FO D, FO D, FO D, FO D D, FO D, FO, T D D Table 2.2: Structural Components at Low Roof Areas Horizontal Elements Sheathing: Unblocked plywood sheathing Joists: 2x6 wood joists at 24” o.c. Roof Purlins: None Beams: 4x10 wood beams Floors Type: 4” concrete slab on grad Vertical Elements Columns: Wood, pipe, and reinforced concrete columns Walls: Partially grouted reinforced masonry block Column Foundations: Concrete square footings Wall Foundations: Concrete strip footings *D-Structural Drawings, FO-Field Observation, T-Testing Source* D, FO D, FO D, FO D, FO D D, FO D, FO, T D D Based on the data collected and presented in this subsection, the building type has been determined to be an RM1 (reinforced masonry bearing walls with flexible diaphragms) as defined in Table 2-2 of ASCE 31 (2003). This determination is based on a lateral force resisting system consisting of reinforced, partially grouted, Concrete Masonry Units (CMU) and a diaphragm consisting of diagonal wood sheathing and plywood sheathing, which are flexible relative to the 9 walls. The RM1 building type identification will assist in determining which structural checklists are required to be used in the identification of potential deficiencies. Structural checklists are discussed further in Section 2.3 of this report. 2.2 Site Hazards and Design Requirements An understanding of the natural hazards specific to the site at which the building is located is essential for an accurate evaluation of the structure. Soil conditions, seismic hazards, and windstorm characteristics all effect the structural evaluation and design requirements of a building. The tables presented in this section identify the natural hazards specific to the site in question. Table 2.3 contains the soils information that applies to this site. Site classifications range from A to F (A being hard rock and F being very plastic clay) and are determined based on the average soil properties for the top 100 feet of soil. In the absence of a soils report, the site class is assumed to be Class D as prescribed in ASCE 31 (2003), Section 3.5.2.3.1. Class D sites have a shear wave velocity between 600 ft/sec and 1200 ft/sec. Shear wave velocity is the velocity at which shear waves are able to be transmitted through the soil and range from less than 600 ft/sec to as high as 5,000 ft/sec. Lower shear wave velocity values are associated with softer soils which amplify ground shaking. Ground shaking is the primary cause of damage to man-made structures and geologists have observed that areas with soft soils tend to repeatedly experience the most damage to structures. An example of a soft soil area is San Francisco where some neighborhoods repeatedly experienced significant damage in both the 1906 and 1989 earthquakes. The United States Geologic Survey (USGS) describes site Class D as consisting of “some Quaternary muds (less than 1.8 million years old), sands, gravels, silts, and mud. Significant amplification of shaking by these soils is generally expected.” 10 Table 2.3: Soils Information at Site Under Consideration Description: Stiff soil Shear wave velocity: 600 ft/sec < Vs < 1200 ft/sec Site class: D (assumed per ASCE 31-03, section 3.5.2.3.1) Soil stability: Stiff soil Reference: ASCE 31-03, section 3.5.2.3.1 Comments: A soils investigation was not available for this site. Site class D is assumed as per ASCE 31 (2003), section 3.5.2.3.1. The above description and shear wave velocity range are those relating to the assumed site class D. Table 2.4 contains the seismic hazard information relating to the building evaluated in this report. The seismic hazard is based on the Risk-targeted Maximum Considered Earthquake (MCER) ground motion response acceleration values for a short-period of 0.2 seconds and a longperiod of 1.0 second. General MCER values are determined as prescribed in Section 11.4.3 of ASCE 7 (2010) and site specific MCER values are determined as prescribed in Sections 21.1 and 21.2. MCER values can also be determined using the USGS Ground Motion Parameter Software (2014). The MCER ground motion response acceleration values are significant because they will be used to determine the seismic response coefficient (discussed further in Section 3.1 of this report) which will be multiplied by the seismic weight to determine design base shear values. Higher MCER values will result in higher design base shear values. A site visit and any other resources available determine site-specific vulnerabilities. In this case, vulnerabilities were determined by researching data available through the Association of Bay Area Governments, Earthquake and Hazards Program (2014). Fault rupture is a brittle fracture at the ground surface and can be a complex phenomenon to predict (typically predicted by experienced geologists). Fault ruptures can cause significant damage due to differential displacements in the foundation. Slope failures include a wide range of landslides or landslips. Potential for slope failures can be determined by site observations and consulting with an experienced geologist. Slope failures pose a significant risk to structures due to displacement of 11 soils under the foundation and/or impact from nearby landslides. The distance to the nearest fault can be determined using the USGS Quaternary Faults Web Mapping Application referenced below. Site proximity to faults increases the risk of significant ground motion during a seismic event which can result in an increase in structural damage to structures. Table 2.4: Seismic Hazard Information Hazard Spectral Acceleration1 Vulnerability2 0.2 sec period: 1.0 sec period: Fault rupture: Slope failure: Liquefaction: MCER 2.499 g 0.953 g None None High risk 1.27 miles Distance to Nearest Fault3 References: 1. ASCE 7 (2010), Section 11.4 2. Association of Bay Area Governments, Earthquake and Hazards Program (2014) 3. USGS Quaternary Faults Web Mapping Application (20140 Table 2.5 contains windstorm characterization information relating the building evaluated in this report. The design wind speed is determined by the local authority having jurisdiction and the site exposure is determined based on ground surface roughness that is determined by considering natural topography, vegetation, and constructed facilities. A site surrounded by tall vegetation, buildings, and topography will deflect wind and reduce the design wind values applied to the building. It is important to consider whether wind forces or seismic forces will govern the evaluation and upgrade design of a facility in order to ensure adequate resistance to the governing lateral force. In this case the building consists of heavy partially grouted masonry walls and most of the building is relatively short compared to surrounding buildings. Due to the high seismic weight of the structure, low design wind speed, and high ground surface roughness, it was determined that seismic forces will govern 12 the analysis and design of upgrades to the lateral force resisting system of the building evaluated in this report. Table 2.5: Windstorm Characterization Parameter Wind speed (mph)1: Site exposure category: Site exposure description: Description 85 B Terrain with buildings, forest or surface irregularities 20 feet or more in height covering at least 20% of the area, extending one mile or more from the site. References: 1. City of Fremont 2.3 Identified Deficiencies The seismic deficiencies identified using ASCE 31 (2003) and structural calculations addressed in this report are listed in Table 2.6, and the locations of identified deficiencies are illustrated in Figure 2.5. The significance of each deficiency is discussed in this section in the same order listed in Table 2.6 and the upgrade design of the deficiencies are discussed in Chapters 3, 4, and 5 of this report. Deficiency S-1 is a major collector with a partially failed connection at one end. The collector transfers shear forces from one shear wall to another. If the collector fails completely, lateral forces will not be shared between shear walls and may result in one of the shear walls being overstressed. The collector is also acting as a major girder and holds up 4.5’ of roof trusses. If the connection were to fail completely, the trusses resting on the girder would be unsupported at one end and would result in a collapse of the roof system. Although gravity forces are unlikely to fail the connection completely, lateral forces resulting from a seismic event may 13 cause the partially failed connection to fail completely resulting in a major collapse of the high roof section of the building. Deficiency S-2 is a lack of in-plane force transfer elements between the diaphragm and the shear walls. If the shear forces in the diaphragm are not transferred to the shear walls through in-plane connection elements, the diaphragm may shear away from the tops of the walls resulting in localized failures. As localized failures are compounded they may result in major failures due to improperly supported walls. Deficiency S-3 is