Six-Monthly Environmental Compliance Report of
Stipulated Conditions of Environmental Clearance
(April-September, 2014)
FOR
Group Housing Project
“Vedanta”
At Sec-108, Dharampur,
Gurgaon
HARYANA
Submission to:
Ministry of Environment and Forests (MOEF)
Submitted by:
Raheja Developers Ltd.
Dec, 2014
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Page 2 of 16
Contents
Description
Chapter 1 Introduction and Project Description
1.1
Introduction
Page No.
1.2
1.3
1.4
Chapter 2
Part A
Project Description
Present Status
Purpose of the Report
Compliance of Stipulated Conditions of Environmental Clearance
Specific Conditions for buildings in operational phase
I. Construction Phase
4
4
5
Part B
Chapter 3
3.1
3.1.1
3.1.2
3.1.3
II. Operation Phase
General Conditions
Details of Environmental Monitoring
Ambient Air Quality Monitoring
Ambient Air Quality Monitoring Stations
Ambient Air Quality Monitoring Methodology
Ambient Air Quality Monitoring Results
7
10
3.1.4
3.2
3.2.1
3.2.2
3.2.3
3.2.4
Discussion on Ambient Air Quality in the Study Area
Ambient Noise Monitoring
Ambient Noise Monitoring Locations
Methodology of Noise Monitoring
Ambient Noise Monitoring Results
Discussion on Ambient Noise Levels in the Study Area
12
12
12
13
13
14
3.3
3.3.1
3.3.2
3.3.3
3.3.4
3.4
Groundwater Quality Monitoring
Groundwater Quality Monitoring Locations
Methodology of Groundwater Quality Monitoring
Groundwater Quality Monitoring Results
Discussion on Groundwater Quality in the Study Area
Soil Monitoring
14
14
14
14
15
15
3.4.1
3.4.2
3.4.3
3.4.4
Tables
3.1
3.2
Soil Monitoring Locations
Methodology of Soil Monitoring
Soil Monitoring Results
Discussion on Soil Characteristics in the Study Area
15
16
16
16
Details of Ambient Air Quality Monitoring Stations
Techniques used for Ambient Air Quality Monitoring
11
11
3.3
3.4
3.5
3.6
3.7
3.8
Ambient Air Quality Monitoring Results
Details of Ambient Noise Monitoring Stations
Ambient Noise Monitoring Results
Details of Water Quality Monitoring Station
Groundwater Quality Monitoring Results
Details of Soil Quality Monitoring Location
12
13
13
14
14
15
3.9
Figures
3.1
3.2
Annex
Physico-Chemical Characteristics of Soil in the Study Area
16
Variation of Ambient Air Quality
Location wise variation of Ambient Noise Level
12
13
4
6
6
11
11
11
12
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Description
1
2
Environmental clearance letter
Monitoring Reports
Page 3 of 16
Page No.
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Page 4 of 16
Chapter 1
Introduction and Project Description
1.1
Introduction
The Group Housing Complex “Vedanta” is being developed in Dharampur, Sector 108, Gurgaon
Haryana, by /s Raheja Developers. Pvt. Ltd. to facilitate Residential services.
This project has been awarded ‘Gold” grading by SEAC, Haryana.
The project has been sanctioned by the Department of Town & Country Planning (DTCP), Govt.
of Haryana.
This project has been granted environmental clearance by the State Environmental Impact
Assessment Authority, under category 8(a), Haryana vide reference number DEH/09/SEIAA/831
dated 07/07/2009. The total cost of the project is Rs. 153 crores.
1.2
Project Description
Salient Features:
This project involves construction of group housing on a plot area of 43171.796 sq.m. Total Builtup area is 91607.71 sq.m. The proposed building comprises of 2Basements+GF+19 Floors
having two blocks type A and type B. There are 491 no. of dwelling units, 22 nos. of villas, I
community center, 86 EWS and 48 no. of servants units. The project will accommodate 3067
people.
The height of the building is 62 M. The NOC from airport authority has already been obtained.
The total water requirement is will be 510KLD, which will be supplied by HUDA/Bore well. The
waste water generation will be about 363 KLD which will be treated in STP of 436 KLD capacity.
