CERN PROJECT DOCUMENT IDENTIFIER FCC-ACC-MIN-0031 CH-1211 Geneva 23 Switzerland Date : FCC EDMS NO. 1548459 2015-09-23 MEETING MINUTES – APPROVED Subject: Infrastructure & Operation Coordination Group #18 Date and Time: 2015-09-23, from 10:00 to 11:55 Place: 30/6-019 Participants: Michael Benedikt, Davide Bozzini, Charlie Cook, Eugenia Hatziangeli, Philippe Lebrun, Volker Mertens (chair), John Osborne, Guillermo Peon, Aniko Judit Rakai, Ingo Rühl, Peter Sollander (secretary) Excused: Paul Collier, Rende Steerenberg, Laurent Tavian WBS: File Location/Link: https://edms.cern.ch/document/1548459 Agenda 1. Minutes of the previous meeting 2 2. Combining FCC-hh and FCC-ee: CE challenges 2 3. Power estimates for cooling and ventilation 3 4. CFD simulations for the design of the FCC ventilation system 4 5. Status of ongoing work in IOWG (Tour de table) 6 6. Review of outstanding actions 6 7. AOB 9 Page 1 of 9 EDMS NO. 1548459 1. Minutes of the previous meeting Volker welcomed to the 18th meeting. He suggested the following generic sequence for future IOWG meetings, which was adopted: approval of minutes, topical presentations, round-table and open actions, AOB. He has asked Peter to update the list of working group members. The minutes of the meeting held August 28th were approved with a few corrections and will be published on EDMS 1537241. Concerning the length of the machine Michael said that he will provide a short list of more fine-grained length intervals in the range 93 to 100 km. He commented that the most important input will come from the iteration of the civil engineering study, which looks into the non-intersecting 100 km version protruding more under the pre-Alps. Volker reported that the Special Technologies Working Group meeting planned for the beginning of September had been postponed to a later date and does no longer demand a presentation from the FCC IOWG. 2. Combining FCC-hh and FCC-ee: CE challenges Charlie presented some of the challenges faced by the civil engineering team to accommodate both the FCC-hh and FCC-ee machines. He listed three main issues: 1. Separating the beam lines by up to 13 m at the main interaction points would require a 1.8 km stretch of double tunnel resp. an enlarged tunnel, on both sides of the IPs (the rock between the two tunnels would have to be removed and replaced by concrete once the distance would underpass 3 m). Michael noted that one may not need a full 6 m diameter tunnel for the lepton machine. On a question he explained that the current assumption is that we first build the lepton machine and later the hadron machine and that the design should allow to house both. John remarked that the civil engineering cost for these enlarged parts could become enormous. The enlargements would typically be excavated first with several road headers working simultaneously. The other parts of the ring would subsequently be drilled with tunnel boring machines (TBM); two TBMs could be used if a double tunnel option would be chosen, like in the case of the Eurotunnel. Philippe asked where the top-up ring would be located. Michael recalled that it is represented by the green line in the graph Page 2 of 9 EDMS NO. 1548459 shown in the previous meeting. John proposed to make first cost estimates for different options of the 4 x 1.8 km. 2. The swing of the FCC-hh ring across the tunnel cross-section by up to 2 m. Early data indicate that there could be differences in transverse position which would require a tunnel diameter of up to 8 m. Michael said that the accelerator design people have to review the position of the rings. A tunnel diameter of 8 m would be excluded. However there might be no easy solution as the geometry varies strongly with the assumed cell length. 3. The required span of the experimental caverns is uncertain. Currently there are two options for the FCC-hh experimental caverns, one with 38 m span for a twin solenoid detector and one of 44 m for a toroid detector. The FCCee detector sizes are not yet known; 6 m are assumed as radius in the two options shown. Philippe suggested to use the ILC detectors as example and added that the limit on the lepton detector comes from the top-up ring. Michael asked whether the second tunnel could have a smaller diameter. John replied that 6 metres is the standard European tunnel-boring diameter and that a smaller diameter may actually be more expensive. Ingo asked whether the cavern size already included the space for cranes. Charlie replied that the height will be defined by the requirement to get the detectors into the caverns. John believed that there is enough height above the detectors. Volker asked John to produce a more detailed design of the cavern cross section. Guillermo asked whether there would be separate service galleries; Volker confirmed that this should be foreseen. 3. Power estimates for cooling and ventilation Davide presented the latest results from the power consumption study of the LHC, including data for this year’s very warm summer. In slide 3 the data for June-July-August of 2012 (beam energy 4 TeV, blue data points) and 2015 (6.5 TeV, orange) are compared (without experiments which account for another ca. 20 MW). The power of the cooling and ventilation systems follows the ambient temperature (slide 4), with a peak 12 MW daily average on the hottest day. Overlaid are short-term variations from the machine operation. While the cryogenics load is more or less constant the power consumption from magnet powering or RF and consequently the thermal load can vary from one day to the Page 3 of 9 EDMS NO. 1548459 next; this has not been detailed further. Volker noted that the latter seems to dominate. Davide explained