Fakultät Maschinenwesen Institut für Energietechnik Bitzer-Stiftungsprofessur für Kälte-, Kryo- und Kompressorentechnik Title: Technical Specification of the Hydrogen pumps for the ESS Cryogenic Moderator System (CMS) Client: Forschungszentrum Jülich GmbH, 52425 Jülich Zentralinstitut für Engineering, Elektronik und Analytik (ZEA) Engineering und Technologie (ZEA1) Contractor: Technische Universität Dresden Fakultät Maschinenwesen Bitzer-Stiftungsprofessur für Kälte-, Kryo- und Kompressorentechnik Marcel Klaus Yannick Beßler Originator/sub-project leader Project leader (FZ Juelich) (TU Dresden) Date: 2016-02-06 Mail (letters) MMail (parcel) Technische Universität Technische Universität Dresden Dresden 01062 Dresden Helmholtzstraße 10 Germany 01069 Dresden Germany Visiting address Georg-Schumann-Bau Section A, room 118 b Münchner Platz 3 01187 Dresden Internet tudresden.de/mw/iem/kk t 1. BACKGROUND AND AIMS The European Spallation Source is a neutron science facility funded by a collaboration of 17 European countries currently under design and construction in Lund, Sweden. The ESS accelerator will deliver protons with 5 MW of power to a rotating metal target at 2.0 GeV with a nominal current of 62.5 mA. A key feature of ESS is a tungsten target wheel, which will transform high-energy protons via the spallation process to fast neutrons. A moderator-reflector system then transforms these fast neutrons into slow neutrons, which are the final form of useful radiation provided by the neutron source. A key feature of the target system will be the hydrogen moderators, which use supercritical hydrogen at 18.5 K and 1.5 MPa to reduce the energy of the neutrons before they reach the instrument lines. The neutrons will deposit significant amounts of energy into the hydrogen that shall be removed to maintain the hydrogen at its nominal operating temperature of 18.5 K. The target moderator cryoplant (TMCP) will provide the cooling for the hydrogen cryogenic moderator system (CMS). The heat deposited into the hydrogen will be removed via a heat exchanger in a hydrogen circulation coldbox that will transfer the heat from the hydrogen circuit to a gaseous He circuit operating at approximately 18 K which is connected to the target cryoplant coldbox. The system described herein contains the hydrogen pumps that considers necessary for the duty performed by the CMS. However, contractor is encouraged to propose modifications in the design the tests to be carried out if they improve the performance of system and simplify operation and/or reduce investment costs. ESS the and the This technical specification defines the requirements for the design, manufacture, inspection, tests, transport and installation of the ESS Cryogenic Moderator System hydrogen pumps. 2 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. 2. ACRONYMS CMS ESS FZJ LV Cryogenic moderator system European Spallation Source Forschungszentrum Juelich Low Voltage 3 3. APPLICABLE DOCUMENTS CE Certificate following directives for the product CGA S-1.3-2008: Compressed Gas Association CGA Pressure relief device standards Part 3 – Stationary storage containers for compressed gases EN 10204: Metallic products - Types of inspection documents EN 12517-1: Non-destructive testing of welds - Part 1: Evaluation of welded joints in steel, nickel, titanium and their alloys by radiography - Acceptance levels EN 12517-2: Non-destructive testing of welds - Part 2: Evaluation of welded joints in aluminium and its alloys by radiography Acceptance levels EN 13445: Unfired pressure vessels EN 1435: Non-destructive examination examination of welded joints EN 1779: Non-destructive testing – Leak testing – Criteria for method and technique selection EN 287-1: Qualification test of welders - Fusion welding - Part 1: Steels EN 288-3: Specification and approval of welding procedures for metallic materials - Part 3: Welding procedure tests for the arc welding of steels EN 30042: Arc-welded joints in aluminium and its weldable alloys Guidance on quality levels for imperfection EN 439: Welding consumables - Shielding gases for arc welding and cutting EN ISO 14731: Welding coordination - Tasks and responsibilities EN ISO 15614-1: Specification and qualification of welding procedures for metallic materials - Welding procedure test - Part 1: Arc and gas welding of steels and arc welding of nickel and nickel alloys EN ISO 17635: Non-destructive testing of welds - General rules for metallic materials EN ISO 3834-2: Quality requirements for fusion welding of metallic materials - Part 2: Comprehensive quality requirements EN ISO 5817: Welding – Fusion-welded joints in steel, nickel, titanium and their alloys (beam welding excluded) – Quality levels for imperfections 4 93/68/EWG, including of welds all - required Radiographic Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. EN