The 236 KLD of treated water will be reused in horticulture, cooling of DG, flushing and washing
and the excess water will be discharge into the drain with permission.
Total solid waste generation will be 1320 Kg/day, which will be disposed off as per SWM &
Handling Rules.
Parking:
The building project will have adequate parking facility with 612 ECS in basement, open and stilt
area.
Electricity:
The building will avail electricity from Dakshin Haryana Vidyut Vitran Nigam Ltd. The power
requirement is approximately 4635 KVA.
1.3
Present Status
Project is in construction phase.
1.4
Purpose of the Report
This six-monthly report is being submitted as per the condition stipulated in the Environmental
Clearance letter.
Further, the study will envisage the environmental impacts that have generated in the local
environment due to the project.
The environmental assessment is being carried out to verify:
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions





Page 5 of 16
That the project does not have any adverse environmental impacts in the project area and its
surrounding
Compliance with the conditions stipulated in the Environmental Clearance Letter.
That the Project Management is implementing the environmental mitigation measures as
suggested in the approved Form-1, Form-1A, Environmental Management Plan (EMP) and
building plans.
The project proponent is implementing the environmental safeguards in true spirit.
Any non-conformity in the project with respect to the environmental implication of the project.
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Page 6 of 16
Chapter 2
Compliance of Stipulated Conditions of Environmental Clearance for Buildings in Construction &
Operational Phase
PART A – SPECIFIC CONDITIONS
I.
S.
No.
1
2
3
4
5
6
7
8
Construction Phase
Conditions of Environmental Clearance
Status of Compliance
A first aid room will be provided in the
project both during construction and
operation phase of the project.
Adequate drinking water and sanitary
facilities
should
be
provided
for
construction workers at site. Provision
should be made for mobile toilets. Open
desiccation by the labours strictly
prohibited. The safe disposal of waste
water and solid wastes generated during
the construction phase should be ensured.
All the topsoil excavated during construction
activities should be stored for use in
horticulture/landscape development within
the project site
Disposal of muck during construction phase
should not create any adverse effect on the
neighboring communities and be disposed
taking the necessary precautions for general
safety and health aspects of people, only in
approved sites with the approval of
competent authority.
Construction spoils, including bituminous
material and other hazardous materials, must
not be allowed to contaminate watercourses
and the dump sites for such material must be
secured so that they should not leach into the
ground water and any hazardous waste
generated during construction phase, should
be disposed off as per applicable rules and
norms with necessary approval of the
Haryana State Pollution Control Board.
The diesel generator sets to be used during
construction phase should be of low sulphur
diesel type and should conform to
Environment (Protection) Rules prescribed
for air and noise emission standards
The diesel required for operating DG sets
shall be stored in underground tanks and if
required, clearance from Chief Controller of
Explosives shall be taken.
Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be
closely monitored during construction phase.
Adequate measures should be taken to
reduce ambient air and noise level during
construction phase, so as to conform to the
First aid facility is readily available at the project
site in the custody of the project in charge
Supply of drinking water and provision of
sanitary facility have been provided within the
project site. There is provision of mobile toilets
for the construction workers and open
desiccation is prohibited. The safe and proper
disposal of solid waste is in practice.
Top soil is stored at secured location and will be
used for landscaping after completion of civil
work.
There is no larger quantity of muck generated
during construction activity.
Hazardous waste generated is being disposed
as per HSPCB guideline
Construction spoils, including bituminous
material and other materials is disposed off in
scientific manner. There is no adverse impact on
the watercourses. This is a construction project
for residential purposes therefore; no hazardous
waste would be produce.
Low sulphur diesel is being used to run the DG
sets during power failure and it confirms to
Environment (Protection) Rules prescribed for
air and noise emission standards
The diesel required for operating DG sets is
stored/ secured in such a way that no accidents,
spillage and leakage possible. However,
permission will be taken during operation phase.
Ambient noise level monitoring was carried out
and it was found to be within the prescribed limit
of residential standards during day and night.
Incremental pollution loads on the ambient air
and noise quality is closely monitored during
construction phase. Adequate measures have
been taken to reduce ambient air and noise level
during construction phase.
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
S.
No.