a lack of sufficient out-of-plane wall anchorage from the diaphragm to the tops of masonry shear walls. A lack of adequate out-of-plane wall anchorage may result in the tops of masonry walls detaching from the diaphragm and deflecting toward the inside or outside of the building. This type of deflection may result in collapse of masonry walls and possible the collapse of the roof system Out-of-plane anchorage failures is one of the most common types of failure according the Preliminary Survey of Damage to the Commercial District referenced at the end of this report. Deficiency S-4 is a lack of continuity in cross diaphragm cross ties. The tops of parallel shear walls are supported by the continuity of cross tie members which develop out-of-plane forces into the diaphragm. Cross tie members in flexible wood diaphragms typically consist of 2x wood members incorporated into the trusses and joists of the roof system. Lateral forces can cause separation to occur at discontinuities in cross ties resulting in a weekend diaphragm. Discontinuities were identified at ridge locations and at locations where outriggers at gabled ends meet perpendicular to trusses or joists. These connections are typically performed using toenails or hangers, which are not designed to transfer lateral forces. Deficiency S-5 is the lack of seismic strapping at diaphragm re-entrant corners. Tension forces in chords can be concentrated at re-entrant corners. Without seismic strapping to develop 14 chord forces into the diaphragm, separation of the diaphragm and perpendicular shear walls may occur as illustrated in Figure 2.4. Figure 2.4: Re-entrant Corner Failure [from ASCE 31 (2003)] Deficiency S-6 is the insufficient capacity of the wood diaphragm. The diagonal 1x sheathing and the unblocked plywood sheathing do not have sufficient shear capacity in multiple locations. The diaphragm distributes lateral forces to lateral force resisting shear walls. Shear failure of the diaphragm can reduce the structure’s ability distribute lateral forces adequately. Deficiency S-7 is the discontinuity of diaphragm chords. Diaphragm chords consist of horizontal reinforcement in shear walls used to resist tensile forces induced when the flexible diaphragm deflects. Discontinuities in diaphragm chords exist at gabled ends and at entry ways. Discontinuities in diaphragm chords may result in separation of shear walls due to inadequate tensile capacities. The ASCE 31 (2003) checklists used in this evaluation identified other non-structural deficiencies that will not be discussed in this report. It is important to recognize, however, that a complete evaluation of a building per ASCE 31 (2003) may include a significant number of nonstructural deficiencies. For additional information on typical nonstructural seismic deficiencies, see the non-structural checklists in Section 3.7 of ASCE 31 (2003). 15 Table 2.6: Identified Deficiencies Illustrated in Figure 2.5 No. S-1 S-2 S-3 S-4 S-5 Item 16” wide flange girder: Shear transfer: Out-of-plane anchorage: Cross ties: Description The 16” wide flange girder between the chapel and cultural hall has broken loose from the wall at the north end Load path does not exist to transfer diaphragm shear to interior or exterior shear walls Out-of-plane wall anchors are insufficient or do not exist Type* EQ, G Continuous cross ties are missing or are insufficient to transfer out-of-plane anchorage loads into the diaphragm Strapping has not been provided at re-entrant corners EQ Re-entrant corners: S-6 Wood The capacity of the unblocked roof sheathing is not adequate diaphragms: to resist seismic forces S-7 Diaphragm Some diaphragm chords are not continuous at breaks in chords: walls *EQ-Earthquake deficiency, G-Gravity deficiency Figure 2.5: Locations of Deficiencies Listed in Table 2.6 EQ EQ EQ EQ EQ 16 CHAPTER 3 FLEXIBLE WOOD DIAPHRAGM AND ASSOCIATED COMPONENTS The building uses a flexible wood diaphragm to distribute seismic forces to vertical lateral-force-resisting elements. The diaphragm is flexible and consists of two different wood systems. At the low roof areas, the diaphragm system consists of unblocked ½” plywood sheathing. At the high roof areas, the diaphragm system consists of unblocked 1x8(nominal) diagonal sheathing. Flexible diaphragms are typically analyzed using a beam analogy. The sheathing is treated like the web of a wide flange beam and the chords are treated like the flanges. Figure 3.1 shows the free-body diagram typically used for diaphragm analysis. The “load” shown in Figure 3.1 represents the lateral earthquake force and “v” represents the resulting base shear at the shear walls resisting the seismic force. Figure 3.1 demonstrates how shear forces are developed in “web” or diaphragm of the building while tension and compression forces are developed in the “chords”. Figure 3.1: Free-body Diagram of Forces Acting on Diaphragm and Diaphragm Components 17 3.1 Diaphragm Shear Forces The diaphragm upgrade design is performed by dividing the diaphragm into boxes and analyzing each box individually while taking to account any shared seismic weights at box boundaries and shared resulting values such as diaphragm shear and chord forces. Box boundaries should lie on shear walls and length to width aspect ratios of boxes should not exceed those prescribed in Table 4.2.4 of the American Wood Council’s Special Design Provisions for Wind and Seismic referenced at the end of this report. Grid lines are also defined at box boundaries in order to assist in evaluating the capacities of lines of shear walls that span multiple boxes. In this analysis, the diaphragm was divided up into boxes as demonstrated in Figure 3.2. Figure 3.2: Layout Box and Grid Line Assignments for Diaphragm Analysis 18 To analyze the diaphragm of each box illustrated in Figure 3.2, the seismic base shear is calculated with Equations 3.1-3.4 below. π = πΆπ π Eq. 3.1 Where W is the seismic weight tributary to the diaphragm of each box, taken as the unfactored dead load for this structure, and ranging from 4 – 35 kips. The seismic response coefficient, Cs, is calculated using the following equations from section 12.8.1.1 of ASCE 7 (2010) – πΆπ = ππ·π π πΌπ ( ) Eq. 3.2 Where SDS is the design spectral response acceleration parameter in the short period range and is equal to 1.28g for this site. The response modification factor, R, is equal to 3.5 for this retrofit and the importance factor, I = 1.25. Furthermore, the value of Cs is not required to be greater than – πΆπ = ππ·1 π πΌπ π( ) Eq. 3.3 Where SD1 = 0.74g is the design spectra response acceleration parameter at a period of 1.0 second and T = 0.19s is the fundamental period of the structure. Finally, the response coefficient must be greater than – πΆπ = 0.044ππ·π πΌπ ≥ 0.01 Eq. 3.4 Since the structure is one story, the base shear is also equal to the diaphragm shear force. The diaphragm shear force of each box was compared to the nominal unit shear capacities, which are found in Table 4.2A, 4.2B, 4.2C, and 4.2D of AWC (2008), of the diaphragm at that box to determine which areas of the diaphragm need to be upgraded. Table 3.1 compares the seismic demand applied to the diaphragm, Vdiaphragm, and the nominal shear capacity, Vcapacity, at grid lines for each section of Figure 3.2 where there was a shear capacity deficiency. 19 The analysis of the existing diaphragm determined that the diagonal straight 1x8 sheathing should have ½” plywood sheathing added on top of it. All of the high roof and much of the low roof diaphragm also required blocking. Adding blocking to plywood edges increases the shear capacity of the diaphragm and is typically needed at locations where diaphragm shear forces are concentrated such as at major shear walls. Often blocking is required at major shear walls but is not needed further away from major shear walls because diaphragm shear forces are distributed throughout the diaphragm as they move further away from locations of high concentrations. Figure 3.3 identifies areas of the diaphragm that would need to be upgraded by adding plywood sheathing and blocking to plywood panel edges (indicated in blue) or simply by adding blocking to the existing plywood (indicated in red). 