ISO 9001: Quality Management Systems - Requirements EN13480: Metallic industrial piping IEC: International Electrotechnical Commission ISO 10438-1: Petroleum, petrochemical and natural gas industries Lubrication, shaft-sealing and control-oil systems and auxiliaries - Part 1: General requirements ISO 10438-2: Petroleum, petrochemical and natural gas industries Lubrication, shaft-sealing and control-oil systems and auxiliaries - Part 2: Special-purpose oil systems ISO 10438-3: Petroleum, petrochemical and natural gas industries Lubrication, shaft-sealing and control-oil systems and auxiliaries - Part 3: General-purpose oil systems ISO 10440-1: Petroleum, petrochemical and natural industries, rotary-type positive displacement compressor-Part 1: Process compressor ISO 2372 Group G: Mechanical vibration of machines with operating speeds from 10 to 200 rev/s - Basis for specifying evaluation standards ISO 2954: Mechanical vibration of rotating and reciprocating machinery -- Requirements for instruments for measuring vibration severity ISO 3740: Acoustics - Determination of sound power levels of noise sources - Guidelines for the use of basic standards ISO 8573-1: Compressed air classes PED: Pressure Equipment Directive PED 97/23/EC with Annexes I to VII EMCD: Directive 2004/108/EC on electromagnetic compatibility ROHS: Directive 2002/95/EC on certain hazardous substances equipment Directive 2006/42/EC on machinery SPVD: Directive 2009/105/EC on simple pressure vessels (codified version) ATEX Directive: Directive 94/9/EC33 on equipment and protective systems intended for use in potentially explosive atmospheres - Part 1: Contaminants and purity the in restriction of the use of electrical and electronic 5 6 ATEX 137 / Directive 99/92/EC - Minimum requirements for improving the safety and health protection of workers potentially at risk from explosive atmospheres (15th individual Directive within the meaning of Article 16(1) of Directive 89/391/EEC Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. 4. ESS SITE CONDITIONS 4.1. Environment conditions Typical environmental conditions at ESS, Lund Sweden are listed as below Outdoor conditions Ambient temperature: 250 K to 310 K Relative Humidity: 10% to 100 % CMS room conditions (cryostat with installed pumps) Ambient temperature: 250 K to 310 K Relative Humidity: 10% to 100 % The outer parts of the pump have to be designed for outdoor conditions. The CMS room is equipped with a swing door wall to open to the ambient in an emergency case. Temperature and relative humidity have to be expected to be the same like outdoor conditions. 4.2. Cooling water If necessary, cooling water with a controlled supply temperature between 288 and 305 K will be available 4.3. Electricity Low Voltage (LV) switchgear at 400 V, LV UPS power and cables to the contractors LV power distribution and control system 220 V AC, 50 Hz 24 V DC with battery backup for measuring instruments and logic control circuits where necessary Earth connections 4.4. Instrument air The instrument air will be available with one single interface point in the CMS room. Instrument air quality supplied by ESS will be accordance with standard ISO 8573-1, Dust content class 2 oil content class 2 and moisture content class 2. The supply pressure will be 7 bar (6 bar gauge). 4.5. Helium ESS will provide helium with a purity of 99.996 (Helium grade 4.6) for leak tests, commissioning and acceptance tests. 7 4.6. Nitrogen ESS will supply nitrogen gas that might be required for installation and commissioning of the pumps. No liquid nitrogen will be supplied by ESS. 4.7. Magnetic field / Radiation levels Magnetic fields and radiation levels in the CMS room will be negligible. The equipment will not be accessible during hydrogen operation of CMS as it is proposed by ESS right now. 5. PERFORMANCE OF THE HYDROGEN PUMPS All pressure values in this specification are given as absolute pressure. This chapter specifies the required hydrogen pump performance. The hydrogen pumps shall be designed to reach the operational reliability as specified in section 5.4. Operation shall be stable for the specified values in section 5.2. The contractors proposal shall include a set of two pumps fulfilling the specified requirements. The liquid hydrogen control system shall be designed to fully automatic operation in all steady state operation modes as listed in section 5.2. Furthermore, the control system shall be capable handling all transient defined in section 5.3 with minimal operator intervention. The specified performances are considered as achieved when they have been proved in acceptance tests as specified in chapter 10. Nevertheless, the specified values shall be achieved also during any later operation within the warranty period (see section 5.4). 