9
10
11
12
13
14
15
16
17
Conditions of Environmental Clearance
stipulated standards.
Fly ash should be used as building material
in the construction as per the provisions of
Fly Ash Notification of September, 1999 and
amended as on 27th August 2003
Ready mix concrete must be used in building
construction
Storm water control and its re-use as per
CGWB and BIS standards for various
applications
Water demand during construction should be
reduced by use of pre-mixed concrete, curing
agents and other best practices referred
Permission from competent authority for
supply of water shall be obtained prior to
construction/ operation of the project
Roof should meet prescribed requirement as
per Energy Conservation Building Code by
using
appropriate
thermal
insulation
materials to fulfill requirement
Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it is aspirational for non-air-conditioned
spaces by use of appropriate thermal
insulation material to fulfill requirement.
The approval of the competent authority shall
be obtained for structural safety of the
building due to earthquake, adequacy of fire
fighting equipments etc. as per National
Building Code including protection measures
from lighting etc. If any forest land is involved
in the proposed site, clearance under forest
Conservation Act shall be taken from the
competent Authority
During Construction phase the project
proponent will use water brought to the site
by tankers from safe area. In no case the
ground water will be abstracted/developed
except with the permission of the DC/CGWA.
Page 7 of 16
Status of Compliance
Fly ash is being used in Ready Mix Concrete as
building material in the construction as per the
provisions of Fly Ash Notification of September,
1999 and amended as on 27th August 2003
Ready Mix Concrete is being used for the
project.
Storm water was controlled by laying proper
internal drainage network within the project site.
To conserve water, pre-mixed concrete, curing
agents and other best practices are followed.
Assurance for Water supply will be obtained
from for the operation phase.
Energy conservation measures
adopted for roof treatment.
would
be
Energy conservation
adopted for walls.
would
be
measures
All approvals from the competent authority are
under process for structural safety of the building
due to earthquake, adequacy of fire fighting
equipments etc and will be submitted soon.
No forest land is involved. The project site is
designated under residential land use;
For the construction purposes, water will be
brought to the site by tanker; however,
permission from HUDA will be obtained if
required.
II. Operation Phase
S.
No
1
2
Conditions of Environmental Clearance
Status of Compliance
The STP shall be installed for the treatment
of the sewage generated to the prescribed
standards including odour and treated
effluent will be recycled to achieve zero
discharge. The STP should be installed at
the farthest place in the project area.
Separation of gray and black water should
be done by the use of dual plumbing line.
Treatment of 100% gray water by
decentralized treatment should be done
There is a provision of STP for treating entire
sewage generated from the building.
Provision of dual plumbing has been made for
separation of grey and black water. It is ensured
that 100% treatment of grey water according to
the specified condition and treated waste water
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
3
4
5
6
7
8
9
10
11
ensuring that the recirculated water should
have BOD maximum 10 pm and the
recycled water will be used for flushing,
gardening and HVAC makeup and DG set
cooling.
For disinfections of the treated wastewater
ultra violate radiation or ozonization should
be used.
The solid waste generated should be
properly collected and segregated. Wet
garbage should be composted and dry/inert
solid waste should be disposed off to the
approved sires for land filling after
recovering recyclable material
Diesel power generating sets proposed as
source of backup power for lifts, common
area illumination and for domestic use
should be of enclosed type and conform to
rules made under the Environment
(Protection) Act, 1986. The location of the
DF sets should be in the basement as
promised by the project proponent with
appropriate stack height as per the CPCB
norms. The diesel used for DG sets should
be of low sulphur contents (Maximum
0.25%)
Ambient Noise level should be controlled to
ensure that it does not exceed the prescribed
standards both within and at the boundary of
the proposed Commercial Complex.
The project proponent should maintain at
least 15% as green cover area for tree
plantation especially all around the periphery
of the project and on the road sides
preferably with local species so as to provide
protection against particulate and noise. The
open spaces inside the plot should be
preferably landscaped and covered with
vegetation/grass.
Weep holes in the compound walls shall be
provided to ensure natural drainage of rain
water in the catchment area during the
monsoon period
Rain water harvesting for roof run-off and
surface run-off as per plan submitted should
be implemented. Before recharging the
surface runoff, pre run off treatment must be
done to remove suspended matter, oil and
grease. The bore well for rain water
recharging should be kept at least 5 m above
the highest ground water table.