that it would be interesting to dispose of a full year worth of data, to derive more information on the dependencies. EN-EL will demand a Fellow to study CERN’s power consumption in more detail. Guillermo noted that there is a significant difference between the calculated (i.e. expected) consumption for EN-CV and what EN-EL is measuring (slide 7). Davide noted that the 10 MW for general services also include the power drawn from all the sockets around the machine; cooling and ventilation is only a part of it. Michael remarked that the 75 MW of power installed for CV include also the spares, backup systems, etc. which are not running all the time; Guillermo confirmed that. The 31 MW correspond to what is in principle all the time running, resp. could be running; clearly services for which there was not demand from the thermal load would be (automatically) switched off. Peter inquired about the next steps. Guillermo said that one should look more in detail what is running or not, and compare again the calculated and measured values. Peter wondered how that would scale to FCC. Philippe commented that to first order the ventilation needs scale with volume and the cooling needs by dissipated power. He considered the cited peak consumption of 22 MW to be wrong. The installed power and the average power consumption shall not be mixed. Michael also cautioned against “over-designing” the system. Volker suggested complementing the estimates by a bottom-up compilation departing from the present draft specifications. Action: EN-EL and EN-CV to understand better the consumption data and their main contributors and reduce the apparent discrepancies. 4. CFD simulations for the design of the FCC ventilation system Aniko Judit Rakai presented first results of numerical CFD simulations for the design of the ventilation system (CFD = Computational Fluid Dynamics). She noted that the FCC tunnel has neither a simple (pipes, supports, cable trays) nor a regular (fire curtains) cross-section. To make the calculations less complicated simplifications need to be made. The fire curtains are supposed to be open during normal operation. Assuming isothermal conditions is another start parameter. Page 4 of 9 EDMS NO. 1548459 3D (software/computer based CFD) calculations have been carried out and compared to values obtained using an analytical 2D approach (textbook equations); in both cases the Navier-Stokes equations need to be solved all along the length of the tunnel. Similar results have been obtained. It seems therefore reasonable to use an analytical method to estimate the pressure drop along the FCC tunnel. Volker observed that the value of ACH = 0.5 (air change rate/h) is probably too low. In LHC it would be closer to or above 1. Michael noted that the pressure drop is dominated by tunnel friction and asked how important the surface quality of the walls is. Aniko replied that it is important that the tunnel is “hydraulically smooth”. Philippe commented that this condition is easy to reach and that the habitual surface of accelerator tunnels can indeed be considered smooth. Volker asked how equipment like cable ladders, support posts etc. can be included in the model. Aniko answered that she can consider the equipment as an obstruction, knowing the size of it. Philippe noted that the electron machine should also be studied. It is different in that it will bring heat into the tunnel, unless there is a way to absorb a significant fraction of this heat, like as in LEP into the non-insulated cooling pipes. The isothermal assumption may be too simplistic. The booster ring shall be added as well. On a question about the sensitivity of the results obtained with respect to the tunnel lengths Aniko replied that it is linear with the length and pressure assuming constant friction and curtains in regular intervals. A priori the safe passage compartment should be slightly over-pressurised with respect to the machine tunnel. Philippe remarked that the difference shall be no larger than 50 Pa to allow opening (or closing) the doors to the safe passage. To avoid the pressure difference to build up there must be several ventilation feeding points into the tunnel sections. In case of loss of ventilation (power cut, fault) relief valves should ensure that the safe passage can still be accessed without too big difficulties. NDLR (following meeting on October 28th): André commented that the over-pressure should be between 20 and 80 Pa. This is still ok to open or close doors. Page 5 of 9 EDMS NO. 1548459 5. Status of ongoing work in IOWG (Tour de table) Michael suggested to start drafting the positions of technical infrastructure around the ring. Civil engineers and FCC-ee machine designers shall discuss together to converge on the layout. Michael recalled that an FCC-ee optics and beam dynamics review is planned for October 14th (with an FCC-hh injection energy review two days later) and that the tunnel integration question will come up. Volker noted that the preparation for the next FCC week has started. The structure of the technical infrastructure session will soon need to be prepared. Volker mentioned the goals listed by Philippe after the 2015 FCC week and said that he has started to contact the people in charge of work packages to know what has been done so far and what can be done before the FCC week in April 2016. Davide is looking for a contact person who has been involved in the electrical work for the Gotthard tunnel. John has a contact at AMBERG who in turn can find a person for questions about the electrical distribution system. John is still collecting data for the geological tools. With that he will be able to provide a more detailed risk study by the end of this year. Charlie noted that Youri Robert has set up, in collaboration with GS-SE, an FCC-specific page within the GIS system, where various tunnel footprints can be superimposed on other layers of information (satellite image, topographic maps, height model, etc.). Peter reported that a collaboration with TU Delft has started in the area of the RAMS study. A small workshop was held at CERN mid-September to define the work for a more in-depth study of cryogenics reliability. Next week there will be a RAMS workshop at the Tampere University which is part of the FCC RAMS team. The first results from the RAMS study will be presented at the FCC I&O meeting in October. 