5.1. ESS / CSM hydrogen pump operational modes FZJ has defined two categories of operating modes: Normal operating mode and abnormal operating mode. Normal operation mode: Steady-state operation modes 8 Nominal design mode (full flow, two pumps in series) Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. Nominal low power mode (full flow or adjusted flow, two pumps in series) Nominal turndown mode (full flow or adjusted flow, two pumps in series) Natural convection (no pump operation) Transient operation modes Cool down (max. possible flow, two pumps in series) natural convection (no pump operation) Warm up (full flow, two pumps in series or fixed pump shaft) Switching modes/beam trip (full flow or adjusted flow, two pumps in series) Maintenance mode (no pump operation) Abnormal system operation Loss of utility power (go to mode warm up) Loss of Circulator (unreliable pump to be stopped + bypassed by closing a valve) safety critical event/loss of vacuum & leakage (all pumps to be stopped, open valves) Abnormal Target Station operation (go to mode warm up) From a pump service point of view this modes translate into specific ranges of temperature, pressure, mass flow and the circulated fluid itself that the pumps shall accommodate. Sections 5.2 and 5.3 outline in detail the requirements for the hydrogen pump operation. Figure 1: Simplified flow scheme of two hydrogen pumps in series. 9 5.2. Steady state operation modes 5.2.1. Nominal design mode This mode will occur with neutron beam on and should be the most common mode seen at ESS. This mode features the highest LH2 flow rate (= cooling capacity) needed accompanied by highest pressure drop and temperature spread at full flow. Two pressure levels are foreseen: on above the critical pressure of 1.28 MPa and one below as it can be seen in Table 2. Table 1: Nominal design mode requirements. Operation mode Nominal, two pumps in series (LH2) Single pump (LH2) Pressure level Power Mass flow, g/s high low high low Pressure, MPa Suction Discharge 1.4 1.55 Temperature, K Suction max 1000 min 1000 1.4 1.55 17.64 max 1000 1.0 1.15 22.06 min 1000 1.0 1.15 17.79 max > 800 1.4 1.5 21.09 min > 800 1.4 1.5 17.64 max > 800 1.0 1.1 22.06 min > 800 1.0 1.1 17.79 21.09 The pumps will circulate almost incompressible liquid above critical pressure or subcooled liquid far away from the boiling curve as it can be seen in the phase diagram or figure 1. 10 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. 10 15 20 25 35 40 45 critical pt. 1 1 liquid solid Pressure in MPa 30 0.1 normal boiling pt. 0.1 gaseous 0.01 0.01 10 15 20 25 30 35 Temperature in K 40 45 Figure 2: Phase diagram of hydrogen (parahydrogen) from 0.01 to 2 MPa and 10 to 45 K. 5.2.2. Nominal low power mode This mode will occur with the beam on, but operating at less than full power. During initial operations in particular, neutron beam power could vary from approximately 2 - 10% of nominal design for extended periods of time. The hydrogen pumps shall be capable of supplying constant full mass flow rate and considerably less mass flow rate (e.g. by using a variable frequency drive) to guarantee operational flexibility. The contractor shall provide information to which degree the mass flow rate can be reduced and in which timescale this shift is possible. 5.2.3. Nominal turndown mode The mode will occur with neutron beam off. The pump remains at full mass flow rate or decreases to less mass flow rate because less cooling capacity is needed. The contractor shall provide information to which degree the mass flow rate can be reduced and in which timescale this shift is possible. 5.3. Transient modes The contractor shall supply all instrumentation and equipment to enable all transient operation modes of the hydrogen pumps. This includes transitions from one steady state to another as specified in section 5.2, as well as the modes specified hereafter. 5.3.1. Cool down 11 The contractor shall provide pumps that can circulate not only liquid hydrogen but gaseous hydrogen, too. During the cool down of the helium refrigerator hydrogen gas has to be circulated through the connecting helium hydrogen heat exchanger to cool the CMS down to nominal operating conditions. The pump has to accommodate relatively high mass flow rates for gaseous hydrogen from 300 K down to nominal design conditions for liquid hydrogen (above or slightly below the critical pressure of 1.28 MPa). Around the critical temperature of 33 K the pressure will be above its critical value of 1.28 MPa to avoid two phase flow. 5.3.2. Warm up In cases of longer shut downs and/or maintenance periods the pumps have to be able to circulate hydrogen at elevated temperatures warming the system up to about ambient temperatures. The pump has to accommodate relatively high mass flow rates for liquid (above or slightly below the critical pressure of 1.28 MPa) and gaseous hydrogen up from nominal conditions up to 300 K. Around the critical temperature of 33 K the pressure will be above its critical value of 1.28 MPa to avoid two phase flow. 5.3.3. Switching modes Beam trips The mode will occur with unintended and unexpected neutron beam shut off. The pump remains at full mass flow rate or decreases to less mass flow rate if a longer beam off period has to be anticipated. The contractor shall provide information to which degree the mass flow rate can be reduced and in which timescale this shift is possible. 