20 Table 3.1: Diaphragm Seismic Demands, As-built Capacity and Retrofit Strategy Box Grids Box A Box B Box C 1, 2 2, 3 3, 5 A, C 7, 10 D, E 2, 3 D, E D, E C, E 7, 10 2, 3 3, 5 E, G 5, 8 8, 12 E, G 6, 9 G, H Box E Box G Box H Box I Box J Box K Box L Box M Box N Box O Vdiaphragm (lb/ft) 369 413 491 132 1030 424 298 346 435 663 318 427 510 525 406 705 292 1914 361 Vcapacity (lb/ft ) 255 255 255 100 100 255 255 255 255 100 100 255 255 100 100 100 100 255 255 Retrofit Strategy Add blocking Add blocking Add blocking Add plywood and blocking Add plywood and blocking Add blocking Add blocking Add blocking Add blocking Add plywood and blocking Add plywood and blocking Add blocking Add blocking Add plywood and blocking Add plywood and blocking Add plywood and blocking Add plywood and blocking Add blocking Add blocking Figure 3.3: Diaphragm seismic upgrade illustrating deficient areas retrofitted with blocking or plywood sheathing 21 3.2 Tensile Capacity of Diaphragm Chords Chords are a diaphragm boundary element designed to resist the tension or compression resulting from the diaphragm moment created as the flexible diaphragm deflects between shear walls. Chords must be designed to resist both tensile forces and compressive forces. As mentioned previously, chords can be analyzed in a manner similar to the flanges of a simply supported wide flange beam with a uniformly distributed load. Figure 3.4, from Hsiao and Tezcan (2012), illustrates how chords correspond to the flanges of a wide flange beam. Figure 3.4: Chord Force Illustration [from Hsiao and Tezcan, 2012] The maximum bending moment occurring at the midspan of the diaphragm can be 2 calculated as π€π ⁄8, where w is the distributed seismic load and l is the unsupported length. 22 From this, the chord force is the bending moment divided by the distance between the tension and 2 compression chord, π€π ⁄8π. The chords of many older masonry building do not have adequate capacity to resist the tensile and compressive forces experienced during a seismic event. Inadequate chord capacities can result tension cracks in the masonry as illustrated in Figure 3.5. Figure 3.5: Chord Failure [from Hsiao and Tezcan, 2012] The Handbook for the Seismic Rehabilitation of Existing Buildings published by the Federal Emergency Management Agency (1992) provides details for common chord reinforcement techniques as illustrated in Figure 3.6. In this detail, a continuous steel angle us bolted to the masonry shear wall at the diaphragm in order to increase the tensile capacity of the chord. Steel straps are welded to the angel and nailed to blocking under the plywood sheathing in order develop out-of-plane forces in to diaphragm. 23 Figure 3.6: Chord Retrofit Strategy [adapted from FEMA 1992] The allowable tensile strength for yielding of steel chord reinforcing elements can be calculated as demonstrated Equation 3.8 from the American Institute of Steel Construction (2011). ππππππ€ππππ = πΉπ¦ π΄π Ωπ‘ Eq. 3.5 Where Fy is the specified minimum yield stress of the steel element, typically 40 ksi for rebar, Ag is the gross area of steel cross section, and Ωt is is the safety factor, 1.67 for limit states involving yielding. The allowable compressive strength of the masonry wall that will resist compressive chord forces can be calculated using Equation 3.9 from the Building Code Requirements for Masonry Structures. πΉπππππ€ππππ = 2 π′π β −( ) ] [1 4 140π πππ β π ≤ 99 Eq. 3.6 24 Where f’m is the compressive strength of the masonry, typically 1,500 psi for normal weight CMU block, h is the effective laterally unsupported length of the wall, and r is the radius of gyration of the wall The chords in the building evaluated in this report consist of horizontal reinforcement running along the tops of masonry walls. At 12” masonry walls the horizontal chord reinforcement consists of 4 #5 rebar, at 8” masonry walls the horizontal chord reinforcement consists of 4 #4 rebar, and at 6” masonry walls the horizontal chord reinforcement consists of 2 #4 rebar. Although the existing chords were not identified as potential deficiencies during the evaluation of the structure due to tension or compression resisting capacities, the chords were found to be discontinuous at multiple locations including gabled ends and building entryways. Discontinuities in chords are common and should be considered during site visits. Discontinuities can be corrected by adding reinforcement as illustrated in Figure 3.6 at locations where breaks in the chords exist. Figure 3.7 illustrates the locations where chord discontinuities were observed and Table 3.2 summarizes the chord forces at discontinuous locations and retrofit strategies are listed based on Simpson Strong-tie published capacities. Table 3.2: Chord Retrofit Strategies Identified in Figure 3.7 Chord C1 C2 C3 C4 C5 C6 C7 Chord Force (lbs) 773 659 13645 1202 3704 12425 9391 Retrofit Capacity (lbs) 845 845 18430 12980 4585 12980 12980 Retrofit strategy (1) Simpson CS22 Strap (1) Simpson CS22 Strap (2) Simpson CMST12 Straps (2) Simpson CMST14 Straps (1) Simpaon CMSTC16 Strap (2) Simpson CMST14 Straps (2) Simpson CMST14 Straps 25 Figure 3.7: Location of Chord Discontinuities Summarized in Table 3.2 3.3 Tensile Capacity of Continuous Cross Ties Diaphragms are required to be provided with tension ties between the chords that develop out-of-plane forces into the diaphragm. Figure 3.8 illustrates a simplified example of how cross ties are typically oriented in a building. 26 Figure 3.8: Cross Ties Example [from ASCE 31 (2003)] If cross ties are not continuous, the tension in the ties will be concentrated into the flexible diaphragm at the location of the discontinuity which could result in a separation of the diaphragm at that point and a decrease in out-of-plane support for the masonry walls. Ties must be designed to resist an axial tension determined by the following equation. πΉπ = 0.4ππ·π π Eq. 3.7 Where Fp is the axial tension the tie must be designed to resist, SDS=1.28 is the spectral response acceleration, and W is the seismic weight tributary to tie. The diaphragm ties for the building evaluated in this report consist of 2x wood members. Although the ties were determined to have the capacity necessary to resist tensile forces, the ties are not continuous at multiple locations. Discontinuities in cross ties are commonly found at locations where outriggers attach to roof trusses along gabled ends and at diaphragm ridges. In order to reinforce the ties and make them continuous, seismic strapping with the capacity to resist the same tensile forces are added to 27 the ties. It was determined from out-of-plan anchorage calculations summarized in Table 4.1 that the highest out-of-plane force that the cross ties will be required to transfer is 2005lbs. It is recommended that all straps used to make cross ties continues be Simpson CS14 straps with a 2ft end length. Simpson CS14 straps have a tensile capacity of 2490lbs and will be adequate in all locations. Figure 3.9 illustrates a location where a discontinuity in the cross tie exists and details how the discontinuity could be upgraded using a seismic strap on top of the plywood sheathing. Out-of-plane anchorage is also detailed to support the tops of masonry walls. Figure 3.9: Detail of Continuous Cross Tie Retrofit Strategy Figures 3.10 and 3.11 identify the locations on the low roof and high roof where seismic strapping is needed to make the existing cross ties continuous. The seismic straps would be installed on top of the diaphragm over joists, truss top chords, and/or blocking as demonstrated in Figure 3.9. 28 Figure 3.10: Plan Showing Low Roof Continuous Cross Tie and Chord Reinforcement Locations Figure 3.11: Plan Showing High Roof Continuous Cross Tie and Chord Reinforcement Locations 29 CHAPTER 4 DIAPHRAGM TO SHEAR WALL LOAD TRANSFER ELEMENTS Seismic forces must be transferred from the diaphragm to the shear walls in all directions. To ensure that load transfer elements can resist seismic forces in principle directions, the elements are analyzed for out-of-plane forces as well as in-plane forces. 4.1 Out-of-plane Force Resisting Elements Out-of-plane anchorage is a very common deficiency in many masonry buildings and is a common location where failures can occur during seismic events. When proper out-of-lane anchorage does not exist, masonry walls can separate from the diaphragm resulting in a loss of support at the top of the wall which could lead to a collapse of the wall as illustrated in Figure 4.1. Figure 4.1: Out-of-plane Anchorage Failure [from Hsiao and Tezcan 2012] When out-of-plane anchorage fails the masonry wall is deflected by seismic forces in a cantilevered fashion and excessive stresses result at the fixed end of the wall near the foundation. Figure 4.2 is the result of an out-of-plane pushover analysis performed on a masonry wall of a 30 synagogue in San Francisco. The red shown in the figure are areas of high stress which are most likely to experience cracking during a seismic event do to the loss of out-of-plane anchorage at the top of the wall. Figure 4.2: Results of Out-of-plane Pushover Analysis on Masonry Wall [from Paret, Freeman, Searer, Hachem, and Gilmartin, 2007] This section presents the design of the out-of-plane upgrade using ASCE 7-10, section 12.11.2.1. The out-of-plane force is calculated using the following equation: πΉπ = 0.4ππ·π ππ πΌπ ππ Eq. 4.1 Where Fp is the design force in the individual anchors and SDS=1.28 and is the design spectral response acceleration parameter at short periods. ka = 1.0 + Lf/100 where Lf is the span in feet of a flexible diaphragm that provides the lateral support for the wall, Ie=1.25 and is the seismic importance factor, and Wp is the weight of the wall tributary to the anchor. The out-of-plane anchorage force is calculated for three different scenarios: high 12” masonry wall, low 8” masonry wall, and low 6” masonry wall. The following figure presents the wall types that the out-of-plane force connections are designed to resist using an anchor spacing of 2ft on center. Wall weights are listed and identified by color. Wall weights at box boundaries 31 as well as partitions within boxes contribute to the seismic weight that the load path must be designed to resist. Figure 4.3: Layout of Walls and Associated Seismic Weights The out-of-plane anchorage forces at the top of walls are resisted by bolting a large steel angle to the side of the truss using through bolts and one threaded rod epoxied into to the top of the wall. At the face of the wall, the out-of-plane forces are resisted using a horizontal installation of a Simpson HTT or similar hardware. Table 4.1 summarizes out-of-plane forces at typical walls. The anchors are recommended to be installed at every truss or joist so the calculations summarized in Table 4.1 are based on a 2ft anchor spacing. The ¾” rod and HTT4 capacities are based on an installation using Simpson SET Epoxy. 