The ground water level and its quality should
be monitored regularly in consultation with
Central Ground Water Authority.
There should be no traffic congestion near
the entry and exit points for the road
adjoining the proposed project site. Parking
should be fully internalized and no public
Page 8 of 16
will be used for flushing, landscaping & DG
Cooling in the operation phase.
Same will be complied during operation phase.
Solid waste will be disposed through authorized
waste collector and disposed in the solid waste
management facility at approved site for solid
waste treatment and disposal.
DG sets installed would be of enclosed type
conforming to the rules made under EP Act
1986.
DG stack would go above building block. The
height above building block would be as per
CPCB norms.
Low sulphur diesel (with maximum sulphur
content of 0.25%) would be used for operating
DG Sets.
Ambient noise level at the project site during
operation phase will be monitored and it will be
ensured that the ambient noise level would not
exceed the prescribed standards both within and
at the boundary of the project site as per the
residential standards.
Landscape will be developed after completion of
entire civil construction works. There is provision
of green belt development in the project area
and of green cover area for tree plantation
especially all around the periphery of the project
and on the road sides preferably with local
species so as to provide protection against
particulate and noise.
There is provision of weep holes in the
compound walls for natural drainage of rain
water in the catchment area during the monsoon
period
Adequate number of RWH pits will be
constructed in the operational part of the
building. RWH pits have been designed as per
CGWB norms.
The ground water level and its quality would be
monitored regularly in consultation with Central
Ground Water Authority.
It will be ensured that no traffic congestion take
place.
No public space will be utilized for parking during
operation phase
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
12
13
14
15
16
17
space should be utilized.
A report on the energy conservation
measures conforming to energy conservation
norms finalize by Bureau of Energy
Efficiency should be prepared incorporating
details about building materials and
technology, R & U Factors etc. and submit to
the IA Division of Environment Department,
Haryana in three months time
Energy
conservation
measures
like
installation of CFLs/ TELs for lighting the
areas outside the building should be integral
part of the project design and should be in
place before project commissioning. Used
CFLs and TFLs should be properly collected
and disposed off/ sent for recycling as per
the prevailing guidelines/ rules of the
regulatory authority to avoid mercury
contamination. Use of solar panels should be
done to maximum extent possible.
The solid waste generated should be
properly collected and segregated as per the
requirement of the MSW Rules 2000. The
wet garbage should be sent for composting
and dry/inert solid waste should be disposed
off to the approved site for land filling after
recovering recyclable materials.
The provision of the solar water heating
system shall be as per the norms specified
by HAREDA and shall be made operational
in each building block
The project will be operationalized only after
commissioning of the infrastructure for
supply of water by HUDA or with permission
of DC.CGWA for using ground water from
the tube well/bore wells.
In no case except as provided by the CGWA,
the ground water will be exploited and
developed.
Page 9 of 16
The report on the energy conservation measures
conforming to energy conservation norms
finalized by Bureau of Energy Efficiency will be
prepared and the same will be submitted to the
IA Division of Environment Department, Haryana
Energy efficient luminaries like CFL would be
used in common areas during the operational
phase of the project.
Solid waste will be collected by MCG authorized
collector and disposed off securely at Municipal
Waste Management Facility
Solar water heating system will be provided after
completion of civil construction works
Same will be complied during operation phase.
It is ensured that in no case except as provided
by the CGWA, the ground water will be exploited
and developed.
PART B – GENERAL CONDITIONS
S.
No.
I
II
III
Conditions of Environmental Clearance
Status of Compliance
The environmental safeguards contained in
the EIA/EMP report should be implemented
in letter and spirit.
Environmental Safeguards as prescribed by the
ministry of environment and forests in the
clearance document is being implemented in
true spirit.
Six monthly environmental compliance reports
has been prepared and is being submitted to the
HSPCB and Regional office, MOEF, GOI,
Northern Region, Chandigarh.
Six-monthly monitoring reports should be
submitted to the HSPCB and Regional Office,
MOEF, GOI, Northern Region, Chandigarh
and a copy to the Regulatory Authority of
Haryana.
