Issue Register – BioMeat Company Last updated: 2/9/11 BioMeat System Management Issue Register as at 2/9/11 Issue No: 1 Raised by: Project director, Layla and Fouad Issue Date Raised: Severity classification: 30/8/11 Medium Issue Description: Rich picture has some issues have to prepare, which are: cover all stockholders and replace the arrows by suitable relationships. Risk: Change: Rich picture has to reflect the stakeholders on this project, and if it does not the management of our project would be affected because the rich picture is incomplete in order the scope would affected. Redrawing the rich picture would change the scope of our project management. Time risk concerned. More investigation: Treatment: Research for rich picture examples and read SAM book. Redraw rich picture within complete scope view, and use proper arrows. And add more stack holders. Out of scope matter: Responsible team member: We need to do more reading to find out the suitable way for drawing a rich picture. Fouad Date of remedy: Due date to reconsider: 3/9/2011 5/9/2011 Status: Open Action History: The team have meeting on 1/9/11 and decided to assign the task for Fouad. Issue Register – BioMeat Company Issue No: 2 Last updated: 2/9/11 Raised by: Project director Issue Date Raised: Severity classification: 30/8/11 High Issue Description: Meeting minute template has to be more effeciont. Risk: Change: Incomplete meeting minute template would affect the quality of our project management. No changes required for other parts. More investigation: Treatment: Asking the project director what columns we need to add in the template. Fix the meeting minute template by adding new columns which are: finished, finished time. Out of scope matter: Responsible team member: Old files should be repaired. Quality assurance would improve. And no other parts would be affected. All group members. Date of remedy: Due date to reconsider: 2/9/2011 3/9/2011 Status: Open Action History: The team have meeting on 1/9/11 and decided to assign the task for Layla (for next presentation.) and for all group members for after presentations. Issue Register – BioMeat Company Issue No: 3 Last updated: 2/9/11 Raised by: Project director Issue Date Raised: Severity classification: 30/8/11 High Issue Description: No presentation driver in the presentations. Risk: Change: Without time keeper we wouldn’t manage the time of presentation properly. Write the name of the time keeper in meeting minute. More investigation: Treatment: We have meeting to prepare how will be the time keeper work in next presentation. In every presentation we have to assign time keeping to one of the members team. Out of scope matter: Responsible team member: Quality assurance would improve. And no other parts would be affected. All group members Date of remedy: Due date to reconsider: 6/9/2011 8/9/2011 Status: Open Action History: The team have meeting on 1/9/11 and decided to assign the task for Fouad (for next presentation.) and for all group members for after presentations. Issue Register – BioMeat Company Issue No: 4 Last updated: 2/9/11 Raised by: Project director Issue Date Raised: Severity classification: 30/8/11 High Issue Description: No presentation driver in the presentations. Risk: Change: Without presentation driver we wouldn’t manage the presentations properly. Write the name of the presentation driver in meeting minute. More investigation: Treatment: We have got knowledge (from PD) that the presentation has to have a presentation driver to do drive the slides for team members while they present the slides. In every presentation we have to assign presentation driving to one of the member’s team. Out of scope matter: Responsible team member: Quality assurance would improve. And no other parts would be affected. All group members Date of remedy: Due date to reconsider: 1/9/2011 8/9/2011 Status: Open Action History: The team have meeting on 1/9/11 and decided to assign the task for Sri (for next presentation.) and for all group members for after presentations.