32 Table 4.1: Summary of Out-of-plane Anchorage Retrofit Strategy Wall Type 12" CMU Top 12" CMU Face 8" CMU Top 6" CMU Top Wall Height (ft) 18 14 9 9 Total Weight (psf) 124 124 71 55 Out-ofplane force (lbs/2ft) 2005 1559 898 898 Anchor Capacity (lbs) 2710 3610 1355 1355 Upgrade Anchor Type (2) 3/4" Rods HTT4 (1) 3/4" Rod (1) 3/4" Rod Figure 4.2 is a detail of out-of-plane anchorage attaching diaphragm cross ties to the face of a CMU wall. This detail applies to locations where the roof joists are perpendicular to the wall. Figure 4.4: Detail of Out-of-plane Anchorage Retrofit Strategy at Face of Perpendicular Masonry Wall Figure 4.3 is a detail of out-of-plane anchorage attaching the diaphragm to the face of a CMU wall using blocking and a Simpson HTT. This detail applies to locations where the roof joists are parallel to the wall. 33 Figure 4.5: Detail of Out-of-plane Anchorage Retrofit Strategy at Face of Parallel Masonry Wall Out-of-plane anchorage is also required at interior non-loadbearing CMU walls. Figures 4.4 and 4.5 are details of out-of-plane anchorage at interior CMU partitions. Figure 4.4 is detailed for locations where the partition is parallel to joists and/or trusses. Figure 4.5 is detailed for locations where the partition is perpendicular to joists and/or trusses. Figure 4.6: Detail of Out-of-plane Anchorage Retrofit Strategy at Top of Parallel CMU Partition 34 Figure 4.7: Detail of Out-of-plane Anchorage Retrofit Strategy at Top of Perpendicular CMU Partition Additional out-of-plane conditions are detailed in conjunction with in-plane shear transfer elements detailed in subsection 4.2. 4.2 In-plane Force Resisting Elements Shear forces are required to be transferred from the diaphragm to the shear walls. If shear forces are not transferred to shear walls the flexible diaphragm may break loose from the shear walls thus preventing diaphragm shear forces to be transferred into the lateral force resisting shear walls. Loss of this type of connection can result in localized failures of the diaphragm and possibly collapse of masonry walls. The minimum shear force that needs to be resisted by shear transfer elements at diaphragm boundaries is calculated by the lesser of the following equations. ππ = 1.25ππ·1 πΆπ ππ Eq. 4.7 ππ = π£π’ π· Eq. 4.8 35 Where SD1=0.74 and is the design spectral response acceleration parameter, Wd is the total seismic dead load tributary to the diaphragm, vu is the unit shear strength of diaphragm, D is the depth of diaphragm, and Cp is the horizontal force factor (0.50 for straight or diagonal sheathing and tongue and groove decking, 0.75 for blocked panels or multiple panel systems). Shear forces are transferred at the top of walls using full height blocking, boundary nailing, and Simpson A35 and HGA10 framing clips. Figure 4.6 details in-plane shear transfer elements in conjunction with out-of-plane anchorage at joist locations at exterior walls. The in-plane load path is plywood diaphragm to boundary nailing to full height blocking to Simpson framing clip to top of shear wall. The out-ofplane anchorage load path is cross tie (joist) to through bolts to steel angle to epoxy anchor at top of shear wall. Figure 4.8: Detail of In-plane and Out-of-plane Anchorage Retrofit Strategy at Joists 36 Figure 4.7 is a condition similar to figure 3.6 but involves a truss heal at high roof locations. The in-plane and out-of-plane load paths are the same as those of figure 4.6. The truss heal connection is a split ring connection and many of the connections are splitting. Plywood gusset reinforcement has been detailed at the truss heals in addition to the in-plane and out-ofplane anchorage. Seismic strapping has also been detailed to act as chord reinforcement at gabled ends where the chord (reinforced bond beam) is not continuous. Plywood sheathing has also been detailed to be added on top of the 1x8 diagonal sheathing. Figure 4.9: Detail of In-plane and Out-of-plane Anchorage Retrofit Strategy at Truss 4.3 Masonry Shear Wall Capacities Masonry shear walls are the vertical elements of the lateral force resisting system and are essential for keeping the building from tipping over during a seismic event. If masonry shear walls are overstressed, concentrations of shear stresses can build up at door and window openings 37 as illustrated in Figure 4.10. This figure is the result of an in-plane pushover analysis performed on a masonry synagogue in San Francisco. Areas indicated in red are locations of concentrated stresses which may result in cracking of the masonry. Figure 4.10: Results of In-plane Pushover Analysis for Masonry Wall [from Paret, Freeman, Searer, Hachem, and Gilmartin, 2007] In order to identify potential shear wall deficiencies, preliminary calculations were performed according to section 3.5.3.3 of ASCE 31 (2003). The average stress in shear walls was calculated using the following equation. ππ£π π£π = 1 ππ ( ) π π΄π€ Eq. 4.9 Where Vj is the story shear at level j, Aw is the summation of the horizontal crosssectional area of the shear walls in the direction of loading, and m is the component modification factor. The locations and compositions of shear walls are presented in the following figure. 38 Figure 4.11: Plan Identifying Shear Walls and Associated Weights and Equivalent Thicknesses Although preliminary calculations did not identify any of the shear walls as potential deficiencies, during the site visit it was observed that some of the shear walls were not continuous through the attic space to the diaphragm. Table 4.2 summarizes the analysis of the shear walls indicating that all shear walls are sufficient. The following figure details a potential upgrade measure to a discontinuous shear wall. Out-of-plane anchorage is detailed in addition to the discontinuous shear wall detail. 39 Table 4.2: Summary of Shear Wall Stresses Grids 1 Low 10 High 10 Low 11 Low 12 High 2 Low 3 Low 4 Low 5 High 5 Low 6 High 7 High 7 Low 8 High 9 High A High B Low C High D Low E High E Low F Low G High H High Base Shear (kips) 76.0 574.5 41.6 44.9 311.9 379.8 479.0 125.4 186.9 323.4 112.6 419.5 138.9 317.2 112.6 266.3 343.2 443.3 547.3 681.8 447.5 187.2 664.0 186.4 Equivalent Solid Thickness Wall (in) 4.6 6.5 4.6 4.6 6.5 4.6 4.6 4.6 6.5 4.6 6.5 6.5 4.6 6.5 6.5 6.5 4.6 6.5 4.6 4.6 6.5 4.6 4.6 4.6 Shear Stress (psi) 14.0 28.8 12.6 14.0 25.6 21.6 11.4 37.9 20.7 25.0 45.1 19.8 12.2 15.4 45.1 16.1 12.8 35.5 12.2 36.8 8.9 11.2 40.6 60.3 Allowable Stress Unity Check (psi) (Actual/Allow.) 70.0 0.20 70.0 0.41 70.0 0.18 70.0 0.20 70.0 0.37 70.0 0.31 70.0 0.16 70.0 0.54 70.0 0.30 70.0 0.36 70.0 0.64 70.0 0.28 70.0 0.17 70.0 0.22 70.0 0.64 70.0 0.23 70.0 0.18 70.0 0.51 70.0 0.17 70.0 0.53 70.0 0.13 70.0 0.16 70.0 0.58 70.0 0.86 40 Figure 4.12: Discontinuous Shear Wall Upgrade Detail 41 CHAPTER 5 SPECIAL CONDITIONS This chapter analyzes two special conditions that were identified as deficiencies during the site visit. The locations of the special conditions are identified in Figure 5.1. Figure 5.1: Plan Showing Locations of Special Conditions 5.1 Special Condition 1 The first special condition is a 21x62 steel wide flange girder. The girder was identified as a deficiency because the connection of the girder to the CMU wall at one end has broken loose. The girder is holding up 43.5ft of roof trusses and also acts as a collector to drag seismic forces into the CMU shear walls at each end. If the girder connection fails completely it could result in the collapse of the 43.5ft roof section resting on the girder at one end. The existing partial failure appears to be due to lateral forces possible from a past seismic event. A future seismic event 42 could cause the connection to fail completely suggesting that an upgrade of the connection from the wide flange collector to the shear wall is critical. The design of the wide flange girder is guided by section 12.10.2 