The project proponent will sent one copy of
the EMP report to Additional Director,
Regional Office, MOEF, GOI, Sector 31, and
Chandigarh and to the Chairman, Haryana
State Pollution Control Board for their
reference.
Already been submitted.
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
S.
No.
IV
V
VI
VII
Page 10 of 16
Conditions of Environmental Clearance
Status of Compliance
The SEIAA, Haryana reserves the right to
add
additional
safeguard
measures
subsequently,
if
found
necessary.
Environment Clearance granted will be
revoked if it is found that false information
has been given for getting approval of this
project.
All other statutory clearances such as the
approvals for storage of diesel from Chief
Controller of Explosives, Fire Department,
Civil
Aviation
Department,
Forest
Conservation Act, 1980 and Wildlife
(Protection) Act, 1972, shall be obtained, as
applicable by project proponents from the
respective authorities.
These stipulations would be enforced among
others under the provisions of Water
(Prevention and Control) Act, 1981, the
Environmental Protection Act 1986, The
Public Liability (Insurance) Act, 1991 and EIA
Notification, 2006.
The project proponent will not violate any
judicial orders/ pronouncement issued by the
Hon’ble Supreme Court/High Courts.
The project will accept any suggestion by the
SEIAA for environmental safeguard.
All other statutory clearances required for the
project will be obtained soon from the concerned
authorities.
These stipulations are being enforced among
others under the provisions of Water (Prevention
and Control) Act, 1981, the Environmental
Protection Act 1986, The Public Liability
(Insurance) Act, 1991 and EIA Notification,
2006.
The project proponent will abide any judicial
orders/ pronouncement issued by the Hon’ble
Supreme/High Courts.
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Page 11 of 16
Chapter 3
Details of Environmental Monitoring
3.1
AMBIENT AIR QUALITY MONITORING
3.1.1
Ambient Air Quality Monitoring Stations
Ambient air quality monitoring has been carried out at one location, being near main gate to
assess the ambient air quality. This will enable to have an analytical understanding about air
quality and the changes in the air environment in the study area with respect to the condition
prevailing. The locations of the ambient air quality monitoring stations are given in Table 3.1.
Table 3.1 Details of Ambient Air Quality Monitoring Station
S. Locn.
No. Code
1.
AAQ-1
3.1.2
Location Name/ Description
Environmental Setting
Near main gate
Residential
Ambient Air Quality Monitoring Methodology
Monitoring was conducted in respect of the following parameters:
 Particulate Matter 2.5 (PM 2.5)
 Particulate Matter 10 (PM 10)
 Sulphur Dioxide (SO2)
 Oxides of Nitrogen (NO x)
 Carbon Monoxide (CO)
The duration of sampling of PM2.5, PM10, SO 2 and NOx was 24 hourly continuous sampling per
day and CO was sampled for 8 hours continuous, thrice in 24 hour duration monitoring. The
monitoring was conducted for one day at the location. This is to allow a comparison with the
National Ambient Air Quality Standards.
The air samples were analyzed as per standard methods specified by Central Pollution Control
Board (CPCB) and IS: 5182.The techniques used for ambient air quality monitoring and minimum
detectable levels are given in Table 3.2.
Fine Particulate Sampler APM 550 instruments have been used for monitoring Particulate Matter
2.5 (PM2.5 i.e. <2.5 microns), and Respirable Dust Sampler APM 450 was used for sampling
Respirable fraction (<10 microns), gaseous pollutants like SO2, and NOx. Bladder and Aspirator
bags were used for collection Carbon monoxide samples. Gas Chromatography techniques have
been used for the estimation of CO.
Table 3.2 Techniques used for Ambient Air Quality Monitoring
S.
Parameter
No.
1
Particulate Matter
2.5
2
3
4
5
Technique
Fine Particulate Sampler
APM 550, Gravimetric
Method
Particulate Matter 10 Respirable Dust Sampler
APM 450, with cyclone
separator, Gravimetric
Method
Sulphur dioxide
Modified West and Gaeke
Oxides of Nitrogen Jacob & Hochheiser
Carbon Monoxide
Gas Chromatography
Technical Protocol
IS-5182 (Part-IV)
IS-5182 (Part-23)
IS-5182 (Part- II)
IS-5182 (Part-VI)
IS-5182 (Part-X)
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
3.1.3
Page 12 of 16
Ambient Air Quality Monitoring Results
The detailed on-site monitoring results of PM 2.5, PM 10, SO2, NOx and CO are presented in
Table 3.3.