5.3.4. Fault conditions Loss of utility power If there is a loss of utility power to the CMS, a battery based UPS supplied by ESS will power the hydrogen pump control system. If the power loss exceeds 5 minutes, an ESS supplied generator will be brought on line to power the CMS control system and instrument air. However the hydrogen pumps shall react in a manner that is selfprotecting and will not result in a risk of damaging any equipment even at complete loss of electrical power and instrument air without backup systems. Pump malfunction or vibration of shaft/impeller 12 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. If the pump shaft starts to develop vibration to a larger degree than acceptable by the contractor (provide that information) the pump rotational speed has to be reduced or the machine be stopped entirely. Due to redundancy, the remaining second pump has to take over at least 80 % (800 g/s) of the nominal mass flow (1000 g/s). The goal of 80 % has been set arbitrarily from an application point of view. A higher flow rate in the single pump operation is favored. The contractor may evaluate the highest possible flow rate and simultaneously ensuring highest possible reliability/availability plus efficiency of serial and single pump operation. 5.4. Testing and commissioning During the initial tests at FZJ and at ESS nitrogen gas, helium gas and subcooled liquid nitrogen may be utilized for testing the pumps and circuit functionality. The pumps have to be able to circulate highest possible mass flow rates with the following alternative fluids: Operation with helium gas instead of hydrogen: The contractor shall provide the characteristic curve / field (for different revolutionary speeds) for helium gas circulation from 300 to 17 K based on a suction pressure of 1.43 MPa. Operation with cold nitrogen gas: The contractor shall provide the characteristic curve / field (for different revolutionary speeds) for nitrogen gas circulation from 300 to 80 K based on a suction pressure of 1.43 MPa. Operation with liquid nitrogen: The contractor shall provide the characteristic curve / field (for different revolutionary speeds) for liquid nitrogen circulation at from 65 to 75 K based on a suction pressure of 1.43 MPa. 5.5. Additional design The type of sealing between cryostat flange and mating flange of the pump may be proposed by the contractor. In comparable systems significant cooling of the mating flange due to unexpected pump behavior (internal circulation) occurred. The contractor shall decide whether rubber o-ring made or metal gasket with CF type flange or maybe an alternative sealing type is the best solution for the hydrogen pumps. Furthermore the contractor shall propose and deliver filter elements to protect the pump of debris. Which filter(s) has to be applied where protecting the sensible rotating equipment? 13 The flow scheme in figure two shall be evaluated and be optimized by the contractor in terms of fulfilling the specified requirements and an optimal control strategy of the two pumps in series. In principal the utilization of the control valve V4 and V5 downstream of each pump and the check valves to bypass a pump should be evaluated. Proposals for appropriate valve sizes and types shall be provided. By not actively using the pumps at nominal design mode temperatures and pressures and during cool down due to geometry of piping a thermosyphon could be effectively used for the ESS CMS. What pressure drop over the impeller would occur for a fixed pump shaft at flow rates between >0 and 200 g/s hydrogen? 