of ASCE 7 (2010). The load combination applied at this condition is the following. (1.2 + 0.2ππ·π )π· + ΩπΈ ππΈ + 0.2π Eq. 4.1 Where SDS is the design spectral response acceleration parameter at short periods, D is the dead load tributary to the girder, ΩE the overstrength factor assigned in Table 12.2-1 of ASCEb7 (2010), QE is the effect of horizontal seismic forces. At this location QE is determined by the diaphragm shear force tributary to the wide flange collector at Grid Line E due to Box J and Box N which was determined to be 59.3 k. D is determined to be 0.475k per foot, SDS was determined to be 1.283, and ΩE was determined to be 2.5 from table 12.2-1 of ASCE 7 (2010). The girder was analyzed in Risa 3D and found to be adequate. The reaction force at each end of the girder was used to design a new connection from the girder/collector to the CMU wall. Figure 5.2 details the potential upgrade measure at the end of the beam that had the failed connection. The failed CMU wall is detailed to be removed and replaced with reinforced concrete and a ¼”x8” steel plate is used to drag the force from the collector into the CMU shear wall. Figure 5.3 details the connection at the un-failed end of the collector where a similar steel plate is used to drag the force from the wide flange into the CMU wall. 43 Figure 5.2: Detail of Special Condition 1 Retrofit Strategy at Failed Connection Figure 5.3: Detail of Special Condition 1 Retrofit Strategy at Un-failed Connection 5.2 Special Condition 2 The second special condition is a location were roof trusses are resting on a ledger. This condition was identified as a deficiency during the site visit due to a lack of out-of-plane anchorage. Without out-of-plane anchorage, a seismic event could cause lateral forces to shake the masonry wall and possibly cause the roof trusses to slip off of the ledger resulting in the 44 collapse of the roof section resting on the ledger. Due to the risk of caollapse during a seismic event, an upgrade at this location is considered critical. The out-of-plane design forces were determined in the manner describe in subsection 4.1. Elements intended to transfer in-plane shear forces are also design as described in subsection 4.2 and detailed below. The overstressed split ring connection at the truss heal is also detailed to be reinforced with plywood gussets. Figure 5.4 details the potential upgrade measures described for this condition. Figure 5.4: Detail of Special Condition 2 Retrofit Strategy 45 CHAPTER 6 SUMMARY This report follows a typical approach to analyzing and upgrading existing structures. Potential deficiencies were identified as directed in ASCE 31 (2003) by reviewing as-built drawings, performing site observations, and performing preliminary calculations. After potential deficiencies were identified, further analysis of deficient structural systems was performed using ASCE 7 (2010) and ASCE 41 (2006). The deficiencies identified in this report are typical for buildings constructed of CMU walls and flexible diaphragms. During seismic events, the most common failures occur at the connection from the walls to the diaphragm. The load path is often lacking sufficient strength to resist in-plane and out-of-plane forces. Cross ties often lack continuity resulting in separation of the diaphragm at discontinuities and diaphragms often lack proper shear capacity due to insufficient blocking. Upgrading weaknesses in structural systems reduces the risk of potential failure during a seismic event. When individual elements of a structure are prevented from failing, the redundancy of the system is maintained. 46 APPENDIX This appendix contains a summary of the spreadsheets used to perform the structural analysis. Base shears, diaphragm shears, and chord forces are summarized for the grid lines and boxes illustrated in figure 3.2. The information gathered for each box are also summarized. This appendix also contains a summary of the Risa 3D analysis performed at special condition 1. 47 Table A.1: Base Shear Summary Base Shear Summary Code Ref.: Current IBC/CBC SDS = 1.283 Cs = 0.458 R = 3.5 Ie = 1.25 Seismic Weight * Cs or Base Shear Diaphragm Level Grids High High High High High High High High High High High High High High High High High High High High Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low 5 6 7 7 8 8 9 10 10 12 A C C E E E G G G H 1 2 2 2 2 3 3 3 3 3 3 4 5 5 5 5 7 7 10 11 B B B B B D D D D D D D D E E E E E F F ASD Base Shear Along Grid kips 36 22 27 54 25 36 22 27 83 60 51 28 57 57 26 48 38 67 23 36 15 12 13 33 16 13 15 25 16 11 13 24 15 6 22 20 8 19 8 9 14 16 19 9 8 14 11 13 5 8 25 17 13 25 17 16 12 16 17 19 Box I.D. Box M Box O Box E Box J Box M Box N Box O Box E Box J Box N Box E Box E Box J Box J Box M Box N Box M Box N Box O Box O Box A Box A Box B Box G Box K Box B Box C Box G Box H Box K Box L Box H Box C Box D Box I Box L Box D Box I Box F Box F Box A Box B Box C Box D Box F Box A Box B Box C Box D Box F Box G Box H Box I Box G Box H Box I Box K Box L Box K Box L Length of Wall Along Grid (ft) 29.0 8.0 15.0 53.0 33.0 33.0 8.0 15.0 49.0 39.0 53.0 20.0 20.0 24.5 19.0 40.5 14.0 46.0 14.0 14.0 24.5 15.0 15.0 38.5 11.0 15.0 15.0 62.0 62.0 18.5 18.5 15.0 0.0 0.0 40.0 18.5 15.5 36.0 15.0 14.5 30.0 27.0 34.0 13.0 17.0 22.5 35.0 45.0 8.0 20.0 34.5 31.0 8.0 40.5 25.0 18.0 40.5 37.0 33.0 43.0 48 Table A.2: Diaphragm Shear Summary Di a phra gm Shea r Summa ry Code Ref.: Current IBC/CBC Di a phra gm Cs = 0.458 Di a phra gm Shea r * Cs Unbl ocked Di a phra gm Ca pa ci ti es (pl f): Wa l l s perp. to di recti on ASD of l oa d Di a ph. s hown Wei ght bel ow to Tri buta ry determi ne Di a phra gm to Box req'd bl k'g Level Gri ds Gri d Box I.D. di s ta nces (ki ps ) (ft) Hi gh 5 16 Box M 28.5 Hi gh 6 15 Box O 30 Hi gh 7 20 Box E 53 Hi gh 7 24 Box J 53 Hi gh 8 16 Box M 28.5 Hi gh 8 27 Box N 62 Hi gh 9 15 Box O 30 Hi gh 10 20 Box E 53 Hi gh 10 24 Box J 53 Hi gh 12 27 Box N 62 Hi gh A 7 Box E 19 Hi gh C 7 Box E 19 Hi gh C 35 Box J 75 Hi gh E 35 Box J 75 Hi gh E 15 Box M 39 Hi gh E 18 Box N 39 Hi gh G 15 Box M 39 Hi gh G 18 Box N 39 Hi gh G 11 Box O 8 Hi gh H 11 Box O 8 Low 1 9 Box A 42.5 Low 2 9 Box A 42.5 Low 2 10 Box B 51 Low 2 19 Box G 47.5 Low 2 10 Box K 51 Low 3 10 Box B 51 Low 3 12 Box C 59 Low 3 19 Box G 47.5 Low 3 10 Box H 39 Low 3 10 Box K 51 Low 3 12 Box L 59 Low 4 10 Box H 39 Low 5 12 Box C 59 Low 5 4 Box D 21 Low 5 8 Box I 29 Low 5 12 Box L 59 Low 7 4 Box D 21 Low 7 8 Box I 29 Low 10 4 Box F 20 Low 11 4 Box F 20 Low B 6 Box A 24.5 Low B 6 Box B 24.5 Low B 7 Box C 24.5 Low B 4 Box D 24.5 Low B 4 Box F 24.5 Low D 6 Box A 24.5 Low D 6 Box B 24.5 Low D 7 Box C 24.5 Low D 4 Box D 24.5 Low D 4 Box F 24.5 Low D 20 Box G 62.5 Low D 13 Box H 62.5 Low D 13 Box I 66 Low E 20 Box G 62.5 Low E 13 Box H 62.5 Low E 13 Box I 66 Low E 6 Box K 24.5 Low E 7 Box L 24.5 Low F 6 Box K 24.5 Low F 7 Box L 24.5 ASD Shea r Loa d Al ong Gri d (pl f) 405.6 1913.7 1029.8 317.6 405.6 704.7 1913.7 1029.8 317.6 704.7 132.2 132.2 662.7 662.7 524.7 292.3 524.7 292.3 361.2 361.2 369.2 369.2 413.2 298.5 427.0 413.2 491.4 298.5 158.6 427.0 509.7 158.6 491.4 148.1 114.2 509.7 148.1 114.2 147.8 147.8 133.0 108.0 117.3 209.8 196.2 133.0 108.0 117.3 209.8 196.2 423.6 345.7 435.1 423.6 345.7 435.1 126.4 119.4 126.4 119.4 Ca s e 1 255 Di s t. from the edge of the di a ph. to Tota l the poi nt Di a ph. a t whi ch Wei ght bl k'g i s no Tri buta ry l onger to Gri d req'd. (ki ps ) (ft) 16 5.3 15 13.0 20 19.9 24 5.2 16 5.3 27 19.8 15 13.0 20 19.9 24 5.2 27 19.8 7 Not Req'd 7 Not Req'd 35 23.1 35 23.1 15 10.0 18 2.5 15 10.0 18 2.5 11 1.2 11 1.2 9 6.6 9 6.6 10 9.8 19 3.5 10 10.3 10 9.8 12 14.2 19 3.5 10 Not Req'd 10 10.3 12 14.7 10 Not Req'd 12 14.2 4 Not Req'd 8 Not Req'd 12 14.7 4 Not Req'd 8 Not Req'd 4 Not Req'd 4 Not Req'd 6 Not Req'd 6 Not Req'd 7 Not Req'd 4 Not Req'd 4 Not Req'd 6 Not Req'd 6 Not Req'd 7 Not Req'd 4 Not Req'd 4 Not Req'd 20 12.4 13 8.2 13 13.7 20 12.4 13 8.2 13 13.7 6 Not Req'd 7 Not Req'd 6 Not Req'd 7 Not Req'd Ca s e 3 190 Di s t. from the edge of the di a ph. to the poi nt a t whi ch bl k'g i s no l onger req'd. (ft) 7.6 13.5 21.6 10.6 7.6 22.6 13.5 21.6 10.6 22.6 Not Req'd Not Req'd 26.7 26.7 12.4 6.8 12.4 6.8 1.9 1.9 10.3 10.3 13.8 8.6 14.2 13.8 18.1 8.6 Not Req'd 14.2 18.5 Not Req'd 18.1 Not Req'd Not Req'd 18.5 Not Req'd Not Req'd Not Req'd Not Req'd Not Req'd Not Req'd Not Req'd 1.2 0.4 Not Req'd Not Req'd Not Req'd 1.2 0.4 17.2 14.1 18.6 17.2 14.1 18.6 Not Req'd Not Req'd Not Req'd Not Req'd 49 Table A.3: Chord Forces Chord Forces Code Ref.: Current IBC/CBC Diaphragm Level Grids ASD Chord Force Along Grid High High High High High High High High High High High High High High High High High High High High Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low Low 5 6 7 7 8 8 9 10 10 12 A C C E E E G G G H 1 2 2 2 2 3 3 3 3 3 3 4 5 5 5 5 7 7 10 11 B B B B B D D D D D D D D E E E E E F F 3,704 263 628 12,425 3,704 2,849 263 628 12,425 2,849 13,645 13,645 4,208 4,208 2,204 10,923 2,204 10,923 9,391 9,391 773 773 632 