Table 3.3 Ambient Air Quality Monitoring Results
S. Locn.
No. Code
1.
3.1.4
Location
PM10
(g/m3)
PM2.5
(g/m3
SO2
NOx
CO
(g/m3) (g/m3) (mg/m3)
Limit
100
60
80
80
2.0
AAQ-1 Near main gate
158
57
17
51
1.27
Discussion on Ambient Air Quality in the Study Area
PM10 levellevels at the project site are above the limit of 100 μg/m (for residential, rural and other
areas as stipulated in the National Ambient Air Quality Standards). PM2.5, SO2, NOx and CO was
observed within the corresponding stipulated limits (Limit for Pm2.5 60 μg/m3, SO2 and NOx: 80
g/m3 and limit for CO: 2.0mg/m3) at all monitoring locations. Station wise variation of ambient air
quality parameters has been pictorially shown in Figure 1
160
140
120
100
Code Limit
80
60
40
AAQ-1 Nearby area
toward the main gate of
project site
20
(ug/m3)
(mg/m3)
PM10 PM2.5
(ug/m3)
(ug/m3
(ug/m3)
0
SO2
NOx
CO
Figure 3.1 Location-wise Variation of Ambient Air Quality
3.2
AMBIENT NOISE MONITORING
3.2.1
Ambient Noise Monitoring Locations
The main objective of noise monitoring in the study area is to assess the present ambient noise levels in the
nearby area of project site & project boundary due to various construction allied activities and increased
vehicular movement. A preliminary reconnaissance survey has been undertaken to identify the major noise
generating sources in the area. Ambient noise monitoring was conducted at 2 locations in the nearby area
of the project site as given in Table 3.4.
Table 3.4 Details of Ambient Noise Monitoring Stations
S. No. Locn. Code
Location Name/ Description
1.
N1
Near main gate
2.
N2
Backside of the building
3.2.2
Methodology of Noise Monitoring
Present Land use
Residential
Residential
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Page 13 of 16
Noise levels were measured using integrated sound level meter manufactured by Quest
Technologies. The integrating sound level meter is an integrating/ logging type with Octave filter
attachment with frequency range of 31.5 to 16000 Hz. This instrument is capable of measuring
the Sound Pressure Level (SPL), Leq and octave band frequency analysis.
Noise level monitoring was carried out continuously for 24-hours with one hour interval starting at
0030 hrs to 0030 hrs next day. The noise levels were monitored on working days only. During
each hour Leq were directly computed by the instrument based on the sound pressure levels.
Lday (Ld), Lnight (Ln) and Ldn values were computed using corresponding hourly Leq.
Monitoring was carried out at ‘A’ response and fast mode.
3.2.3
Ambient Noise Monitoring Results
The time wise ambient noise monitoring results is summarized in Table 3.5. The location-wise
variation of noise levels are graphically presented in Figure 3.2.
Table 3.5 Ambient Noise Monitoring Results
Sr.
No.
D-1
D-2
Day Time - dB(A)
Limits as per
Results
CPCB
guideline
54.3
55
52.1
Test Locations
Near Main Gate
Back Side of the building
Night Time - dB(A)
Results
Limits as per
CPCB guideline
42.7
41.2
45
60
50
40
30
Near Main Gate
20
Back Side of the building
10
0
Results
Limits as
per CPCB
guideline
Day Time - dB(A)
Results
Limits as
per CPCB
guideline
Night Time - dB(A)
Figure 3.2 Ambient Noise Level
3.2.4. Discussion on Ambient Noise Levels in the Study Area
Day Time Noise Levels (Lday):
The day time noise level at all the locations were found to within the limits prescribed for
Residential area i.e. 55 db(A).
Night Time Noise Levels (Lnight):
The night time noise level at all the locations were found within limit prescribed for Residential area
i.e. 45 dB (A).
