Victorian Desalination Project Community Liaison Group Minutes from Meeting Number 22 on 25 August 2011 Date: Thursday 25 August 2011 Location: Plant site and Community Information Centre Present: John Nicol (Chair) Peter Sammut (DSE) Meeka Bailey (DSE – Secretary) Chris Herbert (AquaSure) John Ridley (AquaSure) Louisa McPhee (AquaSure) Serena Middleton (Thiess Degrémont) Steve Burns (Thiess Degrémont) Karen Lee (Thiess Degrémont) Max Tolson (Thiess Degrémont Nacap) Graeme Tait (Thiess Degrémont Nacap) Cr Veronica Dowman (Bass Coast Shire) Neville Goodwin (Bass Coast Community Representative) Ian Anderson (Cardinia Community Representative) Sonia Rappell (City of Casey) Apologies: Chloe Munro (AquaSure) Cr Geoff Ablett (City of Casey) Cr Stuart Halligan (Cardinia Council) Site tour attendees: Allen Bawden (Bass Coast Shire Council) Felicity Sist (Bass Coast Shire Council) Peter Fitchett (City of Casey Council) 1. Site tour The Community Liaison Group (CLG) attended the Victorian Desalination Project plant site for a site walk. The group met Thiess Degrémont Project Director John Barraclough at the viewing platform and was escorted on a site tour by area safety manager Marcus Roylance. The site walk included the roof of the reverse osmosis (RO) building which afforded a view over the seawater lift pump station, screen and feed building, dual media pressure filters and backwash facilities on the southern side. The viewing gallery that will be within the bridge linking the administration building and RO building was also pointed out. On the northern side the remineralisation buildings, power substation and water storages were viewed. The group saw the various stages of membrane installation and planting of the green roof on the RO building. The group then walked through the RO building, seeing the RO racks and glass reinforced piping as well as various mechanical and electrical components. Following the tour, the group returned to the Community Information Centre for the CLG meeting. 2. Welcome / Introductions / Apologies Mr Nicol welcomed everyone to the 22nd CLG meeting and thanked AquaSure and Thiess Degrémont for enabling the group to see the site through a walking tour. Mr Nicol welcomed Graeme Tait, the Project Manager of the Thiess Degrémont Nacap Pipeline Joint Venture (PLJV). Mr Nicol commented that the site tour highlighted how outstanding the project is in terms of its civil engineering scale. 3. Minutes of previous meeting The minutes were adopted as drafted. 4. DSE update Mr Sammut updated the group on DSE activities. There has been continued work with landowners by the DSE Property Team regarding compensation although settlements of final compensation are expected to remain at the current level until reinstatement is completed. Mr Sammut said the PLJV land liaison (for construction) and DSE property teams (for land acquisition and compensation) were doing a good job of working with people, as well as together, and that this would be important to continue during reinstatement. The standard of reinstatement is very important to landowners and PLJV were encouraged to continue to work with landowners on this important next step of the pipeline/power works. Mr Sammut detailed the Independent Review and Environmental Auditor’s (IREA) findings for the month of August. There were no non‐compliances and four areas for improvement with no observations. Four areas for improvement: AquaSure EMS documentation of procedure reviews Audit of review and approval of operational controls Documentation of review and approval authorisation Weather and dust monitoring station The correspondence with one community member is included with the minutes. 5. AquaSure/Thiess Degrémont Presentation Mr Burns discussed the matter of electrical redundancies reported in the media this week. Mr Burns said the desalination project is quite unique, with very unique challenges. The EBA for the project was developed with this in mind. It was designed to allow for flexible rostering arrangements in order to maximise productivity on the project to help get the project delivered on time. . The project’s focus right now is mechanical and electrical installations. Thiess Degrémont recently introduced a 4 day on, 4 day off (4x4) roster for electricians with a goal of achieving maximum productivity. However, the 4x4 roster was not delivering improved productivity or any added value so it is Thiess Degrémont’s intention to return to a traditional construction roster (56 hours per week over 6 days). As a result of that change, around 160 electricians will be made redundant from the project, some earlier than expected. There have been suggestions by the electrical union in the media that this action was designed to provoke strike action. Thiess Degrémont categorically rejects that claim. Mr Burns said the electricians on the project are failing to meet the most basic productivity standards, despite being paid very well, and Thiess Degrémont has taken the necessary action to address that. This is about productivity and nothing more. Mr Burns said they have taken a strong stand on this matter in the media in recent days and wanted to keep the CLG updated. 