5.6. Availability and reliability The hydrogen pumps shall maintain the flow in the CMS continuously for 24 h/day, 7 days/week during normal operations. Scheduled operational interruptions at ESS are planned two times annually (once in summer and once in winter). The planned duration of these scheduled down times is approximately 14-16 weeks, during which time the hydrogen pumps may not be required to operate. During normal operations, the availability should exceed 99% without counting the utilities failures in order to contribute to the overall goal of 95% of the ESS. This value includes scheduled and unscheduled down time. For the purpose of this specification, availability shall be defined as follows: Availability = MTBF / (MTBF + MTTR) Where MTBF is the mean time between failures. MTTR is the mean time to repair, including the mean time to identify the cause of a system failure, locate the failed line-replaceable unit, warm up and gain access to the unit, replace it with a spare available on-site (or repair interconnections, as applicable), restore and cool-down the system and resume operation. The availability goal shall be considered after operating the hydrogen pumps for two years. Therefore a warranty of 24 month of operating time after commissioning at ESS, Lund Sweden, is inquired by the contractor The design and construction of all components of the hydrogen pumps shall consider an operation lifetime of at least 25 years. ESS will take responsibility to assess the plants availability based on the input data given by the contractor and reasonable engineering judgement. 6. SPARE PARTS The contractor shall propose a list of spare parts considered necessary for reliability requirements and lifetime operation of the 14 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. hydrogen pumps. All spare parts are in the scope of delivery. The following amounts of spare parts deemed necessary by ESS for efficient operation and maintenance: one maintenance kit for each pump (bearings, impeller etc.) Besides these spare parts required by ESS as part of the supply, the contractor is invited to submit a list of all additional spare parts, which he considers necessary for operation of the hydrogen pumps. 7. PUMP CONTROL SYSTEM The contractor shall propose a control strategy and necessary hardware for the pumps at all specified operating conditions. Requirements related to instrumentation, monitoring and control All electrical equipment shall belong to Group2 Class II, according to ELSÄK-FS 1995:6 The pumps shall be equipped it with instrumentations needed for automatic control of the machines Adequate alarms shall be set, to monitor and control the system All surveillance and control shall be managed in a PLC system interfacing ICS Analogue output and input shall be connected to the control system via: o Either 4-20mA DC connection, in 2-wire (twisted and shielded) mode protected against polarity inversion with galvanic insulation and an impedance lower than 500 Ohms, or o Field bus connections: the accepted standard is PROFIBUS and PROFINET Digital output and input signals shall be connected to the control system via: o Input 24V DC; o Digital Output 24 V DC; o Field bus connections: the accepted standard is PROFIBUS and PROFINET. For temperature measurements outside of the vacuum vessel, PT100 sensors shall be used. For temperature measurements inside of the vacuum vessel,: o At above 50 K: PT-100 Class A sensors, according to IEC751, shall be used, the accuracy shall be better than ±1% for the whole scale and the long-term stability shall be less than ±0.1 K; o At between 2 K and 50 K: E.g. Cernox sensors shall be used, the accuracy shall be better than ±0.5% for the 15 whole scale and the long-term stability shall be less than ±10 mK; o Each sensor below 50 K shall be supplied with its calibration data and serial number versus physical location and external pin connection; o Display unit: K. All sensors shall be cabled with 4 wires to a precision transducer, using a low measuring current according to the sensor data sheets. Requirements on electrical power supply All electrical equipment shall belong to Group2 Class II, according to ELSÄK-FS 1995:6 Power for pumps shall be provided to a connection box in the perimeters of the equipment UPS will be provided for instruments and control system 7.1. Overview and Control strategy The hydrogen pumps control strategy (see Figure 9) shall be based in EPICS in order to provide monitoring and operational capabilities for the CMS. Configuration tools and operator applications (synoptic displays, alarm displays, archive viewer, etc. ) shall be implemented as plugins of the Control System Studio (CSS) framework following the ESS Standards. CSS shall be running in the standard ESS operative system. Functions for supervisory controls and batch operations shall be running in the EPICS process controller and implemented in SNL for a fully automated operation of the plant. The EPICS IOC shall be running in an ESS standard control box. All the Process Variables shall be time stamped in the IOC. The IOC shall be properly configured with an appropriate time provider. Local PLCs shall be used for all functions with substantial technical safety requirements and deterministic sequence programs. Each PLC shall have an interface to the EPICS process controller (IOC). This interface shall be implemented with the appropriate EPICS driver for the used PLCs. Sensors and actuators shall be connected through PROFIBUS or PROFINET, while the communication between PLC shall be solved with PROFINET. 