July 2012 - Cunningham Science and Math Replacement

advertisement
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
Cunningham Science and Math Complex
Project Overview
Construction Architect:
Contractor:
Project Budget:
Actual Bid Day Amount
Actual Notice to Proceed Date:
Current Contract Completion Date
Phase I:
Phases III / IV:
* Includes soft costs
tBP Architecture
Taisei Construction Corp.
$ 63,435,782 *
$ 35,149,900 **
February 8, 2010
August 1, 2012
March 15, 2013
** Contract amount with General Contractor
Project Description: This project consists of a new three story math/science
complex including a 70,000 sf laboratory core, with primarily dry labs on the first
floor, wet biology labs on the second floor, and chemistry labs on the third floor.
There is 20,000 sf of office space and 20,000 sf of classrooms dedicated to each
discipline, primarily in separate zones. The labs wrap around a central service
core consisting of tech offices, lab preparation rooms, and lab storage rooms.
Students will enter the labs from the opposite side of the central service core
providing safe separation of students and chemicals. Student break-out spaces,
computer labs, and a resource center for studying and tutorial sessions will be
provided.
Progress
Exterior: This month the color coat of plaster was applied on the east and north
elevations of Wing A and the south elevation of Wing B. Exterior cement board
was installed on the east elevation of wing C and progress continued around
other elevations of Wing C as various components that make up the “skin” of the
building were installed. Concrete walkways were placed around the west south
and east sides of Wing A.
Wing A: Inside the Equipment Room the installation of piping to the Equipment
continued. Final connections to plumbing fixtures were focused on at the first
floor laboratories while ceramic tile was installed at the women’s first floor
restroom. The mortar beds at the remaining restrooms were installed so that
waterproofing and ceramic tile installations could begin.
The casework
installation started at the third floor. The installation of seismic bracing for the
3609A3-7.21
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
plumbing piping was completed on the third floor while the t-bar grid, light fixtures
and air conditioning registers continued to be installed at the ceiling of the third
floor. The final connection pieces for the stainless steel ductwork on the roof and
the sound traps that get mounted on the roof were ordered.
Wing B: The first floor interior walls were textured and the installation of paint
began. The walls at the second floor were floated smooth in preparation for
texture and gypsum wallboard was installed at the third floor. Work at the shafts
continued so the adjacent room finishes could be completed as well.
Wing C: At Wing C the air conditioning linear diffusers and the light fixtures were
installed in the soffits at the first level while flexible ducting to register locations
was installed on the floors above. Hydronic piping and ductwork continued at the
main shaft so that framing could continue in an attempt to complete this shaft at
all floors. The added fresh air ducting was installed in the restrooms and
electrical/data installations continued.
Issues
The Contractor’s June schedule update was submitted which now projects a late
October 2012, substantial completion for Phase 1. The Contractor continues to
face challenges in maintaining adequate manpower on the project, and
completion of the MEP systems continues to drive the project completion.
Budget
Refer to current Budget Summary Report sheet included herein.
Schedule
The current contract completion date for Phase I is August 1, 2012, and for
Phases III / IV is March 15, 2013.
Logs



3609A3-7.21
Outstanding RFI’s – There are ten (10) outstanding RFI’s as of this publish
date.
Outstanding Submittals – There are four (4) Submittals currently in the review
process as of this publish date.
PCO Summary Log – There are thirty-four (34) PCO’s currently in the pricing
/ review process.
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
Contract Change Orders























3609A3-7.21
CCO #01 – Add $21,601.00 and 0 CD’s
CCO #02 – Add $37,963.36 and 0 CD’s
CCO #03 – Add $19,278.00 and 0 CD’s
CCO #04 – Add $97,898.00 and 38 CD’s
CCO #05 – Add $11,809.00 and 0 CD’s
CCO #06 – Add $73,400.00 and 0 CD’s
CCO #07 – Add $6,979.00 and 0 CD’s
CCO #08 – Deduct $56,982.00 and 0 CD’s
CCO #09 – Add $14,740.00 and 0 CD’s
CCO #10 – Add $29,713.00 and 0 CD’s
CCO #11 – Add $1,339,948.00 and 0 CD’s
CCO #12 – Add $55,793.00 and 0 CD’s
CCO #13 – Add $2,272,645.00 and 137 CD’s
CCO #14 – Add $142,077.00 and 0 CD’s
CCO #15 – Deduct $60,521.00 and 0 CD’s
CCO #16 – Add $46,489.00 and 0 CD’s
CCO #17 – Add $61,765.00 and 0 CD’s
CCO #18 – Add $57,995.00 and 0 CD’s
CCO #19 – Add $25,358.00 and 0 CD’s
CCO #20 – Add $15,294.00 and 0 CD’s
CCO #21 – Add $24,653.00 and 0 CD’s
CCO #22 – Add $142,281.00 and 0 CD’s
CCO #23 – Add $105,696.00 and 0 CD’s
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
Progress Photos
Wing A – Plaster Finish Applied at the East Elevation
3609A3-7.21
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
Progress Photos
Wing A – Ceramic Tile Installed at the Women’s 1st Floor Restroom
Progress Photos
3609A3-7.21
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
Wing B – Interior Walls Ready for Paint at First Floor
3609A3-7.21
San Joaquin Delta College
Progress Report Number 29
Reporting Period: July 2012
Progress Photos
Wing C – Hydronic Piping, Ductwork and Framing Continue at the Main Shaft
3609A3-7.21