3 Mr Nicol asked if attempts to drive productivity had met with resistance. Ms Middleton said there had been incidents of intimidatory behaviour towards supervisors and workers staying in sheds after breaks had finished. Mr Goodwin asked if there was any accuracy to the rumours that the redundancies were put in place because of unproductive acts being undertaken by union members. Mr Burns said that there had been incidents such as power disconnections. Mr Burns commented that there are a lot of good workers in a large workforce on site doing a good job but it was very difficult for them when there was a core of people not having the same intent. Cr Dowman asked whether electricians were paid more if the project went on longer or if they were paid a set amount for completing a job. Mr Burns said workers were paid hourly and therefore everyday work goes on they get paid. Mr Sammut commented on the high quality of work being achieved by electricians, describing what he saw with cable laying and terminations as impeccable and impressive. Mr Burns agreed the work was first class and that the electricians were exercising their trade professionally but the ongoing productivity issues persist. Mr Burns provided details on plant site construction: Over 4,300 people working on the project Concrete poured: 63,839m3 of 76,089m3 (83.9%) Precast concrete erected: 35,807m2 of 47,676m2 (75.1%) Structural steel erected: 5,520t of 5,955t (92.7%) Underground High Density Poly Ethylene pipe installed: 13,903 Lm of 17,369 lm (80.0%) Community update Ms Lee presented a community update. There has been a lot of community interest in the green roof and the plants that will be in both the coastal park and on the green roof. As a result, the Community Information Centre now features a sample of the roof system and living plant displays. Thiess Degrémont also recently invited and hosted directors of the Bass Coast Landcare Network on a site visit. They were shown through some of the works being carried out in the coastal park through their partnership with Australian Ecosystems. The Community Relations Team has hosted site visits with Suez Environnement, Chisholm Institute of TAFE and Degrémont. Community presentations since the last CLG include Baw Baw Garden Group, two classes from Newhaven College, two classes from Sydenham Catholic Regional College, Safety Beach Probus and Monash University first year medical students. Through Thiess Degrémont’s community partnership program, support has been provided to Friends of the Wonthaggi State Coal Mine, Wonthaggi Pony Club and the You Are My Sunshine Foundation. Recently the Wonthaggi Community Relations team also donned their Masterchef hats and hosted a dinner for the volunteers of the State Coal Mine. Ms Middleton advised that some plant site workers had assisted a local dancing teacher to enter a Zumba competition with a small Zumba class held in the RO building. This is now on Facebook, where people can vote for their favourite video. Pipeline and power supply construction update Mr Tolson presented an update pointing out that the statistic “100% complete” was appearing increasingly as work progressed. Pipe stringing complete (100%) 82.4 km pipe laying complete (98%) Power conduit welded and trefoiled complete (100%) Power conduit laying complete (100%) 86 km cable laid (98%) Fibre Optic Cable: Distributed temperature sensor (DTS) ‐ 82.8km conduit installed, 61.7km cable 4 installed Fibre Optic Cable: Communications 1 (pipeline) – 56km conduit installed, 3.2km cable installed Fibre Optic Cable: Communications 2 (power) – 90.8km conduit installed, 64.4km cable installed 44 of 45 road crossings complete Mr Burns said hydrotesting for the first 8km of pipeline had been successfully completed. Ms Rappell asked which section had been completed. Mr Burns advised the section between Talinga Court (Berwick) and Pound Road (Cardinia). Mr Sammut said a lot of work had been done by AquaSure, Thiess Degrémont, DSE and Melbourne Water for hydrotesting and that the operational relationships worked well. Mr Tolson updated the group regarding road and traffic management describing the implementation of the Traffic Management Strategy, repair of haulage roads, traffic control for safety and the management of enquiries and complaints by the PLJV Safety Manager for safety issues and the Land Liaison Team for concerned neighbours. The response to repairs is handled by Project Managers and road repair crews and there is consultation through the Traffic Management Liaison Group, involving councils and road authorities. PLJV generally logs 8‐9 road-related complaints each month. Mr Tolson said PLJV understands and empathises with the inconvenience caused by disruption to local roads and is as keen as the community to see the roads reinstated. Repairs are carried out in accordance with a system agreed with the road authorities. Wet weather has presented a significant challenge. Mr Tolson showed images to describe the range of road impacts and repair responses experienced. Minor repairs on Grantville Glen