8. INSTRUMENTATION, INTERLOCKS AND ELECTRICAL DESIGN Temperature measurement 16 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. PT-100 to monitor representative main pump flange temperature (prevent freezing of rubber o-ring / metal gasket) Cernox sensor for temperature of the impeller housing Revolutional speed Rotational speed pick-up of pump shaft Power demand Power demand of electric drive (shaft power) / frequency converter Vibrations Accelerometer to monitor the relevant pump impeller/shaft vibrations to prevent risk of pump failure An interlock for too intense vibrations at the pump shaft/impeller is foreseen at ESS. Other critical events, strategies how to prevent a risk of total pump failure und required instrumentation shall be proposed by previous experience with hydrogen pumps of the contractor. 9. REQUIREMENTS TO MECHANICAL DESIGN, MANUFACTURE AND MOUNTING The contractor shall provide full CE certification with all required (sub-)directives for the specified device and parts. 10. TESTS All necessary tests to as far as reasonably achievable shall be conducted to verify and proof the specified performance. Using a surrogate fluid test instead of a test in actual (liquid) hydrogen is accepted. The non-dimensional performance (i.e. a work coefficient vs. flow coefficient curve) of a pump shall be accurately quantified during a test program using a surrogate test fluid and satisfying the following conditions: 1. The Reynolds Number (Re) of the surrogate fluid test conditions shall be close to those of the actual fluid conditions, or both the test fluid and the actual fluid Reynolds Numbers are sufficiently high so as to preclude (eliminate) any low Reynolds Number effects, 17 2. Holding fixed values of the flow coefficient used will tend to produce similar velocities at all points in the flow path. This can be assumed for incompressible media such as the (liquid) hydrogen and the proposed surrogate liquid nitrogen, The compressibility of liquid hydrogen is small enough that it usually does not produce appreciable errors in testing with a surrogate fluid such as liquid nitrogen. The change in density of the (liquid) hydrogen should be evaluated to ensure that it will not produce unacceptable errors in the correlation of tested to actual performance. Usually the density change of (liquid) hydrogen between inlet and exit is less than a couple of percent, and can be ignored with minimal error, 3. The effects on the pump operating clearances due to testing the pump at a different temperature than at the actual conditions shall not be significant Bearing design analysis and clearance shall be conducted to cope with differences between the surrogate test fluid and the actual specified (liquid) hydrogen operation. A separate offer shall be provided based on the full-scale test specification with liquid hydrogen which can be found in the appendix. 11. QUALITY MANAGEMENT A high degree of quality consciousness is necessary for the manufacture of ESS CMS hydrogen pumps. Therefore, the contractor is obligated to use a suitable quality management (QM) system. The EN ISO 9001 standard shall be the basis for all quality assurance measures. For execution of this contractor, the contractor shall have a documented and supervised QM system described in a QM handbook. This contains the quality policy of the contractor, the definition of responsibilities, and the processes, procedures and means for quality assurance. During the execution of the contractor, the contractor shall pay special attention to the following points, which are to be implemented in his QM plan: 11.1. General requirements Quality assurance shall be independent of any business interests of the contractor’s involved department. Organizationally, it shall be subordinated to the managing direction. The quality management officer assigned by the managing direction, who shall be named in the QM plan, shall possess all necessary 18 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. competence. If required, he/she shall be authorized to interrupt the production process in order to initiate corrective measures and to supervise and evaluate the implementation and results of these measures. The contractor agrees to system, process and/or product audits carried out by FZJ throughout the duration of the contractor, depending on the respective contractual content. The suitability of production, test and assembly procedures for which there are no previous experience or established regulations shall be verified and documented by means of a qualification procedure in co-ordination with FZJ. 11.2. Quality assurance in design The plans shall activities. This organizational and contribute to the FZJ. The execution of documented. describe the different design and engineering includes the definition and regulation of technical interfaces between various groups that design process. The plan shall be submitted to the measures defined in the plans shall be 11.3. Quality assurance in procurement The procurement documents for third-party parts and services shall include all required information, such as: Product specification; Product requirements; Conditions of acceptance; Quality certificates and reports to be submitted; Descriptions of functions and operating manuals; Labelling. 