6. Review of outstanding actions Actions are ordered by completion status, new and ongoing actions first. Status is one of {New, Ongoing, On hold, Completed, Postponed or Cancelled}. Page 6 of 9 EDMS NO. 1548459 Description and Comments Develop a map indicating electrical power and water cooling needs at different locations around FCC ring. Status Ongoing Assigned IOWG Identify limits on sector lengths coming from technical Ongoing infrastructure and accelerator systems Mauro: no hard limits, in the worst case add ventilation booster. IOWG, Accelerator systems Progress with study leading to selection on single or double tunnel option for work towards CDR. Ongoing IOWG Estimate radiation doses, “cooling” times and remote-handling needs for removal of LHC insertions towards its use as FCC high-energy injector (see Markus’ presentation on 29th July). Ongoing HSE Define straight sections to detail level, which permits documenting infrastructure requirements and constraints. Michael will provide the list, lengths of RF sections, collimators etc. Ongoing Accelerator design Study ground settling in newly excavated tunnel and impact on machine alignment. Checking tunnel stability. Tunnel and caverns are concerned. Ongoing M. Jones, Accelerator physics Create a top-down operation model of the injector chain and use for FCC availability studies. Presentation in October 2015 Ongoing RAMS team Define work topics, work period and supervision line for all personnel requests. Ongoing Supervisors Review practical limits on magnet mass and length. Not started IOWG Review and validate WBS items. Long term. Ongoing IOWG Elaborate and communicate work package descriptions (identified by 4 digits in column A of the WBS) of the Infrastructure & Operation study: 5 lines or about 100 words Ongoing IOWG Pending input from magnet study group with a general description and a focus on the work foreseen. Long term. Page 7 of 9 EDMS NO. 1548459 Description and Comments Detail cooling and ventilation power consumption estimates. Presentation in this meeting. To be refined. Status Ongoing Assigned G. Peon D. Bozzini Michael inquired about the option of the 2nd tunnel. Philippe said that RP had indicated that the 2 tunnels should be separated by 7 m of rock; upon that the 2-tunnel option had been virtually abandoned. Doors were an issue; a chicane and an air look would be needed at each connection between the tunnels. NDLR (following meeting on October 28th; cf. comments from Ralf and Michael in minutes of meeting #19): André commented that the demand for 7 m distance applies only for the case that access was needed with beam on. Moreover the 2tunnel option should not be abandoned for some critical straight sections in order to bypass highly radioactive areas, e.g. collimators. The main argument is probably to have a separate fire-proof area (the “safe area”) and be able to prove that access to it can be guaranteed under all conditions (pressure drop). From the volume a single 6 m tunnel would roughly correspond to two 4.5 m tunnels while providing more flexibility. John concurred, saying that the m3 to excavate would be similar but the cost surely not. ILC and CLIC all concluded that a single tunnel would be ok. Michael said that a summary presentation listing the advantages and drawbacks of both solutions shall be foreseen towards the end of the year. NDLR (following meeting on October 28th): André noted that this had already been done for Safety. Also the accessibility matrix has already been revised by HSE. Philippe said that the regular arc cell shall be elaborated and integrated to a greater level of detail, to include all known equipment. The cross section shall also be refined including the transport gear for material as well as the “people mover”. Guillermo argued that it would be difficult to know the requirements for CV at this stage. Philippe replied that one should do an “educated guess” or scale up. Michael explained the idea to lump the RF section of the FCC-ee machine in two zones, at 90 and 270° with respect to the experiments. To make up for the energy loss along the circumference the power converters would be “tapered”, i.e. the machine would be more sectorised, with different converter settings along the arc. Page 8 of 9 EDMS NO. 1548459 John and Charlie inquired about the timetable for the study of the nonintersecting 100 km option. Volker confirmed that the study shall be concluded by December 2015, allowing a full risk/cost comparison between the all main variants. Michael and Volker noted that the registration for the FCC week 2016 will soon open. The programme for the IO related session(s) needs to be worked out; potential contributors shall be identified. Michael suggested to form various working groups. 7. AOB The next meeting will be held on October 28th with three main topics: - Update on the cryogenics study (L. Tavian); - Deformations and movements on CERN installations (M. Jones); - First results from the reliability study (A. Niemi). Page 9 of 9