4,830 659 632 612 4,830 5,199 659 680 5,199 612 984 7,109 680 984 7,109 1,202 1,202 3,337 4,126 5,521 600 739 3,337 4,126 5,521 600 739 2,272 1,467 786 2,272 1,467 786 4,126 6,027 4,126 6,027 Box I.D. (lbs) Box M Box O Box E Box J Box M Box N Box O Box E Box J Box N Box E Box E Box J Box J Box M Box N Box M Box N Box O Box O Box A Box A Box B Box G Box K Box B Box C Box G Box H Box K Box L Box H Box C Box D Box I Box L Box D Box I Box F Box F Box A Box B Box C Box D Box F Box A Box B Box C Box D Box F Box G Box H Box I Box G Box H Box I Box K Box L Box K Box L Summary of Chord types Chord chord types Unity check & their Capacities as indicated for chord capacities as Defined in each Box capacity defined on the Right Analysis below : (lbs) Type. Cap., (lbs) Check 1 1 1 1 2 2 1 1 1 1 1 1 1 2 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 4 4 2 4 4 2 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 4 2 2 1 2 2 2 2 29,760 29,760 29,760 29,760 19,200 19,200 29,760 29,760 29,760 29,760 29,760 29,760 29,760 19,200 29,760 29,760 29,760 29,760 29,760 29,760 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 3,020 3,020 19,200 3,020 3,020 19,200 29,760 29,760 29,760 29,760 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 19,200 3,020 19,200 19,200 29,760 19,200 19,200 19,200 19,200 0.1 0.0 0.0 0.4 0.2 0.1 0.0 0.0 0.4 0.1 0.5 0.5 0.1 0.2 0.1 0.4 0.1 0.4 0.3 0.3 0.0 0.0 0.0 0.3 0.0 0.0 0.0 0.3 0.3 0.2 0.2 0.3 0.2 0.3 0.4 0.0 0.0 0.2 0.0 0.1 0.2 0.2 0.3 0.0 0.0 0.2 0.2 0.3 0.0 0.0 0.1 0.1 0.3 0.1 0.1 0.0 0.2 0.3 0.2 0.3 Type 1 12" CMU w / (4) #5 29,760 Type 2 8" CMU w / (4) #4 19,200 Type 3 6" CMU w / (2) #4 9,600 Type 4 Double Top Plate 3,020 50 Table A.4: Box A Flexible Diaphragm Seismic Forces Box A: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 42.5 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 30 Exterior Walls Hor'z 22.5 24.5 15 ft Summary of Weights Vert. Diaph. = 20,825 lbs Trans wall = 35,582 lbs Longwall = 14,411 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 56,407 lbs Longto tal = 35,236 lbs ft Wtrans = 1,327 plf 0 ft Wlo ng = 1,438 plf 0 0 psf Wtrans = 1,129 plf 27,158 17,395 7,828 lbs Wlo ng = 1,365 plf Top Btm Left Right Grid ID: B D 1 2 na Length: 42.5 42.5 24.5 24.5 ft Height: 9.0 9.0 10.0 4.5 ft Wall Unit w t.: 71 71 71 71 psf Chord Type: 2 2 2 2 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 27,158 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads B D 1 2 Manual lbs lbs lbs lbs Diaph. : 17618 17618 28203 28203 Length: 24 40 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 27158 27158 17395 7828 Wall w t.: 78 10 psf Tot.Trib.Wt : 44776 44776 45598 36031 H Parapet: 0 0 ft ASD Load: 14,355 14,355 14,619 11,552 Unit w t.: 0 0 psf ULT Load: 20,507 20,507 20,884 16,502 Wlo ng Diaphragm B D 15 1 2 4 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 17,618 17,618 10,404 28,203 28,203 2,409 1129 1365 ASD Load: 5,651 5,651 3,337 9,046 9,046 773 362 438 ULT Load: 8,073 8,073 4,767 12,923 12,923 1,104 517 625 51 Table A.5: Box B Flexible Diaphragm Seismic Forces Box B: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 51 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 27 Exterior Walls Hor'z 35 15 15 ft Summary of Weights Vert. Diaph. = 24,990 lbs Trans wall = 38,131 lbs Longwall = 9,358 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 63,121 lbs Longto tal = 34,348 lbs ft Wtrans = 1,238 plf 0 ft Wlo ng = 1,402 plf 0 0 psf Wtrans = 969 plf 16,295 7,828 7,828 lbs Wlo ng = 1,340 plf Top Btm Left Right Grid ID: B D 2 3 na Length: 51 51 24.5 24.5 ft Height: 9.0 4.5 4.5 4.5 ft Wall Unit w t.: 71 71 71 71 psf Chord Type: 2 2 2 2 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 32,589 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads B D 2 3 Manual lbs lbs lbs lbs Diaph. : 17174 17174 31560 31560 Length: 39 34 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 32589 16295 7828 7828 Wall w t.: 78 10 psf Tot.Trib.Wt : 49763 33468 39388 39388 H Parapet: 0 0 ft ASD Load: 15,954 10,730 12,628 12,628 Unit w t.: 0 0 psf ULT Load: 22,791 15,329 18,040 18,040 Wlo ng Diaphragm B D 19 2 3 3 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 17,174 17,174 12,862 31,560 31,560 1,971 969 1340 ASD Load: 5,509 5,509 4,126 10,123 10,123 632 311 430 ULT Load: 7,869 7,869 5,894 14,461 14,461 903 444 614 52 Table A.6: Box C Flexible Diaphragm Seismic Forces Box C: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 59 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 34 Exterior Walls Hor'z 45 15 0 ft Summary of Weights Vert. Diaph. = 28,910 lbs Trans wall = 46,163 lbs Longwall = 14,254 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 75,073 lbs Longto tal = 43,164 lbs ft Wtrans = 1,272 plf 0 ft Wlo ng = 1,762 plf 0 0 psf Wtrans = 969 plf 18,851 7,828 7,828 lbs Wlo ng = 1,500 plf Top Btm Left Right Grid ID: B D 3 5 na Length: 59 59 24.5 24.5 ft Height: 9.0 4.5 4.5 4.5 ft Wall Unit w t.: 71 71 71 71 psf Chord Type: 2 2 2 4 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 37,701 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads B D 3 5 Manual lbs lbs lbs lbs Diaph. : 21582 21582 37537 37537 Length: 75 34 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 37701 18851 7828 7828 Wall w t.: 53 42 psf Tot.Trib.Wt : 59283 40432 45364 45364 H Parapet: 0 0 ft ASD Load: 19,006 12,963 14,544 14,544 Unit w t.: 0 0 psf ULT Load: 27,152 18,518 20,777 20,777 Wlo ng Diaphragm B D 25 3 5 3 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 21,582 21,582 17,214 37,537 37,537 1,907 969 1500 ASD Load: 6,922 6,922 5,521 12,040 12,040 612 311 481 ULT Load: 9,889 9,889 7,888 17,200 17,200 874 444 687 53 Table A.7: Box D Flexible Diaphragm Seismic Forces Box D: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 21 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 13 Exterior Walls Hor'z 8 0 15.5 ft Summary of Weights Vert. Diaph. = 10,290 lbs Trans wall = 12,330 lbs Longwall = 17,175 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 22,620 lbs Longto tal = 27,465 lbs ft Wtrans = 1,077 plf 0 ft Wlo ng = 1,121 plf 0 0 psf Wtrans = 832 plf 945 7,828 13,671 lbs Wlo ng = 859 plf Top Btm Left Right Grid ID: B D 5 7 na Length: 21 21 24.5 24.5 ft Height: 9.0 4.5 4.5 4.5 ft Wall Unit w t.: 71 10 71 124 psf Chord Type: 2 2 4 1 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 13,419 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads B D 5 7 Manual lbs lbs lbs lbs Diaph. : 13733 13733 11310 11310 Length: 26 34 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 13419 945 7828 13671 Wall w t.: 44 42 psf Tot.Trib.Wt : 27152 14678 19138 24981 H Parapet: 0 0 ft ASD Load: 8,705 4,706 6,136 8,009 Unit w t.: 0 0 psf ULT Load: 12,435 6,722 8,765 11,441 Wlo ng Diaphragm B D 3 5 7 5 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 13,733 13,733 1,872 11,310 11,310 3,068 832 859 ASD Load: 4,405 4,405 600 3,628 3,628 984 267 275 ULT Load: 6,293 6,293 858 5,182 5,182 1,406 381 393 54 Table A.8: Box E Flexible Diaphragm Seismic Forces Box E: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: High Wt Factors Code Cs Final L (Horiz.): 53 ft ASD 0.7 0.46 0.32 W (Vert.): 19 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 53 Exterior Walls Hor'z 20 15 15 ft Summary of Weights Vert. Diaph. = 20,140 lbs Trans wall = 101,866 lbs Longwall = 23,560 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 122,006 lbs Longto tal = 43,700 lbs ft Wtrans = 2,302 plf 0 ft Wlo ng = 2,300 plf 0 0 psf Wtrans = 2,302 plf 65,720 23,560 23,560 lbs Wlo ng = 2,300 plf Top Btm Left Right Grid ID: A C 7 10 na Length: 53 53 19 19 ft Height: 21.0 10.0 10.0 10.0 ft Wall Unit w t.: 124 124 124 124 psf Chord Type: 1 1 1 1 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 138,012 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads A C 7 10 Manual lbs lbs lbs lbs Diaph. : 21850 21850 61003 61003 Length: 0 0 ft Spec. Load: 0 0 0 0 Height: 0 0 ft In Plane w t : 138012 65720 23560 23560 Wall w t.: 0 0 psf Tot.Trib.Wt : 159862 87570 84563 84563 H Parapet: 0 0 ft ASD Load: 51,252 28,075 27,111 27,111 Unit w t.: 0 0 psf ULT Load: 73,217 40,107 38,730 38,730 Wlo ng Diaphragm A C 61 7 10 3 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs 21,850 21,850 42,542 61,003 61,003 1,958 2302 2300 Tot.Trib.Wt : ASD Load: 7,008 7,008 13,645 19,567 19,567 628 738 738 ULT Load: 10,012 10,012 19,493 27,952 27,952 897 1,055 1,054 55 Table A.9: Box F Flexible Diaphragm Seismic Forces Box F: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 20 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 17 Exterior Walls Hor'z 20 15 14.5 ft Summary of Weights Vert. Diaph. = 9,800 lbs Trans wall = 12,780 lbs Longwall = 14,663 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 22,580 lbs Longto tal = 24,463 lbs ft Wtrans = 1,129 plf 0 ft Wlo ng = 999 plf 0 0 psf Wtrans = 1,129 plf 12,780 13,671 15,656 lbs Wlo ng = 999 plf Top Btm Left Right Grid ID: B D 10 11 na Length: 20 20 24.5 24.5 ft Height: 9.0 9.0 4.5 9.0 ft Wall Unit w t.: 71 71 124 71 psf Chord Type: 2 2 1 2 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 12,780 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads B D 10 11 Manual lbs lbs lbs lbs Diaph. : 12232 12232 11290 11290 Length: 0 0 ft Spec. Load: 0 0 0 0 Height: 0 0 ft In Plane w t : 12780 12780 13671 15656 Wall w t.: 0 0 psf Tot.Trib.Wt : 25012 25012 24961 26946 H Parapet: 0 0 ft ASD Load: 8,019 8,019 8,002 8,639 Unit w t.: 0 0 psf ULT Load: 11,455 11,455 11,432 12,341 Wlo ng Diaphragm B D 4 10 11 6 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 12,232 12,232 2,304 11,290 11,290 3,746 1129 999 ASD Load: 3,923 3,923 739 3,621 3,621 1,202 362 320 ULT Load: 5,605 5,605 1,056 5,173 5,173 1,716 517 458 56 Table A.10: Box G Flexible Diaphragm Seismic Forces Box G: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 47.5 ft ASD 0.7 0.46 0.32 W (Vert.): 62.