11.4. Quality assurance in production Production shall take place in compliance with the requirements of this technical specification. The contractor shall master the procedures and processes applied The contractor shall fulfil the following tasks and requirements in the production preparation stage as well as during production: Recognize critical particular care; Take special measures, such as separate inspections in order to ensure compliance with the quality requirements; production steps and supervise these with 19 Prepare a test plan and a test sequence plan specifying the testing processes used and to what extent, in addition to when, how, where and by whom; Take suitable corrective measures in case of defects and faults and verify the suitability and effectiveness of such measures; Prevent recurrence of known faults. 11.4.1. Preparation for production Production documents The production documents for the hydrogen pumps shall include at least the following documents and any other documents that may be needed for the production processes: Planning documents with schedules, including exact information on all work processes with a duration of more than one week, as well as the regulation of mutual influences resulting from dependencies for the work processes and the resulting chronological classification; Description of the necessary preliminary tests for the production; Description of all production processes; Description of welding work and welding inspections; Workshop drawings and parts lists; Quality plans for production and inspection with processes and work instruction; Necessary forms (measuring reports, process reports etc.). These documents shall be submitted to FZJ not later than fifteen workdays before the production of the respective items starts. Welding requirements All welding work shall conform to the requirements in Section 9. Before the production is started, the contractor shall submit to FZJ: Proof of qualification of the welders employed according to EN 287-1, proof of qualification of welding supervisor according to EN ISO 14731 or persons with equivalent competence; Fabrication inspection plans with production and test sequence plans; Welding instructions according to the relevant section of EN 288; Documentation of preliminary tests conducted. 20 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. Preliminary tests If necessary, the contractor shall conduct all preliminary tests necessary to fulfil the technical specification. The contractor is responsible for planning and developing the test set-up, execution, analysis and documentation of all preliminary tests necessary for production of the components including, but not limited to, the following potential problem areas: Determination of material and definition of material properties Welding procedures Joint and connection technology The following shall be defined in advance for all preliminary tests: Goal and procedure; Test setup and measuring equipment; Test variables and precision; Test certificates. This information shall be submitted to FZJ for information purposes before starting the respective preliminary test. The results of the preliminary tests, including the relevant general conditions, shall be documented. All documents on the preliminary tests shall be submitted to FZJ in duplicate no later than fifteen workdays before the production of the respective items starts. Equipment The contractor is responsible for the design, manufacture of all equipment required for the including but not limited to the following: Tests; Production; Inspections; Handling, storage, packing and transport. construction and following tasks, Materials The choice of the materials shall comply with the requirements in section 9. According to the requirements in the relevant regulations, material certifications shall be enclosed to the documentation and submitted to FZJ. 11.4.2. Execution of production 21 Production shall be executed under conditions that are appropriate to the technical requirements of the respective production step. The necessary standards of cleanliness shall be maintained. All materials shall be clearly identified and stored so as to involve no danger of confusion. Ferritic and non-ferritic materials shall be stored and processed separately. All employees in production shall be trained in the tasks that they area to perform; there shall be proof of this. Special emphasis is to be placed on problems in production steps affecting quality. This applies in particular to personnel employed only temporarily in production. The obligations of the contractor concerning production include, but are not limited to, the following tasks: Procurement of material and supplied parts; Production of components; Production of spare parts; Assembly (production and assembly equipment); Execution of inspection and tests; Cleaning and packing. 