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
3.3
GROUNDWATER QUALITY MONITORING
3.3.1
Groundwater Quality Monitoring Locations
Page 14 of 16
Keeping in view the importance of groundwater as an important source of drinking water to the
local population, sample of ground water was collected from the project site for the assessment
of impacts of the project on the groundwater quality.
Water sample was collected from one location near the project site. The sample was analyzed for
various parameters to compare with the standards for drinking water as per IS: 10500 for ground
water sources. The details of water sampling locations are given in Table 3.6.
Table 3.6 Details of Water Quality Monitoring Station
S. No.
1.
3.3.2
Locn. Code Location Name/ Description
GW1
Project Site
Methodology of Groundwater Quality Monitoring
Sampling of ground water was carried out on September 2014. Samples were collected as grab
sample and sampling forms are filled in as per the sampling plan. The preservative sample were
properly added to preserve as per standard operating procedures (SOP) and stored immediately in
ice boxes, which were ensured for appropriate temperatures. Sample for chemical analysis was
collected in polyethylene carboys. Sample collected for metal content were acidified to <2 pH with
1 ml HNO3. A sample for bacteriological analysis was collected in sterilized glass bottles.
Soon after the completion of sampling, chain of custody sheets for the samples are filled in and
then they were transported by road to ITL Labs Pvt. Ltd., Delhi for further analysis. Proper care was
taken during packing and transportation of samples. All the samples reached the central laboratory
within the holding times for different parameters. After ensuring the same the samples were
forwarded immediately for analysis.
The samples were analyzed as per the standard procedures specified in 'Standard Methods for the
Examination of Water and Wastewater' published by American Public Health Association (APHA)
and CPCB. The analytical techniques and the test methods adopted for testing of ground water are
given in Table 3.7.
3.3.3
Groundwater Quality Monitoring Results
The detailed groundwater quality monitoring results are presented in Table 3.7.
Table 3.7 Groundwater Quality Monitoring Results
S.
No.
Parameter
Unit
Results
Protocol
Drinking Water Specification
(IS: 10500:1991)
Desirable Limit
Permissible Limit
5 Hazen Unit
Unobjectionable
Agreeable
1
15 Hazen Unit
--5
Organoleptic and Physical Parameters
1.
2.
3.
4.
Colour
Odour
pH
Turbidity
---NTU
5.
Total Dissolved solids
mg/l
1970
IS 3025 Part 16 / APHA
21ST ED., 3112
500
2000
Desirable Characteristics in Drinking Water
6.
Total Hardness as CaCO3
mg/l
553
IS 3025(Part 21)
200
600
mg/l
mg/ l
178
26
IS: 3025(PART-40)
IS 3025 Part 46
75
30
200
100
mg/l
316
IS 3025(Part 23)
200
600
mg/l
mg/l
833
134
IS: 3025(PART-32)-2003
IS 3025(Part 24)
250
200
1000
400
7.
8.
9.
10.
11.
Calcium as Ca
Magnesium as Mg
Total Alkalinity as Calcium
Carbonate
Chloride as Cl
Sulphate as SO4
2
Agreeable
7.2
1.70
IS: 3025(PART-4)-2002
IS: 3025(PART-5)-2002
IS: 3025(PART-10)-2012
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
Iron as Fe
mg/l
Fluoride as F
mg/l
Copper as Cu
mg/l
Free Residual Chlorine
mg/l
Nitrate as NO 3
mg/ l
Sulphide as H2S
mg/l
Barium (as Ba)
mg/l
Mangnese as Mn
mg/ l
Mineral Oil
mg/ l
Boron
mg/l
Phenolic
mg/l
Compound(C6H5OH)
23.
Zinc as Zn
mg/l
24.
Aluminium
mg/l
25
Ammonia
(as
Total
mg/l
Ammonia-N)
26.
Anioinic Detergents (as
mg/l
MBAS)
Parameters Concerning Toxic Substances
27.
Cadmium as Cd
mg/l
28.
Lead as Pb
mg/l
29.