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 34.5 Exterior Walls Hor'z 40.5 38.5 62 ft Summary of Weights Vert. Diaph. = 59,375 lbs Trans wall = 56,936 lbs Longwall = 66,102 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 116,311 lbs Longto tal = 125,477 lbs Wtrans = 2,449 plf ft Wlo ng = 2,008 plf 0 psf Wtrans = 1,570 plf 44,375 19,969 lbs Wlo ng = 1,465 plf Top Btm Left Right Grid ID: D E 2 3 na Length: 47.5 47.5 62.5 62.5 ft Height: 4.5 4.5 10.0 4.5 ft Wall Unit w t.: 71 71 71 71 psf Chord Type: 2 2 2 2 H Parapet: 0 0 0 0 ft Length Par.: 0 0 0 0 Par. Unit w t.: 0 0 0 Wall Trib w t: 15,176 15,176 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads D E 2 3 Manual lbs lbs lbs lbs Diaph. : 62738 62738 58156 58156 Length: 160 130 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 15176 15176 44375 19969 Wall w t.: 58 58 psf Tot.Trib.Wt : 77915 77915 102531 78124 H Parapet: 0 0 ft ASD Load: 24,979 24,979 32,871 25,047 Unit w t.: 0 0 psf ULT Load: 35,685 35,685 46,959 35,781 Wlo ng Diaphragm D E 11 2 3 22 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 62,738 62,738 7,082 58,156 58,156 15,057 1570 1465 ASD Load: 20,123 20,123 2,272 18,653 18,653 4,830 503 470 ULT Load: 28,748 28,748 3,245 26,648 26,648 6,899 719 671 57 Table A.11: Box H Flexible Diaphragm Seismic Forces Box H: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 39 ft ASD 0.7 0.46 0.32 W (Vert.): 62.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 31 Exterior Walls Hor'z 25 62 15 ft Summary of Weights Vert. Diaph. = 48,750 lbs Trans wall = 13,055 lbs Longwall = 35,322 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 61,805 lbs Longto tal = 84,072 lbs ft Wtrans = 1,585 plf 0 ft Wlo ng = 1,345 plf 0 0 psf Wtrans = 1,504 plf 9,905 19,969 44,375 lbs Wlo ng = 1,295 plf Top Btm Left Right Grid ID: D E 3 4 na Length: 31 31 62.5 62.5 ft Height: 4.5 4.5 4.5 10.0 ft Wall Unit w t.: 71 71 71 71 Chord Type: 2 2 2 2 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 9,905 Concentrated Load On Diaphragm psf Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads D E 3 4 Manual lbs lbs lbs lbs Diaph. : 42036 42036 30902 30902 Length: 70 70 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 9905 9905 19969 44375 Wall w t.: 10 10 psf Tot.Trib.Wt : 51940 51940 50871 75277 H Parapet: 0 0 ft ASD Load: 16,652 16,652 16,309 24,134 Unit w t.: 0 0 psf ULT Load: 23,789 23,789 23,299 34,477 Wlo ng Diaphragm D E 7 3 4 24 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 42,036 42,036 4,575 30,902 30,902 16,210 1504 1295 ASD Load: 13,483 13,483 1,467 9,912 9,912 5,199 482 415 ULT Load: 19,261 19,261 2,096 14,160 14,160 7,428 689 593 58 Table A.12: Box I Flexible Diaphragm Seismic Forces Box I: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 29 ft ASD 0.7 0.46 0.32 W (Vert.): 66 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 8 Exterior Walls Hor'z 18 40 36 ft Summary of Weights Vert. Diaph. = 38,280 lbs Trans wall = 8,717 lbs Longwall = 40,390 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 46,997 lbs Longto tal = 78,670 lbs ft Wtrans = 1,621 plf 0 ft Wlo ng = 1,192 plf 0 0 psf Wtrans = 1,538 plf 11,718 44,375 34,875 lbs Wlo ng = 1,180 plf Top Btm Left Right Grid ID: D E 5 7 na Length: 21 21 62.5 62.5 ft Height: 4.5 4.5 10.0 4.5 ft Wall Unit w t.: 10 124 71 124 psf Chord Type: 4 1 2 1 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 945 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads D E 5 7 Manual lbs lbs lbs lbs Diaph. : 39335 39335 23498 23498 Length: 53 17 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 945 11718 44375 34875 Wall w t.: 10 10 psf Tot.Trib.Wt : 40280 51053 67873 58373 H Parapet: 0 0 ft ASD Load: 12,914 16,368 21,760 18,714 Unit w t.: 0 0 psf ULT Load: 18,448 23,382 31,086 26,735 Wlo ng Diaphragm D E 4 5 7 32 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 39,335 39,335 2,450 23,498 23,498 22,163 1538 1180 ASD Load: 12,617 12,617 786 7,537 7,537 7,109 493 379 ULT Load: 18,024 18,024 1,123 10,767 10,767 10,155 705 541 59 Table A.13: Box J Flexible Diaphragm Seismic Forces Box J: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: High Wt Factors Code Cs Final L (Horiz.): 53 ft ASD 0.7 0.46 0.32 W (Vert.): 75 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 20 Exterior Walls Hor'z 24.5 53 49 ft Summary of Weights Vert. Diaph. = 79,500 lbs Trans wall = 69,006 lbs Longwall = 139,500 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 148,506 lbs Longto tal = 219,000 lbs Wtrans = 2,802 plf ft Wlo ng = 2,920 plf 0 psf Wtrans = 2,802 plf 93,000 186,000 lbs Wlo ng = 2,920 plf Top Btm Left Right Grid ID: C E 7 10 na Length: 53 53 75 75 ft Height: 10.5 10.5 10.0 20.0 ft Wall Unit w t.: 124 124 124 124 psf Chord Type: 1 2 1 1 H Parapet: 0 0 0 0 ft Length Par.: 0 0 0 0 Par. Unit w t.: 0 0 0 Wall Trib w t: 69,006 69,006 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads C E 7 10 Manual lbs lbs lbs lbs Diaph. : 109500 109500 74253 74253 Length: 0 0 ft Spec. Load: 0 0 0 0 Height: 0 0 ft In Plane w t : 69006 69006 93000 186000 Wall w t.: 0 0 psf Tot.Trib.Wt : 178506 178506 167253 260253 H Parapet: 0 0 ft ASD Load: 57,229 57,229 53,621 83,437 Unit w t.: 0 0 psf ULT Load: 81,756 81,756 76,602 119,196 Wlo ng Diaphragm C E 19 7 10 56 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 109,500 109,500 13,118 74,253 74,253 38,738 2802 2920 ASD Load: 35,122 35,122 4,208 23,817 23,817 12,425 899 937 ULT Load: 50,174 50,174 6,011 34,024 34,024 17,750 1,284 1,338 60 Table A.14: Box K Flexible Diaphragm Seismic Forces Box K: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 51 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 40.5 Exterior Walls Hor'z 33 11 18.5 ft Summary of Weights Vert. Diaph. = 24,990 lbs Trans wall = 40,237 lbs Longwall = 15,216 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 65,227 lbs Longto tal = 40,206 lbs ft Wtrans = 1,279 plf 0 ft Wlo ng = 1,641 plf 0 0 psf Wtrans = 969 plf 32,589 17,395 1,103 lbs Wlo ng = 1,398 plf Top Btm Left Right Grid ID: E F 2 3 na Length: 51 51 24.5 24.5 ft Height: 4.5 9.0 10.0 4.5 ft Wall Unit w t.: 71 71 71 10 psf Chord Type: 2 2 2 4 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 16,295 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads E F 2 3 Manual lbs lbs lbs lbs Diaph. : 20103 20103 32613 32613 Length: 45 17 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 16295 32589 17395 1103 Wall w t.: 78 78 psf Tot.Trib.Wt : 36397 52692 50008 33716 H Parapet: 0 0 ft ASD Load: 11,669 16,893 16,033 10,809 Unit w t.: 0 0 psf ULT Load: 16,670 24,133 22,904 15,442 Wlo ng Diaphragm E F 19 2 3 3 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 20,103 20,103 12,862 32,613 32,613 2,056 969 1398 ASD Load: 6,448 6,448 4,126 10,461 10,461 659 311 448 ULT Load: 9,211 9,211 5,894 14,944 14,944 942 444 640 61 Table A.15: Box L Flexible Diaphragm Seismic Forces Box L: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: Low Wt Factors Code Cs Final L (Horiz.): 59 ft ASD 0.7 0.46 0.32 W (Vert.): 24.5 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 37 Exterior Walls Hor'z 43 18.5 18.5 ft Summary of Weights Vert. Diaph. = 28,910 lbs Trans wall = 48,956 lbs Longwall = 15,004 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 77,866 lbs Longto tal = 43,914 lbs ft Wtrans = 1,320 plf 0 ft Wlo ng = 1,792 plf 0 0 psf Wtrans = 1,058 plf 37,701 1,103 22,785 lbs Wlo ng = 1,668 plf Top Btm Left Right Grid ID: E F 3 5 na Length: 59 59 24.5 24.5 ft Height: 7.0 9.0 4.5 7.5 ft Wall Unit w t.: 71 71 10 124 psf Chord Type: 2 2 4 1 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 29,323 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads E F 3 5 Manual lbs lbs lbs lbs Diaph. : 21957 21957 38933 38933 Length: 44 68 ft Spec. Load: 0 0 0 0 Height: 9 9 ft In Plane w t : 29323 37701 1103 22785 Wall w t.: 78 10 psf Tot.Trib.Wt : 51280 59658 40036 61718 H Parapet: 0 0 ft ASD Load: 16,440 19,126 12,835 19,787 Unit w t.: 0 0 psf ULT Load: 23,486 27,323 18,336 28,267 Wlo ng Diaphragm E F 27 3 5 4 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs 21,957 21,957 18,790 38,933 38,933 2,121 1058 1668 Tot.Trib.Wt : ASD Load: 7,043 7,043 6,027 12,488 12,488 680 339 535 ULT