Alvie Rd and more extensive repairs on Turnbull Woolamai Rd were shown. Mr Tolson said localised drainage problems had been an issue in a year of record rainfall when roads would have suffered increased damage but this had been exacerbated by heavy haulage. Crocodile cracking is a common effect that is difficult to repair. PLJV is not responsible for clearing drains but had done so in some areas in order to limit impacts on road edges and crocodile cracking (image from Dalyston‐Glen Forbes Rd). Repair work on a section of Turnbull Woolamai Rd where crews attempted to pull up and replace a damaged section of road provided an example of where repair crews were challenged by lack of foundation to use as a base for hotmix, making it impossible to reinstate a long lasting seal. Another repair option used was illustrated for Stewart Rd where the seal was removed to stabilise the road surface, making it safer, allowing regrading and repairs in wet weather. Mr Tolson said Stewart Rd would be permanently reinstated and the temporary works also provided an improved base for the future permanent rehabilitation works. Mr Tolson said recent improved weather has assisted with condition of roads. The number of outstanding repairs has reduced from 48 to 30, and this would continue to fluctuate. Roads are being progressively cleared of heavy haulage trucks and the haul roads on the easement are due to be removed during September to November 2011. Permanent road reinstatement works are scheduled for November to February 2012. Efforts are being made to clear roads of heavy haulage sooner rather than later. Mr Tolson showed the group a chart illustrating the number of road‐related complaints we have received by PLJV over the past 12 months. Mr Tolson said the numbers of complaints directly reported to PLJV are relatively low. The highest number of complaints received was 29 during peak construction in March 2011. PLJV acknowledges Cr Dowman’s concerns from the last CLG about increasing community concern about road maintenance and encouraged CLG to ask community 5 members to report issues directly. Mr Herbert reinforced that a little more than 200,000m³ of spoil, out of a total of 1,000,000m³ of haul road material, remained to be removed. Mr Tait confirmed that 240,000m³ was left to remove and would be done in September and October just prior to reinstatement. Mr Nicol commented that given his significant municipal experience he understood the challenges that PLJV were facing and that PLJV’s strategy appeared to be as responsible as a local government’s handling of such road issues, and reiterated that responses to road issues should be as quick as possible. Cr Dowman said outstanding repairs had reduced, and that a Peacock Rd complaint has been dealt with. Mr Tait said PLJV has a weekly works plan. Mr Tolson said the weekly work cycle was supported by a 24‐hour response to pot holes where safety was a concern. Cr Dowman asked if haul road material was being removed by particular routes. Mr Tolson advised that only approved haulage routes would be used. Mr Tait said the material is being removed to landfill. 6. Community representatives Mr Goodwin thanked Mr Burns and Ms Middleton for the site walk and commented on the magnitude of the project. Mr Goodwin raised the issue of complaints by school bus drivers about language used on open CB radio channels. Ms Lee said that as it was an open channel it is difficult to identify those responsible, however, it is known to be used by project sub‐contractors and the matter had been addressed. Mr Herbert asked if another channel could be used. Ms Lee said the school bus drivers had been very helpful with this matter and were considering going to a different channel themselves. Mr Goodwin said he had driven over local roads and felt they were generally in good shape with a couple of holes on Stewart Road. Dry weather had assisted this. He raised the issue of mud complaints, however he felt this was primarily due to farmers in paddocks feeding stock and bringing mud onto roads. Mr Goodwin said the area had similar problems in 1996 and the issue has returned with more substantial rain recently. Mr Goodwin said an issue with a landowner having difficulty enabling her cows to cross the easement had been resolved. Mr Tolson said the landowner had been in regular contact and this recent issue had been satisfactorily resolved. Mr Goodwin raised a further landowner issue regarding rehabilitation and horse facilities on a particular property. Mr Goodwin tabled a number of papers relating to this. Mr Sammut said he was also aware of this case and DSE was following the issue up also. Mr Tolson said the issues were around the location of horse yards and was confident the matter would be closed out to the landowner’s satisfaction. Mr Anderson asked when Main Drain Road would reopen. Mr Tolson said he would take this on notice and report back. Action: Mr Tolson to report back to Mr Anderson regarding Main Drain Road. Cr Dowman and Ms Rappell had no issues to raise. Meeting closed 12.05pm 6 7. Next meeting To be held on 22 September at City of Casey at 10am.