San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 Cunningham Science and Math Complex Project Overview Construction Architect: Contractor: Project Budget: Actual Bid Day Amount Actual Notice to Proceed Date: Current Contract Completion Date Phase I: Phases III / IV: * Includes soft costs tBP Architecture Taisei Construction Corp. $ 63,435,782 * $ 35,149,900 ** February 8, 2010 August 1, 2012 March 15, 2013 ** Contract amount with General Contractor Project Description: This project consists of a new three story math/science complex including a 70,000 sf laboratory core, with primarily dry labs on the first floor, wet biology labs on the second floor, and chemistry labs on the third floor. There is 20,000 sf of office space and 20,000 sf of classrooms dedicated to each discipline, primarily in separate zones. The labs wrap around a central service core consisting of tech offices, lab preparation rooms, and lab storage rooms. Students will enter the labs from the opposite side of the central service core providing safe separation of students and chemicals. Student break-out spaces, computer labs, and a resource center for studying and tutorial sessions will be provided. Progress Exterior: This month the color coat of plaster was applied on the east and north elevations of Wing A and the south elevation of Wing B. Exterior cement board was installed on the east elevation of wing C and progress continued around other elevations of Wing C as various components that make up the “skin” of the building were installed. Concrete walkways were placed around the west south and east sides of Wing A. Wing A: Inside the Equipment Room the installation of piping to the Equipment continued. Final connections to plumbing fixtures were focused on at the first floor laboratories while ceramic tile was installed at the women’s first floor restroom. The mortar beds at the remaining restrooms were installed so that waterproofing and ceramic tile installations could begin. The casework installation started at the third floor. The installation of seismic bracing for the 3609A3-7.21 San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 plumbing piping was completed on the third floor while the t-bar grid, light fixtures and air conditioning registers continued to be installed at the ceiling of the third floor. The final connection pieces for the stainless steel ductwork on the roof and the sound traps that get mounted on the roof were ordered. Wing B: The first floor interior walls were textured and the installation of paint began. The walls at the second floor were floated smooth in preparation for texture and gypsum wallboard was installed at the third floor. Work at the shafts continued so the adjacent room finishes could be completed as well. Wing C: At Wing C the air conditioning linear diffusers and the light fixtures were installed in the soffits at the first level while flexible ducting to register locations was installed on the floors above. Hydronic piping and ductwork continued at the main shaft so that framing could continue in an attempt to complete this shaft at all floors. The added fresh air ducting was installed in the restrooms and electrical/data installations continued. Issues The Contractor’s June schedule update was submitted which now projects a late October 2012, substantial completion for Phase 1. The Contractor continues to face challenges in maintaining adequate manpower on the project, and completion of the MEP systems continues to drive the project completion. Budget Refer to current Budget Summary Report sheet included herein. Schedule The current contract completion date for Phase I is August 1, 2012, and for Phases III / IV is March 15, 2013. Logs 3609A3-7.21 Outstanding RFI’s – There are ten (10) outstanding RFI’s as of this publish date. Outstanding Submittals – There are four (4) Submittals currently in the review process as of this publish date. PCO Summary Log – There are thirty-four (34) PCO’s currently in the pricing / review process. San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 Contract Change Orders 3609A3-7.21 CCO #01 – Add $21,601.00 and 0 CD’s CCO #02 – Add $37,963.36 and 0 CD’s CCO #03 – Add $19,278.00 and 0 CD’s CCO #04 – Add $97,898.00 and 38 CD’s CCO #05 – Add $11,809.00 and 0 CD’s CCO #06 – Add $73,400.00 and 0 CD’s CCO #07 – Add $6,979.00 and 0 CD’s CCO #08 – Deduct $56,982.00 and 0 CD’s CCO #09 – Add $14,740.00 and 0 CD’s CCO #10 – Add $29,713.00 and 0 CD’s CCO #11 – Add $1,339,948.00 and 0 CD’s CCO #12 – Add $55,793.00 and 0 CD’s CCO #13 – Add $2,272,645.00 and 137 CD’s CCO #14 – Add $142,077.00 and 0 CD’s CCO #15 – Deduct $60,521.00 and 0 CD’s CCO #16 – Add $46,489.00 and 0 CD’s CCO #17 – Add $61,765.00 and 0 CD’s CCO #18 – Add $57,995.00 and 0 CD’s CCO #19 – Add $25,358.00 and 0 CD’s CCO #20 – Add $15,294.00 and 0 CD’s CCO #21 – Add $24,653.00 and 0 CD’s CCO #22 – Add $142,281.00 and 0 CD’s CCO #23 – Add $105,696.00 and 0 CD’s San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 Progress Photos Wing A – Plaster Finish Applied at the East Elevation 3609A3-7.21 San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 Progress Photos Wing A – Ceramic Tile Installed at the Women’s 1st Floor Restroom Progress Photos 3609A3-7.21 San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 Wing B – Interior Walls Ready for Paint at First Floor 3609A3-7.21 San Joaquin Delta College Progress Report Number 29 Reporting Period: July 2012 Progress Photos Wing C – Hydronic Piping, Ductwork and Framing Continue at the Main Shaft 3609A3-7.21