Load: 10,061 10,061 8,610 17,840 17,840 972 485 764 62 Table A.16: Box M Flexible Diaphragm Seismic Forces Box M: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: High Wt Factors Code Cs Final L (Horiz.): 28.5 ft ASD 0.7 0.46 0.32 W (Vert.): 39 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 19 Exterior Walls Hor'z 14 29 33 ft Summary of Weights Vert. Diaph. = 22,230 lbs Trans wall = 76,410 lbs Longwall = 71,019 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 98,640 lbs Longto tal = 93,249 lbs ft Wtrans = 3,461 plf 0 ft Wlo ng = 2,391 plf 0 0 psf Wtrans = 2,640 plf 70,680 62,868 27,690 lbs Wlo ng = 1,731 plf Top Btm Left Right Grid ID: E G 5 8 na Length: 28.5 28.5 39 39 ft Height: 10.0 20.0 13.0 10.0 ft Wall Unit w t.: 124 124 124 71 Chord Type: 1 1 1 2 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 35,340 Concentrated Load On Diaphragm psf Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads E G 5 8 Manual lbs lbs lbs lbs Diaph. : 46625 46625 49320 49320 Length: 30 33 ft Spec. Load: 0 0 0 0 Height: 20 20 ft In Plane w t : 35340 70680 62868 27690 Wall w t.: 78 78 psf Tot.Trib.Wt : 81965 117305 112188 77010 H Parapet: 0 0 ft ASD Load: 26,278 37,608 35,967 24,689 Unit w t.: 0 0 psf ULT Load: 37,540 53,725 51,382 35,271 Diaphragm E G 10 5 8 17 Forces V V T Chord V V T Chord Wtrans Wlo ng lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 46,625 46,625 6,873 49,320 49,320 11,548 2640 1731 ASD Load: 14,955 14,955 2,204 15,819 15,819 3,704 847 555 ULT Load: 21,364 21,364 3,149 22,599 22,599 5,291 1,210 793 63 Table A.17: Box N Flexible Diaphragm Seismic Forces Box N: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: High Wt Factors Code Cs Final L (Horiz.): 62 ft ASD 0.7 0.46 0.32 W (Vert.): 39 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 40.5 Exterior Walls Hor'z 46 33 39 ft Summary of Weights Vert. Diaph. = 48,360 lbs Trans wall = 123,008 lbs Longwall = 64,623 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 171,368 lbs Longto tal = 112,983 lbs Wtrans = 2,764 plf ft Wlo ng = 2,897 plf 0 psf Wtrans = 2,764 plf 27,690 101,556 lbs Wlo ng = 2,897 plf Top Btm Left Right Grid ID: E G 8 12 na Length: 62 62 39 39 ft Height: 12.0 20.0 10.0 21.0 ft Wall Unit w t.: 124 124 71 124 psf Chord Type: 1 1 2 1 H Parapet: 0 0 0 0 ft Length Par.: 0 0 0 0 Par. Unit w t.: 0 0 0 Wall Trib w t: 92,256 153,760 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left ΔV Right Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 0 0 0 0 0 0 0 0 0 0 0 Interior Walls Hor'z Vert. Grid Loads E G 8 12 Manual lbs lbs lbs lbs Diaph. : 56492 56492 85684 85684 Length: 0 0 ft Spec. Load: 0 0 0 0 Height: 0 0 ft In Plane w t : 92256 153760 27690 101556 Wall w t.: 0 0 psf Tot.Trib.Wt : 148748 210252 113374 187240 H Parapet: 0 0 ft ASD Load: 47,688 67,407 36,348 60,029 Unit w t.: 0 0 psf ULT Load: 68,126 96,295 51,925 85,756 Diaphragm E G 49 8 12 13 Forces V V T Chord V V T Chord Wtrans Wlo ng lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 56,492 56,492 34,054 85,684 85,684 8,884 2764 2897 ASD Load: 18,120 18,120 10,923 27,483 27,483 2,849 887 929 ULT Load: 25,885 25,885 15,604 39,262 39,262 4,071 1,267 1,327 64 Table A.18: Box O Flexible Diaphragm Seismic Forces Box O: Flexible Diaphragm Seismic Forces Code Ref.: Current IBC/CBC Redundancy Factor: ρ= 1.3 Diaphragm Input Location: High Wt Factors Code Cs Final L (Horiz.): 30 ft ASD 0.7 0.46 0.32 W (Vert.): 8 ft ULT 1.0 0.46 0.46 Bldg. Elev.: 66 ft Roof DL: 20 psf Roof SL: 0 psf Roof T DL: 20.0 psf Wall Lengths at Base of Wall: Length @ B ase: 14 Exterior Walls Hor'z 14 8 8 ft Summary of Weights Vert. Diaph. = 4,800 lbs Trans wall = 57,660 lbs Longwall = 29,760 lbs Trans special= 0 lbs Longspecial= 0 lbs Trans to tal = 62,460 lbs Longto tal = 34,560 lbs ft Wtrans = 2,082 plf 0 ft Wlo ng = 4,320 plf 0 0 psf Wtrans = 2,082 plf 78,120 19,840 19,840 lbs Wlo ng = 3,080 plf Top Btm Left Right Grid ID: G H 6 9 na Length: 30 30 8 8 ft Height: 10.0 21.0 20.0 20.0 ft Wall Unit w t.: 124 124 124 124 psf Chord Type: 1 1 1 1 H Parapet: 0 0 0 0 Length Par.: 0 0 0 Par. Unit w t.: 0 0 Wall Trib w t: 37,200 Concentrated Load On Diaphragm Horiz Loading Vert Loading Load Weight x y ΔV Top ΔV Btm ΔV Left Number (lbs) (ft) (ft) (lbs) (lbs) (lbs) (lbs) 1 33000 15 4 16,500 16,500 16,500 16,500 16,500 16,500 16,500 16,500 Grid Loads G H 6 9 Manual lbs lbs lbs lbs Diaph. : Interior Walls ΔV Right Hor'z Vert. 33780 33780 47730 47730 Length: 0 8 ft Spec. Load: 0 0 0 0 Height: 0 20 ft In Plane w t : 37200 78120 19840 19840 Wall w t.: 0 124 psf Tot.Trib.Wt : 70980 111900 67570 67570 H Parapet: 0 0 ft ASD Load: 22,756 35,875 21,663 21,663 Unit w t.: 0 0 psf ULT Load: 32,509 51,250 30,947 30,947 Wlo ng Diaphragm G H 42 6 9 2 Forces V V T Chord V V T Chord Wtrans lbs lbs lbs lbs lbs lbs lbs lbs Tot.Trib.Wt : 33,780 33,780 29,278 47,730 47,730 821 2082 3080 ASD Load: 10,835 10,835 9,391 15,309 15,309 263 668 988 ULT Load: 15,478 15,478 13,416 21,871 21,871 376 954 1,411 65 Figure A.1: Special Condition 1 RISA Results 66 Table A.19: Special Condition 1 RISA Results Basic Load Cases BLC Desciption 1 D 2 EQ Category DL EL Joint Load Combinations Description 1 D+EQ 2 D 3 EQ BLC Y Y Y Factor -1 -1 -1 BLC 1 1 2 Joint Coordinates Label 1 N1 2 N2 X (ft) 0 43.5 Y (ft) 0 0 Z (ft) 0 0 Y Reaction Reaction Z Reaction Joint Boundary Conditions Joint Label X 1 N1 Reaction 2 N2 Distributed 1 1 Factor 1.457 1.457 2.5 BLC 2 Factor 2.5 X-Rot Fixed Fixed Y-Rot Fixed Fixed Z-Rot Member Distributed Loads 1 Member Label M1 Direction Y Magnitude (k/in) -0.475 Direction X Magnitude (k) 59.3 Shape W21x62 Material A36 Gr.36 Joint Loads 1 Joint Label N2 Member Data 1 Label M1 ASD Steel Code Checks Member 1 M1 Unity Check 0.989 Joint Reactions Joint Label 1 N1 2 N2 3 Totals: 4 COG (ft): X (ft) -148.25 0 -148.25 X: 21.75 Y (ft) 16.403 16.403 32.806 Y: 0 Type Length (ft) WF Beam 43.5 Z (ft) 0 0 0 Z: 0 Mx (k-ft) My (k-ft) Mz (k-ft) NC NC 0 NC NC 0 67 REFERENCES Amrhein, J.E. (1998). “Reinforced Masonry Engineering Handbook”. Masonry Institute of America, Boca Raton, NY. American Concrete Institute. (2005). Building Code Requirements for Masonry Structures, Farmington Hills, MI. American Institute of Steel Construction (AISC). (2011). Steel Construction Manual, Chicago, IL. American Society of Civil Engineering (ASCE). (2003). Seismic Evaluation of Existing Buildings, Reston, VA. American Society of Civil Engineering (ASCE). (2010). Minimum Design Loads for Buildings and Other Structures, Reston, VA. American Society of Civil Engineering (ASCE). (2006). Seismic Rehabilitation of Existing Buildings, Reston, VA. Association of Bay Area Governments. Earthquake and Hazards Program. Association of Bay Area Governments, January 25, 2014. <http://quake.abag.ca.gov> American Wood Council (AWC). (2012). National Design Specifications for Wood Construction, Leesburg, VA. American Wood Council (AWC). (2008). Special Design Provisions for Wind and Seismic, Leesburg, VA. Bruneau, Michel (1992). “State-of-the-art Report on Seismic Performance of Unreinforced Masonry Buildings”. J. Struct. Eng. 120:230-251. Federal Emergency Management Agency (FEMA). (2000). Prestandard and Commentary for the Seismic Rehabilitation of Buildings, Washington, DC. 68 Federal Emergency Management Agency (FEMA). (1992). Techniques for the Seismic Rehabilitation of Existing Buildings, Washington, DC. Hsiao, K and Tezcan, J. (2012). “Seismic Retrofitting of Chord Reinforcement for Unreinforced Masonry Historic Buildings with Flexible Diaphragms”. American Society of Civil Engineering, Reston, VA. Luco, N., Ellingwod, B., Hamburger, R., Hooper, J., Kimball, J., and Kircher, C. (2007). “RiskTargeted Versus Current Seismic Design Maps for the Conterminous United States”. Structural Engineering Association of California, Sacramento, CA. Paret, T., Freeman, S., Searer, G., Hachem, M., and Gilmartin, U. (2007). “Using Traditional and Innovative Approaches in the Seismic Evaluation and Strengthening of a Historic Unreinforced Masonry Synagogue”. Wiss, Janney, Elstner Associates, Inc. Emeryville, CA. Shah, H., Gere, J., Krawinkler, H., Rojahan, C., and Zsutty, T. (1983). “A Preliminary Survey of Damage to the Commercial District”. Earthquake Engineering Research Institute. Oakland, CA. S.K. Gosh Associates Inc. (2012). “Changes Between ASCE 7-05 and ASCE 7-10”. S.K. Gosh Associates Inc., Palatine, IL. United States Geologic Survey (USGS). (2009). “Earthquake Probability Mapping Tool”. usgs.gov. April 29, 2014. United States Geologic Survey (USGS). (2014). “Ground Motion Parameter Software, version 5.1.0”. usgs.gov. January 25, 2014. United States Geologic Survey (USGS). (2014). “Soil Type and Shaking Hazard in the San Francisco Ba Area”. usgs.gov. April 29, 2014. 69 United States Geologic Survey (USGS). (2014). “Quaternary Faults Web Mapping Application”. usgs.gov. January 25, 2014. Whittaker, A., Huang, Y., and Luco, N. (2014). “Maximum Direction Ground Motions”. www.nibs.org. National Institute of Building Sciences. Washington, DC.