11.4.3. Inspection during production Intermediate inspections are required for critical production steps and are to be defined by the contractor in a schedule. Acknowledged inspection procedures shall be defined and followed for these inspections. These inspection procedures are to be prepared by the contractor and approved by FZJ. The FZJ shall be notified in writing at least fifteen workdays in advance of the first test, inspection or stopping point and at least five workdays in advance of all other tests, inspections or stopping points. FZJ shall notify the contractor in due time whether he will be present at these events. As a rule, the contractor and FZJ shall have fifteen workdays to solve any problems that arise during an inspection. Continuation of the work after the stopping point requires the written confirmation of FZJ. 11.5. Tests The obligations of the contractor concerning quality assurance for this contract include, but are not limited to, the execution of all inspections and tests as described in Chapter 7 of this technical specification. If necessary, the contractor shall recommend and agree upon with FZJ his own test procedures. 22 Error! Use the Home tab to apply Überschrift 1 to the text that you want to appear here. All tests shall be conducted according to detailed written test procedures, which shall be submitted to FZJ approval at least four weeks before the first test. The suitability of special tests procedures shall be verified and documented on a qualification process base. Forms are to be prepared for all tests, indicating the type and extent of the tests (the specified values to be tested, the test conditions and limiting values to be observed, test frequency, extent, type, procedure, tests means used, evaluation criteria). The test forms shall be submitted to FZJ at least fifteen workdays before the first test. All required documents and materials, such as pre-test documents, drawings, reports, calibrations, specifications, test sequence plans, work samples, etc. shall be made available by the contractor for each test. The contractor is responsible for providing and supervising suitable test means and test equipment. FZJ assumes that all test means used comply with the relevant standards, are in good working order and properly calibrated. FZJ shall be notified in writing at least fifteen workdays in advance of the first test and five workdays in advance of all other tests. FZJ shall notify the contractor in due time whether he will be present for a test. The contractor shall submit a copy of the completed test form to FZJ no later than two weeks after completion of a test. If the result of a test does not fulfil the requirements of the valid regulations and this technical specification, then the evident deviations shall be eliminated and the affected component shall be subjected to a new test at the expense of the contractor. 12. DOCUMENTATION The execution of this contractor requires careful documentation throughout the entire contract phase. Where possible and feasible, the documents shall be prepared using MS office applications. All drawings delivered to FZJ shall be CAD drawing (.stp for 3-D, .dxf and .pdf for 2-D). All documents shall be made available printed and electronically. Three hard copies of all documents shall be provided for the documents requiring FZJ approval, and the final documents. All technical documents relevant to the contractor shall be in English. The national language is permitted for documents intended only for contractor’s internal use. Dimensions shall be indicated using the SI system. The document numbers shall be assigned by FZJ on request, but not later than to the first examination of the respective document and shall appear on each page of all further versions of the documents. Independently of the documentation for FZJ, the contractor shall 23 maintain a list of all documents prepared, indicating the revision status. All changes to valid documents shall be marked clearly to indicate the revision status (index). In case of renewed changes, the markings of the previous revision are to be removed. Documents not conforming to this form will be rejected and deemed not submitted. The traceability of all documents shall be given. 24