Nickel as Ni
mg/l
30
Arsenic (As)
mg/l
0.16
0.15
0.03
ND
4.6
ND
0.02
0.01
ND
ND
ND
IS 3025 Part 53
IS 3025 Part 60
IS 3025 Part 42
IS 3025 Part 26
IS 3025 Part 34
IS 3025(Part 29)
IS 13428 or IS 15302
IS 3025 Part 59
IS 3025 Part 39
IS 3025 Part 57
IS: 3025(PART-43)
2.45
0.001
0.039
IS 3025(Part 49)
IS 3025(Part 55)
IS 3025(Part 34)
ND
Annex K of IS 13428
ND
0.005
ND
ND
IS 3025(Part 41)
IS 3025(Part 47)
IS 3025(Part 54)
IS 3025(Part 54)
Page 15 of 16
0.3
1.0
0.05
0.2
45
0.05
0.7
0.1
0.5
0.5
No relaxation
1.5
0.05
1.0
No Relaxation
No Relaxation
No Relaxation
0.3
No relaxation
1.0
0.001
0.002
5
0.03
15
0.2
0.5
No relaxation
0.2
1.0
0.003
0.01
0.02
0.05
No Relaxation
No Relaxation
No Relaxation
0.05
* BDL: below detection limit : detection limit
3.3.4
Discussion on Groundwater Quality in the Study Area
The ground water quality in the project area is observed to having total alkalinity up to 316 which is
slightly higher than desirable limit of 200 mg/L. Total dissolved solids in the ground water is 1970
mg/L which is higher than the prescribed limit of 500 mg/L.
3.4
SOIL MONITORING
3.4.1
Soil Monitoring Locations
The objective of the soil monitoring is to identify the impacts of ongoing project activities on soil
quality and also predict impacts, which have arisen due to execution of various constructions
allied activities. Accordingly, a study of assessment of the soil quality has been carried out.
To assess impacts of ongoing project activities on the soil in the area, the physico-chemical
characteristics of soils were examined by obtaining soil samples from selected points and
analysis of the same. One sample of soil was collected from the project site for studying soil
characteristics, the location of which is listed in Table 3.8.
Table 3.8 Details of Soil Quality Monitoring Location
S. No.
1.
3.4.2
Locn. Code
S1
Location Name/ Description
Nearby area of Project Site
Methodology of Soil Monitoring
The sampling has been done in line with IS: 2720 & Methods of Soil Analysis, Part-1, 2nd edition,
1986 of American Society for Agronomy and Soil Science Society of America. The homogenized
samples were analyzed for physical and chemical characteristics (physical, chemical and heavy
metal concentrations). The soil samples were collected in the month of May 2014.
The samples have been analyzed as per the established scientific methods for physico-chemical
parameters. The heavy metals have been analyzed by using Atomic Absorption Spectrophotometer and Inductive Coupled Plasma Analyzer.
3.4.3
Soil Monitoring Results
Project: Group Housing Project “Vedanta” At Sec-108, Dharampur, Gurgaon. Haryana
Half-yearly Compliance Report of EC Conditions
Page 16 of 16
The physico-chemical characteristics of the soil, as obtained from the analysis of the soil sample,
are presented in Table 3.9.
Table 3.9 Physico-Chemical Characteristics of Soil in the Study Area
S. No
3.4.4
1.
Parameter
pH
Unit
-
Results
2.
Conductivity
mS
1.4
3.
Moisture Content
%
5.7
4.
Total Alkalinity
mg/kg
114
5.
Water Holding capacity
mg/kg
52
6.
Phosphorous as P
%
<0.36
7.
Porosity
%
42
8.
Zinc as Zn
mg/Kg
0.84
9.
Iron as Fe
mg/Kg
0.69
10.
11.
Chloride as Cl
Sodium as Na
mg/100gm
meq/100gm
214
12.
Potassium as K
meq/100gm
25
13.
Nitrogen as N
mg/kg
22
7.8
3
14.
Bulk Density
g/cm
15.
Organic Content
%
16.
Cation Exchange Capacity
meq/100gm
17.
Heavy Metals
67
1.46
0.76
11
Lead(Pb)
mg/kg
0.77
Copper(Cu)
mg/kg
1.42
18.
Calcium
mg/100gm
13.10
19.
Magnesium
mg/100gm
1.11
Discussion on Soil Characteristics in the Study Area
The soil in study area is characterized by neutral nature. The soil quality in the project area has
not been affected by the project activities.